Project 9
Project 9
E1844 V13
January,2013
Public Disclosure Authorized
Dessie
Table of Content
Acronym .............................................................................................................................................................. 6
Executive Summary ............................................................................................................................................. 7
1. Introduction................................................................................................................................................... 14
1.1 Background.............................................................................................................................................. 14
1.2. Objective of the Environmental and Social Impact Assessment ............................................................ 16
1.2.1. Specific objectives: .......................................................................................................................... 16
2. Approaches and Methodology ..................................................................................................................... 16
2.1 Data Collection methods and tools Information ..................................................................................... 17
2.2 Field Survey ............................................................................................................................................. 17
2.3. Review of Existing Literature and Maps: ................................................................................................ 17
2.4. Public Involvement and Stakeholders Consultation .............................................................................. 18
2.5. Data Analysis and Report Writing: ......................................................................................................... 19
3. Project Description ........................................................................................................................................ 19
3.1. Project Location...................................................................................................................................... 19
3.2 Project rational ........................................................................................................................................ 20
3.3. Project activities ..................................................................................................................................... 22
4. National policies and regulatory framework ................................................................................................ 23
4.1 Policy framework..................................................................................................................................... 23
4.1.1 Constitution of the Federal Democratic Republic of Ethiopia ......................................................... 23
5.1.2. National and Regional Conservation Strategy ................................................................................ 24
4.1.3. Environmental Policy of Ethiopia .................................................................................................... 24
4.1.4 Sectoral Environmental Policies ....................................................................................................... 25
4.1.5 National Health Policy ...................................................................................................................... 25
4.1.6. Ethiopian Roads Development (Policy Framework) ........................................................................ 25
4.2 Legislative Framework............................................................................................................................. 27
4.2.1 Establishment of Environmental Protection Organs (Proclamation No. 295/2002)........................ 27
4.2.2 Environmental Impact Assessment (Proclamation No. 299/2002) .................................................. 27
4.2.3 Environmental Pollution Control (Proclamation No. 300/2002)...................................................... 28
4.2.4 National Rural Land Administration and Use (Proclamation No. 456/2005) ................................... 28
4.2.5 EPA’s Environmental Impact Assessment Guidelines (2002) ........................................................... 29
4.2.6 Ethiopian Road Authority’s Environmental Impact Assessment Guideline ..................................... 30
4.3. Institutional Framework ......................................................................................................................... 30
2
4.3.1 Federal and Regional States ............................................................................................................. 31
4.3.2 Federal Environmental Protection Authority (EPA) ......................................................................... 31
4.3.3 The Ethiopian Roads Authority (ERA) ............................................................................................... 33
4.4 Summary of the World Bank’s Safeguards Policies ............................................................................. 33
5. Description of Baseline Environment ............................................................................................................ 34
5.1. Bio-physical Environment....................................................................................................................... 34
5.1.1. Location ........................................................................................................................................... 34
5.1.2. Topography ..................................................................................................................................... 36
5.1.3. Climate ............................................................................................................................................ 36
5.1.4. Geology ........................................................................................................................................... 38
5.1.5. Soil ................................................................................................................................................... 40
5.1.6. Hydrogeology .................................................................................................................................. 40
5.1.7. Flora and Fauna ............................................................................................................................... 41
5.2. Socio-Economic Environment ................................................................................................................ 41
5.2.1. Demographic Features and Settlement Patterns ............................................................................ 41
5.2.2. Health service .................................................................................................................................. 42
5.2.3. Education:........................................................................................................................................ 42
5.2.4. Land use/cover ................................................................................................................................ 43
5.2.5. The existing Road Network, Utilities and Transport Study ............................................................. 45
6. Project Alternatives analysis ......................................................................................................................... 47
7. Environmental Impacts Identifications, Prediction and Analysis .................................................................. 48
7.1. The positive Impacts .............................................................................................................................. 48
7.1.1 Employment Opportunity ................................................................................................................ 48
7.1.2. Social Benefits ................................................................................................................................. 48
7.1.3. Urban Development ........................................................................................................................ 49
7.2. Potential Negative Impacts .................................................................................................................... 49
7.2.1. Slope Destabilization Impact ........................................................................................................... 49
7.2.2. Impacts on soil erosion ................................................................................................................... 49
7.2.3. Impact on Water Resources ............................................................................................................ 49
7.2.4. Impacts on Air Quality, Noise and Vibration ................................................................................ 50
7.2.5. Impacts on Quarry and Borrow Pits ................................................................................................ 50
7.2.6. Impacts on Socio-Economic Environment....................................................................................... 50
7.2.7. Impact on Public Utilities ................................................................................................................ 51
3
7.2.8..Impact on Traffic Accidents and Safety Risks .................................................................................. 51
8. Impact mitigation measures.......................................................................................................................... 52
8.1. Mitigation Measure Impact on Slope Destabilization ............................................................................ 52
8.2. Mitigation Measures impact on soil erosion.......................................................................................... 52
8.3. Mitigation measures Impact on Water Resources ................................................................................. 53
8.4. Mitigation measure impact Air Quality, Noise and Vibration ................................................................ 54
8.5. Mitigation Measures for Soil Erosion at Quarry Sites ............................................................................ 54
8.6. Mitigating measures Impacts on Socio-Economic Environment............................................................ 55
8.7. Mitigation measure Impact on Public Utilities ....................................................................................... 55
8.8. Mitigation Measures Impact on Traffic Accidents and Safety Risks ...................................................... 55
9. Environmental Management and Monitoring Plan ...................................................................................... 61
9.1. Environmental Management Plan ......................................................................................................... 61
9.2. Monitoring Plan and Implementation Program ..................................................................................... 61
9.3. Environmental and Social Monitoring.................................................................................................... 65
9.4. Environmental Cost Estimate ................................................................................................................. 65
10. Conclusion and Recommendation .............................................................................................................. 68
10.1 Conclusions ........................................................................................................................................... 68
10.2 Recommendations ................................................................................................................................ 68
Annexes ............................................................................................................................................................. 69
Annex.1. References...................................................................................................................................... 69
Annex. 2. TOR of the Gravel road EIA consultancy ....................................................................................... 70
Annex .3. CV of EIA Team member .............................................................................................................. 76
4
Figures
FIGURE 2. PUBLIC CONSULTATION FORUM AT 02 KEBELE (LEFT) AND 01KEBELE (RIGHT) .................................................. 19
FIGURE 3: SHOWING LOCATION OF THE CITY WITHIN WHICH THE PROJECT IS LOCATED ........................................................ 20
FIGURE 4. LOCATION OF PROPOSED GRAVEL ROAD AND ROAD NETWORK ........................................................................... 21
FIGURE 5. LOCATION MAP OF THE DESSIE GRAVEL ROAD PROJECT ..................................................................................... 35
FIGURE 6. LOCATION MAP OF THE DESSIE CITY ................................................................................................................... 35
FIGURE 7. ELEVATION AND SLOPE MAP OF DESSIE CITY ....................................................................................................... 36
FIGURE 8.DESSIE TOWN ADMINISTRATION MAJOR LAND USE/COVER MAP, 2012............................................................ 45
Tables
TABLE 1.SUMMARY OF ENVIRONMENTAL AND SOCIAL IMPACTS .......................................................................................... 10
TABLE 2.MITIGATION MEASURES FOR THE ADVERSE IMPACTS .............................................................................................. 11
TABLE 3: DESSIE STATION HIGHEST RAINFALL ................................................................................................................. 37
TABLE 4: DESSIE STATION AVERAGE MAXIMUM TEMPERATURE ..................................................................................... 38
TABLE 5. POPULATION SIZE OF DESSIE TOWN BY SEX DISTRIBUTION, 2011 .................................................................... 42
TABLE 6. HEALTH INSTITUTIONS IN 2012 G.C .............................................................................................................................. 42
TABLE 7.EDUCATIONAL INSTITUTIONS IN 2012 G.C ...................................................................................................................... 43
TABLE 8 LAND USE/COVER OF THE DESSIE TOWN ADMINISTRATION ................................................................................... 44
TABLE 9 :-SHOW THE ASSET REGISTERED FOR DESSIE CITY IN 2012/2013 ............................................................................. 46
TABLE 10.SUMMARY MAJOR IMPACTS AND PROPOSED MITIGATION MEASURES ............................................................ 57
TABLE 11- ENVIRONMENTAL AND SOCIAL IMPACT MANAGEMENT, MONITORING PLAN ...................................................... 63
TABLE 12.DESSIE GRAVEL ROAD PROJECT ENVIRONMENTAL COST ESTIMATE ...................................................................................... 67
5
Acronym
ADSWE Amhara Design and Supervision Works Enterprise
ANRS Amhara National Regional State
BoEPLAU Bureau of Environmental Protection, Land Administration and Use
CSA Central statistic Agency
CSE Conservation Strategy of Ethiopia
DEM Digital Elevation Model
EEPCo Ethiopian Electric Power Corporation
EIA Environmental Impact Assessment
EIS Environmental Impact Statement
EISR Environmental Impact Study Report
EMB Environmental Management Branch
EMP Environmental Management Plan
EPA Environmental Protection Authority
EPC Environmental Protection Council
ERA Ethiopian Road Authority
ESMF Environmental and Social Management Framework
FAO Food and Agricultural Organization
FDRE Federal Democratic Republic of Ethiopia
Ha Hectare
MASL Meter above Sea Level
MUDC Ministry Urban Development and Construction
NGO Non Governmental Organization
ROW Right-of-Way
SIA Social impact assessment
ULGDP Urban Local Government Development Program
USA United State of America
6
Executive Summary
Dessie is one of the oldest cities in the country and the capital city of South Wollo Zone in the
Amhara National Regional State. It is located on the Addis Ababa - Mekelle highway, at about
400 km distance from Addis Ababa, in the northern part of the country.
