220kV BENACO - KYAKA TL                                                   Schedule of Rates and Prices                                                  ICB No.: ..........................
220kV OHTL
                          SCHEDULE 2 - LOT 1 : Plant and Mandatory Spare Parts Supplied from Within the Employer's Country
  NOTE:
  1.Plants, working tools, accessories and other machinery/installation facility is obliged to pay the import and excise duties. The supply will be made by a local supplier
  who is VAT registered taxpayer, VAT is 18%.
  2.All Unit Price shall be in Tanzanian Shillings (TZS)
  3. Unit Price shall be VAT Exclusive.
  4.Unit Price shall be Carriage and Insurance Paid (CIP) Benaco - Kyaka transmission line
  SCHEDULES 2 - LOT 1: Plant and Mandatory Spare Parts Supplied from Within the Employer's Country
                                                                                                             Code                     Est. Qty.   Unit Price       Total Price
                                                                                                                            Unit                    (TZS)             (TZS)
    Item No                                        Description
                                                                                                          Country of                                 CIP                CIP
                                                                                                         Manufacturing                    1           2               (1) x (2)
      A1       OTHER SERVICES
     A1-1      Project Office
               Project office for the Engineer and Employer’s staff, full furnished as described in
     A1-1.1    the Technical Specification (TS)                                                                             each         2.0         0.0                  0.0
     A1-1.2    Operational Costs for Employer's Offices for the entire Project Contract duration as                       lumpsum        1.0         0.00                0.00
               per TS.
     A1-2      Equipment & Supervisor Offices tools for -PIU
               Items below shall Include all necessary specifications as per               Technical
               Specifications (TS)
     A1-2.1    Laptop Computer                                                                                               pcs        10.0         0.0                  0.0
     A1-2.2    Handheld GPSMAP 60CSx accuracy 0.5m to 5m                                                                     pcs         4.0         0.0                  0.0
Shedule No.2                                                            __________________________                                                                         Page 1 of 3
                                                                         Bidder's Stamp and Signature
220kV BENACO - KYAKA TL                                                 Schedule of Rates and Prices                                              ICB No.: ..........................
                                                                               220kV OHTL
  SCHEDULES 2 - LOT 1: Plant and Mandatory Spare Parts Supplied from Within the Employer's Country
                                                                                                           Code                  Est. Qty.   Unit Price      Total Price
                                                                                                                        Unit                   (TZS)            (TZS)
    Item No                                       Description
                                                                                                        Country of                              CIP               CIP
                                                                                                       Manufacturing                1            2              (1) x (2)
     A1-3      Housing/Accommodation
     A1-3.1    Housing/ accommodation for the Engineer's/ Employer’s staff at site, full furnished
               as described in the Technical Specifications (TS)                                                        each       2.0          0.0                 0.0
     A1-3.2
               Operational Costs for Employer's Housing/Accommodation for the entire Project                           lumpsum     1.0          0.00               0.00
               Contract duration as per TS.
     A1-4      Vehicles :
               Inclusive the following items:
               • All necessary fuel, lubricant, tools, spares and full maintenance for the full
               contract duration up to a maximum of 300,000km for each vehicle according to
               relevant drivers logbook.;
               • Temporary replacement vehicles for any vehicle under repair or maintenance for
               more than twenty four (24) hours;
               • Permanent replacement vehicles for vehicles beyond repair or during extensive
               repair period exceeding four (4) working days;
               • Insurance and licenses for normal operation on and off site and on and off duty.
               • All vehicles shall be brought to the country and should have local dealers within
               the country.
               • The price indicated below shall includes expenses required for the duration of
               the Contract.
               • An efficient licensed driver for each vehicle.
Shedule No.2                                                           __________________________                                                                    Page 2 of 3
                                                                        Bidder's Stamp and Signature
220kV BENACO - KYAKA TL                                                 Schedule of Rates and Prices                                              ICB No.: ..........................
                                                                               220kV OHTL
  SCHEDULES 2 - LOT 1: Plant and Mandatory Spare Parts Supplied from Within the Employer's Country
                                                                                                           Code                  Est. Qty.   Unit Price      Total Price
                                                                                                                        Unit                   (TZS)            (TZS)
    Item No                                        Description
                                                                                                        Country of                              CIP               CIP
                                                                                                       Manufacturing                1             2             (1) x (2)
     A1-4.1    Type 1: Double Cabin with 2.8 litre diesel engine or above as per TS                                     each       5.0          0.00              0.00
     A1-4.2    Type 2: Medium SUV type, 2.8 litre diesel engine or above as per TS                                      each       1.0          0.00              0.00
     A1-4.3    Operational Costs for Employer's Vehicles for the entire Project Contract duration                      lumpsum     1.0          0.00               0.00
               as per TS.
     A1-5      Communication Facilities
               Mobile Phones and Tablets Computer for use in project oversight by the
               Employer’s Project Implementation Team with all usage charges relevant to the
               transmission project paid for by the Contractor, as described in TS
    A1-5.1 Mobile Phones as described in TS                                                                             each       10.0         0.00               0.00
    A1-5.2 Tablets Computer as described in TS                                                                          each       10.0         0.00               0.00
  Subtotal Other Services                                                                                                                                          0.0
                                                                 SCHEDULE 2, TOTAL (VAT EXCLUSIVE)                                                                 0.00
Shedule No.2                                                           __________________________                                                                    Page 3 of 3
                                                                        Bidder's Stamp and Signature