ESIA - Metu - Mesha
ESIA - Metu - Mesha
June 2022
Table of Contents
0. Executive Summary .............................................................................................................................11
0.1. Introduction .......................................................................................................................... 11
0.2. The project............................................................................................................................ 11
0.3. The purpose of ESIA study ................................................................................................. 12
0.4. Impact Assessment Methodology ...................................................................................... 12
0.5. Public and Stakeholder consultations................................................................................ 12
0.6. Baseline Bio-physical and socio-economic conditions .................................................... 13
0.6.1. Biological ..............................................................................................................................13
0.6.2. Physical conditions...............................................................................................................14
0.6.3. Socio-economic conditions ..................................................................................................15
0.7. Impact assessment and mitigation ..................................................................................... 16
0.8. Conclusion ............................................................................................................................ 18
1. Introduction .........................................................................................................................................19
1.1. The ESIA Process ................................................................................................................. 20
1.2. Purpose of the ESIA Report ............................................................................................... 22
1.3. Structure of the ESIA Report ............................................................................................. 22
2. Methodological approach for the ESIA study ......................................................................................25
2.1. Environmental and Social Impact Assessment Process .................................................. 25
2.1.1. Approaches to determine Environmental and Social impacts and their significance .........25
2.2. Cumulative Impact Assessment ......................................................................................... 27
2.3. Stakeholders Engagement ................................................................................................... 28
2.3.1. Objectives of Stakeholders Engagement .............................................................................28
2.3.2. Approaches to Stakeholders Engagement ..........................................................................29
3. Assumptions/Gaps in knowledge ........................................................................................................30
4. Administrative structure, Policy and Legal Framework.......................................................................30
4.1. Institutional Framework ...................................................................................................... 30
4.2. Administrative Structure..................................................................................................... 30
4.2.1. Federal Level ......................................................................................................................... 30
4.2.2. Regional Level ....................................................................................................................... 30
4.3. Policy and Legal Framework............................................................................................... 30
4.3.1. National Policies ..................................................................................................................30
4.3.2. Legislative Framework .........................................................................................................37
Ethiopia is striving to ensure access to power by its growing population. To this effect, the country
has diversified the sources of power, i.e., wind, solar and geothermal. Some wind power has
entered the national grid but there are initiations for feasibility studies for solar power in the
different dryland areas of Ethiopia, e.g., Afar and Somali. Masha town is endowed with natural
resources and has huge economic resources to contribute to the national economy and improve
the quality of life of its own and surrounding communities. The lack of power has been a
bottleneck for local economic development and national economy through attracting
investments. Masha town is located 70 km from Metu substation. The Metu – Masha 230 kV single
circuit transmission line project is anticipated to boost economic development in Masha and its
surroundings and improve quality of life. Furthermore, the construction of a new sub-station at
Masha could be a pivotal hub for subsequent distribution of power to other Woreda towns in
Sheka Zone of the South West Ethiopia Peoples’ Regional State and Ilubabor Zone.
The Metu – Masha 230 kV single circuit transmission line project is a schedule 1 project according
to the Ethiopia classification of development projects. Such projects require a full ESIA study.
The project is being developed by the Ethiopian Electric Power (EEP), as part of the
Ethiopian Electric Power Transmission Line Project (EPTLP) and is being sponsored by the World
Bank which provides technical and financial support.
The Metu – Masha 230 kV single circuit transmission line project comprises the following:
• Construction and operation of a new substation at Masha town, which will take about
9 ha of land (300 X 300 meters);
• Construction and operation of a 230 kV single circuit transmission line from Metu
(existing substation) town to Masha town at the newly constructed substation site (total
length of the line: 65.1km). The transmission line will comprise approx. 180 towers.
The main purpose of this ESIA study is to update the 2016 Environmental and Social Impact
Assessment study and address the gaps of the 2016 report. As part of the effort to update the
2016 report and address the gaps, a transmission line rerouting was studied to avoid a highly-
forested area. Detailed information on the baseline the bio-physical and social environments were
collected. Furthermore, impacts were identified and assessed to propose mitigation measures
and prepare Environmental and Social Management Plan (ESMP).
