The document provides a detailed estimate for the construction of a two-storied residential building with a total plinth area of 157.23 Sqm, owned by Md. Hamidul Islam. The total estimated cost for the project is 71,87,595 Taka, which includes land value and construction costs for both the ground and first floors. The ground floor costs 42,25,595 Taka and the first floor costs 29,62,000 Taka.

Uploaded by

sazzad076464
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
30 views3 pages

Hamidul Islam

The document provides a detailed estimate for the construction of a two-storied residential building with a total plinth area of 157.23 Sqm, owned by Md. Hamidul Islam. The total estimated cost for the project is 71,87,595 Taka, which includes land value and construction costs for both the ground and first floors. The ground floor costs 42,25,595 Taka and the first floor costs 29,62,000 Taka.

Uploaded by

sazzad076464
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 3

ESTIMATE

Detailled Estimated for construction of -02(Two) Storied Residential Building 157.23 Sqm.

Name of the owner,s: Md. Hamidul Islam. S/o: Late. Wajed Ali Sarkar, P.S: Rayganj,
Dist.- Sirajganj.

J.L No. 191, Plot No .R.S-1939, Kh, No. R.S-98, Mouza : Nolka Sengati,
Thana: Rayganj, District: Sirajganj .
There is a proposed 02 storied Residential building on the plot ,plinth area=157.23 Sqm.

Value of land:

14.0 Decimal X5,00,000/-=70,00,000/-


SUMMARY :

For land =70,00,000/-

Ground Floor Cost = 42,25,595.00 /-


1st Floor Cost = 29,62,000.00/-
= 71,87,595.00/-

In word :(Seventy One Lac Eighty Seven Thousand Five Hundred Ninety Five Taka Only)
ESTIMATE FOR GROUND FLOOR

Item No .01 Earth work in Excavation =250.00 Cum @ Tk. 120/- Cum =30,000.00 /-
Item No .02 Lean Cement Concrete =30.00 Cum @ Tk. 3250/- = 97,500.00 /-
work
Item No .03 Sand Filing at Foundation =950.00 Cum @ Tk. 120/- = 1,14,000.00 /-
& Floor
Item No .04 Brick work & Sub =45.00 Cum @ Tk.2358/- = 1,06,110.00 /-
structure
Item No .05 Brick work & Super =500.00 Sqm @ Tk.850/- = 4,25,000.00 /-
structure
Item No .06 Reinforcement Cement =65.00 Cum @ Tk. 6,687/- =4,34,655.00 /-
Concrete work
Item No .07 Reinforcement work =15.00 Ton @ Tk 73,000/- = 10,95,000.00 /-
R.C.C
Item No .08 Non Glazed Ceramic Tiles =190.00 Sqm @ Tk.2000/- =3,80,000.00 /-
Works at Floor
Item No .09 Grill Work =90.00 Sqm @ Tk.2537/- = 2,28,330.00 /-
Item No .10 Thai work for window =50.00 Sqm @ Tk.3000/- = 150,000.00 /-
Item No .11 Wood work for Door =30.00 Cum @ Tk. 8000/- =2,40,000.00 /-
Item No .12 Plastering work =1000.00 Sqm @ Tk.225/- = 2,25,000.00 /-
Item No .13 Colour wash =1000.00 Sqm @ Tk.300/- = 3,00,000.00 /-
Item No .14 Electrical Works = L.S. =1,50,000.00 /-
Item No .15 Sanitary = L.S. = 1,50,000.00 /-
Item No .16 Septic tank = L.S. = 50,000.00 /-
Item No .17 Sock well = L.S. = 50,000.00 /-
Total = 42,25,595.00 /-
In word :(Fourty Two Lac Twenty Five Thousand Five hundred Ninety Five Taka Only)
ESTIMATE FOR 1st Floor

Item No .01 Brick work & Super structure =300.00 Sqm = 3,00,000.00/-
@Tk.1000/-
Item No .02 Reinforcement Cement =60.00 Cum @Tk.7000/- = 4,20,000.00/-
Concrete work
Item No .03 Reinforcement work =9.00 Ton @Tk.73,000/- = 6,57,000.00/-
Item No .04 Non Glazed Ceramic Tiles =125.00 Sqm = 2,50,000.00/-
Works at Floor @Tk.2000/-
Item No .05 Grill Work =100.00 Sqm = 3,00,000.00/-
@Tk.3000/-
Item No .06 Plastering work =600.00 Sqm @Tk.225/- =1,35,000.00/-
Item No .07 Colour wash =600.00 Sqm @Tk.300/- = 1,80,000.00/-
Item No .08 Sanitary = L.S. = 1,00,000.00/-
Item No .09 Thai work =40.00 Sqm @Tk.3000/- = 1,20,000.00/-
Item No .10 Labour Cost for Civil work =L.S. = 1,50,000.00/-
Item No .11 Electrical Works = L.S. = 1,50,000.00/-
Item No .12 Wooden Cowkat &Shatter =1.00 Cum = 80,000.00/-
@Tk.80,000/-
Item No .13 Painting & Varnishing = L.S. = 90,000.00/-
Item No .14 Collapsible Gate Works =10.00 Sqm @Tk.3000/- = 30,000.00/-
Total = 29,62,000.00/-

.In word :(Twenty Nine Lac Sixty Two Thousand Taka Only)