AUDIT REQUIREMENT SHEET
DATE OF AUDIT : DEPARTMENT : Maintenance MAINTENANCE
AUDITEE NAME : AUDITOR NAME:
Audit Standard - ISO9001:2015/IATF 16949 :2016
Clause Requirements of clause Actual Observation +VE/NC/OI
4.2 Quality Manual is available?
4.4.1 Procedure for Maintenance-?
Quality objectives are defined ?
Exa. Break Down Hrs. -(Target/Achieved ) ?
6.2/
10.3
Exa. Maintenance Cost Targets ,Achievement
Verify Continual Improvement project ?
8.4.2.2 Whether Statuatory & regulatory requirements available?
e.g. cranes are tested by competent person & test
7.1.5.2.1
certificates issued are retained
Whether List of Machinery available?
6.3.1
Whether List of Minimum spare parts available?
Preventive & Predictive Maintenance schedule is
available?
Breakdown report is evident?
8.5.1.5 Machine History Card is updated ?
MTBF & MTTR record vident?
External Agencies service reports are maintained ?
Last audit NC corrective action verification &
10.2.2
horizontal deployment verification,
Auditee Signature Auditor Signature
Total NC - Total OI -