According to information from the city council, the current population of the city is estimated at
174,705 people. The city, however, is deficient in infrastructure development and social service
facilities. The infrastructures like gravel road, solid waste management facilities are much below
the demand and requirements of the population of such medium sized urban area. Sustainability
is one of the eight Millennium Development Goals (MDGs) set by the International community
and hence, governments are expected to work towards those targeted goals.
Dessie gravel road project has investigated its design and Engineering work, Geology and
Geotechnical study, Environmental Impact Assessment (EIA), and Socio-economic Studies by
independent consultant of the Amhara Design and Supervision Works Enterprise. The
implementation of this Project will create employment opportunities; improve transportation and
the living condition of the local people. However, the road project will bring negative
environmental and social impacts. The environmental issues are considering through
Environmental Impact Assessment (EIA) before the implementation of development plan to
ensure sustainable development. Prior to implementation of the proposed road project, it is very
essential to identify environmental issues to provide information for decision making and
integrate environmental considerations into the higher level of decision making.
The methodology adopted for conducting this environmental impact assessment study followed
the Federal Democratic Republic of Ethiopia, Ministry of Urban development and construction
Environmental and social Management Framework and Resettlement policy framework- urban
7
local government development project manual November 2008 that meet the requirements of the
World Bank, Federal and Regional Environmental Protection Organs.
The collection of secondary data on environmental components was collected from relevant
documents and literature sources (desktop study) and primary data was also collected through
general public meeting, focus groups discussions, and site observation.
According to the reports of the Administration, kebele 01 and 02 (the project area) do not get
adequate transport services due to heavy damage of road. Most of social services such as health,
schools, and market place and bank services are confined in the center of the city where adequate
road and transport facilities are available. As a result, the community in the study area in general
and mothers in particular were facing various problems and difficulties due to lack of transport
services in the area. The problems are very acute during the time of pregnancy when women
have to walk on foot for long distances or are carried on horse carts to receive medical checkup
or to have delivery. The long walk they make on foot or on horse carts expose them to difficult
situations and unexpected problems.
In addition to the problem of road accessibility, lack of proper drainage system in the above
kebeles is also another bottle necks. The run off originated from the tip of the hills that
surrounded the city were drains down towards the city creating flood at various places. Despite
the fact that the city is threatened by flood, the existing drainage system covers only a small part
of the city, mainly the central part just following the road route. Consequently, the project area is
suffering not only from lack of road access but also from the problems of flood.
8
Therefore, the construction of the proposed road project will offer the local community easy,
comfortable and quick access to markets and other social services. Following the increased
access and transport opportunities, other socio-economic development will follow including
education, health, communication, market, and banking. The project will reduce travel time to
the social services by mode and location particularly to the clinic and Hospital that are found in
Dessie city.
Construction of proposed gravel road project for kebele 01 and 02 of Dessie city involve
delineation of the project target routes, identification of affected environmental, social and
economic resources, excavation of the route, cut and fill, surfacing and Calvert building with the
necessary downstream structures and Water ways or drainage (1.5m width one side) and walk
way.
The total length of the route is 2 km and 30m width gravel road on the beneath of Tossa hill.
During construction of the road there will be significant biodegradation, air and noise pollution.
The relevant policy, legal and institutional frameworks within which the project will be
implemented have been reviewed and highlighted in the document. Accordingly, Projects to be
implemented under the (Urban Local Government Development Plan (ULGDP) should adhere to
acceptable environmental and social safeguards. The projects should, as far as possible, not result
in significant disturbance of sensitive ecological resources. It should not result in involuntary
resettlement and land acquisition, and where this is necessary it is minimized by exploring all
viable alternatives and where it is unavoidable, compensatory programs are prepared and
implemented
This part of the report addresses potential impacts associated with the proposed gravel road
construction project and analysis of the related impacts. The project environmental impacts have
9
been those identified as specific to the site such as land clearance, removal of soil and vegetation,
land escape alteration particularly at quarry site, silt deposition and pollution.
Environmental
Adverse Slope Destabilization Impact Impacts on Ambient Air Quality, Noise
Impacts on soil erosion Traffic Accidents and Safety Risks
Impact on Water Resources Impact of Road Noise
Accidents from Slips and falls of Stone and soil
Materials
Impacts on Quarry and Borrow Pits
Impacts on Vibration
Positive Employment opportunity
Urban development
Increase livelihood
Social
Adverse Impacts on Ambient Air Quality, Noise Impacts on Ambient Air Quality, Noise
Traffic Accidents and Safety Risks Traffic Accidents and Safety Risks
Impact of Road Noise Impact of Road Noise
Loss of Properties and Displacement people
Positive Employment opportunity Employment opportunity
Urban development Urban development
Increase livelihood Increase livelihood
access roads provision
Establishment of proper drainage system
Mitigation measures are proposed for each of the likely adverse impacts to be posed by the
project and respective to each stage of the project implementation processes.
The proposals for mitigation measures have been detailed for implementation both at the design,
construction and operation phases of the project. The design of gravel road is to ensure the basic
10
objective of providing appropriate transport facilities, and the designer is advised to incorporate
the necessary facilities and provisions for improved environmental performances.
The contractor should erect stone slips and falls control barriers around perimeter of
Accidents from Slips and falls of
cuts, and roadways
Stone and soil Materials
Leveling of the exploited blocks before abounding the used quarry;
Impacts on Quarry and Borrow
Pits In order to minimize the effect of flood, landslide and erosion on road & wetland,
the surface rainwater has to be diverted through appropriate ditches or channels
above the quarry
11
Minimize the area of ground clearance i.e. land clearing for road construction
Loss of Properties and
should be restricted to what is absolutely necessary for the road construction;
Displacement people
Replanting right species of trees on the road side that could provide benefit such
as shade, soil conservation and prevention of gullies, scenery, and protection from
dust, noise and wind etc.
Pay compensation to the affected people
Carefully and clearly mark pedestrian-safe access routes
Traffic Accidents and Safety
Risks Assign traffic safety personnel to direct traffic during school hours
Maintain supply of supplies for traffic signs, road marking, and guard rails to
maintain pedestrian safety during construction
Replanting and maintaining of vegetation
Landslides, Slumps and Slips Draining the subsurface (reduces pore water pressure)
Construct artificial barriers
Reduce slope angle
Impact of Road Noise Plant 30m tree buffer strips between road and surrounding habitation
The environmental management for the Gravel road will be a performance-based site assessment
and management to ensure road designers and operators select the most appropriate and
innovative means of meeting the specified environmental goals. Accordingly, the gravel road
Environmental Management will have to comply with the following environmental goals;
12
Accordingly management and monitoring indicators are identified and discussed in detail,
including in a matrix form to help as a checklist for control of major parameters.
The costs required during operation phase of the project will be part of the day to day
administrative and operational is estimated about 262, 240 Eth. Birr.
The budget will be allocated for training and awareness creation of personnel on the principles
Conservation of natural resource, traffic facilities and salary for permanent and temporary staff.
13
1. Introduction
1.1 Background
Dessie is one of the oldest cities in the country and the capital of South Wollo Zone in the
Amhara Regional State. It is located on the Addis Ababa - Mekelle high way, at about 400 km
distance from Addis Ababa, in the northern part of the country.
According to information from the city council, the current population of the city is estimated at
174,705 people. The city, however, is deficient in infrastructure development and social service
facilities. The infrastructures like gravel road and solid waste management facilities do not
adequately addressed demand and requirements of the population of such medium sized urban
area.
Dessie city Administration has identified 18 priority municipal projects to be addressed in 2012/
2013 and has developed capital investment plans accordingly. Gravel road construction is planed
as one of those priority development areas that have been targeted for the plan period. The
objective of this plan is described as to meat public satisfaction through efficient service delivery
and infrastructure development.
Accordingly, the city administration has planned to carry out the implementation of gravel road
construction project under component-1 of the “Urban Local Government Development Project”
ULGDP. The ULGDP represents the third phase of joint collaboration between the World Bank
and Ethiopian Government to support urban development, and creates a new fiscal instrument in
the form of a specific purpose grant (SPG) to urban local governments to support key
performance improvements required for sustainable, accountable service delivery, which is an
additional component to the government’s fiscal architecture of predictable resource transfers to
the urban sector.
14
Assessment (EIA) and Social Impact assessment (SIA) before implementing a project can help to
ensures sustainable by providing information for decision making to reduce adverse impacts
This report deals with the environmental and social impacts of the proposed development
scheme. The environmental and social impact assessment study was conducted by a team that
consists of multi disciplinary professionals that include environmentalist, geologist, socio-
economist, design engineers (structural engineers), and surveyors.
The report is arranged in the format using environmental and social impact assessment guidelines
of the GOE, the World Bank and the African Development Bank for road development projects as
follow.
Section 1: Introduction
Section 2: Methodology
15
1.2. Objective of the Environmental and Social Impact Assessment
It is understood that construction of the gravel roads will have economic and social benefits in
the improvement of the quality of living and facilitate the economic development of the area by
reducing the prevailing impaired and retarded mobility of goods and services. However, it is also
possible that some aspects of the construction of the gravel roads may have some negative or
undesired impacts on the social, economical and bio-physical environment of the area concerned
if appropriate measures that can correct or mitigate undesirable and unintended results are not
incorporated.
The methodology adopted for conducting this environmental impact assessment study followed
the Federal Democratic Republic of Ethiopia, Ministry of Urban development and construction
Environmental and Social Management Framework and Resettlement policy framework- urban
local government development project manual November 2008 that meet the requirements of the
World Bank, Federal and Regional Environmental Protection Organs.
The collection of secondary data on environmental components was collected from relevant
documents and literature sources (desktop study) and primary data was also collected through
general public meeting, focus groups discussions, and site observation.
16
2.1 Data Collection methods and tools Information
Secondary data were collected through, reviewing published international conventions and
protocols ratified by the Federal Democratic Republic of Ethiopia (FDRE), national and regional
state policies, legislatives, regulations and guidelines related to environment and base line data
(rain fall, master plan population, health service.) were also collected from stakeholders and
authorities with whom consultations made at the project area, Dessie city cabinet members,
local sector offices (Dessie city service, agricultural office finance and local economic office).
