Force Majeure
Force Majeure
MAJEURE ON COMMERCIAL
CONTRACTS IN THE LIGHT OF COVID 19
BY:
MANISHA PARIDA
MADHUSUDAN LAW COLLEGE
UTKAL UNIVERSITY, BHUBANESWAR
TABLE CONTENTS _
ACKNOWLEDGEMENT:..........................................................................2
INTRODUCTION.........................................................................................3
FORCE MAJEURE: MEANING AND DEFINITION.............................3
FORCE MAJEURE IN THE TIMES OF COVID-19...............................6
STATUTORY PROVISION UNDER INDIAN LAW:..............................8
ABSENCE OF A FORCE MAJEURE CLAUSE:.....................................10
BURDEN OF PROOF...................................................................................11
NOTICE REQUIREMENT:.........................................................................12
DUTY TO MITIGATE:.................................................................................13
RELEVANT CASE LAWS:.........................................................................17
CONCLUSION...............................................................................................28
1|Page
ACKNOWLEDGEMENT
Firstly, I would like to express my heartful thanks to Mr. Amitesh Mani Singh,
SM(Law), NALCO, Bhubaneswar, for his constant guidance throughout the
process of completion of the project.
I would also like to thank the staff of the Law Department, NALCO,
Bhubaneswar, for their support and provision of relevant materials and cases
that contributed to the successful completion of the project.
Manisha Parida
6th Semester, B.A.LL.B.
Madhusudan Law
College Cuttack, Odisha
2|Page
INTRODUCTION
Force-majeure is a term that has its origin in the French language meaning “a
superior force”. The term force majeure which seems to have been borrowed
from the Code Napoleon had received interpretation in several decisions of
the English Courts in earlier years. In Matsoukis v. Priestman and Co.1,
Justice Bailhache opined that force majeure would include strikes and break-
down of machinery but not bad weather, football matches, or a funeral. In
Lebeeaupin
v. Crispin2, Justice McCardie had observed: “A force majeure clause should
be construed in each case with close attention to the words which precede or
follow it, and with due regard to the nature and general terms of the contract.
The effect of the clause may vary with each instrument.”
The Supreme Court of India reaffirmed the law of force majeure in the case of
Energy Watchdog v. Central Electricity Regulatory Commission & Ors. and
1
(1915) 1 K.B. 681
2
(1920) 2 K.B. 714
3
Black’s Law Dictionary, 11th Edition; @ Pg. 788
3|Page
4
P. Ramanatha Aiyar’s Advanced Law Lexicon, 5th Edition; @ Pg. 2077
4|Page
established the following factors to consider while utilizing a force majeure
clause:
i. The basis of such a clause is that the events are beyond the reasonable
control of the parties and in such conditions parties cannot be held
liable for non-performance of obligations in the contract.
ii. The occurrence of the event has actually rendered the performance
impossible or illegal.
iii. For any event to qualify as a force majeure, it is necessary that the
same is unavoidable by the parties even taking all the measures
necessary or capable in their capacity.
iv. While analyzing the force majeure clause or considering the force
majeure event, it is also necessary to take into consideration that the
best endeavors have been taken to mitigate force majeure events.
{blog ipleaders}
1. Unforeseeability of event
The foremost consideration that Courts examine when deciding a force majeure
claim is whether the event that has rendered performance impossible and/or
illegal was unforeseeable to the parties during their negotiations and execution
of the contract. As a corollary, events that could have been anticipated in the
normal conduct of business and trade – fluctuation in price and disturbances in
the execution of a contract – are not considered unforeseeable and are deemed
to be within the contemplation of parties at the time of contracting.5 The
unforseeability
5|Page
5
Alopi Prashad & Sons v. UOI AIR 1960 SC 588 (‘Alopi Parshad’).
6|Page
of the event is partly adjudged by the unique nature of the event as well as its
consequence on the contract. In making this determination, Courts inquire into
what was within the reasonable commercial contemplation of parties at the time
of contracting. Foreign disturbances6, change in the law7, refusal of regulatory
permission8, injunction orders by Courts,9 and natural calamities10 have all been
held to be unforeseeable events, thereby allowing a force majeure claim. The
unforseeability of an event will also be determined by the scope of the relevant
force majeure clause, if any. The categories of events listed therein – can
provide guidance as to the nature of events the parties contemplated as
providing a basis for force majeure.
