This document outlines the method statement for the installation of electrical conduits and boxes at the Trimetro Garments Factory in Odisha, executed by Blue Star Ltd. It details the purpose, scope, required materials, installation procedures, safety controls, and inspection/testing protocols to ensure compliance with project specifications and safety standards. The document emphasizes the importance of proper installation techniques, safety measures, and adherence to approved drawings and regulations.

Uploaded by

dibyendu3384
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
57 views16 pages

WMS - Conduit

This document outlines the method statement for the installation of electrical conduits and boxes at the Trimetro Garments Factory in Odisha, executed by Blue Star Ltd. It details the purpose, scope, required materials, installation procedures, safety controls, and inspection/testing protocols to ensure compliance with project specifications and safety standards. The document emphasizes the importance of proper installation techniques, safety measures, and adherence to approved drawings and regulations.

Uploaded by

dibyendu3384
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 16

QA QC in Construction

METHOD STATEMENT FOR INSTALLATION OF ELECTRICAL CONDUIT AND BOXES

Project: Trimetro Garments Factory at Odisha


Executed By - Blue Star Ltd.

Customer (Employer)
Project Name Trimetro Garments Factory at Odisha
Service Consultant
Cost Consultant
PMC Collier
GC
Location Odisha
Current Scope
Type of Contract
Project Code
File name METHOD STATEMENT FOR INSTALLATION OF ELECTRICAL CONDUIT AND BOXES
Document number
Sr.No Key Point Description
1 Pourpose

The purpose of generating this method statement is to


define the procedure for Installation of
Electrical Conduit and boxes through guidelines
contained herein to ensure that the job execution
complies with the requirement where applicable in the
project
2 Scope

This method statement covers all processes related to


installation of the mentioned system as per project
specification, manufacturer recommendation,
approved drawings. Civil defense approval and
regulation. The manpower and time scale required
depends on the number of conduits and boxes which
will be install.
3 Reference
a Project specifications
b Panel schedule
c Approved Shop drawings
d Material submittal
e Single line diagram (SLD)
f Project Quality plan
g Project HSE Plan
h Civil Defense Approval
i Programme Minimum H&S Construction Standard
j Health & Safety Plan
k Emergency Response Plan (ERP)
l LOTO Procedure
m Rescue Plan

The Following tools shall be arranged before


4 Material And Equipments starting the job. All Materials are as per
specifications and approved material submittal
a Mini Hacksaw Frame with Blades
b Choke Lime Powder with sufficient length of Thread
c Measuring Tape
d End Cutter
e Ladder/Scaffolding
f Manual Auger Bit
g .Hammer
h Hacksaw/Jigsaw M/C
i Centre punch
j Wooden hammer
k Electrical drill (only for surface installation works)
l Diagonal- cutter pliers
m Shank screwdriver
n Drill M/C portable hand tools
o Portable drill M/C grinding M/C
p Spirit level & water level
q Step ladder
fluorescent vest, and safety gloves to ensure maximum ability of safe work and dust
mask when require.

Procedure
5 INSTALLATION OF MS, PVC, HEAVY GAUGE PVC AND FLEXIBLE EPVC CONDUIT
( OPEN CONDUITING)

Survey and mark out the exact location of all boxes in


a ceiling or wall conduits follow all the
distances, height and marking given in the approved
layout & detail drawings.

Ensure that the work site locations have been released


b and ready for safe works execution
especially the wall surface where boxes and conduits
are to be installed

Rigid heavy duty PVC conduits shall be used for Lighting


c and power systems. Low current
systems, above false ceilings and embedded areas as
Per Project Specifications and approved
shop Drawings
Expansion ring. PVC boxes, adopters, male bushes,
d locking nuts shall be utilized as per
approved shop drawings
Expansion coupler shall be utilized at locations where
e PVC Conduits are crossing construction
expansion joints
Connect conduits terminating in switchgear, fuse
f boards, trunking, adaptable boxes or other non-
spouted enclosure with smooth bore male PVC bushing
and sockets
g Ensure that conduit connections are tight and fixed
rigid
h The outlets shall not run more than the permissible
numbers of conduits to any surface wall outlet
The exposed conduit work is to be installed so as not to
i interfere with ceiling inserts, lights or
ventilation ducts or outlets
j Use approved hot bent method to bend the PVC
conduit if conduit over 25 mm and below
k 25 diameters use cold bent by bending spring
l The conduits on walls are to be run neatly, horizontally
or vertically
Provide pulling wire (GI wire or equivalent strength
m cord) in each conduit. Secure the wire inside the box or
at end of conduits and covered.
Any changes in the routing of conduits shall be mark in
n the as built drawing & All installed conduits to be
protected until the next activity and final handover
6 INSTALLATION OF STEEL CONDUIT (RGS AND HEAVY GAUGE RIGID STEEL):