Primary data were collected using observation, focus groups discussion, general public meetings,
and key informants.
Checklists and camera was used to collect data from secondary sources from site observation,
camera was used to collect information from site observations and meetings, interview and FGD
guide used to track discussion and collect information.
17
procedural Guidelines, Amhara region Revised EIA Guidelines, Environmental Impact
Assessment Guidelines on Road were reviewed.
To meet the requirements of both the national and regional regulatory authorities and ULGDP’s
ESMF and seek the views and concerns on the proposed Salaysh-SegnoGebya gravel road
project, formal as well as informal consultations were conducted with concerned officials and
experts at different administrative levels, and with representatives of the local community of the
affected and interested groups (Dessie city municipality,).
Formal public hearing and consultations with participants from different society groups was held
at Kebele 01 and 02meeting hall on March, 22, 2012- March 30, 2012 (see photo on Figure 1.).
In addition, discussions were conducted with semi structured interviews with relevant individuals
and institutions at City, woreda and Kebele levels to solicit their views, concerns and comments
to maximize the social and environmental outcomes of the project, obtaining key information
from indigenous and current experiences and knowledge, impact identification , scoping,
examination of alternatives , planning of potential mitigation measures and identify deliverables
that can be provided by different stakeholders.
Public consultation was extended beyond the affected community in the project area, to
understand the views of any member of the public that is knowledgeable on the impacts of the
project or is better informed on environmental trends of the project area.
Based on the discussions made with the communities, they reflect their fear and suggest the
possible adverse impacts associated design, construction and implementation of the gravel road
project (a) Displacement of local communities,(b)aggravate landslide and flood hazard,(c) loss
18
of market places(Segno-Gebeya),(d) loss of fences, shops and plantation trees, and(e) impact on
telephone lines and waterlines. However, the community has also mention the advantage of the
implementation of the project like (a) Improve access to markets, (b) Improve access to health
facilities, and linkage with other Kebeles (c) increase land value and improve health condition,
(d) Reduce traffic accident, and (e) creates employment opportunity during road construction
phase as well as operational phase.
3. Project Description
3.1. Project Location
Dessie city is located between 110 13’ N latitude and 390 65’ E longitudes. It is situated at about
400 km distance North of Addis Ababa on the high way to Mekelle. The proposed gravel Road
Project is located in Dessie city and connects two kebeles of the city, namely kebele 01 and 02 to
the main road and market place of the city (Segno gebeya).
19
The location
of Dessie city
Figure 3: Showing location of the city within which the project is located
Among the critical problems identified by Dessie city administration, the heavily damaged and
heavily trafficked earth roads for kebele 01 and 02 is one of the major problems of the city. The
proposed road development project will have a length of 2 km.
According to the reports of the Administration, the above kebeles (the project area) do not get
adequate transport services due to heavy damage of road. Most of social services such as health,
schools, and market place and bank services are confined in the center of the city where adequate
road and transport facilities are available. As a result, the community in the study area in general
and mothers in particular were facing various problems and difficulties due to lack of transport
20
services in the area. The problems are very acute during the time of pregnancy when women
have to walk on foot for long distances or are carried on horse carts to receive medical checkup
or to have delivery. The long walk they make on foot or on horse carts expose them to difficult
situations and unexpected problems.
In addition to the problem of road accessibility, lack of proper drainage system in the above
kebeles is also another bottle necks. The run off originated from the tip of the hills that
surrounded the city were drains down towards the city creating flood at various places. Despite
the fact that the city is threatened by flood, the existing drainage system covers only a small part
of the city, mainly the central part just following the road route. Consequently, the project area is
suffering not only from lack of road access but also from the problems of flood.
Therefore, the construction of the proposed road project will offer the local community easy,
comfortable and quick access to markets and other social services. Following the increased
access and transport opportunities, other socio-economic development will follow including
education, health, communication, market, and banking. The project will reduce travel time to
the social services by mode and location particularly to the clinic and Hospital that are found in
Dessie city.
21
3.3. Project activities
The project work mainly involves foundation excavation and compaction of Sub-base and Road
base course at the road location, while material production and transportation will be done at
outside of the city centers.
Internal diameter of 90cm Concrete pipe for storm water drains including Class B bedding.
Internal diameter 15cm Concrete pipe for inlet of water to the ditch every 30m interval both
sides.
Curbing, channeling, open chutes, down pipes and concrete lining of open drains
Concrete Curbing C-25 Concrete as Shown on the detail to be used at the edge of Asphalt
road. Cost including production, hauling & Placing
Concrete Curbing C-25 Concrete as shown on the detail no 2 to be used at the edge of the
median & Side walkway. Cost including production, hauling & Placing
Cast in situ Concrete lining of C-20 Concrete for Rectangular Open drains
5cm thick Cement Screed surface finish to cast in situ concrete
22
Cement-mortared stone walls(for retaining wall)
Ancillary Works
Erect and construct 14 Signboard and Sign faces with painted background, Symbols, lettering
and borders in engineering grade retro-reflective material with 2mm thick aluminum the Area
not exceeding 2 sq m
Office Building and laboratory Building Complete as specified including furniture
Similar to other developmental projects; the proposed gravel road construction project that
passes through kebele 01 and 02 Project is influenced by several policies and programs aimed at
development and environmental protection. Therefore; policies, legislations and institutional
frameworks most relevant to development projects in general and to the proposed project in
particular are presented and assessed for relevant.
23
and the environmental rights of the people are enshrined in the constitution by the following
articles that stipulate the rights of peoples in country.
The policy seeks to ensure the empowerment and participation of the people and their
organizations at all levels in environmental management activities, and to raise public awareness
and promote understanding of the essential linkage between environment and development. In
addition to its guiding principles, the policy provides sectoral and cross-sectoral environmental
policies.
24
4.1.4 Sectoral Environmental Policies
The detailed sectoral environmental policies and strategy together with the related law and
regulation are currently in various stages of preparation. One of the policies is the wildlife policy
developed by the Ministry of Agriculture whose prime objective are the preservation,
development and sustainable utilization of Ethiopia's wildlife resources for social and economic
development and for the integrity of the biosphere. This is at present in draft form and covers a
wide range of policies and strategies relating amongst others, to wildlife conservation and
protected areas. A forestry management policy is also under preparation by the Ministry of
Agriculture, to address the problems posed by continued deforestation arising from the use of
wood in construction and as domestic fuel. Water Resources Policy has been formulated by the
Ministry of Water Resources and Biodiversity Policy by the Ministry of Agriculture.
Article 3.4 of the policy states that inter-sectoral collaboration shall be emphasized in developing
safe disposal of human, household, agricultural, and industrial wastes and encouragement of
recycling'. Article 5.2 states that the promotional and preventive activities shall address
'prevention of environmental pollution with hazardous chemical wastes'.
25
“All persons who have been displaced or whose livelihoods have been adversely affected as a
result of state programs have the right to commensurate monetary or alternative means of
compensation, including relocation with adequate state assistance.”
This is the basis for the compensation procedures established by the ERA has and likewise, the
legal framework for the present resettlement and rehabilitation policy framework.
Furthermore, by signing the credit agreements for the RSDPSP (credit 3032) and the RRP (credit
2438) with IDA, The Federal Democratic Republic of Ethiopia committed itself to abide the
involuntary resettlement policy of the World Bank and both parties do agree on the fact that
development projects should not be realized at the expense of the people affected by the projects.
Thus, the legal framework of the RSDPSP are the Ethiopian constitution as transcended into the
ERA procedures and the World Bank Operational Directive (OD) 4.12 on involuntary
resettlement and its operational policy as spelled out in Involuntary Resettlement Sourcebook:
Planning and Implementation in Development Projects.
Apart from the broad policy frameworks at national level, the main reference behind the
preparation of a Resettlement Action Plan (RAP) is ERA's guiding principles as stipulated in its
Resettlement and Rehabilitation Policy Framework. The following statement is quoted from the
ERA's Resettlement and Rehabilitation Framework to show when and where a RAP is required
or not.
At project identification, social screening/social impact assessment (SIA) of the subprojects will
be conducted with the aim to determine whether or not a subproject requires detailed
resettlement action plans. The principles of compensation/rehabilitation will be triggered
wherever there will be a land requirement and adverse social impacts. Should, however, the SIA
findings reveal that more than 200 persons are affected by a subproject, a resettlement action
plan will have to be prepared (ERA 2002). In the same issue the World Bank OP/BP 4.12, as
referred in ERA's Policy Framework, states:
As per the above framework, a threshold has been set whether or not to proceed with a detail
RAP once a social screening is done on any proposed road development project. Road
development that entails the relocation of more than 200 individuals or about 40 households is
expected to draw up a resettlement action plan. Those road projects that would displace less than
200 individuals are not expected to come up with a detailed/full scale RAP and instead
26
appropriate compensation measures for lost assets, arrangements for logistical support and a
relocation grant have to be made.
This law also re-established the Environmental Protection Council, a cross-sectoral co-
coordinating body that advises the federal EPA and supervises its activities. The mandate of the
Council includes: (i) reviewing environmental policies, strategies and laws proposed by the EPA
and issuing recommendations to government; (ii) providing appropriate advice on the
implementation of the Environmental Protection Policy of Ethiopia; and (iii) reviewing and
approving directives, guidelines, and environmental standards prepared by the EPA.
Projects will be subject to EIA in the plan stage and execution is subject to an
environmental clearance from the EPA or Regional Government Environmental Agency,
as applies;
EPA or the Regional Agency, depending on the magnitude of expected impacts, may
waive the requirement of an EIA;
27
All other licensing agencies shall, prior to issuing of a license, ensure that either EPA or
the regional Environmental Agency has authorized implementation of project; and
A licensing agency shall either suspend or cancel a license that has already been issued,
in the case that EPA or the Regional environmental agency suspends or cancels the
environmental authorization.
