0% found this document useful (0 votes)
16 views12 pages

Kitek

The document provides detailed measurements of Kitec pipes for the Rajapushpa Imperia project, listing various types of pipes and their lengths for multiple flats. It includes measurements for hot, cold, and flushing lines, as well as header lines across different flats in Block C. The total quantities for each type of pipe are summarized at the end of the document.

Uploaded by

Epic Joker
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
16 views12 pages

Kitek

The document provides detailed measurements of Kitec pipes for the Rajapushpa Imperia project, listing various types of pipes and their lengths for multiple flats. It includes measurements for hot, cold, and flushing lines, as well as header lines across different flats in Block C. The total quantities for each type of pipe are summarized at the end of the document.

Uploaded by

Epic Joker
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 12

CSAE

Project: Rajapushpa Imperia


Vendor : SKP & COMPANY
Block: C, Imperia
Kitec Pipe Measurement Flatwise
Typical Floor JMS Quantity

S.No Description Unit Flat No-1 Flat No-2 Flat No-3Flat No-4 Flat No-5 Flat No-6 Flat No-7 Flat No-8 Flat No-9 Typical floor
Quantity
1 1620 mm Kitec (HOT) Pipe Mt 28.8 26.50 26.55 26.1 31.00 23 28.6 21.5 28.2 240.25

1620 mm Kitec (Cold) Pipe Mtr 65.85 63.8 67.15 62.6 84 54.7 75.5 72.65 60.5 606.75

3 1620 mm Kitec (FwS) Pipe Mtr 17.6 14.25 17.55 18.85 15.6 9.25 14.7 18 14.4 140.2

4 1620 mm Kitec (MWS) Pipe Mtr 8.15 6.95 9.2 6.40 6.2 7.10 8.3 10.15 8.4 70.85

2532 mm Kitec (Header Line) Pipe Mtr 53.25 35.95 38.1 40.31 50.9 25 27.3 53.868 53.97 378.643

Contractor CBRE CBRE Qs RPPL


Vendor
Kitec
S.No TypicalVendor:SKP
COMPANY
Block:C, &
Imperia
2 1
|2532
|2520mm
Kitec
Pipe Pipe
Floor
mm Measurement
JMS
Kitec Description
Quantity
(Header
Flatwise
From
Line)
Floor
Pi
Mtr Mtr Unit 8th
to
53.25 120.40 No-1 Flat
above
CBRE

35.95 111.50 Flat


2
No
38.10 120.45 | No-3 4
Flat
CBREQS Flat
40.31 113.95

No-
50.90 136.80 Flat
56
No-
25.00 94.05 Flat
No-Flat
27.30 127.10
78 No
No-Flat
No-Flat
122.30
53.87

111.50
9
53.97|

Quantity
378.65 1058.05 Typical
floor

RPPL kq
FLATNO
NO RAJAPUSHPA
FLATKTECH LOC:PROJECT:
CONTRACTOR:-SKP&COMPANY
FLATNO
IMPERIA
FLATNO FLATNO FLATNO FLATNO FLATNO FLATNO FLATNO
09 08 07 06 05 04 03 02 01 BLOCK-"C"

MEASUREMNT
DESCRIPTION INTERNAL
Headrerline Headrer
line Headrer
line Headrer
line Headrer
line Headrer
line Headrer
line Headrer
line Headrer
line
MWS FWS Cold Hot MWS FWS Cold Hot MWS FWS Cold Hot MWS FWS Cold Hot MWS FWS Cold Hot MWS FWS Cold Hot MWS FWS Cold Hot MWS FWS Cold Hot MWS FWS Cold Hot

PLUMBING

FLAT
Pipe/2532 1620MM
WORK
2532 1620 1620 1620 1620 2532 1620 1620 1620 1620 2532 1620 1620 1620 1620 2532 1620 1620 1620 1620 2532 1620 1620 1620 1620 2532 1620 1620 1620 1620 2532 1620 1620 1620 1620 2532 1620 1620 1620 1620 2532 1620 1620 1620 1620
WISE