This section has provided definitions for positive and negative (adverse) impacts. Key impact
parameters have included the following. These are:
• Types of impacts. the types of impacts were classified as direct, indirect, induced and
cumulative.
• Characteristics of impact. These include type, extent, duration, scale and frequency of
impacts.
• Likelihoods of impacts. The likelihoods were rated as unlikely, possible (probable), and
likely.
• Sensitivity/vulnerability/importance of receptors. Low, medium and large were used to rate
this parameter of impacts.
• Magnitude of impacts (significance of impacts). Four rates were used. These are negligible,
minor, moderate, and major.
Cumulative impact assessment was done in a step-based approach on a selected Valued
Environmental Component (VEC). Biodiversity was selected as a key VEC to undertake
cumulative impact assessment (CIA).
Public and stakeholder consultations were carried out from 0ctober 06, 2021 to October 11,
2021. The discussion was made in such a way that participants expressed their views
independently and freely. Impacted assets were inventoried to understand the impacts of the
project on physical structures (houses) and crop trees and coffee shade trees. The following table
summarizes key points raised:
Details of Key issues raised Responses provided
consultations
Illubabor • The project affects houses, cash crops • The project impacts are both
Zone (7 and coffee shade trees which have temporary and permanent. There
meetings) direct impact on household incomes. are houses and trees that could be
• Compensation should be paid on time permanently lost.
Held from and before the start of the project. • Any compensation will be paid
October 06 to • PAPs with small parcels of land should based on the currently functional
October 10, be assisted to build their houses laws and regulation of Ethiopia.
2021
0.6.1. Biological
A total of 115 plant species were recorded from the project area. Not all of these species were
assessed by IUCN conservation criteria, but others have been assessed. Currently, 38 of these
have been assigned IUCN conservation classes. The majority of the 38 species are of least
conservation concern but they exhibit different population trends. Whereas about 71% of them
have a stable population status, 10% of these species have a decreasing population trend. One
species in the project area, Prunus africana, has been assessed as Vulnerable. Although commercial
exploitation of this species is common in other parts of the world, such economic uses of this
species has not been the case in Ethiopia.
The slope of the project area varies from almost flat to 25%. The OHTL crosses different
topography of the project area. With regard to weather condition, the project area receives rain
for 8-9 months. The temperature of the project area also varies across the months. Similarly, the
The Metu – Masha 230 kV single circuit transmission line project crosses two National Regional
States: Oromia and SNNPR. There are 4 Woredas and 8 Kebeles in Oromia and 1 Woreda and
5 Kebeles in SNNPR. Agricultural systems include cultivation of cereal crops, pulses, oil crops,
coffee agroforestry and Enset cultivation. The local communities harvest Non-timber Forest
Products (NTFP) from the forests. This NTFP include honey production. They use the big trees
of the Forest such as Pouteria adolfi-friderici, Cordia africana, Albizia gummifera, etc. for placing their
beehives. Other NTFP includes the collection of spices from the forest.
Power supply to the Zones of the project area is limited. There are Woreda towns in both
Illubabor and Sheka Zones which do not have access to electricity. As a result, most of the
population uses alternative energy sources such as firewood, which is the major source of energy.
Other people also use charcoal, dung, crop residues and kerosene. The use of firewood by the
large portion of the population of the study area is one of the major causes of deforestation. The
lack of electricity affects local economic activities, quality of life and the delivery of education to
the pupils. Furthermore, the pupils are not able to study as much as required due to the lack of
electricity. The soothes from the firewood and dung, for example, pose chronic health risks.
Therefore, power is a necessity for these communities.