8|Page
materially impacted the purpose the contract, such an event would not constitute
a force majeure ground to avoid a contract. This is best highlighted by a close
reading of the decision of the Supreme Court in Satyabrata Ghose v. Muneeram
Bangur & Co.12. In Satyabrata Ghose, the army requisitioned certain lands that
were part of a larger residential development. The developer claimed that the
requisition was unforeseeable and rendered the performance of the contract
impossible. The Supreme Court agreed that the requisition of lands by the Army
was unforeseeable but held that it did not materially impact the purpose the
contract. The Court held that the requisition order was limited in duration and
other lands were still available for development which were untouched and
unaffected by the requisition. On an appreciation of these factors, the Court
rejected the force majeure claim. Satyabrata Ghose is instructive, as it clarifies
that a person making a force majeure claim must not only successfully
demonstrate that an unforeseeable event has occurred, but also that the said
event materially impacted the purpose of the contract. Therefore where a party
seeks to make a force majeure claim or resist one, it is important to examine the
underlying purpose of the contract and investigate whether this purpose has
actually been altered by the alleged force majeure event. It would be prudent
that this understanding of the purpose of the contract be reflected in the
pleadings of the parties.
The concept of force majeure has been a hotly debated topic during this Covid
19 pandemic. Due to the pandemic, there has been delays in payments and the
parties to the contract are unable to perform their obligation within the contract
despite
9|Page
12
ibid
10 | P a g e
wanting to. Therefore they have to resort to the “force majeure” clause in the
contract to safeguard their interests.
The office memorandum stated that force majeure may be invoked in situations
where deemed appropriate; thus it does not apply in all scenarios and will apply
on a conditional basis. The main issue here is whether or not parties to the
contracts/agreements can plead for being excused from performing their part of
the contract citing force majeure given the situation posed by the COVID-19
pandemic.
13
Office Memorandum No.F. 18/4/2020-PPD titled ‘Force Majeure Clause’, issued by Department of
11 | P a g e
Expenditure, Procurement Policy Division, Ministry of Finance, Government of India.
12 | P a g e
In South Delhi Municipal Corporation v. MEP Infrastructure Developers
Ltd., the Delhi High Court cited the Ministry of Road Transport and Highways
(MoRTH) circular of May 18, 2020.
The contractor, in this case, had to fulfil the payments to the employer for the
toll collected.
The term “force majeure” is not defined in the Indian Contract Act 1872.
However, the Hon’ble Supreme Court of India has explained the term Force
Majeure as “the intention is to save the performing party from the consequences
of anything over which he has no control15”
Even though the Indian Contract Act does not specifically explains force
majeure but it contains two sections (section 32 and 56).
14
South Delhi Municipal Corporation v. MEP Infrastructure Developers Ltd. LPA 165/2020.
13 | P a g e
15
(Dhanrajamal Gobindram vs. Shamji Kalidas And Co, AIR 1961 SC 1285; @ Para. 19).
14 | P a g e
happens, cannot be enforced by law unless and until that event has happened.
If the event becomes impossible, such contracts become void.
Illustration
(a) A makes a contract with B to buy B’s horse if A survives C. This contract
cannot be enforced by law unless and until C dies in A’s lifetime."
15 | P a g e
SECTION 56 OF THE CONTRACT ACT, 1872
Section 56 states the "doctrine of frustration" based on the maxim “les noncogit
ad impossibilia” which means that the law will not compel a man to do what he
cannot possibly perform16.
Section 56 of the Act deals with the frustration of a contract and provides that a
contract becomes void, if it becomes impossible, by reason of an event that a
promisor could not prevent after the contract is made.
16
(“Interpretation of Force Majeure, Doctrine of Frustration and Clauses whether Express or Implied”, By
Siddharth Batra, published on www.realtyplusmag.com)
16 | P a g e
Where there is no explicit or exclusive force majeure clause in a contract, then it
is dealt with by Section 56 of the Indian Contract Act 1872. In order to fall
under the ambit of Section 56, the following factors must be considered17;
BURDEN OF PROOF
Where a party claims that its performance was rendered impossible or illegal,
the burden of proving such a fact rests on it alone. Importantly, it is not
sufficient for a party to merely prove that an unforeseen act occurred. It must
necessarily demonstrate how the unforeseen or disruptive act actually impacted
its performance and materially impacted the purpose of the contract. Courts
have clarified that the mere invocation of a disruptive event – earthquake or
civil unrest, in and of itself, is not sufficient to prove a force majeure claim.