RMT RMT RMT


6.39.05
RMT 12.85
RMT RMT RMT RMT RMT RMT RMT RMT RMT RMT RMT RMT RMT RMT RMT RMT RMT RMT RMT RMT RMT RMT RMT 13.55
15.9
RMT 10.3
RMT RMT 15.0o[18.1
RMT RMT 14.25
RMT RMT RMT RMT RMT RMT RMT RMT RMT RMT RMT RMT
3.90 UNIT
RMT4.4
20.65.14.65 MBR
5.4 17.75 6.15/
7.45 17.54
| 13.7
15.3/ 5.9 14.77
20.6 9.4 19.7 14.2
4.1 15.6 14.8 6.356.9 / 6.65 4.10 13.80
5 9.3 3.957.3 778.710.8
CBR
4.28 13.7 6.5 6.4 12.6 5.15 8.8 5.1 25.1 9.2 7.1 4.056.1 19.6 5.8.35 14.7 7.8
6.7/
17.95 GBR
14.85. 4.4 9.1 3.9 14.4, 6.6 5.5 17.7 12.5 5.6 13.8 8.7 / 6.3 13.2 13.25 6.35

10.15 8.30 26.4 6.40 19.35 9.20 19.75 6.95 12.45 8.15
Kitchen
17.25 Corridor
/utility Hall &
8.4 14.2 26.15. 25.8/ 7.1 19.4 6.2

53.97 53.868 40.31 35.95 53.25


27.3 25 50.9 38.1 /

165.47 53.97 176.16853.868 119.05 154.26 40.31 173.65 53.25 8.15 65.85
158.55 38.1 17.5567.15 26.55147.45 35.95 6.95 14.25 63.8 26.5
8.4 14.4 60.5 28.2
10.15
18
72.65 21.5 154.4 27.3 8.3 14.7 75.5 28.6 25 7.1 9.25 54.7
187.7 50.9
23 6.2 15.6 84 31 6.4 18.85 62.6 26.1 9.2 17.6 28.8 Total

REMARKS
Signature Singnature Singnature
Do
CBRE M/s.Rajapushpa inchargeContraetors
53.25 9+1+0.8+2'4+1.4+2'1+2.5+0.5/ MTR Pi12|
pe 2532
4.15+3.8+4.3+1.1+2+1.3+2.7+1.8+1.
Hall,Corridor
8.15 1.50+1.65+17+19+1.40 MTR Pip11|
e 1620
Line MWS Kitchen
0.80+2.2+1.5+3.65+1.9+2.0+2.0+2.0+0.9+0.10+0.10+0.10
17.25 MTR Pi10|
pe 1620
Line Cold Kitchen
5.35 1.7+0.85+0.80+1.9+0.10 MTR Pipe 9|1620
Line Flush BR-3 GBR,
0.80+2.75+1.6+1.7+1+2.2+0.80+2.2+0.10+0.10
13.25 MTR Pipe 8|1620
Liné Cóld BR3 GBR,
6.35 0.80+1.35+1.80+2.3+0.10 MTR Pip71620
e
Line Hot BR-3 GBR,
8.35 1.70+0.35+2.45+1.7+1.9+0.10 MTR Pip61620
e
LinFlushing
e BR-2 CBR,
0.50+1.85+2.45+1.6+1.7+2.2+1.0+1+2.2+0.10+0.10
14.7 MTR Pipe5|1620
Line Cold BR-2 CBR,
7.8 0.50+1.85+1.25+2.30+1.8+0.10 MTR Pipe41620
Line Hot BR-2 CBR,
3.90 1.7+0.20+1.90+0.10 |MTR Pipe 3|1620
BR-1 MBR(Flushing
Line),
+2.25+1.6+1.+2.2+22+0.10+0.10+0.10
20.65 2
MTR Pipe 1620
BR-1 Line),
MBR(Cold
2.4+1.3+3.3+0.30+0.8+1.8+2.25+2.3+0.10+0.10
14.65 MTR Pipe 1|1620
BR-1 Line), MBR(Hot
qty Total Break
up Units Description Sno
Installation Pipe Kitech Works: Description
of
Drawing
Ref.
27-Feb-24 Dat:e No: Item BOQ
No: JMS No: Contract/
WO
Flat1C-Blcok, /Flat Block Company SKP& M/Contractor
S. :
CBRE
Measurement
Sheet Joint RAJAPUSHPA
DrawingRef. BOQNo: RAJAPUSHPA
Item Contractor
Contract/
No:WO PAOPENTES
SnoDescription
VTLTO.