The Metu – Masha 230 kV single circuit transmission line project impacts land and livelihoods
through triggering physical displacement of houses and high crop trees such as Eucalyptus. High
shade trees will also be removed from within 40 m corridor of the RoW. The restrictions of this
project are that no houses will be constructed within the RoW, so are high crop trees and coffee
shade trees. The physical relocation of structures and restrictions of the project negatively affect
certain people. The severity of the impacts of this project in this regard is different for Project
Affected Persons (PAPs) in the rural and urban Kebeles. In urban Kebeles, the PAPs have 200
square meters of land where they have constructed their houses and cultivated some garden
crops and crop trees. In cases where the RoW passes certain section of the plot of land, the
PAPs should relocate the houses elsewhere. This situation is very common in Kolo Korma of
The Metu – Masha 230 kV single circuit transmission line project triggers negative impacts on the
bio-physical and socio-economic conditions in the project area. The ESIA has identified
environmental and socio-economic receptors. It has also developed mitigation measures to
address such impacts to acceptable levels. The ESIA presents an Environmental and Social
Management Plan (ESMP) which summarizes impacts and mitigation measures, and specified a
series of specific management plans that will need to be developed to ensure that negative impacts
will be maintained low and negligible while positive impacts will be further enhanced.
The outcome of impact assessment before and after mitigation is provided in the following table.
Environmental/social Project impacts Project Phase Predicted significance
receptors Before With mitigation
mitigation
Flora Cutting of Pre-Construction High Low1
indigenous trees
along the RoW
1Applying all the requirements of the Biodiversity Management Plan could minimize the impact to low level. But
the impact on the mature trees inside the RoW is permanent.
The Metu – Masha 230 kV single circuit transmission line project is environmentally and socially
feasible to be implemented provided that all provisions of the ESMP are strictly implemented by
the Contractors and monitored by the responsible parties. The present ESIA Update introduces
a rerouting of the transmission line alignment compared to 2016 ESIA - in a highly-forested area,
which significantly reduces the loss of dense forest and the related biodiversity loss, while also
minimizing the loss of tea farm area.
Nevertheless, the project triggers asset loss of people living along the RoW, leading to physical
displacement, removal of crop trees and indigenous coffee shade trees, and impacts to their
livelihood. There is also land which is permanently lost due to tower foundations. In view of these
findings, a Resettlement Action Plan (RAP) and Livelihood Restoration Plan (LRP) are being
conducted for the Metu – Masha 230 kV single circuit transmission line project to ensure that
project affected people maintain or even improve their level of livelihood because of the project.
• Construction and operation of a new substation at Masha town, which will take about
9 ha of land (300 X 300 meters);
• Construction and operation of a 230 kV single circuit transmission line from Metu
(existing substation) town to Masha town at the newly constructed substation site (total
length of the line: 65.1km)
According to the existing Ethiopian law (EIA Proclamation 299/2000), development projects are
required to carry out an Environmental and Social Impact Assessment study to ensure
environmental and social sustainability. In an Ethiopian context, there are three project schedules.
These are:
• Schedule 2: as the environmental and social impacts of this type of projects are minimal,
a partial ESIA study is needed to implement them.
• Schedule 3: projects which fall under this category require no ESIA study.
The current ESIA study has been undertaken according to the EIA Proclamation (Proclamation
No. 299/2002). In an Ethiopian context, the outline of the EIA process is given in Figure 1-1. Since
the current ESIA study is an update to the 2016 study, additional data were collected to fill the
gaps. It is to be noted that the ESIA report for Metu – Masha 230 kV single circuit transmission
line project will be submitted to the competent authority for review and approval.
The Environmental and Social Impact Assessment phase of the EIA process is based on objective
scientific studies resulting in the identification of definable environmental and social impacts and
preparation of mitigation measures to either avoid or minimize these impacts. The EIA stage
forms the basis for the issuance of environmental clearance or approval by the competent
authority.
1. Introduction It introduces the EIA process in Ethiopia, defines the purpose of this ESIA
and provides information on the ESIA team.
2. Methodological approaches This section describes the methods used for the ESIA study.
3. Assumption/Gap in Knowledge This section describes the assumptions/gaps that triggered the ESIA study
4. Administrative, Policy and Legal This provides information on the institutional arrangement for ESIA studies
Framework relevant to this project and a review of policies, laws and strategic
documents. Furthermore, international agreements were also mentioned.