The proclamation is based on the principle that each citizen has the right to have a healthy
environment, as well as the obligation to protect the environment of the country. It contains
provisions for Control of Pollution, Management of Municipal Waste, and Management of
Hazardous Waste, Chemical and Radioactive Substance. It also encompasses provisions for the
formulation of practicable Environmental Standards by the EPA, in consultation with competent
agencies. Furthermore, it empowers the EPA or ERA to assign Environmental Inspectors who
have powers and duties to control pollution.
28
4/1975 states that the Government shall pay fair compensation for property found on the land,
but the amount of compensation shall not take any value of the land into account, because land is
owned by state.
Proclamation No.55/1993, article 5.2, states that ERA shall use, free of charge; land and such
other resources and quarry substances for the purpose of construction of highways, in
construction of camp, storage of equipment and other required services, provided, however, that
it shall pay compensation in accordance with the law for properties on the land it uses.
The Right-of-Way (ROW) is the land allocated and preserved by the law for the public use in
road construction, rehabilitation and maintenance work. For example in the Rural Road (RR50)
standard 15m width on either side of the road centerline fall into the legal ROW.
The document details the required procedures for conducting an EIA in Ethiopia and the
requirements for environmental management. These requirements are presented on a step-by-
step basis in the guideline. In addition, the document specifies tools that may be considered when
engaging in the EIA process. Reference is made to the legislation and policies with which
potential investors and developers in Ethiopia must comply and key issues for environmental
assessment in specific development sectors are detailed for consideration.
29
In addition, the EIA Guideline provides the categories, the relevant requirements for Ethiopian
Road Authority (ERA) and lists project types under each category. In accordance with this
Guideline, projects are categorized into three schedules:
Schedule-I: Projects, which may have adverse and significant environmental impacts and
therefore require a full Environmental Impact Assessment.
Schedule-2: Projects whose type, scale or other relevant characteristics have potential to cause
some significant environmental impacts but are not likely to warrant a full EIA
study.
Schedule-3: Projects which would have no impact and do not require an EIA.
Accordingly, rural road programs fall into Schedule 1 and major rural road upgrading/
rehabilitation fall into Schedule 2. However, projects located in environmentally sensitive
areas such as land prone to erosion; land prone to desertification; areas of historic or
archaeological interest; important landscape; religiously important area, etc. should be
treated as equivalent to Schedule 1 activities.
30
4.3.1 Federal and Regional States
The Federal Democratic Republic of Ethiopia (FDRE) was formally established on 1995. The
FDRE comprises of the Federal states with nine Regional State members. The roles of
government at the different levels (Federal, Regional and Local) are defined by the Constitution
(1995) and Proclamations No. 4 of 1995. The government structure takes power from the centre
to Regions and Woredas. Under these proclamations, duties and responsibilities of Regional
States include planning, directing and developing social and economic programs, as well as the
administration, development and protection of natural resources of their respective regions.
The key functions of EPA are defined in Proclamation 9/1995 and may be summarized as
follows:
preparation of environmental protection policies and laws and to ensure that these are
implemented
This Proclamation re-established the EPA as an autonomous public institution of the Federal
Government of Ethiopia. It also empowers every competent agency to establish or designate an
environmental unit (Sectoral Environmental Unit) that shall be responsible for coordination and
follow-up so that the activities of the competent agency are in harmony with this Proclamation
and with other environmental protection requirements. Furthermore, the Proclamation stated that
each regional state shall establish an independent regional environmental agency or designate an
existing agency that shall (based on the Ethiopian Environmental Policy and Conservation
Strategy) be responsible for:
to establish a system for EIA of projects, policies, strategies, laws and programs
to enforce implementation of this EIA process (i.e. review EIA reports) and the
recommendations which result from it for projects that are subject to Federal licensing,
execution or supervision
32
to enter any land, premises or any other places that falls under the Federal jurisdiction,
inspect anything and take samples as deemed necessary with a view to ascertaining
compliance with environmental protection requirements
In view of the multi-sectoral nature of the EPE and the number of government agencies
involved in various aspects of environmental management, overall co-ordination and policy
review and direction is the responsibility of an Environmental Protection Council (EPC)
within EPA, whose members represent the key agencies concerned with policy
implementation and representatives from the civil society. With these powers, EPA has the
mandate to involve itself on all projects that have a federal, inter-regional (involving more
than one Region) and international scope.
33
purpose of Environmental Assessment is to improve decision making, to ensure that project
options under consideration are sound and sustainable, and that potentially affected people have
been properly consulted.
The World Bank's environmental assessment policy and recommended processing are described
in Operational Policy (OP)/Bank Procedure (BP) 4.01: Environmental Assessment. This policy is
considered to be the umbrella policy for the Bank's environmental 'safeguard policies' which
among others include: Natural Habitats (OP 4.04), Forests (OP 4.36), Pest Management (OP
4.09), Physical Cultural Resources (OP 4.11), and Safety of Dams (OP 4.37), Involuntary
Resettlement Policy (4.12).
34
Salaysh Kebele
Segno Gebya
Road to Mekelle
Road to Addis -
Ababa
35
5.1.2. Topography
The project area of Dessie Town is characterized by significant variations in topography. As we
prepared elevation map from 30m DEM, altitude variations, range from 1924 meter, in low lying
river valley bottoms to about 3037 meter above sea level in the nearby Tossa mountain ridges.
And the proposed road scheme is in range of 2369 to 2592meter above sea level, slopes ranging
from 0.024 to 19 degree.
5.1.3. Climate
There is Dessie meteorological station in project area. At this station highest rain fall and average
maximum and minimum temperature data were recorded. The maximum rains fall data are
received in months of July or August, when the full effect of inter-tropical convergence zone
(ITCT) is observed. The details of highest rainfall, average maximum and minimum temperature
data for Dessie station are shown in the table 3.1, 3.2&3.3 respectively.
Rainfall
Like other parts of the country, Dessie is also experiencing four seasons. These are:
36
Belg (small rains)
Meker (a spell between the main rainy season and small rains)
The hydrologic analysis result that rainfall is the major factor controlling the water cycle of the
area of orographic type, which is formed from condensation of the vapors driven by winds
against highly elevated parts of the area.
The rainfall is weakly bi-modal with a small rainy season during the months of April and May
while along rainy season is experienced during summer comprising the months of July, August
and September.
The rainfall recorded at Dessie metrological station for the past 18 years (1994-2011) indicated
that the mean annual rainfall is about 866.25mm. The proportion of the precipitation in the
months of July and August is about 55% of the annual total. The mean monthly rainfall that
characterize the area for 18 years range from 10.00 mm in December to 228.6 in August.
37
Temperature
Two years (2010-2011) data is obtained from Dessie station for monthly mean temperature. The
two years average value shows that the mean annual temperature of the city is 24.025 0C. The
hottest month with the maximum temperature of 27 0c is May and June while the coldest month
is November and December with the minimum mean temperature of 5 0c and 5.50c. Thus, the
two years average value show variation which range from 5.50c and 5 0c (for November and
December) to 27 0c and 25 0c (for May and June)
J F M A M Ju J A S O N D
Max 21.6 23.3 22.4 24.1 25 27 25.3 25.1 25 24 22.9 21.5
Mimi 7 7.3 8.9 9.4 9.6 9.8 10.2 10.3 8.8 6.2 5 5.5
5.1.4. Geology
5.1.4.1. Regional Geology
The regional geological setting of the stream basin is part of the geological history of the Afro
Arabian geology; the regional geology of the project area can be summarized as follows:
The Precambrian basement complex does not outcrop in the project area. The Mesozoic
sedimentary rocks are observed at some places in downstream. The bedrock in the upper and
middle catchments is mainly Trap Series basalt. The Series is divided into two groups, namely,
Ashangi and Shield Group, and the two groups are similar in litho logy.
The Ashangi Group comprises the older volcanic rocks which were formed by lava and debris
ejected from fissure eruptions. It covers most of the project area and consists predominantly
rhyolitic and ignimbrite with inter-bedded pyroclastic, trachyte. The eruptions took place at
intervals and in some locations there was sufficient time between different episodes to allow
inter-bedded soil or pale soil layers to form.
38
formation to the plain area; the Ashangi formation corresponds with the surrounding ridges and
mountain whereas the quaternary volcanic and sediments with the plain area.
A) Volcanic rock
The volcanic ridges and mountain those encompass the project area/ the study area/ are
dominated by the trepans series especially the Ashangi group volcanic. These Ashangi Group
consists of predominantly highly weathered and jointed at the top rhyolitic/ignimbrite acidic rock
which forms mountain and ridge both upstream and downstream of the project site and around the
project site. This rock is the major construction material within the project and around the project
and it occur widely and predominantly in the project site. It has low strength compared to basaltic
rock origin and it has variegated color which is yellow, white and pink colors. The top part of this
rock is highly weathered and covered by dark brown silt clay soil which is developed from
underlying rock in the most part of the study area. This rhyolitic/ignimbrite rock exposed widely
at the top of mountain and ridge and in some amount it exposed along the river bed
B) Quaternary Sediments
The quaternary sediments are all unconsolidated deposits that filled the river water way and come
from surrounding area and mountain. It also located in some amount along the river banks (older
deposit).It has shallow depth on river bed. The erosion/transportation from the highland and
deposition of sediments in the river bed is a continuous process to the present as witnessed in the
field.
This sediment deposits are composed of gravel and sand. While the deposition of the larger
materials like boulders, cobbles, and pebbles is restricted to narrow transportation and the fine
materials reach furthest extremes of the area following flood plains of streams and much in
Project River.
39
5.1.5. Soil
The soil types reflect the combined effects of soil formation factors: geology (primarily fine
grained, weathering to produce clays), climate (moderate to high rainfall), topography (with
distinct variation between sites on slopes red soils) and time. Climate, topography and human
settlement are the main factors that have influenced both the land use and the natural vegetation
cover type. The nature of soils and the landscape combined with factors such as a long history of
settlement, prevailing agricultural practices, and increasing population pressure which forces
people to cultivate even steeper slopes all exacerbate land degradation.