12 Pipe10|1620
11|1620 Pipe 91620
Pipe 8 7|1620
Pipe Pipe 51620
61620 Pipe 4|1620
Pipe 31620
Pipe 21620
Pipe 11620
Pipe
Contractors
Incharge |2Pipe
532 1620
Pipe
Singnature
Description
of MIS. :
Works:
SKP
|MTR MTR MTR MTR |MTR MTR MTR MTR MTR |MTR MTR MTR Kitech &
Units Company

Pipe
+4.1+4.2+1.8+0.7+3.25+2.3+2.5+0.50 2.2+0.7+1.5+0.60+1.5+1.8+2.3+0.10+0.10
|1.7+1.7+1.65+1.9
|1.7+0.35+1.9+0.10
|1.5+3.05+1.0+2.0+2.0+2.1+0.50+0.10+0.10+0.10
0.60+1.5+2.2+0.7+2.75+1.4+1.6+1.7+2.2+0.80+2.2+0.10+0.10+0.10 |2.2+2+1.8+0.80+1.80+0.10
|2.3+2+2.2+1.8+1.6+1.7+0.80+7+0.10+0.10
|1.7+2.2+0.2+1.9+0.10 |1.7+0.40+1.9+0.10
|2.2+1.9+2.7+2.2+1.6+1.7+1.3+0.10+0.10
2.3+1.5+1.8+1.3+0.10
L Installation

Measurement
Sheet
Joint

/ Date : JMSNo: Block


GBR(FIushing
Line),
BR-3 CBR(Flushing MBR(Flushing
Line),
BR-1
Kitchen
MWS
Line Kitchen
Cold
Line GBR(Cold, GBR, BR-2 CBR,
CBR(Cold
Line), MBR(Cold
Line),
BR-1 MBR,
M/s.Rajapushpa /Flat
Hall,Corridor
Singnature (Hot (Hot (Hot Breakup
/ 28-Feb-24 C-Blcok,
Line),
BR-3 Line) Line) Line)
Line),
BR-3 BR-2 BR-1
BR-2 Flat
2

35.95 6.95 12.45 4.05 17.95 10.8 6.1 19.6 8.7 4.10 13.80
7
Remark
Totalqty CBRE
Signature
CBRE
RAJAPUSHPA
PRÓ
OrnRTRS PVr. LTn
fenntn
Joint Measurement Sheet CBRE
Contractor : M/S. SKP &Company Block /Flat C-Blcok, Flat 3

Contract/ WO No: JMS No:

BOQ Item No: Date: 28-Feb-24

Drawing Ref.
Description of Works: Kitech Pipe Installation

Sno Description Units Break up Total gty Remark

MBR, (Hot Line) BR-1


1|1620 Pipe MTR 2.3+1.6+1.8+0.85+0.10 6.65
MBR(COld Line), BR-1
21620 Pipe MTR 1.9+1.6+2.7+2.2+1.5+1.6+1.7+065+0.10+0.10 14.25
MBR(Flushing Line), BR-1
31620 Pipe MTR |2.2+1.6+0.9+2.5+0.10 7.3

CBR,(Hot Line) BR-2


21620 Pipe MTR 0.90+1.8+2.3+1.6+0.10 6.7
CBR(Cold Line), BR-2
1620 Pipe MTR 2.2+1.7+2.2+2175+1.8+1.6+1.7+0.90+0.10+010 15.05
CBR(Flushing Line), BR-2
1620 Pipe MTR 1.9+0.25+1.7+0.10 3.95

GBR,(Hot Line) BR-3


31620 Pipe MTR 1.15+1.55+3/05+1.8+2.3+0.95+2.2+0.10+0.10 13.2
GBR(Cold Line), BR-3
1620 Pipe |MTR 1.15+1.55+1.6+1.7+1.2+3.05+22+2.2+0.95+2!2+0.10+0.10+0.10 18.1
GBR(Flushing Line), BR-3
1620 Pipe MTR 2.5+0.40+1.4+1.9+0.10 6.3

Kitchen Cold Line


41620 Pipe MTR 5.2+0.90+0.80+3.7+0.90+2.0+2.0+2.05+1.9+0.10+0.10+0.10 19.75
Kitchen MWS Line
1620 Pipe MTR |2.0+1.8+2.0+1.9+1.5 9.20

Hall& Corridor
1.4+2.4+2.1+14+3.1+1.7+1.3+1.25+0.85+0.8+1.1+3+2.7+2.05+7.35+06+2
2532 Pipe MTR
+2.5+0.5 38.1

Contractors Inçharge M/s.Rajapushpa CBRE

Singnature Singnature Signature


Joint Measurement Sheet CE

|Contractor :MIS. SKP &Company Block /Flat C-Blcok, Flat 4

ContractU WO No: JMS No:

BOQ Item No: Date : 28-Feb-24

Drawing Ref.
Description of Woi Kitech Pipe Installation

Sno Description Units Break up Total qty


MBR,(HotLiné) BR-1
1|1620 Pipe |MTR 2.3+1.5+1.81.1+0.9+2.50+0.10+0.10 10.3
MBR(Cold Line), BR-1
1620 Pipe MTR 1.9+2.75+2.2+1.6+1.6+1.7+11+0.5+0.10+0.10 13.55
MBR(Flushing Line), BR-1
1620 Pipe |MTR 1.7+1.5+1.4+2.2+0.10 6.9

CBR, (Hot Line) BR-2


21620 Pipe MTR 1.4+1.5+1.8+2.3+0.10 7.1
CBR(Cold Line), BR-2
1620 Pipe MTR
2.5+0.9+1.4+1.6+1.7+2.1+2.2+1.3+1.9+010+0.10+0.10 15.9
CBR(Flushing Line), BR-2
1620 Pipe |MTR 1.70+1.5+1.15+1.9+0.10 6.35

/ GBR, (HÐt Line) BR-3


3|1620 Pipe MTR 1.1+1.5+2.0+1.70+2.30+0.10 8.7
S//GBR(Cold Line), BR-3
1620 Pipe MTR 1.1+1.5+2.0+2.2+0.90+0.30+2.2+1.6+1.8+0.10+0.10 13.8
GBR(Flushing Line), BR-3
1620 Pipe MTR 1.70+0.50+1.40+1'9+0.10 5.6

Kitchen Cold Ljne


1620 Pipe 0.10+1.5+2.9+3.35+0.60+3.1+0.90+2.0+2.0+y.6+0.10+0.10+0
MTR .10 19.35
Kitchen MWS Line
1620 Pipe MTR 2.0+1.0+1.50+1.9 6.40
/Hall& Corridor
1.3+1.4+2.9+3.4+3.5+0.8+1.4+1.3+0.8+4.9+3.2+1.7+1.2+0.46
5|2532 Pipe MTR +7.25+1,8+2.5+0.5 40.31

Contractor's Incharge M/s Rajapushpa CE

Singnature Singnature Sigr


Joint Measurement Sheet

Contractor : MIS. SKP & Company Block IFlat C-Blcok, Flat 5

Contract/ WO No: JMS No:

BOQ Item No: Date : 28-Feb-24

Drawing Ref.
Description of Work Kitech Pipe Installation

Sno Description Units Break up Total qty


/ MBR, (HÍtLine) BR-1
1|1620 Pipe MTR 1.1+1.8+2.2+2.3+1.8+0.10 9.3
MBR(ColáLine), BR-1
21620 Pipe MTR 1.1+1.8+2.3+2.4+2.3+1.7+1.6+7.5+0.10+0.10 14.8
MBR(FIushing Line), BR-1
31620 Pipe MTR |1.7+0.20+1.2+1.8+0.10 5

CBR, (Hot Line) BR-2


41620 Pipe MTR 12+1.6+2.2+2.3+1.8+0.10 9.2
on CBR(Cold Lihe), BR2
5 1620 Pipe
MTR |1.2+1.6+2.3+24+2.3+16+1.7+0,5+1.6+1.1+1.7+4+1.
|2+1.7+0.10+0.10 25.1
CBR(Flushing Line), BR-2
61620 Pipe MTR |1.7+0.40+1.1+1.8+0.10 5.1

GBR, (Hót Line) BR3


71620 Pipe MTR |1.1+1.5+2.8+2.7+2.4+1.8+0.10+0.10 12.5
GBRCOld Line), BR-3
1620 Pipe MTR 1.1+1.5+2.8+2.7+2.3+1,2+2,5+1,7+16+0.10+0.10+0.
10 17.7
GBR(FIushing Line), BR-3
91620 Pipe MTR 1.7+0.70+1.2+1.8+0.10 5.5

t K i t c h e n Cold Line
1620 Pipe 1.2+1.7+5.3+3.7+0.80+3.6+2.0+0 80+2.0+0 80+2.10+
10 MTR |2,10+0.10+0,10+0,10 26.4
Kitchen MWS Line
11|1620 Pipe |MTR 1.5+1+1.9+1.8 6.2
Hall & Corridor

1.5+1.9+0.8+2.7+0.8+3+06+3. 1+1.5+26+27+1.6+3.
12|2532 Pipe |MTR |7+0,6+3A+15+1+1.4+2.5+0.50 50.9

