Mansi Final Report
Mansi Final Report
INTERNSHIP AT RESIDENTIAL
                           BUILDING “THE SPIRE”
                                    INTERNSHIP REPORT
                                   SUBJECT CODE-3180601
                                          Submitted By:
                                       SOLANKI MANSI N.
                             BACHELOR OF ENGINEERING
                                             in
                                     CIVIL ENGINEERING
                              L.D. COLLEGE OF ENGINEERING
                                     AHMEDABAD-380015
                                         GUJARAT
[APRIL 2024]
                                     CERTIFICATE
      This is to certify that the internship report Submitted along with the internship entitled
    “INTERNSHIP AT RESIDENTIAL BUILDING” has been carried out by
    SOLANKI MANSI N. under my guidance in Partial fulfillment for the degree of
    Bachelor of Engineering in Civil Engineering 8 th semester of Gujarat Technological
    University, Ahmedabad during the academic year 2023-24.
                                 DECLARATION
 We hereby declare that the Internship / Project report submitted along with the Internship
“INTERNSHIP AT RESIDENTIAL BUILDING” submitted in partial fulfillment for the
degree of Bachelor of Engineering in Civil Engineering to Gujarat Technological
University, Ahmedabad, is a Bonafide record of original project work carried out by me at
RAHUL CONSTRUCTION under guidance of SANJAYBHAI CHOTHANI.
  Place: Ahmedabad
  Date:
All the content in this report is an attempted blend of theoretical knowledge and
practical application of construction technology and practices prevalent in India,
incorporating latest Indian standard recommendations. The main objective of the
internship is to enable the students to analyse the integral working of an organization
with mature eye.
                                      LIST OF FIGURE
     Figure 2.1                Design of structure                          2
     Figure2.2                 House Planing (G+2)                          3
     Figure 2.3                Unit plan                                    4
     Figure 2.4                Elevtion, Section &Columns Layout            5
     Figure 3.3                Concreting                                  12
     Figure 3.4                Slump Test                                  15
     Figure 3.5                Types Of Slump                              16
     Figure 3.6                Cube Test Of Concrete                       17
     Figure 3.7                various Method Of Concrete Curing           18
     Figure 3.8                Concrete Cracks                             20
     Figure 3.9                Honey Comb In Concrete                      21
     Figure 3.10                   Admixure Of Concrete                    22
     Figure 3.11                   Type Of Beam                            23
     Figure 3.12                   Formwork                                24
     Figure 3.13                   Steel Work                              26
     Figure 3.14                   Staircase Reinforcement                 30
     Figure 3.15                   Beam-Column Junction                    31
     Figure 3.16                   Beam Reinforcement                      32
     Figure 3.17                   Hidden Beam                             33
     Figure 3.18                   Column                                  34
     Figure 3.19                   Space Bar                               36
     Figure 3.20                   Slab Reinforcement                      37
     Figure 3.21                   Chair                                   39
     Figure 3.22                   Plaster work                            40
     Figure 3.23                   Coupler                                 41
     Figure 3.24                   Extra photo                             42
                                   Certificate                           II
                                   INTERNSHIP Certificate               III
                                   Candidate’s Declaration               V
                                   Acknowledgments                      VI
                                   Abstract                             VII
                                   List of Figures & Tables             VIII
Table content X
Chapter 5   REFFERENCE                          44
                             Chapter – 1: Overview of the company
• Rahul Construction has more than 8 years working in pan Ahmedabad, Gujrat. It has
  executed Structural design for more than 3 million square feet of construction area comprising
  80+ projects.
• Rahul Construction has provided engineering services in Ahmedabad, Gujrat.
GROUND FLOOR
FIRST FLOOR
SECOND FLOOR
Table 1
SLAB THIKNESS :
Table 2
GROUND 125MM
G+1 125MM
 G+2                                                GROUND-125MM
                                                    FIRST FLOOR-125MM
 G+3                                                GROUND-150MM
                                                    FIRST FLOOR -125MM
                                                    SECONED FLOOR-125MM
                                                    THIRD FLOOR-125MM
 G+4                                                GROUND-150MM
                                                    FIRST FLOOR -150MM
                                                    SECONED FLOOR-125MM
                                                    THIRD FLOOR-125MM
                                                    FOURTH FLOOR-125MM
                 Civil engineering is that which deals with the design, Planning, Estimating, surveying
and construction of naturally and physically made environment, including works like roads, canals,
buildings (Industrial and Residential), dams, bridges, port & harbors etc. structures are construct with
the help of civil engineer.