Survey and mark out the exact location of all boxes in


a ceiling or wall (Concealed) follow all the
distances, height and marking given in the approved
Shop Drawing and IFC drawing

After verifying the exact location and provided all the


b necessary mark out, start installing the
box by drilling in the concrete wall, column or ceiling
and fixed the box

c After completing the installation of the box, start fixing


the conduits. Conduit shall be securely
fastened in wall

Where a conduit is placed in a sheet metal enclosure or


d outlet boxes it shall be securely fixed
using Locknuts arrangement

Ensure that conduit threads are properly cut. Conduit


shall be cut using a saw or a roll cutter
e (pipe cutter). Care should be taken to ensure a straight
cut. After cutting end conduit fittings are to be cleand.
Cut end are to be reamed to remove burrns and shurp
edges
Thread less couplings and connector used with conduit
f shall be made tight. Where installed in
locations, they shall be the rain tight type. Thread less
or screw type coupling and connectors
shall not be used on threaded conduit ends unless
listed for the purpose.
Threads of plugs, junction boxes and other fittings shall
g be lightly lubricated with rust
preventive grease before assembly
Provide pulling wire (Gl wire or equivalent strength
h cord) in each conduit. Secure the wire
inside the box or at end of conduits and covered
i Remaining threads on galvanized steel conduits are to
be filled with touch up paint
j Any changes in the routing of conduits shall be mark in
the as built drawing

7 INSTALLATION OF EXPOSED CONDUITS (EMT, RGS HEAVY GAUGE & PVC


COATED)

Survey and mark out the exact location of all boxes in


a ceiling or wall (exposed conduits
installation). Follow all the distances, height and
marking as per approved shop drawing and
IFC's.
Exposed RGS conduits shall be installed in mechanical
b rooms and outdoor installation.
EMT conduits shall be used above false ceiling

Expansion arrangement shall be made for RGS & EMT


conduits when crossing expansion joints. Ensure that
c work site locations have been released and ready for
safe works execution especially the wall surface where
boxes and conduits are to be installed. (wall shall be
painted
minimum first coat of approved paint before installing
the boxes and conduits).

After verifying the exact location and provided all the


d necessary mark out, start installing the
box by drilling in the concrete wall, column, or ceiling
and fixed the box using anchor bolt ( Plastic & metal
anchore)

Electrical Metallic Tubing (EMT) shall be used for


e exposed fixings and above false ceiling
wherever applicable as per the project Specifications
and approved Shop drawings

f Rigid heavy gauge steel conduit is used for all exposed


installation such as mechanical,
electrical equipment rooms and all hazardous area
Ensure that the boxes are Inspected fort alignment,
g height, distances, flatness after fixing and bolts/screw
are securely fastened.
The conduits on walls are to be run neatly, horizontally
or vertically as may be required as per
the approved Shop drawings.

After installation of the boxes, fix conduits. Conduit


h shall be securely fastened in ceiling, or wall using
approved double hole clamp not exceeding the
distance specified in project
specifications

Where a conduit enters a box, fitting, or other


i enclosure, a bushing & locknut shall be provided
to protect the wire from abrasion unless the design of
the box, fitting, or enclosure is such as
to afford equivalent protection

The outlets do not run more than the permissible


j numbers of conduits to any surface wall
outlet. The exposed conduit work is to be installed so
as not to interfere with ceiling inserts, lights or
ventilation ducts or outlets

Thread less couplings and connector used with conduit


shall be made tight. Where installed in
k wet locations, they shall be the rain tight type. Thread
less or screw type couplings and
connectors shall not be used on threaded conduit ends
unless listed for the purpose. Ensure that conduit
connections are wrench tight.