Contractors Incharge M/s Rajapushpa


K
Singnature Singnature Sig1
Joint Measurement Sheet CBR
|Contractor : M/s. SKP & Company Block /Flat C-Blcok, Flat 6

Contract/ WO No: JMS No:

BOQ Item No: Date : 28-Feb-24

Drawing Ref.
Description of Work Kitech Pipe Installation

Sno Description Units Break up Total qty Remark

/MBR,(Hot Lin) BR-1


11620 Pipe MTR |1.5+1.5+2.2+2.4+2.2+2.4+1.8+0.10+0.10 14.2
L 6 MBRICold Line), BR-1
21620 Pipe MTR 1.5+1.5+2.4+2.3+2.3+1.5+2.2+1.6+1.7+2.4+0.10+0.10+0.1
19.7
MBR(Flushing Line), BR-1
31620 Pipe MTR 1.7+0.50+1.8+0.10 4.1

CBR, (Hot Line) BR-2


41620 Pipe MTR 1.1+1.5+1.9+2.4+1.8+0.10 8.8
ÇÉR(Cold Line), BR-2
5|1620 Pipe MTR |1.1+1.5+2.1+2.3+1.5+2.3+1.7+1.6+1.3+0.10+0.10 15.6
ÇBR(Flushing Line), BR-2
61620 Pipe MTR 1.7+0.50+1.05+1.8+0.10 5.15

Kitchen Çold Line


1620 Pipe MTR 1.4+0.80-+3.7+3+2.8+0,80+2.1+2.1+2.4+0.10+0.10+0.10 19.4
Kitchen MWS Line
8|1620 Pipe MTR 1.5+0.90+1.6+1.3+1.8 7.1
Hall, Corridor
92532 Pipe MTR 1.5+2.9+2.5+1.4+1.2+1.7+2.1+3.4+3.6+1.7+3 25

Contractors Incharge M/s.Rajapushpa CBRE

Singnature Singnature Signature


Joint Measurement Sheet CBR

Block /Flat C-Blcok, Flat 7


Contractor : MIS. SKP &Company
Contract/ WO No: JMS No:

BOQ Item No: Date: 28-Feb24

Drawing Ref.
Description of Works Kitech Pipe Installation

Sno Description Units Break up Total qty Remark

MBR,(Hot Line) BR-2


11620 Pipe MTR 2.4+1.5+2.5+1.1+1.8+010 9.4
MBR(Çold Line), BR-2
21620 Pipe MTR 2'3+1.3+2.3+1.7+1.6+1.7+2.5+1.1+0.10+0.10 14.7
MBR(Flushing Line), BR-2
31620 Pipe MTR 17+0.30+1.8+0,10 " 44

gBR,(Hot Line) BR-1


41620 Pipe MTR |1.2+1.6+0.50+2.40+2.4+2.5+18+0.40+0.10 12.6
CBR(ColLine), BR-1/
|1.2+1.6+o.5+2'4+2.3+27+2.3+1.7+1.6+2.0+1.0+1.
5
1620 Pipe MTR
20.6
0+0,10+0.10+0,10
CBR(Flushing Line), BR-1
61620 Pipe |MTR 1.7+1+1.8+1.8+0.10 6.4

GBR, (Hot Line)BR-3


71620 Pipe MTR 1+1.3+2.4+1.8+0.10 6.6
GBR(Cold Line), BR3
1620 Pipe MTR
8 i.0+2.80+1.6+1.7+2.3+2+0.50+2.3+0.10+0.10 14.4
GBR(Flushing Line), BR-3
91620 Pipe MTR 1.80+0.30+1.70+0.10 3.9

Kitchen Cold Line


1620 Pipe 1.643547.441.142 8+0.942.1+2.1+1.9421+0.1040
10 MTR .10+0,10 25.8
Kitchen MVWS Line
11|1620 Pipe MTR 1.5+1.54+1.9+1.5+1.9 8.30

Hall & Corridor


1.4+0.6+1.9+1.8+1.1+0.2+2.5+0.8+1.6+4.2+2.6+2.
12 |2532 Pipe MTR |6+1+2+2.5+0.50 27.3

Contractors Incharge M/s Rajapushpa CBRE

Singnature Singnature Signature


RAJAPUSHPA Joint Measurement Sheet CBRI
|Contractor : MIS. SKP & Company Block /Flat C-Blcok, Flat 8

Contractt WO No: JMS No:

BOQ Item No: Date: 28-Feb-24

Drawing Ref.
Description of Works Kitech Pipe Installation

Sno Description Units Break up Total qty


MBR, (Hot Line) BR-1
1|1620 Pipe MTR 0.55+1.35+2.2+1.7+0.10 5.9
MBR(Cold Line), BR-1

21620 Pipe MTR


0.55+2/70+1.6+1.6+2.2+2.1+1.8+0.25+2.30+0.10+0.10 15.3
MBR(Flushing Line), BR-1
31620 Pipe MTR 1,7+1.65+1,8+0,25+1,95+0.10 7.45

CBR, (HÍt Line) BR-2


41620 Pipe |MTR 2.30+1.40+1.80+0.90+0.10 6.5
CBR(Cold Line), BR-2
1620 Pipe

61620 Pipe
MTR

MTR
1.9+1.35+2.75+2.2+1.
b.4eu11+o9+010+0.i0
CBR(Flushing Line), BR-2
2.2+1.35+0.80+17+0.10
13.7

6.15

GBR, (Hot Line) BR-3


101620Pipe MTR 2,3+1.3+1.8+0,60+2.9+0.10+0.10 9.1
GBR(Cold Line), BR-3
1620 Pipe MTR 2.90+0.50+2.75+2.25+1,6+1,7+2.2+1.1+2.2+0.10+0.10
11 +0,10 17.5
GBR(Flushing Line), BR-3
121620Pipe MTR 1.9+0!70+1.7+0,10 4.4

Kitchen Cold Line

1620 Pipe |2.0+3,45+2,1+3.7+97+3,4+1,1+2,2+2.2+0.10+0,10+0.


13 MTR 10 26.15
Kitchen MWS Line
14|1620 Pipe MTR 1.5+1.6+3.45+1.6+2.0 10.15
Hall & Corrldor
|2532 Pipe 1.90+1.8+1.85+0.2+2.4+1.5+2.6+0.35+3+1.4+3.2+4,1+
15 MTR |2,168+4+2.3+12+1,8+3+1,3+3 53.868

Contractors Incharge M/s.Rajapushpa CB

Singnature Singnature Sign.


RAAPUSHIPA Joint Measurement Sheet CBRE
|Contractor :MIS. SKP&Company Block /Flat C-Blcok, Flat 9

ContractU WO No: JMS No:

BOQ Item No: Date: 28-Feb-24

Drawing Ref.
Description of Worl Kitech Pipe Installation

Sno Description Units Break up Total qty


MBR, (Hot Line) BR-1
11620 Pipe MTR |0.80+1.5+1.8+2.75+1.1+2.3+2.4+0.10+0.10 12.85
MBR(Cold Line), BR-1
21620 Pipe |MTR 0.80+1.50+1.6+1,7+2,2+1.
10+0,10
2*22*1,1+2 4+-0.19+0 17.75
MBR(Flushing Line), BR-1
31620 Pipe MTR 1.7+0,60+1,1+1.9+0.40 5.4
CBR, (Hot Line) BR-2
4\1620 Pipe MTR 2.30+1.8+1.5+0.60+0.10 6.3
CBR(Cold Line), BR-2

5
1620 Pipe MTR
2.2+140+1.3+2.5+2.2+1.6+1.7+0.60+0.10+0.10 13.7
CBR(Flushing Line), BR-2
61620 Pipe |MTR 1.9+1.1+1.7+0,10 4.8

GBR, (HotLine) BR-3


7|1620 Pipe MTR 0.60+3.35+1.8+1.0+2.2+0.10 9.05
GBR(Cold Line), BR-3
1620 Pipe MTR
0.60+1.6+1.7+2.2+2.0+3.35+1.0+2.2+0.10+0.10 14.85
GBR(Flushing Line), BR-3
9|1620 Pipe MTR 1.9+0.5+1.7+0.10 4.2
Kitchen Cold Line

10 1620 Pipe MTR


2.0+2.0+0.90+2.2+1.9+3.4+0.50+1.0+0.10+0.10+0.10 14.2
Kitchen MWS Line
111620 Pipe MTR |1.7+1.7+1.7+1.9+1.4 8.4
Hall & Corridor

12
2532 Pipe
|MTR
1.7+2.72+1.4+2.3+1.35+3.3+0,9+2,9+2+1.8+1.2+5.3+2.
|2+1.7+1,7+12.6+1.1+1.5+2+1.3+2'5+0.5 53.97

Contractorstnaharge M/s.Rajapushpa CB

Singnature Singnature Sign