The dominate soil type of the specific project site (the road alignments run) is lithic Leptosols.
While the soil types of Dessie town administration are Eutric Vertisols and Lithic Leptosols. As
it can be seen from the soil map, the dominant soil type is Lithic Leptosols which accounts
16831.73 ha (97.92%) followed by Eutric Vertisols 355.81ha (2.08%).
Leptosols: Leptosols accommodates very shallow soils over hard rock or highly calcareous
material but also found on deeper soils that are extremely gravelly and/or stony. Leptosols are
azonal soils with an incomplete solum and/or without clearly expressed morphological features.
They are particularly common in mountain regions. Leptosols correlate with the ‘Lithosols’ taxa
of many international classification systems (USA, FAO) and with ‘lithic’ subgroups of other
soils groupings. Leptosols include a wide variety of soils with greatly differing chemical and
physical properties. By and large, Leptosols are free-draining soils with the exception of certain
Hyperskeletic Leptosols that may have groundwater at shallow depth.
Vertisols: Vertisols are mineral soils that are more than 50 centimeters thick; contain 30 percent
or more clay in all horizons and have cracks at least 1 centimeter wide to a depth of 50
centimeters, unless irrigated at some time, in most years. The typical vegetation in natural areas
is grass or herbaceous annuals, although some Verticals support drought-tolerant woody plants.
The high content of swelling clay and movement of soil by expansion and contraction retard the
development of B horizons
5.1.6. Hydrogeology
As indicated in the previous sections the existing geology and geomorphology of the project area
are characterized by jointed bed rock, and gentle to moderate slope landform respectively. These
conditions are suitable for the infiltration, percolation and consequent storage as groundwater of
40
significant amount of the precipitation in these weak zones. Close observation and estimation of
the discharge (base flow) of the stream at the project area and surrounding areas both up- and
down-streams indicates that the recharge of the groundwater to the stream flow is significant. It
increases to downstream direction. This observation can also be confirmed by the existence of
springs, which are found at the periphery of the stream floodplain/bank foot. The area's
groundwater is stored within weathered section and jointed part of the bedrock, which are
overlain by fine- grained soils at many places. The main recharge of ground water is subsurface
recharge (movement of ground water from neighboring area by percolation).
The present poor vegetation cover in the road alignment and surrounding area shall be improved.
Plantation of trees in the road environment could provide benefit such as shade, soil conservation
and prevention of gullies, scenery, and protection from dust and wind.
5.1.7.2 .Fauna
The proposed road project doesn’t cross any protect natural habitat that can be used for feeding
and breeding of important fauna. The proposed road runs through urban area, the route corridor
has no wildlife reserves or habitats that can provide protection for wild animals.
41
Table 5. Population Size of Dessie Town by Sex Distribution, 2011
Source: CSA, Population Size by Sex, Area, and Density by Region, Zone and Woreda, 2011
The settlement pattern of communities around the project area has created significant problem in
the provision of infrastructure and other services. This is mainly due to the unfavorable
topography of the place which is dominated by mountainous and gorge landscape. This
combined with landslide problem that is recurring along ‘Tossa’ mountain ridges has forced
some residents to think resettlement to other better places.
5.2.3. Education:
Dessie city is one of the cities in Ethiopia which host quit large number of students attending
their higher education studies. Dessie University, government and private College, technical
training center, the higher education institutions found in Dessie. The University of Dessie is
established and open on 1996 Ethiopian calendar alone receives ten thousand students in evry
42
year. The University of Dessie is located at the northern periphery of city. The city also has 9
high schools, 37 primary schools, and 28 kindergartens. The number of students of Dessie for the
year 2005 is 40,526. Among these 19,804 are female and 20,722 are male. See below the table
1 University 1 1 2
2 College 2 3 5
3 Technical 1 0 1
training center
The land cover in Dessie town administration is categorized into 8 major classes. The major
classes are the built up area, cultivated land, exposed surface, forestland, grassland, marsh land,
Shrub and bush land, and water body. From the 8 major lands, cultivated land (54.85%) takes the
lion’s share followed by Shrub and bush land (19.50).
As it can be seen from figure.8 (the proposed road alignment superimposed with the land
use/cover, the proposed road alignment passes through built up(urban) area. The proposed road
does not cross any protect natural forest, grassland and cultivated land. The area distribution in
the sub-basin by major land cover is presented in the table below (see the details from the table
below).
43
Table 8 Land Use/cover of the Dessie Town Administration
44
Figure 8.Dessie Town Administration Major Land use/cover map, 2012
The existing road network comprises of about 45.8km long asphalt road, 105.3 km Gravel road
and 47.7km earthen roads and Cobblestone 31.52km road making a total of about 230.32 km.
The road density in the city is 0.00131 km per person. Some of the existing road network like
45
Salaysh-Segno Gebya road is in a very poor condition. Large part of it deteriorated causing a lot
of problems to traffic and has substantially increased the maintenance cost of vehicles, has
heavily increased property loss and disturbs the day-to-day activities of the dwellers. The modes
of transport in the city include horse-drawn carts and taxis. More than 200 carts, around 200 taxis
and Tagro bajaj 80 are rendering the transport service to the city. The city also gives service for
passengers travelling to Addis Ababa, Mekelle, Woldeya, Bahirdar, Lalebela, Western woreda of
South wollo zone , Asayta city and vice versa.
The table below shows the length of asphalt, gravel and compacted earth surfaced roads in
Dessie city studied by the Dessie city infrastructure department.
46
6. Project Alternatives analysis
From a purely natural environmental point of view, the “without project” scenario is preferable
to project implementation, since it would avoid creation of any of the activities related the
project construction and operations and related adverse environmental consequences. However,
the potential social and economic benefits would be foregone; this might be true for other
project. The above is not true for the case of the Salaysh-Segno Gebya gravel road. As discussed
on section of project description one of the upmost environmental and social issues in the city of
Dessie is attributed to the lack of proper road services. Because no action” without the project
means letting the environmental and social issues of the existing earth road to aggravate.
Hence the “without project” alternative is inappropriate not only from social and economic
viewpoint, but also more strongly from the environmental stand points. Since implementation of
the project will improve the present worst social and environmental condition of the city and
associated safety and health issues.
Salaysh-SegnoGebya gravel road project was proposed by Dessie Municipality with the purpose
of adjoining kebele 01 and 02 to the main asphalt road and market places as per the master plan
of the town. The construction of the gravel road does not have other alternative basically for two
major reasons. These are:
a) The proposed road route is based on the master plan of the town and thus, changing the
route could induce the change of the master plan of the town that actually was very
difficult and lengthy process,
b) During master plan preparation, the gravel road route was proposed through thorough
analysis due to the fact that it connects various feeder roads and also connects the
aforementioned two kebeles to the center of the town and main market places.
Therefore, there is no option to change the proposed road route as any alternative action induces
change to the master plan of the town.
47
7. Environmental Impacts Identifications, Prediction and
Analysis
This part of the report addresses potential impacts associated with the proposed gravel road
construction project and analysis of the related impacts.
The major positive impacts of the proposed project are mainly those of solving the lack of access
roads, poor transportation services and establishment of proper drainage system, while adverse
impacts are mainly related to the involuntary resettlement of about 221 householders.
The project environmental impacts have been those identified as specific to the site such as land
clearance, removal of soil and vegetation, land escape alteration particularly at quarry site, silt
deposition and pollution.
The feasibility study of the project indicates that the road construction will create direct job
opportunity for more than 300 citizens of labour and technical experts during the construction
phase within which most of them will be local residents.
48
for social livelihood improvement in the project area. This local income generation related social
benefit will have long term as well as cumulative benefits: As a result of creation of jobs, the
project will have a meaningful impact on poverty reduction as the project area is inhabited by
largely unemployed citizens, the employment priorities would focus on households subsisting
below the poverty line.
The project will modify the natural flow of surface water and drainage patterns along the road
alignments by concentrating flows. Earth works for road construction and foundation of drainage
49
structures, and excavation at quarries and borrow pits can result in an increased soil erosion,
temporarily cut-off the normal natural flow and ultimately siltation in the streams and decline in
water quality. In most places, it is common to see substantially high amounts of silts collected at
side ditches that will eventually discharged into water courses. Furthermore, accidental spillage
of fuels, oils, greases and other pollutants during construction phase can have adverse effects on
water qualities of the streams that would eventually receive those effluents charged with
pollutants. Abstraction of water from rivers for road construction and perhaps for application of
water to suppress dust and for road construction may affect the daily demand of the downstream
users (demand for animal, ecological and irrigation).
Excessive noise levels can also occur from the vehicular movement during operational phase,
there will be a significant increase in vehicular movement, generally, and it is recommended that
noise levels in residential areas should not exceed 55dBA.
50
The housing units that would be affected by the proposed road are either residential houses or
commercial houses (shops, flour mills etc) made of wood and plastered with mud in most cases.
The total number of houses affected by the project is 221 (along Salayesh -Segno-Gebeya Road
alignment) details about compensation cost, see RAP document.
Loss of Fences
Different types of fences such as wood, wood and iron wire, masonry and hallow block, masonry
and corrugated iron sheet, and masonry only will be affected and compensation fee is prepared as
per the guideline.
Loss of Plantation Trees
There is no protected natural forest or vegetation in the road alignment and surrounding area
because the proposed road passes through the town. Though no significant impact on this
vegetation anticipated during the road project construction since the road project is follows the
existing road and settlement, compensation fee is paid for those who owns.
According to the inventory 222 telephone poles, about 289 Electric poles and 6 transformers
will be affected by the proposed road project.
51
The impact of the proposed development project on the traffic flow is generally to increase the
traffic volume in the area. Clearly, there will be more vehicle movement and traffic activity
along the Salaysh-SegnoGebya.
52
Erosion is also envisaged on embankments. Compact the soil on embankments in a well
compacted manner and planting with grasses can minimize the erosion problems on
embankments.