5. Baseline Biological, Physical and It provides baseline natural and social conditions of the project area.
Social conditions
6. Public and Stakeholders Series of consultations with public and stakeholders and summary of points
Consultations discussed
8. Project Alternatives This section evaluates different route alternatives for the Metu – Masha 230
kV single circuit transmission line project and recommends the best
environmentally feasible route.
9. Impact Assessment and Details of potential impacts, their scale and magnitude, direction and
Mitigation measures probability of occurrence were provided. Mitigation measures for impacts
at different phases of the project were provided.
12. Environmental Monitoring, This section outlines key environmental monitoring and auditing issues and
Auditing and Reporting reporting schedule.
Program
13. Conclusion and Main findings of the ESIA study were summarized to draw conclusions. A
Recommendation recommendation with regard to the implementation of the proposed
project was made.
15.4. Annex VI: Factor driving cumulative impact assessment: Forest cover change
between 1984 - 2020
15.5. Annex V: Details of Alternative routes of the Metu – Masha 230 kV single circuit
transmission line project
2.1.1. Approaches to determine Environmental and Social impacts and their significance
The impacts of the proposed project have been assessed based on the following features. These
are types of impacts, characteristics of impacts, likelihoods of impacts, significance of impacts.
Each of these will be described below.
Types of impacts
The types if impacts can be categorized into two, i.e., nature and extent. Table 2-1 gives details of
these two categories of the types of impacts.
Table 2-1. Type of impacts
Name Description
Nature of impacts
Positive These impacts are those that improves the baseline environmental and social conditions
or introduce positive changes to it
Negative These impacts are those that introduce adverse impacts or undesirable changes to the
baseline environmental and social conditions
Types of impacts
Direct These impacts arise due to the activities of the proposed project and their interactions
to environmental and social receptors
Indirect These impacts are due to the interactions of the activities of the proposed project and
environmental and social receptors, which in turn trigger changes in the baseline
conditions due to these interactions. These are the indirect results of the direct impacts
on the baseline conditions.
Induced These impacts are not the result of the project, i.e., these are due to other activities but
occur due to the implementation project (e.g., expansion of large-scale investment due
to power availability)
Characteristics of impacts
The characteristics of the impacts are based on 5 features. These are given in Table 2-2.
Table 2-2. Characteristics of Impacts
Likelihoods of impacts
This section deals with the probability of the occurrence of the impacts. Table 2-3 gives details of
the likelihoods of impacts.
Table 2-3. Likelihoods of impacts
Name Descriptions
Unlikely The occurrence of the impacts is unlikely under normal operating conditions of the project
Possible There is a possibility for the impacts to occur at some point due to the activities of the
project or its normal operation
Likely The impacts occur during the normal operations of the project, i.e., it is inevitable
Sensitivity/vulnerability/importance of receptors
Small
Medium
Large
This Cumulative Effects Assessment (CEA) has been done based on the IFC’s Good Practice
Handbook on Cumulative Impact Assessment and Management (2013). Cumulative Effects
Assessment is usually done in step-based approach and the recommended steps by IFC (2013) is
given below (Figure 2-1).
Figure 2-2. Significant impacts or risk matrix (Hardner et al., 2015). L = low; H = high; C = critical
In Ethiopia, public consultation is an important and mandatory that project planners and
implementers are required to carrying out prior to implementation of development projects.
Regarding this, the Federal Democratic Republic of Ethiopia (FDRE) Constitution, Article 92 sub-
Article 3 indicates that “people have the right to full consultation and to the expression of their
views in the planning and implementation of environmental policies and projects that affect them
directly”.
Ethiopia is divided into eleven National Regional States and two City Governments (Addis Ababa
and Dire Dawa). All these national institutions have a mandated office or Bureau which oversees
the implementation of the requirements of the existing laws with regard to environmental and
social safeguard.
