Packers
Packers
WCP1-018
Packers
Overview
y Packer functions
y Main Packer Families
y Retrievable Packers
y Permanent Packers
Schlumberger Private
y Multizone Packers
y Packer Selection Process
Schlumberger Private
y provides a second conduit
Schlumberger Private
y Downhole safety and control
y e.g., temporary tubing plugs
y Zone separation
y e.g., multiple packer/multiple string
y regulatory monitoring of specific zones
Schlumberger Private
y Selective treatment
y Preventative (e.g., scale) and remedial treatments
y Remedial/repair
y seal/bypass damaged area
y isolation of production zone
Schlumberger Private
Sealing element Slips Casing wall
Schlumberger Private
y Secondly a sealing element must be compressed to effect a
seal against the casing wall.
y The two most important basic components are therefore the
slips and sealing element.
Schlumberger Private
WCP1-018 Packers – slide 8
Production Packers – Types
y Production packers categorized by:
y Retrievability
y retrievable, semi-permanent, permanent
y Setting mechanism
y mechanical, hydraulic, wireline
Schlumberger Private
y Production conduit
y single, dual, multiple/special
y Basic categories (for this presentation)
y Retrievable packers
y Permanent packers
y Dual packer systems
Schlumberger Private
Setting depth shallow to medium
y Low to moderate differential pressures
y Straight wellbore or moderate deviation
y Multiple zones are to be produced
Schlumberger Private
Hold down slips (hydraulic)
y Unset by picking up
y May be reset several times –
similar design and operation to Packing elements
packers used for well service
work
Bottom (hold-up) slips
Continuous mandrel
Schlumberger Private
y Versatility
y one packer can be used with multiple casing weights
y compression, tension or bi-directional set options
y Length
y can generally be used in situations where dog-legs or extreme
deviations are encountered
Schlumberger Private
y generally requires rotation and tubing movement to set
y no provisions for “stored energy” to aid in packer seal and anchor
y injection operations (cooling) may release the packer
Schlumberger Private
y Straight pull release (once
only)
y Single and dual application
compatible Slip (top and bottom)
assembly
Continuous mandrel
Schlumberger Private
Reservoirs with anticipated heavy workover activities
y Applications where it is not possible to rotate tubing
Schlumberger Private
packer set is not dependent on continual tubing weight
y space out operation easier without tubing movement
y more accurate placement and space out
Schlumberger Private
WCP1-018 Packers – slide 17
Permanent Packers
y Permanent packers run by: Latch profile
y Wireline
y Tubing Seal-bore extension
y Coiled tubing
Schlumberger Private
y Permanent packers set by:
y Hydraulic (tubing) Packing elements
pressure
y Mechanical mechanism
y Electric wireline
Bottom sub/adapter
Schlumberger Private
y Deviated and extended reach wells
y Selective single completions
y setting point correlated by wireline
y Dual completions with parallel flow tubes
y Sump packer for gravel packer operations
Schlumberger Private
Seal-bore packer
Schlumberger Private
Lower seal-bore extension Lower seal-bore extension
Schlumberger Private
Seal-bore packer with Permanent packer with
lower seal-bore extension an extra-long upper
and liner top seal-bore seal receptacle for
assembly extreme movement
applications
Schlumberger Private
slips milled
y Incorporates safety release Lower section of packer
system for spear retrieved when upper slips
are removed
Spear/packer retriever
engages
in packer bore or millout
extension
Schlumberger Private
Mechanical Set N Perma Drill Mechanical Set
(Drillable) Magnum
Drillable S, L, LB, LO D, DA, F-1, Perma Drill Magnum G
Seal-Bore FA, FA-1 Magnum H
Retrievable Omegamatic SC-2 Cerso-Trieve UNI-X
Seal-Bore Quantum* HP Perma-Trieve
Wireline Set SOT-1, WR LOK-Set Perma-Trieve G-6, VNI, VI
Retrievable Perma-Latch ER-VI
Schlumberger Private
Packing element
y allow production
through two tubing
strings from the same
Bi-directional
wellbore slip assembly
y enable production from
adjacent high and low
pressure zones
Schlumberger Private
Will workovers likely involve Yes
packer removal within 10 No
Review options and QA/QC programme
years or fullbore access to to make sure that equipment is suitable
pay zone? PBR COMPLETION SYSTEM
Review
Yes
•Casing or liner
Do throughbore Yes Could a PBR be used to provide Yes •Landing conditions
requirements preclude use of fullbore access to pay zone? •Elastomer specs
standard retrievable packers?