Minimizing vegetation cutting during construction as well as provision of standard side and
cross drains will minimize the problem.
Cut of topsoil (excavated soils) should be used for replanting improvements of the
embankments and to refill borrow pits.
Adopt regulation (in consultation with the local communities and their leaders) that prohibit
livestock grazing on road shoulders, embankments, and right-of-way, as necessary,
Public education on soil conservation, and road influences on erosion and sedimentation;
Design and execute adequate and proper drainage structures to reduce erosion or
sedimentation in drainage ways affected by road construction.
Avoid the risk of pollution to soil, surface and ground water sources through the
reduction of accidental spillage of fuels, oils, greases and other pollutants
Whenever there is conflicting demands on water resources between the local people and
the need for road construction, always give priorities to the local people
Implement proper disposal of solid and liquid wastes generated by road construction
activities.
53
8.4. Mitigation measure impact Air Quality, Noise and Vibration
During the road construction period, haulage of construction material increase dust, noise and
vibration. Since the road passes through settlements, raised dust and noise can cause
considerable nuisance, and can result in increased incidence of respiratory related diseases.
Mitigation measure to minimize impacts on noise and vibration:
Reduce noise at the source by monitor and maintenance on noisy machines to minimize its
effects on people living around the project;
Noise and vibration arise from crushing process should be minimized through adequately
designing of the foundation for the facility;
use mechanical hammering which reduces the noise level;
Reduce dust by watering the road to suppress dust
Plant 2m tree buffer strips between road and surrounding habitation
The project will have moderate impact where operation of quarry sites and borrow pits are
practiced. The possible mitigation is,
Borrow areas or quarry sites should be excavated and fill areas filled in such a way as to
facilitate rehabilitation and reinstatement.
After completion of the works, all sites should be rehabilitated and restored.
Large borrow areas should be replanted or transformed into ponds (in consultation with the
competent local authorities).
Where possible, trees along borrow areas or quarry sites edges should be protected.
Cut of topsoil should be used for replanting improvements of the embankments and to refill
borrow pits.
54
8.6. Mitigating measures Impacts on Socio-Economic Environment
The project impact on property which is higher significant due to the presence of settlements.
The recommended mitigation measures for impact under consideration include:
Before clearance of services and property the site for relocation should be designated and
alternative service for water, electricity and the like should be provided. Such sites should be
away from areas for water harvesting and from ground water sites.
The Affected groups should be aware before any property or service is damaged and they
should be consulted for options.
Payment of full and fair cash compensation, which leaves those, affected by relocation at
least no worse off than they were previously.
Minimize the area of ground clearance i.e. land clearing for road construction should be
restricted to what is absolutely necessary for the road construction;
Replanting right species of trees on the road side that could provide benefit such as shade,
soil conservation and prevention of gullies, scenery, and protection from dust, noise and wind
etc.
55
place. Areas such as sites where there are schools, market places, religious and belief sites as
well as residential areas need special attention. In order to mitigate the impact the following is
recommended:
It is necessary to make every reasonable effort to minimize road safety hazards and
inconvenience to other road users, resulting from the passage of his, or his subcontractors'
haulage vehicles, and should impose and enforce compliance with speed limits that may be
established for construction traffic at lower speeds than usual
Proper signs should be in place and training for drivers should be provided to ensure
traffic safety
Maintain supply of supplies for traffic signs (including paint, easel, sign material, etc.),
road marking, and guard rails to maintain pedestrian safety during operation phase.
Carefully and clearly mark pedestrian-safe access routes.
The local people ought to get more information how to behave with motorized vehicles
and keep safe their livestock.
Properly place hazard marks and signs to limit vehicle speeds especially for sections
passing through difficult terrain and denser settlement areas.
56
Table 10.Summary Major Impacts and Proposed Mitigation Measures
phase
Project
grabbing by heavy machineries the road should follow the natural relief as
closely as possible
Careful and proper execution of
construction works
Avoid and/ or minimize side casting of
materials from road cuts on down slopes.
Minimize the area of ground clearance
Construction Phase
Cutting into the soils and rock as well as clearing Impacts on soil Contractor No need
of the protective ground cover to construct the erosion Cuts on erodible surface should be
cost
road. properly executed during dry season i.e.
before the summer rains commence.
Construction of drainage structures (bridges,
Excavated top soils or loss soils cut-off
culverts) and construction of retention walls that
from the old road and selected material
involve excavation for foundation works
sites should be collected and preserved for
Excavation at quarry sites will expose the soil to reuse particularly clay soils for filling of
water erosion gullies, borrow and quarry sites
57
Design and execute adequate and proper
Construction Phase
Earth works for road construction and foundation Impact on Water Contractor No need
drainage structures to reduce erosion or
of drainage structures, and excavation at quarries Resources cost
sedimentation in drainage ways affected
and borrow pits can result in an increased soil
by road construction.
erosion.
Avoid the risk of pollution to soil, surface
Accidental spillage of fuels, oils, greases and other
and ground water sources through the
pollutants during construction phase
reduction of accidental spillage of fuels,
oils, greases and other pollutants
Implement proper disposal of solid and
liquid wastes generated by road
construction activities.
Reduce noise at the source by monitor and
Construction Phase
58
The contractor should erect stone slips and
Construction Phase
Along the Robit road, the settlement area is Accidents from No need
falls control barriers around perimeter of
situated beneath the existing road as a result of Slips and falls of cost
cuts, and roadways
this, hazards related to slips and falls of stone and Stone and soil
soil materials will occur Materials
Construction Phase
59
Carefully and clearly mark pedestrian-safe
OPERATION
Lack of safe access routes Absence of traffic sign Traffic Accidents City admin 50,000
access routes
and pedestrian safety during construction and Safety Risks
Assign traffic safety personnel to direct Police office
traffic during school hours
Maintain supply of supplies for traffic
signs, road marking, and guard rails to
PHASE
City 100,000
Infrastructure (road) and proximity to drainage Landslides, Slumps Draining the subsurface (reduces pore
Adm.
will aggravate landslide in the project area. and Slips water pressure)
Construct artificial barriers
Reduce slope angle
PHASE
OPERATION
60
9. Environmental Management and Monitoring Plan
The environmental management plan and monitoring plans can be seen as protection
against environmental degradation for long term benefit to the society for continued socio-
economic development and environment.
The EMP will ensure the effective implementation of identified mitigation measures. The
proper implementation of construction works with professionals and careful supervisors
and well planned maintenance afterwards will be the best mitigation measures against most
of the potential negative environmental impacts. Various organizations with different
environmental management responsibilities, Dessie city Administration, Dessie City
Kebele Administration(Kebele 01,02,), Dessie City Infrastructure and ULGDP Co-
ordination Core Process, Dessie town Ensuring Sustainable Environmental Protection Core
Process, interested and affected parties(IAs),study and design consultants(ADSWE),
contractors, and construction supervision companies-have been involved during project
preparation and implementation, and will be involved in the implementation of the EMP.
The main environmental issues, their mitigation measures and implementing bodies are
presented in table 7.
to check on whether mitigation and benefit enhancement measures have actually been
adopted, and are proving effective in practice
61
to provide a means whereby any impacts which were subject to uncertainty at the time
of preparation of the EIA, or which were unforeseen, can be identified, and to provide a
basis for formulating appropriate additional impact control measures
To provide information on the actual nature and extent of key impacts and the
effectiveness of mitigation and benefit enhancement measures which, through a
feedback mechanism, can improve the planning and execution of future, similar
projects.
1) Compliance monitoring, which checks whether prescribed actions have been carried
out, usually by means of inspection or enquiries.
62
Table 11- Environmental and Social Impact Management, Monitoring plan
1 CONSTRUCTION PHASE
1 Erosion, slope Stability Survey& Extent& degree of soil erosion& Road alignment, Daily Supervisory
. and waste Management observation landslide, Ensure excavation and drains, quarry Staffs, EPLAUB
1 earth work undertaken during dry sites, dredged and Project
season and to areas necessary only, river areas Proponent
Ensure a proper site for waste
dumping.
1 Clearing, Earthworks & Survey Land clearing earthworks should Road alignment Daily Supervisory
. Waste Management &Observation be confined to what is absolutely Staffs, EPLAUB
2 necessary and Project
Proponent
Do excavation works during dry
season
Ensure a proper site for waste
dumping
1 Noise, Dust and Survey, Collect Level of dust, noise and number of Road, Crusher Daily EPLAU and
. Vibration samples and field community complains about noise. sites/Quarry site Project
3 observation Proponent
1 Quarry Site Visual inspection The extent/size of quarry, Quarry Site Three times .
. &Photographic constructed ditches, soil for first one
EPLAU and
4 record conservation and Revegetation year,
Project
activities annually
Proponent
thereafter
1 Traffic Safety Survey, Posting of warning signs or safety Road & Offices daily Supervisory
. Interview &field signal devices in construction areas Staffs,
5 observation &at material sites EPLAUB and
Project
Traffic and workers occupational
Proponent
safety
63
Number of accidents reported per
month
2 Impact of Road Noise Survey and field Number of community complain Roads& EPLAU and
. observation about noise Settlement areas Project Proponent
3
Check the plantation of tree buffer
between road &surrounding
habitation
64
9.3. Environmental and Social Monitoring
This part of the report presents the estimated total cost for environmental management,
monitoring and training cost of the proposed road construction project. Hence; as it was
mentioned above, the scale and magnitude for most of the project impacts; particularly the
site specific one, is not known at this stage (prior to the detail geometric design and material
investigation), the consultant’s summarized cost estimate a preliminary one. This is true
particularly for costs associated with compensation of PAPs, land acquisition and ROW
issues. Therefore, these preliminary costs estimate to be refined and updated in the final land
acquisition and RAP report.