Parties
17
https://www.mondaq.com/india/litigation-contracts-and-force-majeure/930674/force-majeure-in-times-of-
17 | P a g e
covid-19-challenges-and-the-road-ahead
18 | P a g e
must demonstrate, by a preponderance of probabilities, how the event impacted
the contract in question and resulted in a performance that was either impossible
or illegal18. Accordingly, the pleadings of parties must be sufficiently specific as
to the nature of the force majeure events, the manner in which it has impacted
performance of the contract and proof in support of such pleading. In the
absence of meeting this threshold, a party does not discharge its burden, and its
claim of force majeure is likely to fail.
NOTICE REQUIREMENT
The general law of force majeure set out in Sections 56 and 32 of the Indian
Contract Act, does not impose an obligation on a party to notify the
counterparty as soon as a force majeure event occurs. However, many force
majeure clauses in commercial contracts impose clear and time-bound
obligations to notify counterparties, either when the force majeure event arises
or when performance has been rendered impossible as a result of such an event.
Courts have rejected a force majeure claim on the basis that the party did not
notify the counterparty in a prompt manner when the force majeure event first
arose19. In these instances, Courts have held that notice of the force majeure
event was not given in a time- bound manner or where it was given, it did not
detail the nature of the event and how it impacted performance of contractual
obligations. Implicit in this judicial reasoning is the idea that the genuineness of
a force majeure claim can be tested by how promptly a counterparty is informed
about a disruption that materially impacts the performance of a contract. If a
party provides notice contemporaneously with the event and details the exact
manner in which performance has been impacted, it is more likely that a
subsequent force majeure claim is genuine. On the other hand, where a party
does not give notice while a
18
National Hydroelectric Power Co v. General Electric Co Ltd 2013 SCCOnline Del 1646
19 | P a g e
19
Housing Development and Infra Ltd v. Mumbai Airport Intl Ltd 2013 SCCOnline Bom 1513; Babasaheb v.
Vithal 2009 SCCOnline Bom 1378; BWL Ltd v. Mahanagar Telephone Nigam Ltd 2007 SCCOnline Del 1199.
20 | P a g e
force majeure event is underway, and only notifies a counterparty much later,
there is a threat that a subsequent force majeure claim is disingenuous and is
being made with an attempt to escape contractual liability20.
The parties should not expect much difficulty in preparing a Force Majeure
clause that has expressed the requirement to mitigate the hindrance of the
performance of the contract as the consequence of not having a well-drafted
force majeure clause will burden the affected party with liabilities arising from
non- performance. In the Tullow Seadrill case [2018], the English Commercial
Court reiterated that such reasonable endeavors/mitigation responsibilities place
a severe burden on a party attempting to rely upon a force majeure clause. In
particular, while determining what actions it can and should do to prevent or
lessen the impacts of a force majeure occurrence, the relying party must take
into account both its own business interests as well as those of the innocent
party.
The parties can take the following actions to mitigate the effects of a "Force
Majeure" event:
21 | P a g e
20
https://www.lawctopus.com/academike/the-force-majeure-clause-covid-india
22 | P a g e
o The parties should look into other options for performing the
contractual obligation.
o The party affected by a force majeure event shall promptly notify
other parties of the actions taken to minimise such event21.
“62. In other words, assuming that the EPL has committed a breach of contract,
the Electricity Board as the purchaser of electricity was under duty-bound
to mitigate the loss arising from such a breach.”
21
https://www.mondaq.com/india/litigation-contracts-and-force-majeure/1233892/force-majeure-a-
measure-to-mitigate-risk
22
https://indiankanoon.org/doc/56087922/
23 | P a g e
In Murlidhar Chiranjilal v. Harishchandra Dwarkadas23, the
Supreme Court has held as follows:
“The two principles on which damages in such cases are calculated are
well-settled. The first is that, as far as possible, he who has proved a
breach of a bargain to supply what he contracted to get is to be placed, as
far as money can do it, in as good a situation as if the contract had been
performed; but this principle is qualified by a second, which imposes on a
plaintiff the duty of taking all reasonable steps to mitigate the loss
consequent on the breach and debars him from claiming any part of the
damages which is due to his neglect to take such steps."