                              There are certain fields in civil engineering like Management and Construction
Engineering, Structural Engineering, Transportation Engineering, Water Engineering, Geotechnical
Engineering, Environmental Engineering, Coastal Engineering, Earthquake Engineering, Highway
Engineering etc.
      All building steps are essential for the construction process. Any step of the process is directly
connected with another step. For example, first of all we acquire land then we will able to construct a
building over there but, for that we need documentation. After completing this thing next step is analysis,
planning, framework etc. Investigation of land and nearer area of building are indispensable for selling,
margin, profit and a lot more. So, analysis is must for project benefits. On the other hand, planning is
parallelly on-going. In that step a specific body takes permission from governance with appropriate FSI,
margin, floor area, total built-up area and a lot more documentation.
Pre-Construction Steps:
                Pre-construction steps are those which are happens before initiation of construction
process. The profit, sells, costing, margin and a lot more things are depends on this pre construction steps.
Below are pre-construction steps.
      1.   To Acquire Land or Plot.
      2.   Technical Help.
      3.   Prepare Estimation and Budgets.
      4.   Permission from Authorities.
      5.   Approach a builder.
      Once everything is done, building construction steps are beginning. Like first when we got a land
we clean that land, excavation on that land, then construction etc. steps are there all the steps are included
bellow.
      1. Site preparation or Levelling work
      2. Excavation and PCC
      3. Foundation
      4. Plinth beam or Slab
      5. Superstructure – column
      6. Brick Masonry Work
      7. The lintel Over Door Window Gaps
      8. Floor Slab or Roof Structure
      9. Door Window Framing and Fixations
      10. Electrical and Plumbing
      11. Terrace and Roof Finishing
      12. Internal and Exterior Finishes
      13. Woodwork and Fixture Fittings
      14. Waterproofing and Painting Work
          The roles of civil engineering is mainly depends on the field. Like structural, surveying, construction,
estimation, valuation, billing, and a lot other fields has different roles and responsibilities for civil engineering
on and off site.
          In construction, there are a lot of different positions for civil engineer on site and off site like surveyor,
estimator, site engineer, site supervisor, chief engineer, project manager, billing engineer and safety engineer.
These are the posts for civil engineer in different work. Every different role has different duties and
responsibilities.
          On the site, where I was doing internship, 2 engineers, one from owner and another from contractor.
There were 2 supervisors from owner and contractor. Also one billing engineer was there.
 1. Interpretation of drawing
 2. Preparation of bar bending schedule
 3. Allotting work to labours
 4. Supervision of construction work
 5. Plotting line
 6. Preparing work schedule
 7. Checking of steel work- beam, slab, column, etc.
 8. Checking shuttering and formwork
 9. Checking equipment
 10. Supervision of curing and oiling
 11. To keep record of every work
 12. Find quantity to order
 13. Safety of labours
 14. Testing of materials
 15. Environment
INTRODUCTION OF DRAWINGS :
       Drawings are very crucial for any construction work. It is required from the beginning of every
construction work. There are different types of drawings and every drawings has its own uses and
purpose. Every drawings has detailed measurement and section. For every different step of construction
needs different drawings. Different types of drawings are listed below.
      6. Architectural drawings
      7. Structural drawings
      8. Electrical drawings
      9. Plumbing drawing
1. Architectural Drawing
     A sketch, diagram, plan, or any design of construction work or a component of building are develop
by architecture engineer known as architectural drawing. These are made of lines, projections and based
on scale. The type of architectural drawings are given below.
      1. Site plan
      2. Floor plan
      3. Working drawing
      4. Section drawing
      5. Elevation drawings
2. Structural Drawings
     The drawings which provide information and details about structure like strength of different
structural elements, structural material, grade, size and placement of reinforcement, and how beams,
column and slabs are connected. The different types of drawings are given below.
CONCRETE COMPONENT:
Concrete is made out of six components, cement, fine aggregates, course aggregate, water, air,
admixtures. Every component is equally important. The quantity of material is as per the grade of
concrete like M20, M25 etc. there is fix ratio of cement sand and aggregate.
METHODS OF MIXING:
       There are different ways to mix materials of concrete. There are three types of methods which can
use for concrete mixing listed as below.
   3.1.1 Hand Mixing of Concrete (Mixing concrete manually without a mixer machine)
   3.1.2 Machine Mixing of Concrete (Mixing concrete with a mixer machine)
   3.1.3 Ready Mix Concrete (Mixing in automatic or semi-automatic batching plant)
Machine Mixing:
       Machine mixing is the process of mixing the ingredients of the concrete with a concrete mixer
machine. It highly effective fulfilling the demands of short mixing time, optimum consistency and
homogeneous quality of concrete.