The preliminary cost estimate was made based on past experience on similar projects and from the
Consultant’s EIA findings. Thus, the preliminary Costs related to environmental and social benefit
enhancement and impact mitigation measures, etc. taken into account include:
Costs related to erosion prevention, control and management (soil conservation and
erosion prevention and management and land use management programs, tunnel safety
measures) and mitigating land slides
Costs related to the resettlement and compensation for loss of properties as well as
livelihood (loss of houses, farmlands, plantation trees)
Costs related to the loss of privately owned trees and natural vegetation restoration
65
Roadside Tree Plantation
The total length of the gravel road is 2km.It is proposed to develop roadside tree plantation
on both sides of the main drainage area. Hence 4,000 seedlings will be planted in one running
km. About 8,000 trees shall be planted. Species having aesthetic value, serve as a noise
barrier and best suit to the agro ecology are proposed to be planted on roadside. The species
recommended for the roadside plantation are: Azadirachta indica (Kinin or Nim), Albezia
gummifera (Sesa), casuarina equisetifolia (Arzelibanos), Jacaranda mimosifolia (Jacaranda
Melia azandiarach), Graviliaa robusta, Mileiettia ferruqinea, Schinus molle and Phoenix
reclinate. The cost breakdown of a tree plantation is presented as follow:
Awareness creation and training for both direct project beneficiaries and affected parties.
Awareness creation and training will be provided on: solid waste management, efficient &
effective utilization of money, traffic accident, road maintenance and natural resource
management.(for 80 local communities) for two days by 100 birr perdiem at two phases=
(80x4x100) = 32, 000 birr).
Training for trainers (6kebele experts, 2 Dessie City Infrastructure and ULGDP Co-ordination
Core Process experts and 1 Dessie towns Ensuring Sustainable Environmental Protection
Core Process. For four days by 200 Eth.Birr perdiem=18x200x4= 14,400birr).
Costs required during operation phase of the project will be part of the day to day
administrative and operational cost that the project is also estimated 262, 240 Eth. Birr.
66
Table 12.Dessie gravel Road Project Environmental Cost Estimate
67
10. Conclusion and Recommendation
10.1 Conclusions
The proposed Road Project will traverse an area characterized low to moderate slopes. Route
selection has avoided some of the areas prone to flooding. The adverse direct or indirect
impacts are anticipated in respect of environmentally sensitive areas. During construction
drainage ways and Residential areas can be modified. The movement of livestock can also be
impacted. However by applying the recommended mitigation measures the problems can be
reduced. Respecting local customs in this kind of region is highly recommended. Moreover
the safety livestock, children, women and disabled is important. The use of water from bore
holes and other wells needs a prior agreement with the community..
By applying the mitigation and benefit enhancement measures recommended in this EIA
report properly, there are no environmental grounds for not proceeding with implementation
of the project in the form in which it is presently envisaged, since the long-term benefits of
project implementation outweigh the largely short-term adverse impacts associated with
construction, all of which can be mitigated satisfactorily if close monitoring is adopted.
10.2 Recommendations
It is recommended that the proposed mitigating measures are properly implemented at the
right time. To ensure its proper implementation regular environmental monitoring and
audit are also recommended.
City administration should create harmonious relationship between the local community
and the project by holding regular discussions with local elders so as to develop strong
linkages with and avoid unexpected complaints from local communities.
68
Annexes
Annex.1. References
EPA (2000),Environmental Impact Assessment Guideline, Addis Ababa,
FDRE (1995), Federal Democratic Republic of Ethiopia.: Proclamation for the
Establishment of Environmental Protection Authority. Proclamation No. 09/1995. Addis
Ababa.
FDRE (2002), Federal Democratic Republic of Ethiopia: Environmental Impact
Assessment Proclamation. Proclamation No 299/2002. Addis Ababa.
FDRE (2000), Federal Democratic Republic of Ethiopia: Environmental Pollution
Control Proclamation. Proclamation No 300/2002, Addis Ababa.
FDRE (2000), Federal Democratic Republic of Ethiopia: Proclamation on the
Establishment of Environmental Protection Organs. Proclamation No 295/2002, Addis
Ababa
FDRE (April 1997), Federal Democratic Republic of Ethiopia: Environmental Policy of
Ethiopia, Addis Ababa.
EPA/MEDAC (April 1996), Environmental Protection Authority in collaboration with
Ministry of Economic Development and Cooperation: The Conservation Strategy of
Ethiopia; Vol I-V: Secretariat for the Conservation Strategy of Ethiopia, Addis Ababa.
FDRE (1995), Constitution of the Federal Democratic Republic of Ethiopia Proclamation
No.1/1995, Addis Ababa.
MOA (1983), Ministry of Agriculture, Land Use Planning and Regulatory Department:
Geomorphology and Soils Map of Ethiopia. Addis Ababa.
MOA (1993), Ministry of Agriculture, Ethiopian Forestry Action Program: Draft Final
Report, Volume 2- The challenge for Development, Addis Ababa.
MOA (1997), Draft Ministry of Agriculture, The wildlife Policy of Ethiopia; Draft.,
Addis Ababa.1
MOA (1999), Ministry of Agriculture, Natural Resources Management and Regulatory
Department, Agro-ecological Zones of Ethiopia, Addis Ababa.
World Bank (1995), The World Bank Roads and the Environment: A Hand Book.
69
Annex. 2. TOR of the Gravel road EIA consultancy
1. Back ground
According to the regional proclamation No. 9/2003, Dessie city was given the Status of City
Administration, which will be ruled by a Mayor. After the enactment of the above
proclamation, the city was divided into 16 kebeles; 10 urban, 6 rural Among the critical
problems identified by the city administration; lack of adequate road facilities is major
problems of the city. The current practice is very spontaneous that has no any long-term
strategy. Hence, the city administration took the initiative to reverse this situation through
undertaking a detail road development plan. The city Administration prepared this TOR for
the study of development plan to upgrade the existing road located at salaish -segnogebayee
(kebele 01&02).
The source of finance for this assignment is city administration own budget.The preparation
of development plan includes environmental impact assessment, resettlement action plan,
design, and supervision of works during implementation.
3. General Objective
The general objective of the project is to upgrade the existing road to better standard that can
serve the present traffic load, and can tolerate the high flood running from tossa hill. To
transform the present local market place to an economically active place to the level it best
fits with the changing environment
70
Identify possible negative impact that may occur on the Environment or human during or
after construction of the project and prepare mitigation plan
Consult the public, specifically the people affected by the project
Prepare draft and final report with 5 copies
Follow WB guideline in preparing EIA and RAP
5. Knowledge transfer
The city administration at large and the concerned experts in particular will be participated in
every stage of the project study & plan preparation, expected to gain experience, and built
capacity in such activities of the assigned project.
71
8. Responsibilities of the client
Being the owner of the project, the client will have the following responsibilities:
Assign a permanent counterpart that will communicate with the consultant on the behalf of
the client
Provide the city plan to the consultant.
Provide any available materials and/or information that can be useful for the study
Approve and deliver timely scenarios, preliminary designs and regulations submitted by the
consultant.
Assist and facilitate conditions for the consultant to undertake the field survey and site visit
activities
Facilitate community meetings and dictions and organize progress evaluation work shops
72
experience the design
work
3 Urban planning Professional Undertake at 1
expert urban planner planning and
with min.6 years involve in
experience socio-economic
work
4 Civil Engineer Senior civil Undertake all 1
engineer with civil
min. 8 years engineering
experience works
5 Economist Economists with Play leading 1
min. 6 years of role in the
experience socio economic
study
6 Quantity Quantity Undertake all 1
Surveyor Surveyor or the cost
related profession estimation
with min. 4 years works
experience
7 Lawyer Lawyer with min. Responsible for 1
4 years the production
experience of
relevant
experience
8 Surveyor Surveyor with Undertake all 1
min. 4 years the surveyor
experience works.
9 Sociologist Sociologist with Play leading 1
min. 6 years role in the
experience socio economic
study
10 Environmentalist Post graduate in Play leading 1
environment role to cover all
science or related environmental
field of study considerations
with min. 4 years related to the
experience sub-project
73
11. Time frame of the Project
The client is very keen to see study completed in very short time to respond for the growing
demand of developers in the gravel road project. In light of this relation;
Cost calculation is not yet finalized in the Resettlement Action Plan (RAP) document. Hence
we will include in the final report as compensation cost calculation is finalized.
10. CONCLUSION AND RECOMMENDATION
10.1. Conclusion
Dessie gravel road Project will provide overall benefits to the people of the in general and
01,02 Kebeles in particular. The project has been evaluated to have many beneficial impacts
such as improve employment opportunities, improve transportation, improve access to
markets and social support networks, improve traffic conditions and reducing vehicle
operating costs, and improves the living condition of the local people.
Although the implementation of Dessie gravel road Project has many benefits, obviously it
will also bring a number of adverse impacts to the biophysical and socio-economic
environment both during construction and operation phase. Slope destabilization, impact on
soil resource, impact on water resources, impact of noise and vibration, accident from slips
and falls of stone &soil materials, traffic accidents and safety risks, impact on flora are the
main impacts on the biophysical environment during construction phase of the project. Loss
of housing units, loss of fences, loss of plantation trees, loss of market places, impact on
public utilities are impacts on socio-economic environment during construction phase.
Accidents and safety risks, landslides, slumps and slips, and impacts of road noise are the
main impacts arise during operational phase.
All significant negative impacts are possible of mitigation. To protect the environment and
promote development, monitoring plan has been prepared to control and regulate the adverse
74
impacts for sustainable operation of the project. The project proponent should fund to
implement the mitigation measures as outlined. Those mitigation measures should be
considered vital to the project success and sustainability.
10.2. Recommendations
1. The project proponent should fund to implement the mitigation measures as outlined.
Those mitigation measures should be considered vital to the project success and sustainability.
2. There should be awareness creation and training program for the local community as well
as for concerned City Administration and kebele experts.
3. The community involvement process should be continuous that maintains a regular
means of communication with area residents, to keep them informed of the status of the project
as well as what the community expects from the project proponent and the government.