“18. In Thomas v. Countryside Council for Wales, 1994 (4) All ER 853,
Rougier, J. of Queen's Bench Division had occasion to consider a similar
issue-
"Under the normal law of contract and Tort, the fundamental basis for the
measure of damages is compensation for pecuniary loss which directly
and naturally flows from the breach... There is, however, a qualification
that a plaintiff suing for breach of contract or for that matter or tort cannot
call upon a defendant to pay the full direct consequences unless he
himself has acted reasonably to mitigate loss. It is sometimes loosely
described as a plaintiff’s duty to mitigate".
23
1962 AIR 366, 1962 SCR (1) 653
24 | P a g e
19. The principle has been explained by Viscount Haldane, L.C. in British
Westinghouse Electric and Manufacturing Co. Ltd. v. Underground Electric
Railways Co. of London Ltd., (1912) AC 673, as follows:--
“In M. Lachia Setty and Sons Ltd. v. The Coffee Board, Bangalore 24, it was
clarified that the principle of mitigation of loss does not give any right to the
party who is in breach of the contract but it is a concept that has to be borne in
mind while awarding damages.”
24
AIR 1981 SC 162
25 | P a g e
RELEVANT CASE LAWS
Facts:
In this case, the defendant company started a scheme for the development of a
large piece of land into a housing colony. The plaintiff was granted a plot on
payment of earnest money. The respondent company undertook the job of
constructing roads and drains necessary for making the land suitable for
residential purposes. Before the defendant could make the above-stated
development, the considerable portion of land was required by the government
during the 2nd world War for military purposes. The defendant then attempted to
cancel the contract on the ground that because of the supervening events, its
performance became impossible. The company put forward two options to the
buyers i.e. either to take back the earnest money or to buy the entire amount to
the company and the company would continue its construction on the land once
the war is over. Satyabrata Ghose i.e. the plaintiff denied both the available
options and decided to file a suit on 18th January 1946 against Mugneeram
Bangur and the company, saying that it was bound to the terms of the contract in
January 1946.
Issues:
Judgement:
In this case, the question considered was whether the fact amounts to frustration
of contract. In this matter, Court found that the delay was not of the character
which "totally upset the basis of the bargain and commercial object which the
26 | P a g e
parties had in view" and the plea of frustration was rejected.
27 | P a g e
Few principles stated by the Court in the decision are:
3. If the untoward event totally upsets the very foundation upon which the parties
entered their agreement, the contract can be held to be frustrated.
4. If the contract has an express or implied "force majeure" clause, then the
situation will be analyzed on the basis of that, and not through the application of
principles under Section 56.
Facts
On 1st February 2006, Gujarat Urja Vikas Nigam Limited (GUVNL) issued a
notice inviting tender for the supply of power. Thereafter, on 25 th May 2006,
Haryana Utilities issued a separate notice inviting tender for the purchase of
power.
28 | P a g e
On July 2012, the appellant filed a petition before the CERC, petition no. 155 of
2012, seeking relief due to the impact of change in Indonesian law, to either
release them from the performance obligation of PPA on the ground of
frustration or to evolve a mechanism to restore the same economic condition
that was there before the change in the law.
The CECR then passed an order that the appellant’s claim on the ground of
Force Majeure is not admissible. However, considering the larger public
interest, the central commission proceeded to grant compensatory tariffs to the
appellants.
Issues:
1. Whether the respondent is entitled to invoke and claim benefits for force
majeure?
2. What is the scope of frustration of the contract and does a mere change in
prices lead to frustration of the contract?
Judgment:
Even though there are many judgements passed by the court on this issue, but in
this particular case the court has taken effort to support the fact that “economic
hardship” cannot be considered as a “Force Majeure” event. The judgement also
has various other facets, which are as under;
“35. In M/s Alopi Parshad & Sons Ltd. v. Union of India, 1960 (2) SCR 793,
this Court, after setting out Section 56 of the Contract Act, held that the Act
does not enable a party to a contract to ignore the express covenants thereof and
to claim payment of consideration, for performance of the contract at rates
different from the stipulated rates, on a vague plea of equity. Parties to an
executable contract are often faced, in the course of carrying it out, with a turn
29 | P a g e
of events which they did not at all anticipate, for example, a wholly abnormal
rise or fall in prices
30 | P a g e
which is an unexpected obstacle to execution. This does not in itself get rid of
the bargain they have made. It is only when a consideration of the terms on
Page 38 of the contract, in the light of the circumstances existing when it was
made, showed that they never agreed to be bound in a fundamentally different
situation that had unexpectedly emerged, that the contract ceases to bind. It was
further held that the performance of a contract is never discharged merely
because it may become onerous to one of the parties.”