        There are certain factors which would be affected by selection of mixing. Selection of mixing Is
directly connected with cost and time. Selection of machine is depended on size of construction area and
requirement. If concreting work is less then we can go for hand mixing. Hand mixing is not that much
accurate but still work for small construction work.
Process of Mixing:
    •     First of all, wet the inner surfaces of the drum of concrete mixer.
    •     Coarse aggregates are placed in the mixer first followed by sand and then cement. Mix the
          materials in the dry state in the mixing machine. Normally it should be 1.5 to 3 minutes.
    •     After proper mixing of dry materials, gradually add the correct quantity of water while the
          machine is in motion. Do not add more water than required. It is not advisable as it reduces
          strength.
    •     After adding the water, you must mix concrete for a minimum of two minutes in the drum.
• If there is any segregation of concrete after unloading from the mixer, then remix the concrete.
RMC:
        RMC stands for ready mix concrete. It is very convenient to use because everything is prepared
and we just need to laying it on component. It’s very convenient to use and very accurate mixing is there.
Fig.:-RMC
GRADE OF CONCRETE:
         There is different grade of concrete mix design. Generally M20 used for footing.
And other portion are filled with M25.
CHECKING OF CONCRETING:
    •    Segregation
    •    Bleeding
    •    Water Cement Ratio
    •    Workability
    •    Admixture
    •    Curing
DEFINE SLUMP:
 It can also use indicator of an improper water cement ratio and mixed batch.
    • The cone shall be removed at the base and shall be lifted carefully vertically without disturbing
      concrete mass.
2. SHEAR SLUMP: if the one half of the cone slides down it is called shear slump.
3. COLLAPSED SLUMP: in this case fresh concrete collapsed completely is known as collapsed slump.
4. ZERO SLUMP: if the concrete maintains the actual shape of the mould is called zero slump
The compressive strength of the concrete cube test provides an idea about all the
characteristics of concrete. By this single test one judge that whether Concreting has been
done properly or not.
• Each layers compacted by 35 nos. of strokes with tamping rod 16 mm dia. And 600 mm long.
• And after 7, 14 and 28 days cube test is doing through machine and note reading.
CURING:
Curing is the process of maintaining satisfactory temperature and moisture conditions in concrete long
enough for hydration to develop the desired concrete properties. The potential strength and durability
of concrete will be fully developed only if concrete is properly cured.
                         To prevent the concrete from drying out prematurely due to solar radiation
                          and wind. This prevents plastic shrinkage of concrete.
                         Curing helps the concrete to harden and bond with internal materials and
                          reinforcement. This helps to prevent damage to the bond between concrete
                          and reinforcement due to vibration and impact.
Ponding method
Honey Comb Also Known As Air Pocket. It is also nothing but air voids in concrete, usually formed
during concrete casting
CAUSES OF HONEYCOMBING
It is defined as a material other the basis ingredients of concrete cement, aggregate and water added to the
concrete mix immediately before mixing to modify some properties of concrete in the fresh concrete.
3.10.4 Durability
1. Plastisizer
2. Super plastisizer
3. Retarder
FIG.ADMIXURE
1. Primary beam :
2. Secondary beam :
                                            • Formwork is a temporary
                                              structure which is used to
                                              mold the concrete in
                                              different structural shapes
                                              such as beam, column and
                                              slab.
JECK FORMWORK
  • It should be strong enough to withstand all types of dead and live loads.
  • It should be rigidly constructed and efficiently propped and braced both horizontally and
      vertically, so as to retain its shape.
  • The joints in the formwork should be tight against leakage of cement grout.
  • Construction of formwork should permit removal of various parts in desired sequences without
      damage to the concrete.
  • The material of the formwork should be cheap, easily available and should be suitable for reuse.
  • The formwork should be set accurately to the desired line and levels should have plane surface.
  • It should be as light as possible.
  • The material of the formwork should not warp or get distorted when exposed to the elements.
  • It should rest on firm base.
DRAWINGS:
There are different types of drawings. Drawings related to steel work is made by structural engineer.
Some of the drawings which shows details about steel work are mentioned below.
   •    Column Schedule
   •    Column Ring Schedule
   •    Typical Sections
   •    Footing Schedule
   •    Beam And Column Details
        There are other drawings as well for steel structure. But these are drawings which used In
construction of residential building. There are more then one drawings of single drawings. For example,
column schedule would be different from basement and floors.