Provide pulling wire (Gl wire or equivalent strength


cord) in each conduit. Secure the wire
inside the box or at end of conduits and covered.
l Channel erector system components (Unit
strut or similar) used to support conduits, cable trays,
enclosures, lighting fixtures and other
electrical equipment shall be made hot-dip galvanized
(preferably).
All field cuts unit-strut shall be touch up with approved
paint.
m Any changes in the routing of conduits shall be mark in
the as built drawing
8 INSTALLATION OF EMBEDDED CONDUIT IN SLAB AND WALLS (PVC, RGS):
PVC conduits in reinforced concrete structures are
generally to be installed after placing
a reinforcement and before concreting, using the steel
boxes and fittings such as coupling.
adapters with locknuts, and PVC solvent. Sizes of
conduits and boxes to be installed as per
approved shop drawings.

PVC Conduits shall only install embedded in concrete


b slab or block work, exposed PVC conduits works is not
permitted. Survey and marks out the exact location of
all boxes, conduits in the slab and walls.

Ensure the coupling of conduit and termination into


spouted fittings is to be made watertight
c and permanent using special cement.
Ensure bending of conduits is done using appropriate
methods without compensating the
internal diameter of conduits

For bending purpose only bending spring or PVC elbow


shall be utilized.
d Ensure the connect conduit terminating in switchgear,
fuse boards, trunking adaptable boxes
or other non-spouted enclosures etc. with smooth bore
male PVC bushes and sockets
e Ensure the semi-permanent adhesive use in joints
requiring expansion couplers
Ensure the ends of conduit and conduit fittings are to
f be cleaned and jointed using PVC cement
recommended by manufacturer.

All box unused opening shall be closed using masking


g or duct tape.
Provide pulling wire (GI wire or equivalent strength
cord) in each conduit. Secure the wire
inside the box or at end of conduits

All conduit stubs up are properly capped until wiring


h conductors are drawn in.
All installed conduits to be protected until the next
activity and final handover
i Any changes in the routing of conduits shall be mark in
the as built drawing
9 STANDARD PROCEDURES
a All equipment's connected to power supply must be
grounded
b All metal parts, structural steel, cable trays, piping,
reinforced concrete must be grounded
c All joints shall be according to shop drawing
10 SAFETY CONTROL
a A. Safety Rules during Conduits Installation Activities
b Personal Protective Equipment (PPE) required varying
type of works

Always check and inspect if the scaffolding, ladder used


c for fixing supports, boxes and
conduits are on safe condition and position before
starting the work activities

Be sure that all access for installation of fixing supports,


d boxes and conduits have no
obstruction at all times that may cause accident

e Safety sign board, barricades shall be erected to the


working areas if required.
f Ensure good housekeeping at all times, keep work area
clear from obstruction
g Traffic Management Arrangements, Access & Egress -
Security Measures shall be provided
11 Emergency Arrangements

General: Site general safety procedures will be


followed. In case of emergency the Safety
a Officer or the most senior employee present will stop
the work, and make the necessary
emergency arrangements and report to the assembly
points as described during Site Induction
Course.

Fire Precautions: No significant fire risks associated


b with this activity but general fire
precaution measures will be taken as per Client
instructions

Communication from site areas to Site Office via


mobile phones (Bravo) issued to all
c engineers. In emergency situations the users of mobile
phones (Bravo) to be notified if
deemed that this can speed up notification of relevant
personnel and/or the Project Site
Clinic.
12 INSPECTION AND TESTING PROCEDURES
Inspection, The conduit, boxes and fittings shall be
a given a visual inspection by the Engineer during the
installation

The Contractor should not allow any backfilling of


b trenches or pits where these systems are
installed before inspection by the Engineer and the
appropriate documents are signed
Material delivered shall be inspected under the
Engineer's supervisor about size, quality and

quantity.
c Shop-drawing approved.
• Material approved, Check installation (connection,
routing, and quantity) according to approved shop
drawings. Check dimension, level and finishing of
conduits, boxes and fittings.
Check installation according to approved shop
drawings and manufacturer's recommendation.

13 STATUTE OF COMPLETION:

After finishing the installation works of Grounding


a System, inspection shall be carried out and
approved by relative parties such as: Consultant,
Parson and civil defense.
b

Vendor Signature PMC Signature


uction
ELECTRICAL CONDUIT AND BOXES

Date: 23/12/2024
Location: Odisha

F ELECTRICAL CONDUIT AND BOXES

Remarks
Client Signature