“37. It has also been held that applying the doctrine of frustration must always
be within narrow limits. In an instructive English judgment namely,
Tsakiroglou & Co. Ltd. v. Noblee Thorl GmbH[1961 2 WLR 633], despite the
closure of the Suez canal, and despite the fact that the customary route for
shipping the goods was only through the Suez canal, it was held that the
contract of sale of groundnuts in that case was not frustrated, even though it
would have to be performed by an alternative mode of performance which was
much more expensive, namely, that the ship would now have to go around the
Cape of Good Hope, which is three times the distance from Hamburg to Port
Sudan. The freight for such journey was also double. Despite this, the House of
Lords held that even though the contract had become more onerous to perform,
it was not fundamentally altered. Where performance is otherwise possible, it is
clear that a mere rise in freight price would not allow one of the parties to say
that the contract was discharged by impossibility of performance.”
“38. This view of the law has been echoed in ‘Chitty on Contracts’, 31st
Edition. In paragraph 14-151 a rise in cost or expense has been stated not to
frustrate a contract. Similarly, in ‘Treitel on Frustration and Force Majeure’, 3rd
Edition, the learned author has opined, at paragraph 12-034, that the cases
provide many illustrations of the principle that a ‘force majeure’ clause will not
normally be construed to apply where the contract provides for an
31 | P a g e
alternative mode of
32 | P a g e
performance. A more onerous method of performance by itself would not
amount to a frustrating event. The same learned author also states that a mere
rise in price rendering the contract more expensive to perform does not
constitute frustration.”
“39. Indeed, in England, in the celebrated Sea Angel case, 2013 (1) Lloyds Law
Report 569, the modern approach to frustration is well put, and the same reads
as under
According to the court, to claim the contract is frustrated, it must establish that
the performance of the contractual obligation become impossible and not
merely onerous. It was not mentioned anywhere in the Power Purchase
33 | P a g e
Agreements with
34 | P a g e
the states of Haryana and Gujarat that the coal is to be brought exclusively from
Indonesia or at a certain price. Moreover, it was mentioned in the PPA that the
entire coal has to be supplied by the person who sets up the power plant i.e.
Adani Enterprises. The change in Indonesian Law which increased the prices of
coal did not alter the fundamental basis of the PPA agreement i.e. to supply coal
to the state. There are various ways to fulfill the obligations of the contract.
35 | P a g e
4. HALLIBURTON OFFSHORE SERVICES INC. V. VEDANTA
LIMITED
The genesis of the present dispute emanates from an international tender floated
by the Respondent in 2018 for the integrated development of three-block fields
via the building of oil wells and rigs in the State of Rajasthan. Pursuant to the
bidding process, the Petitioner was awarded the contract in April 2018. The
Contract executed between the Parties mandated submission of eight bank
guarantees which were issued by ICICI Bank, Respondent No.2 and submitted
by the Petitioner. The relevant chronology of facts which led to the present
dispute is that while the project was nearing completion the project could not be
completed owing to restrictions imposed by the Government of India vide its
Circular dated 26.03.2020 due to Covid-19. Accordingly, the Petitioner invoked
the Force Majeure Clause of the Contract.
In essence, the case of Petitioner was that it was unavoidably handicapped in
performing the contract as the performance of the contract required travel of
person from overseas, as well as workmen from various parts of the country. In
reply, the Respondent countered the contentions of the Petitioner by arguing
that the production of petroleum was an “essential commodity” and therefore
was exempted from various orders relating to the restrictions imposed owing to
Covid-19. Accordingly, the Petitioner with an intention to arbitrate the above
dispute approached the Hon’ble Delhi High Court under Section 9 of the Act,
1996 apprehending the termination of the Contract by Respondent and
subsequent invocation of the bank guarantees. During the course of the Court
proceedings, the Petitioner informed the Court that the Respondent had
36 | P a g e
terminated the contract and had written to the Bank for invocation of the eight
bank guarantees.