The eleven NRS and 2 City Administrations have mandated office to oversee the ESIA studies of
development projects in their respective constituency. The Environmental protection offices of
Ilubabor Zone and its Woreda such as Metu, Ale, Gebre Dima have the mandate to supervise
the implementation of the requirement of the Environmental and Social Management Plan of the
project to ensure health environment and integrity of biodiversity. The Sheka Zone and Masha
woreda have the same mandate to ensure the integrity of the environment as a whole.
• provide for early consideration of environmental impacts in projects and programs design;
Section 3.3. of the Environmental Policy deals with Biodiversity issues. The following are directly
relevant to biodiversity:
• Develop laws that help protect community rights and regulate access to genetic resources
and bio-safety;
• Ensure that threat, rarity demand and environmental and economic factors are taken into
account when setting conservation criteria;
• Ensure that local communities participate in the planning and management of adjacent
protected areas;
• Ensure that protected areas cover the various ecosystems and, when necessary, connect
them by corridors; and
• Allow a major part of economic benefits derived from biodiversity conservation are
channeled to local communities affected.
The policy provides a framework to promote the conservation and sustainable utilization of
biodiversity.
Applicability to the Power Transmission Line project
This Policy document informs the project Proponent and the Contractor to implement the
provisions of the EIA proclamation No. 299/200 requirements before starting the project such
as consideration of the impacts of the project on social and natural environment. It also informs
them to implement the provisions of the Environmental and Social Management Plan (ESMP) at
all phases of the project. The policy also provides information on safeguarding natural resources,
for example, Biodiversity issues.
Applicability to the Power Transmission Line project
The objective of the Water Sector Policy is to enhance and promote all national efforts towards
the efficient, equitable utilization of Ethiopian water resources. Furthermore, the policy aims for
optimized utilization that allows for sustainable socioeconomic development.
• Ensure genetic resources and essential ecosystems of the country are conserved,
developed and sustainably used;
• Ensure that local communities share the benefits from genetic resources and indigenous
knowledge;
• promotion of sustainable utilization of wildlife for tourism, hunting, trade, ranching and
food.
• promotion of eco-tourism in protected areas and international conventions;
• expand wildlife sector for investments for conservation; and
• protection of wildlife through proper administration of protected areas, conservation of
endemic and threatened species and promotion of wildlife health services.
Applicability to the Power Transmission Line project
This policy informs the contractor and the project proponent to ensure the protection and safety
of wildlife of the project area. It also guides them to avoid practices that adversely affect the
wildlife of the project area.
Policy on Public Health
The aim of this policy is to give special attention to women and children, underserved segments
of the population and victims of manmade calamities and disaster and environmental pollution
due to project activities as well.
This policy directly emphasizes on the following.
• Combating diseases that are related to malnutrition and poor living conditions;
• Promotion of occupational health and safety of workforces;
The following points could be mentioned with regard to the core principles of the land policy of
Ethiopia.
• The Constitution of the FDRE asserts State ownership of land; there are no private
property in land;
• Even if there are debates on the land ownership and tenure systems in Ethiopia, there is
no legal action to legalize private ownership of land;
• The administration of land is decentralized but the formulation of broad land policy rests
with the federal Government;
• The State still maintains primary rights in property and this could move toward a system
of long-term leases that vest strong secondary rights in landholders, allowing them to
sublease or make other land transactions (e.g., mortgages). These long-term leases would
help to address some of the weaknesses in the existing land tenure system.
2 Article 6 of Environmental Pollution Control Proclamation stipulates that Standards are to be set.
• Conserve, manage, develop and properly utilize the wildlife resources of Ethiopia;
Apart from issuing different laws and regulation for environmental protection and natural
resources conservation, the Government of Ethiopia has put in place several national strategies
and plans3 over the years towards ensuring sustainable development of the country. The currently
running two government development strategy and plan are: the Climate Resilient Green
Economy (CRGE) strategy and the second Growth and Transformation Plan (GTP II). The CRGE
aims at attaining sustainable development goal of carbon emission reduction to the target set for
2030 for the country while the latter aims at bringing the economic development to the level of
the middle-income countries by 2025.