75
Annex .3. CV of EIA Team member
1. Proposed position: Environmentalist
2. Name of firm: ADSWE
3. Name: Wubneh Belete Abebe
4. Date of birth: 5. Dec. 1971 Nationality:
Ethiopian
6. Education: MSc Degree in Environmental Sciences specialization environmental planning
and management; at UNESCO-IHE, Delft, The Netherlands
B.Sc. Degree in Agricultural Engineering (12+5) at Alemaya University of
Agriculture, (1989/90 to 1993/94)
Academic: Elementary and Secondary Education: Azezo, Fassiledes
Elementary and Secondary School
7. Membership in
8. /
professional association:
9. Other training: TOT on knowledge management and WoCAT(EthioCAT) organized &
delivered by MoA, Training given by Dr. Hanspeter (WoCAT specialist,
Switzerland),for 4 days
TOT on PRA and LFA (Participatory Rural Appraisal and Logical framework
analysis) organized and delivered by SIDA Amhara, for 12 Days at Dessie
On-farm research on Watershed management, Soil and Water conservation and
agro- forestry, organized and delivered by SIDA Amhara, for 10 days, at
Kombolcha
Management, Finance, Integrated Rural Development, Policy, Project and
Development Planning, organized and delivered by Amhara region
management Institute, for 73 days,
Local Level Participatory Planning (LLPPA) training, organized and delivered
by WFP and SCF-UK for 10 days, at Dessie
Practical training on water harvesting for 20 days organized and delivered by
Agriculture bureau at Woldeya
GIS & automated Land evaluation for 15 days organized and delivered by
ADSWE, Training By Atkilit Girma (Msc), lecture & Consultant in Geo-
information, Mekele University
Watershed and river basin management, short course given by UNESCO-IHE
Institute for water education, Delft Netherlands
10. Countries of work 11. Ethiopia
experience:
76
12. Language & degree of 13. English: Excellent (speaking, reading, writing).
proficiency: 14. Amharic (Mother Tongue): Excellent (speaking, reading, writing).
77
From: 38. May 2, 1995 To: 39. June 7,1999
Employer: Sayint district (South Wollo)
Position 40. Soil and Water Conservation Expert
held:
41. Detailed Tasks 42. Work undertaken that Best Illustrates Capability to Handle the Tasks
Assigned Assigned
43. Assist the 44. Name of 45. Sena Irrigation Project, Wojegie irrigation project
international environmental project
expert. 46. Year 2008 - 2009
47. Location Bolso Sorie woreda,
48. Client 49. SNNPR
50. Main 51. Diversion weir, Gravity Irrigation of 80ha and 100ha
Project Features
52. Positions 53. Environmentalist
held
54. Activities 55. Collection of environmental baseline, prepare EIA
performed report
56. 57. Name of 58. Koga Irrigation and watershed management project
project
59. Year
60. Location Mecha woreda
61. Client 62. ANRS and MoWR
63. Main 64. Earth Dam project, gravity irrigation of 7000ha
Project Features
65. Positions 66. SWC expert and later, Environmentalist for MSc
held thesis study
68. Evaluation of EIS prepared and follow-up of
67. Activities
implementation of Environmental management plan (EMP)
performed
and watershed management plan
78
Involve in the identification and preparation of Soil and Water Conservation/Irrigation related projects and the
development of participatory and sustainable Soil and Water conservation/ irrigation system for the
organization,
Collaborates and works closely with all the other partners in activities related to soil and water conservation/
irrigation,
Supervises the soil and water conservation/irrigation activities,
Inspects Soil and water conservation/irrigation activities during progress and upon completion; insures that
defects are corrected in accordance with instructions and plans,
Coordinates and participates in the preparation, review analysis of budget proposals of agricultural and
environmental projects/activities,
Coordinates and participates in agricultural and environmental projects appraisal; participates in determining
priorities among programs/projects,
Coordinates and participates in the monitoring and follow up of agricultural and environmental projects, ensures
timely preparation of progress, annual and periodic reports,
Deliver Training on:
LLPPA, SWC and Land Use planning so many times for Government and NGO Staffs
Training government Woreda experts, Supervisors and Development Agents, on soil and water conservation
and LLPPA,
Guiding community meetings on development issues and training farmers on natural resource conservation
Planning, Monitoring and Evaluating physical and biological soil and water conservation (SWC) activities,
Planning and preparing documents of land use planning and watershed management,
Coordinating and guiding community based development activities,
Preparing Integrated watershed Management project proposals and implementing the so,
Implementing, supervising, and monitoring agricultural, and environmental activities,
79
Area Based watershed on-farm research coordinator, in Amhara Region, South Wollo zone, from July 1996 to
Nov. 1997
75. Certification
I, the undersigned, certify that to the best of my knowledge and belief, this CV correctly describes myself, my
qualifications, and my experience. I understand that any willful misstatement described herein may lead to my
disqualification or dismissal, if engaged.
80
1.Proposed position: Socio-Economist
2.Name of firm: ADSWE
3.Name: Tadesse Belay
4.Date of birth: 76. Sep. 1974 Nationality:
Ethiopian
5.Education: MSc Degree in Development Economics (2006/07-2008/09) in Ethiopian Civil
Service College (ECSC)
BSC Degree in Agricultural Economics at Alemaya University of Agriculture,
(1993/94 to1996/97)
Academic: Elementary and Junior Secondary school at Gundewyen and High
Schools in Mertulemariam Town (1982/83- 1992/93)
6.Membership in
77. /No/
professional association:
7.Other training: o Two weeks intensive training in “the study, design & implementation of
small scale irrigation & environmental rehabilitation projects for practicing
professionals”.
o Ten days intensive training in project analysis
Project analysis
o Project cycle
o Participatory approach in project formulation
o Valuating cost and benefit, the financial and economic
analysis
o Monitoring methods and tools
o Overall indicators
o GIS and Automated land Evaluation
1. Topics covered during the training:
A. ARCPad, ArcGIS 9.2 & Geoprocessing tools
B. DIVA_GIS
C. ArcHydro
2. Introduction to land evaluation and on:
o Economic and Biophysical
o Automated land evaluation software (ALES)
o Automated land evaluation under ArcGIS 9.2
3. Introduction to ERDAS Imagine 9.1
8.Countries of work 78. Ethiopia
81
experience:
9.Language & degree of 79. English: Excellent (speaking, reading, writing).
proficiency: 80. Amharic (Mother Tongue): Excellent (speaking, reading, writing).
11..Detailed Tasks 12.Work undertaken that Best Illustrates Capability to Handle the Tasks
Assigned Assigned
95. Spatial Socio 96. Name of 97. North west amhara Land Use Planning & Env’tal
economy expert in Amhara project impact assessment study project
Design & Supervision 98. Year 2010 - 2011
Works Enterprise 99. Location North west Amhara Growth Corridor,
100. Client 101. Amhara Land Administration & Use Bureau
102. Main 103. Land Use Planning on about 2 million ha.
Project Features
104. Positions 105. Spatial Socio-Economist
held
82
11..Detailed Tasks 12.Work undertaken that Best Illustrates Capability to Handle the Tasks
Assigned Assigned
106. Activities 107. Collection of Spatial socio-economic baseline Data,
performed prepare Socio-economic Evaluation report
108. Planning Specialist 109. Name of 110. Small scale Irrigation project
in Kobo Girana valley project
Development program office 111. Year 112. January 10, 2005 to April 2009
113. Location Kobo woreda, at Waja & Hormat
114. Main 115. Drip & Sprinkler Irrigation project, 10 projects
Project Features irrigating about 35 ha each, irriating 350 ha totally.
116. Positions 117. Senior Planning and Programming expert and acting
held head of planning, monitoring & Resource Mobilization Service
118. Activities 119. Preparing socio-economic Feasibility report and
performed follow-up of its implementation.
120. Socio-economy 121. Name of 122. Small scale Irrigation project
expert in Commission of project
Sustainable Agricultural & 123. Year 124. February 1998 to January 2005
Environmental ehabilitation 125. Location At different woredas of the Amhara Region
in Amhara region 126. Main 127. Dam & Diversion Irrigation project, 13 implemented
Project Features projects irrigating irriating 868 ha totally.
128. Positions 129. Socio-Economic expert of the study Team
held
130. Activities 131. Preparing socio-economic Feasibility report.
performed
132. Socio-economy 133. Name of 134. Small scale Irrigation project
expert in Tefera Berhie project
General Water works 135. Year 136. April 2009 to Sep 2010
Consultancy Service (Part At 2 woredas of the Amhara Region & 4 Woredas
timer) 137. Location of SNNRP
138. Client 139. Amhara water resource Development Bureau &
SNNRP water resource Bureau
140. Main 141. Diversion Irrigation project, 9 implemented projects
Project Features irrigating irriating 1000 ha totally.
142. Positions 143. Socio-Economic expert of the study Team
held
83
11..Detailed Tasks 12.Work undertaken that Best Illustrates Capability to Handle the Tasks
Assigned Assigned
144. Activities 145. Preparing socio-economic Feasibility report.
performed
146.
147.
148. Expertise duties
Develop Methdologies for gathering Data, Analysing Data and writing reports for irrigation and related project
preparation,
Plans, organizes and controls the overall activities of the implementation of these irrigation projects.
Preparing fund raising proposalfor funding agencies.
Prepare implementation progress report for different clients (For funding agents, for management bodies
situated at different levels).
Coordinates and participates in the preparation, review analysis of budget proposals of agricultural and
environmental projects/activities,
Coordinates and participates in agricultural and environmental projects appraisal; participates in determining
priorities among programs/projects,
Coordinates and participates in the monitoring and follow up of agricultural and environmental projects, ensures
timely preparation of progress, annual and periodic reports,
Guiding community meetings on development issues and in identifying their own problems, set solutions their
identified problems in pariticipatory and rapid approach.
84
13. Certification
I, the undersigned, certify that to the best of my knowledge and belief, this CV correctly describes myself, my
qualifications, and my experience. I understand that any willful misstatement described herein may lead to my
disqualification or dismissal, if engaged.
85