NAME OF THE DOCUMENT: Hira for Night work
INSTAKART SERVICES
PRIVATE LIMITED DOCUMENT NO: PACE-HTEI-HIRA-007
PO ORDER: 2414569783
PROJECT NAME: KALASH, NCR BIGBOX
PROJECT LOCATION: PATLI, HAJIPUR, GURGAON
DOCUMENT SUBMISSION STATUS
☐FIRST SUBMISSION
☐ RESUBMISSION WITH INCORPORATED COMMENTS
DOCUMENT CATEGORY
☐ REVIEW
☐ INFORMATION
PREPARED BY CHECKED/REVIEWED BY APPROVED BY
Name: Mr. Sampath Kumar M Name: Mr. Shinu S Name: Mr. Rajeev Chopra
REV NO: ISSUE DATE: Designation: EHS Designation: EHS - Manager Designation: Project Manager
Date: 11/3/2025 Date: 11/3/2025 Date: 11/3/2025
SIGNATURE: SIGNATURE: SIGNATURE:
DOCUMENT REVIEW STATUS
(INSTAKART SERVICES PVT LTD)
☐ APPROVED
☐ APPROVED WITH COMMENTS. WORK MAY PROCEED SUBJECT TO COMPLIANCE WITH COMMENTS.
☐ REJECTED, REVISE AND RESUBMIT
☐ RETAINED FOR INFORMATION
DATE REVIEWED BY
NAME:
SIGNATURE:
HZARAD IDENTIFICATION AND RISK ASSESMENT
Name of the Project:KALASH, NCR- BIGBOX Risk Assessment Team: Mr. Rajeev Shopra Mr. Sampath Kumar M
Name of the Activity: Night work Document No: PACE-HTEI-HIRA-007
Rev: 00
GENERAL REQUIREMENTS:
֍ Night Work permit shall be taken before commencing activity
֍ Hazard & Control Measures clearly communicated to all personnel/ TBT conducted.
֍ If any inciend or accidend occures, it will informd to EPR team.
֍ Round the clock diligent supervision at all times.
֍ Shall provide adequate shelter/rest facility and drinking water supply nearer to the work location.
֍All physical inspection need to be done before used with checklist.
֍All mechine TPI need to be done before use.
Sr No Steps to be performed during Risk Level Residual Risk
erection of task Additional Control Measures
Hazard Risk Present Control Measures
(if residual risk rating is beyond acceptable level)
Likelihood Consequences Risk rating Likelihood Consequences Risk rating
1. Pre medical of all employee medical examination
2. Safety induction to all.
1. Poor health condition
3. Job oriented training.
2. lack of rquired 1. Personal 1. Competency assessment during employment.
4. Mandatory and job specific PPEs.
1 Manpower moblization in yard skill/comptency Injuries 2 3 6 3 1 3 2. Periodical health checkup of employees.
5. Trained person is only doing their job.
3. Unauthorized person.
6. Ensure the id card is with night workers, do not allow those with
out an id card.
1. Night work TBT conducted at before start the work.
1. Work will be done labours shifit timings.
2. arrange water and emergncy contect number know details all
workers
3. Adequate illumination has been ensured in case of night work.Lux
level 250 to 350.
4. Adequate illumination has been ensured in the worker access
area.
5. Ensure the continuous supervision at site.
6. Mandatory and job specific PPEs.
7. Ensure the drining water and rest sheet and toilet for the night
1. Personal Injury. workers. 1. Ensure that the firstaider and emeregncy vehicles are
1. Electrocuted.
2.Damage of floor 8. Ensure the the operator & worker does not drink and drive. available on the night shift.
2. Toppling of Material
and objects 9. Ensure that an Unauthorized person driving is not driving the 2. After the work is completed, check that all the
2 Night work 3. slip & trip 3 4 12 3 1 3
3.Fatality. vehicle. workers go outside.
4. falling hazard
10. Ensure one hour of rest time for night workers. 3. Ensure the night work permit available at site.
5. Poor illumination
11. Ensure that workers do not work on the roof at night.
12. Ensure the electrical cable is lying over heated lines.
13. Ensure that the worker is not sleeping in the work area.
14. Only experienced trained authorized persons will be carried out
the night work.
15. Ensure that the elctrician is available on site for night work.
1. Proper PPES should be wear.
2. Ensure the electrical cables or not laying in ground floor.
1. slip & trip. 1. Personal
3. Adequate illumination has been ensured in case of night work.Lux 1. All scarp materials is segregated and store in the
3 Housekeeping 2. Electrocuted. Injuries 3 2 6 2 1 2
level 150 to 200. designated area.
3. Poor illumination 2. Electrocation.
3. All scrap materials are segregated and dumped in the dustbin.