Conservation Strategy of Ethiopia
The Conservation Strategy of Ethiopia (CSE) evaluates the state of the natural resources, the
environment and the development in Ethiopia, and examines the interconnected causes and
effects of the existing situation. The CSE considers a holistic view of natural, human-made and
cultural resources and their uses and abuses. The overarching objective of this document is to
integrate the whole existing and future federal and regional government planning in all sectors
that impacts on the environment, including agriculture, forestry, wildlife, fisheries, soil, water,
3 Conservation Strategy of Ethiopia, Food strategy of Ethiopia (1996), Plan for Accelerated and Sustained Development to End Poverty
(PASDEP), Climate Resilient Green Economy (CRGE) strategy, Growth and Transformation Plan (2010-2015)- GTP I and Growth and
Transformation Plan (2016-2020)-GTP II
Ethiopia aims to become one of the middle-income country in 2025. Following a conventional
development path will lead to high emission of Greenhouse Gases (GHGs)and destruction of
natural resources. The Government has envisioned development through following a green
economy development path, often termed as Climate-Resilient Green Economy (CRGE). The
CRE follows a sectoral approach and identified priorities that help the country to achieve its
development goals while limiting 2030 GHGs emission to around today’s 150 Mt CO2e – around
250 Mt CO2e less than estimated under a conventional development path. The green economy
plan is based on four pillars.
I. Improving crop and livestock production practices for higher food security and farmer
income while reducing emissions;
II. Protecting and re-establishing forests for their economic and ecosystem services,
including as carbon stocks;
III. Expanding electricity generation from renewable sources of energy for domestic and
regional markets; and
IV. Leapfrogging to modern and energy-efficient technologies in transport, industrial sectors,
and buildings.
The Environmental Protection Authority (EPA) has developed guidelines for the implementation
of environmental laws. The guidelines are meant to guide developers, competent authorities,
reviewers and stakeholders in carrying out and managing the EIA process.
EIA Directive 1/2008
Based on the EIA Proclamation No 299/2002, the Ethiopian Government issued Directive No. 1/
2008 that determines the categories of projects subject to the Environmental Impact Assessment
Proclamation and provides for the list of such projects and permits regional governments to
issues their own directives as they deem it necessary. Directive No. 1/2008 provides for the list
of project types that are subject to EIA procedure that include textile factories; tanneries; abattoir
Ethiopia has signed environment related international agreements. As a result, Ethiopia is a party
to the following international environmental agreements (with the date of ratification). This ESIA
has taken these Multi-lateral Environmental agreements into consideration (Table 4-1).
Table 4-1. International conventions relevant to this project
Hazardous substance
Stockholm Convention Potential leakage of PCBs containing materials
Rotterdam Convention on the Prior Informed Consideration of this convention for management plans
Consent Procedure for Certain Hazardous for disposing hazardous wastes
Chemicals and Pesticides in International Trade
Wastes
Basel Convention on Hazardous Waste (1989) Acquisition of permit from other countries for the
transboundary movement of hazardous wastes
Bamako Convention (1991) If applicable, implement the provisions of this
convention for movement of hazardous substances
across countries
Labour
Freedom of Association and Protection of the Ensure the workers have the freedom of association
Right to Organize Convention, 1948 (No. 87) and rights to organize
Discrimination (Employment and Occupation) Expressly forbid discrimination in employment and
Convention, 1958 (No. 111) occupation
Abolition of Forced Labour Convention, 1957 Human resource policies and procedures are
(No. 105) developed and implemented to prohibit forced labour
Minimum Age Convention, 1973 (No. 138) Develop and implement a policy for prohibition of the
employment of children
• Soil erosion
• Electromagnetic fields
The table below provides a comparison of the main ESHS policies of Ethiopia vis-à-vis the WB
ESHS safeguards, and likely gaps between them.