•Nipple arrangements
No
CONSIDER OPTIONS
Is access to zone of interest limited Yes •Roll or swage casing RETRIEVABLE PACKER
by buckled or collapsed casing? •Sidetrack well SYSTEM
•Use short permanent packers Review:
•Consider inflatable packers for
•Hold-down method
No limited differentials
•Equalization
•Setting method
•Positioning
•Internal seals
•Landing conditions
Schlumberger Private
within 5 years vs. multi-strings)
No
Is fullbore access to a liner required? Yes Does a PBR offer advantages over a Yes
(Access to small bore pipe, scale/asphaltene large bore packer? (eg max through bore Polished Bore Receptacle
removal, or to avoid flow restrictions) or liner cap isolation) (PBR) Completion
No No
PACKER COMPLETION
Can packer be set well above top pay without limiting functional Yes
Consider benefits and problems with shallow
requirements for isolation, well kill, artificial lift and
setting depth (below SSV, above top of liner
flow optimization?
and above recompletion targets)
No
Yes PACKER COMPLETION
Will production logging be required
Set packer so tubing shoe is
under flowing conditions?
50 to 100 ft above perforations
PACKER COMPLETION
No Minimum safe distance between packer
and perforations 5 ft for wireline correlations
0.2% depth for tubing packers
Schlumberger Private
Yes
Is packer P > 5000 psi? No Is temp at set No Is H2S or No Are regular workovers Yes Does retrievable have
depth >225°F? CO2 present? needed? good reliability?
Yes
Yes Yes No No Yes
Is temp at set depth <160°F?
Yes No
Run
Check seal selection retrievable
Permanent Packer packer
Schlumberger Private
95 Hard Viton 32-250 10,000 5,000 5% OK OK OK NO OK NO
Bonded
V-Ryte 32-300 15,000 NO 15% OK OK OK NO Note #1 NO
32-400 5% <200°F OK
A-Ryte 80-300 15,000 NO 20% NO OK OK OK Note #1 OK
80-450 7%
A-HEET 80-300 15,000 NO 20% NO OK OK OK Note #1 OK
80-450 7%
R-Ryte or 200-400(2) 10,000 NO 15% Note #4 OK OK OK OK OK OK
Molyglass 325-450 (2) 7%
Seal-Ryte 40-400 15,000 NO 15% Note #4 OK OK OK OK Note #1 OK
40-450
K-HEET 100-550 15,000 NO Note #3 OK OK OK OK Note #1 OK
Note #1: The elastomeric seals in these units may be susceptible to explosive decompression, however, explosive decompression does not usually occur while
seals are in service.
Note #2: Refer to Baker Technical Data Manual, Unit No 8218-3 for complete temperature range information.
Note #3: There are no known H2S limitations below 550°F.
Note #4: For temperatures below 400°F and more than 15% H2S, contact Houston Engineering Department for additional information
Environmental Compatibility
Material1 Temp °F H2S Oil Base/ Light Bromide CO2 Amine Solvents2 High pH
Diesel Brine Comp Decomp Inhib. Max Exp Comp Fluids,
Comp Comp Time pH >10
Nitrile to 175 100 ppm OK OK NO OK OK 6 hours OK
Schlumberger Private
3
to 300 NO NO 4 hours NO (pH <10
OK to 250°F)
Viton™ to 200 20% OK OK
to 300 15% OK OK OK OK NO 24 hours NO
450 max 5% NO 4 hours
Aflas™ to 200 limit unknown OK 6 hours
to 300 20% NO OK OK OK OK 4 hours OK
450 max 7% NO NO
Note #1 These recommendations are based on expected long term completions
Note #2 Some examples of solvents are: xylene, toluene, methanol
Note #3 Some permanent packer applications may allow use of nitrile above 300°F. Contact AEG
Environmental Compatibility
Material1 Temp °F2 H2S Oil Base/ Light Bromide Amine Acids Solvents4 High pH
Comp Brine Comp Inhib Max Exp Max Exp Comp Fluids,
Comp Time Time pH >10
Nitrile to 175 OK OK OK NO OK 8 hours 6 hours OK
Schlumberger Private
400 6 hours 4 hours 24 hours
Viton™3 to 175 OK OK OK OK OK 24 hours 24 hours NO
350 NO 4 hours 4 hours
Aflas™3 to 175 OK NO OK OK OK 48 hours 4 hours OK
350 8 hours NO
EPDM3 to 500 OK NO OK OK OK OK NO OK
Note #1 These recommendations are for relatively short term exposure R & S applications only. (Typically <30 days). Longer term
completion applications should follow other guidelines
Note #2 Pressure ratings are dependant on size and type of tool and are less related to chemical resistance than temperature.
Refer to Tech Manual for pressure ratings.
Note #3 These materials are special order only. Long load times and/or product development are likely.
Note #4 Some examples of solvents are: xylene, toluene, methanol.
Schlumberger Private
Business process Deliverable Key decision
EXIT
Activity Product ?
CONTINUE
Next activity ETC Breaking activities down into manageable
units and defining their purpose in
manageable bits is essential to effective
planning
Version 1a
Course WCP-1
Schlumberger Private
Date Created March 26, 2003
Checked by
Date Checked
Comments