Information of Drawings:
        Every different drawing contains different information. Steel drawings has information like,
   •    Dimeter Of Bar
   •    Spacing Between Two Bars
   •    Column Size
   •    Column Steel
   •    Reference Section
   •    Indicate Diameter of Bar
   •    Ring Size and Details
   •    Stirrups Size
   •    Bottom Bars (Straight, Bent Ups)
   •    Beam Ring (Left Support, Middle Support, Right Support)
   •    Side Face Bars
   •    C/C Spacing
   •    Remark
        With the help of above details steel foreman made steel work for different component like column,
beam, ramp, slab, and stair-case. Sometime bar bending schedule is not given so we have to make that for
work.
Concrete is weak in tension and strong in compression. Plain concrete structures will fail by crushing of
concrete which happens suddenly without any prior deflections and cracks when subjected to tension or
flexure. This type of failure is called brittle failure. To carry tension, steel is required in every component
of building.
The steel bind with binding wire according to the steel drawings given by structural engineer.
There are different tools which used in steel work are listed below.
BANDING MACHINE:
This machine bends bars with proper angels and there is another machine which cut the bars.
Bar threading machines are used to cut threaded ends into bars or tubes, so they can be screwed together.
       Once steel work is done, checking is must. Below is list which things we have to check as an
engineer on site.
• Height Of Pardi
• Tight Coupling
• Ring Sizes
• Proper Lapping
                                • Concrete: M20
                                • Steel :Fe 415
                                                                        COLUMN
                                                                        MAIN BAR
                                                                        16MM TMT
                                                                        BAR
COLUMN MAIN
BAR
16MM TMT BAR
                                                                         TOP   EXTRA
                                                                         BAR
                                                                         12mm
FORMWORK
                                                                        8mm @200
                                                                        mmc/c
                                                                        angle   of
                                                                        hook
                                                                        bending is
                                                                        135o
                                                                         TOP BEAM
                                                                         BAR
                                                                         16MM
                                                                         8mm @100
                                                                         mmc/c
                                                                         angle    of
                                                                         hook
                                                                         bending is
                                                                         135o
                                    • Concrete: M25
                                    • Steel :Fe 500
   FORMWORK
                                     SIDE EXTRA BAR
                                                                         BOTTOM     BEAM     BAR
                                     16 MM
                                                                         16MM
                      • Concrete: M25
                      • Steel :Fe 500 TMT bar
                      • 4 – legged stirupes used
KENDA MEPI
LAPPING BAR:
• Panels are designed in such way that it is possible to form different sizes of the column.
• These panel are light weight, easy to carry, easy to assemble and easy to remove.
  • The design of attachment consist different type of clamps, Waller, clips etc. to make the panel
    joint robust.
• These advance system of formwork will decrease the total time took for erection.
COLUMN SHUTTERING
          A steel bar placed in between the two layers of the main reinforcement in the beam is
           called a spacer bar.
   Longer span :
   T10@150c/c ALT bent up
   Shorter span :
   T10@100c/c ALT bent up
SHUTTERING
  • Then above wooden girder, GI runner and weller are placed properly and bind with
    binding wire.
• After then 12mm plywood sheet place and fix and check level with auto level machine.
         Chair reinforcement or simply chair rods are small structural elements that are used to place the
          reinforcement bars in the correct position and maintains the correct space between the top and
          bottom reinforcements.
         Chair bars are used primarily on the slab and flooring. The diameter of the chair bar should not
          be less than 12 mm.
FIG. CHAIR
1. Maintain the required spacing between the top and bottom reinforcement cage in footings, slabs,
raft foundations, etc.
3. To protect the upper and lower cages from displacement and sagging during concreting due to movement
of trolleys, walking of workers, dead load of new concrete etc.
5. To increase the tension property of concrete. This helps to prevent structural collapse due to failure in
the tension zone.
  • Plastering is the process of covering rough walls and surfaces in structure with cement mortar is
    called plaster.
  • The ratio of plaster is 1:4 (cement sand)
  • The thickness of internal plaster is 10 mm.
  • Curing of plaster is doing up to 7 days.
  • It is measure in sq. ft.
  • A coupler is a threaded device for joining reinforced bar and transfer the load one bar to other
    bar.
• And we provide coupler at where the dia. Of bar is 20mm, 25mm, 32mm.
 •   There were learning sessions for interns about the basic application of bookish knowledge to
     real projects.
 •   By visiting the site, we were able to know about the practical aspects of structural
     planning,         orientation of column, reinforcement detailing drawing and its
     importance.
• https://youtube.com/playlist?list=PL81CACWn0dIarhZOBWqU55WY0UeZmqwEM
• https://youtube.com/playlist?list=PL5DYIL_VeL0ttam-x-btg7qaccL5V0vEA