Further, while discussing the scope of the force majeure clause in contracts it
was observed by the court that:
“Para 63. It is the settled position in law that a Force Majeure clause is to be
interpreted narrowly and not broadly. Parties ought to be compelled to adhere to
contractual terms and conditions and excusing non-performance would be only
in exceptional situations. As observed in Energy Watchdog it is not in the
domain of Courts to absolve parties from performing their part of the contract. It
is also not the duty of Courts to provide a shelter for justifying non-
performance. There has to be a ‘real reason’ and a ‘real justification’ which
the Court would consider in order to invoke a Force Majeure clause”.
The lockdown caused due to the pandemic of COVID-19 could invoke the
Force Majeure clauses in a contract, however, parties cannot take shelter under
this situation to hide contractual breaches that have occurred before or escape
from
37 | P a g e
38 | P a g e
their contractual obligations. As held by the Delhi High Court in the present
case “Parties ought to be compelled to adhere to contractual terms and
conditions and excusing non-performance would be only in exceptional
situations.”
"2. ..............We confirm having sold to you African raw cotton on the following
terms and conditions subject to the usual Force Majeure Clause. "
25
AIR 1961 SC 1285
39 | P a g e
"19 The addition of the word "usual" refers to something which is invariably
to be found in contracts of a particular type. Commercial documents are
sometimes expressed in language, which does not, on its face, bear a clear
meaning. The efforts of Courts is to give a meaning, if possible. "
"20. Applying these tests to the present case and in the light of the provisions of
s. 29 of the Indian Contract Act, it is clear that the clause impugned is capable
of being made certain and definite by proof that between the parties or in the
trade or in dealings with parties in British East Africa, there was invariably
included a force majeure clause of a particular kind.
In our opinion, the contract was not void for vagueness or uncertainty by
reason of the reference in the terms stated, to the force majeure clause."
40 | P a g e
sometimes expressed in language which does not, on its face, bear a clear
meaning. The effort
41 | P a g e
of the court is to give it a meaning, if possible. The Hon'ble Court dismissed the
present appeal made. The contention advanced that the contract is vague on
account of the vagueness and uncertainity in the aforesaid terminology in
contract "usual force majeure clause", was rejected.
6. In COSID Inc v. SAIL26, the Delhi High Court was deciding whether a
foreign arbitral award ought to be enforced in India. The contract was governed
under Indian Law. The arbitral tribunal rejected SAIL’s plea of force majeure
and awarded damages against it. The foreign party sought enforcement of the
award in India against SAIL. The Delhi High Court, upon a review of the
reasoning of the tribunal noted that its appreciation of SAIL’s force
majeure claim was incorrect and enforcing the award against it would violate
the public policy of India. The Delhi High Court accordingly refused
enforcement.
42 | P a g e
26
COSID v. Steel Authority of India Ltd. AIR 1986 Del 8 (‘COSID’)
43 | P a g e
CONCLUSION
Force Majeure has always been a crucial and important aspect of law due to the
protection that it provides when used by the parties to a contract. The case laws
have made it clear that making a force majeure claim is not always successful.
In order for a party to be relieved from the performance of its bargain, without
the levy of damages it must successfully meet a range of considerations. First,
the event must be unforeseeable to the parties and not within their reasonable
contemplation at the time of contracting. Second, the event must have a material
impact on the very purpose of the contract. Third, if the written contract has a
force majeure clause, the said stipulation will have to be examined to determine
whether the event in question qualifies as a force majeure event and if so, what
impact it has on the contract. Even if these considerations are met, the party
making a force majeure claim may be required to give timely notice of the event
and its impact on its performance and will have to discharge the requisite
burden of proof placed upon it.
44 | P a g e
be examined in order to assess the relative
45 | P a g e
strengths and weaknesses of such party’s stand. Relevant letters and
correspondence (including force majeure notices) should also meticulously
document not just the fact that a force majeure event has occurred, but also the
specific effects of the same on the contractual obligation which the party seeks
to be excused from performing.
The situation on account of the outbreak of corona virus, the subsequent lock
downs and restriction on movement as declared by the Government and a halt to
the economic activities is something which no reasonable and average
contracting party could have foreseen. Based on the current jurisprudence as it
stands, the aforesaid exceptional circumstances may only result in litigation in a
catena of commercial contracts. It is then a matter of interpretation by the courts
whether a contract containing force majeure clause would cover such
restrictions in movement and lock downs imposed by the Government. The
recent interim Order of the Hon'ble High Court of Delhi in M/s Halliburton
Offshore Services Inc.
v. Vedanta Limited (supra) is certainly a step in evolving the jurisprudence in
this direction.
46 | P a g e
47 | P a g e