TK0000263120
STATE COMPANY
   FOR OIL PROJECT          COMMISSIONING ACTIVITIES
                                     COMMISSIONING
                        MECHANICAL RUNNING TEST CHECK
                         SHEET - STEAM TURBINE(1 OF 2)
 System No.            U37-P03                     Sub-System No.               U37-P03-101
 Sub-System Description                                    PGU STG A
 Item No.              37-STG-001A                 Task No.                37-STG-001A-CM-0001-13
  NO                              CHECK LIST                                        RESULT
   1        Precommissioning tasks completed.                               YES □   NO □     N/A □
   2        Commissioning functional checks completed.                      YES □   NO □     N/A □
   3        Driver running tests completed.                                 YES □   NO □     N/A □
   4        Alignment verified.                                             YES □   NO □     N/A □
   5        Oil levels checked.                                             YES □   NO □     N/A □
   6        Cooling water system running.                                   YES □   NO □     N/A □
   7        Requierd overrides installed.                                   YES □   NO □     N/A □
            Inlet strainer with the fine mesh and PGs on
   8                                                                        YES □   NO □     N/A □
            suction/discharge
   9                                                                      YES □
            Check the removing the fine mesh after verification of cleanliness      NO □     N/A □
  10        Circuits and safety devices lined-up.                           YES □   NO □     N/A □
  11        Job safety analysis reviewed.                                   YES □   NO □     N/A □
            Check that lube oil system or lube oil circuit from oil mist
  12                                                                        YES □   NO □     N/A □
            generator flushed.
  13        Check that the lube oil level in lube oil reservoir.            YES □   NO □     N/A □
            Check bearings and bearing housings for cleanliness. If
  14                                                                        YES □   NO □     N/A □
            applicable, check that bearing lubricating rings have
            Check that the entire lube oil system has been properly
  15                                                                        YES □   NO □     N/A □
            flushed and is clean.
  16        Check that the lube oil system put in service.                  YES □   NO □     N/A □
  17        Check the opening of governor valve.                            YES □   NO □     N/A □
  18        Check that steam supply & exhaust valve closed.                 YES □   NO □     N/A □
  19        Check that the turbine casing warmed up.                 YES □          NO □     N/A □
            Check that all steam trap correctly installed serviced
  20                                                                 YES □          NO □     N/A □
            based on P&ID
  21                                                                 YES □
            Speed tachometer function checked by opening by-pass valve.             NO □     N/A □
  22        Check cooling water serviced.                                   YES □   NO □     N/A □
Form No.: ITRF-CM-0001-13
                                                                        TK0000263120
   STATE COMPANY
   FOR OIL PROJECT          COMMISSIONING ACTIVITIES
                                    COMMISSIONING
                       MECHANICAL RUNNING TEST CHECK
                        SHEET - STEAM TURBINE(2 OF 2)
 System No.           U37-P03                   Sub-System No.           U37-P03-101
 Sub-System Description                             PGU STG A
 Item No.             37-STG-001A               Task No.            37-STG-001A-CM-0001-13
  NO                            CHECK LIST                                   RESULT
  23        Check steam leaking at valve stem, flange & coupling.    YES □   NO □     N/A □
  24        Check the barring condition.                             YES □   NO □     N/A □
  25        Check the manual trip valve opration properly.           YES □   NO □     N/A □
            Depending on the type, check that the governor
  26                                                                 YES □   NO □     N/A □
            contains oil up to the correct level.
  27        Check the governor set position at zero speed.           YES □   NO □     N/A □
            Check the speed indicator at zero rpm, if electronic
  28                                                                 YES □   NO □     N/A □
            speed indicator is provided.
  29        Check the steam turbine is properly preheated            YES □   NO □     N/A □
    REMARKS
Form No.: ITRF-CM-0001-13
                                                                                                       TK0000263120
                                  COMMISSIONING ACTIVITIES
                                       COMMISSIONING
                          STEAM TURBINE SOLO RUN TEST RECORD ( 1 of 2)
System No. :                                                   Sub-System No. :
                                          U37-P03                                                  U37-P03-101
Sub-system Description :                                                PGU STG A
Package No. :                                                 Task No. :
                                         37-STG-001A                                          37-STG-001A-CM-0001-13
                TEST ITEM                           Unit     Design Value           Test Record           Reamark
                            Min. speed              rpm
     Governor
    changeable
 speed range check
                            Max. speed              rpm
Electrical overspeed trip test                      rpm
Noise Level Check                                   dB
Mechanicl Trip Test Result (Pass/Fail)
No load running test                          Refer to the next sheet
Overall Test Result (Pass/Fail)
Remark
                       CONTRACTOR (COMMISSIONING)                                        EMPLOYER
  Name
 Position
Signature
   Date
                                                                                                            TK0000263120
                                                   COMMISSIONING ACTIVITIES
                                                        COMMISSIONING
                                           STEAM TURBINE SOLO RUN TEST RECORD ( 2 of 2)
System No. :                                                                Sub-System No. :
                                                        U37-P03                                         U37-P03-101
Sub-system Description :                                                         PGU STG A
Package No. :                                                               Task No. :
                                                       37-STG-001A                                 37-STG-001A-CM-0001-13
                                        Instrument   DESIGN &
No load running test
                                         TAG.NO.     CRITERIA TIME
               Turbine Speed                                         rpm
                    Inlet Steam                                   kg/cm2g
                  Exhaust Steam                                   kg/cm2g
 Pressure
                 Gland leak Steam                                 kg/cm2g
                  Sealing Steam                                   kg/cm2g
                 Control Oil Supply                               kg/cm2g
                  Lube Oil Supply                                 kg/cm2g
                    Inlet Steam                                      °C
                  Exhaust Steam                                      °C
                                  DE                                 °C
                  Bearing
                Temperature
 Temperature
                               NDE                                   °C
                               Inlet                                 °C
                L/O SUPPLY
                               Oulet                                 °C
                  GLAND    Inlet                                     °C
                CONDENSER
                 C/W INLET Oulet                                     °C
                     Ambient                                         °C
                                  V                                  µm
                   DRIVE
                                  H                                  µm
                    SIDE
 Vibration
                                  A                                  µm
                                  V                                  µm
                    NON
                   DRIVE          H                                  µm
                    SIDE
                                  A                                  µm
                                       CONTRACTOR (COMMISSIONING)                              EMPLOYER
       Name
 Position
Signature
           Date