Commissioning Activities Commissioning: Mechanical Running Test Check Sheet - Steam Turbine (1 of 2)

The document outlines the commissioning activities for a steam turbine, detailing a mechanical running test check sheet and a solo run test record. It includes a checklist of precommissioning tasks, functional checks, and operational tests, with results recorded for each item. The document serves as a formal record of the commissioning process for the steam turbine system U37-P03.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
18 views4 pages

Commissioning Activities Commissioning: Mechanical Running Test Check Sheet - Steam Turbine (1 of 2)

The document outlines the commissioning activities for a steam turbine, detailing a mechanical running test check sheet and a solo run test record. It includes a checklist of precommissioning tasks, functional checks, and operational tests, with results recorded for each item. The document serves as a formal record of the commissioning process for the steam turbine system U37-P03.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 4

TK0000263120

STATE COMPANY
FOR OIL PROJECT COMMISSIONING ACTIVITIES
COMMISSIONING
MECHANICAL RUNNING TEST CHECK
SHEET - STEAM TURBINE(1 OF 2)
System No. U37-P03 Sub-System No. U37-P03-101
Sub-System Description PGU STG A
Item No. 37-STG-001A Task No. 37-STG-001A-CM-0001-13

NO CHECK LIST RESULT

1 Precommissioning tasks completed. YES □ NO □ N/A □

2 Commissioning functional checks completed. YES □ NO □ N/A □

3 Driver running tests completed. YES □ NO □ N/A □

4 Alignment verified. YES □ NO □ N/A □

5 Oil levels checked. YES □ NO □ N/A □

6 Cooling water system running. YES □ NO □ N/A □

7 Requierd overrides installed. YES □ NO □ N/A □


Inlet strainer with the fine mesh and PGs on
8 YES □ NO □ N/A □
suction/discharge
9 YES □
Check the removing the fine mesh after verification of cleanliness NO □ N/A □

10 Circuits and safety devices lined-up. YES □ NO □ N/A □

11 Job safety analysis reviewed. YES □ NO □ N/A □


Check that lube oil system or lube oil circuit from oil mist
12 YES □ NO □ N/A □
generator flushed.
13 Check that the lube oil level in lube oil reservoir. YES □ NO □ N/A □

Check bearings and bearing housings for cleanliness. If


14 YES □ NO □ N/A □
applicable, check that bearing lubricating rings have
Check that the entire lube oil system has been properly
15 YES □ NO □ N/A □
flushed and is clean.
16 Check that the lube oil system put in service. YES □ NO □ N/A □

17 Check the opening of governor valve. YES □ NO □ N/A □

18 Check that steam supply & exhaust valve closed. YES □ NO □ N/A □

19 Check that the turbine casing warmed up. YES □ NO □ N/A □


Check that all steam trap correctly installed serviced
20 YES □ NO □ N/A □
based on P&ID
21 YES □
Speed tachometer function checked by opening by-pass valve. NO □ N/A □

22 Check cooling water serviced. YES □ NO □ N/A □

Form No.: ITRF-CM-0001-13


TK0000263120

STATE COMPANY
FOR OIL PROJECT COMMISSIONING ACTIVITIES
COMMISSIONING
MECHANICAL RUNNING TEST CHECK
SHEET - STEAM TURBINE(2 OF 2)
System No. U37-P03 Sub-System No. U37-P03-101
Sub-System Description PGU STG A
Item No. 37-STG-001A Task No. 37-STG-001A-CM-0001-13

NO CHECK LIST RESULT

23 Check steam leaking at valve stem, flange & coupling. YES □ NO □ N/A □

24 Check the barring condition. YES □ NO □ N/A □

25 Check the manual trip valve opration properly. YES □ NO □ N/A □

Depending on the type, check that the governor


26 YES □ NO □ N/A □
contains oil up to the correct level.

27 Check the governor set position at zero speed. YES □ NO □ N/A □

Check the speed indicator at zero rpm, if electronic


28 YES □ NO □ N/A □
speed indicator is provided.

29 Check the steam turbine is properly preheated YES □ NO □ N/A □

REMARKS

Form No.: ITRF-CM-0001-13


TK0000263120

COMMISSIONING ACTIVITIES
COMMISSIONING
STEAM TURBINE SOLO RUN TEST RECORD ( 1 of 2)
System No. : Sub-System No. :
U37-P03 U37-P03-101

Sub-system Description : PGU STG A

Package No. : Task No. :


37-STG-001A 37-STG-001A-CM-0001-13

TEST ITEM Unit Design Value Test Record Reamark

Min. speed rpm


Governor
changeable
speed range check
Max. speed rpm

Electrical overspeed trip test rpm

Noise Level Check dB

Mechanicl Trip Test Result (Pass/Fail)

No load running test Refer to the next sheet

Overall Test Result (Pass/Fail)

Remark

CONTRACTOR (COMMISSIONING) EMPLOYER

Name

Position

Signature

Date
TK0000263120

COMMISSIONING ACTIVITIES
COMMISSIONING
STEAM TURBINE SOLO RUN TEST RECORD ( 2 of 2)
System No. : Sub-System No. :
U37-P03 U37-P03-101

Sub-system Description : PGU STG A

Package No. : Task No. :


37-STG-001A 37-STG-001A-CM-0001-13
Instrument DESIGN &
No load running test
TAG.NO. CRITERIA TIME
Turbine Speed rpm

Inlet Steam kg/cm2g

Exhaust Steam kg/cm2g


Pressure

Gland leak Steam kg/cm2g

Sealing Steam kg/cm2g

Control Oil Supply kg/cm2g

Lube Oil Supply kg/cm2g

Inlet Steam °C

Exhaust Steam °C

DE °C
Bearing
Temperature
Temperature

NDE °C

Inlet °C
L/O SUPPLY
Oulet °C

GLAND Inlet °C
CONDENSER
C/W INLET Oulet °C

Ambient °C

V µm
DRIVE
H µm
SIDE
Vibration

A µm

V µm
NON
DRIVE H µm
SIDE
A µm

CONTRACTOR (COMMISSIONING) EMPLOYER

Name

Position

Signature

Date