Table 4-3. Gap analysis of Ethiopian and WB ESHS policies
4 The 2003 EIA guideline series 1 lists the types of projects under each of the three project schedules.
Figure 5-1. The proposed route for Metu – Masha 230 kV overhead transmission line
There are immense economic and social benefits of access to electricity. Currently, Masha Town
has electricity which runs on Diesel generator and this runs only for very short hours (until 09:00
pm). Due to a high cost of fuel, there are more days without power in a week. Although the
town and its surrounding areas are endowed with resources for investments and development
of enterprises to spur local economic development and regional integrations, electricity has been
an apparent bottleneck. Students of Masha Town use candles to study and this potentially limits
the time required to spend studying and preparing for the next days’ lessons. The new sub-station
at Masha Town will also be used as a springboard to distribute electricity to Woreda Towns to
foster regional economic development.
Operation phase
• Transportation of
construction
materials
Immediate areas 40 m (20 m • Houses and planting trees are • Monitoring the • Cultivation • Construction of
outside the RoW in either allowed distance of high restricted houses allowed
side) trees to the temporarily due • Planting trees
RoW corridor to construction allowed
and the OHTL activities • As some trees
grow over 40 m,
avoid plant these
trees very close
to the edge of the
RoW on both
sides
Footprint of the new Masha substation
Construction of new 300 m x 300 • This area is currently a Construction phase • Dust emission • Permanent loss of
substation at Masha m in area grazing area with very • Scattered trees due to truck land
scattered trees. These will be removed movements and • No other
scattered trees will be • Excavation of excavation restrictions
removed foundations • Relatively high
• There are no houses and traffic of dump
crop fields truck to transport
soil wastes may
affect livestock
and human
movements
• Temporary
increase in
ambient noise
Project components
Temporary working 20 m x 20 m • Working area for Construction phase • Access to the site
area at each tower site construction, store materials • Clearing of restricted
temporarily vegetation and
• Construction and erection of trees
Towers
Permanent tower area 10 m x 10 m • There are about 180 Towers Construction phase • No trees or
inside the RoW • Fully Clear tea crops allowed on
bushes and 10 m x 10m area
vegetation
The general schematic representations of the features and restrictions are given in Figure 5-2. Cultivation of cereal crops and Enset is
allowed inside the RoW. Since the cultivation of coffee requires shade trees, this cultivation practice is limited inside the RoW. The
coffee shade trees of the project usually grow high and could pose risks to the Metu – Masha 230 kV single circuit transmission line
project.
The project Area of Influence (AOI) for the assessments of the impacts of the Metu – Masha 230
kV OHTL has considered the following features. For determining the AOI, IFC Performance
Standard 1 (January 1, 2012)5 was uses. These standard states the Area of Influence encompasses:
• the area likely to be affected by: (i) the project and the client’s activities and facilities that
are directly owned, operated or managed (including by contractors) and that are a
component of the project; (ii) impacts from unplanned but predictable developments
caused by the project that may occur later or at a different location; or (iii) indirect project
impacts on biodiversity or on ecosystem services upon which Affected Communities’
livelihoods are dependent.
• Associated facilities, which are facilities that are not funded as part of the project and that
would not have been constructed or expanded if the project did not exist and without
which the project would not be viable.
• Cumulative impacts that result from the incremental impact, on areas or resources used
or directly impacted by the project, from other existing, planned or reasonably defined
developments at the time the risks and impacts identification process is conducted
The direct impact zone of the Metu – Masha 230 kV single circuit transmission line project
includes the spatial extent of the Right-of-Way and access road (Figure 5-3). That is:
• 40 m Right-of-Way corridor
5 IFC Performance Standard 1: Assessment and Management of Environmental and Social Risks and Impacts,
January 1, 2012
The indirect AOI of the project is areas that are affected by cumulative impacts. These include
Metu – Gore Road construction and large-scale investment plans. Figure 5-4 shows the indirect
AOI of the project.
A brief summary of the Metu – Masha 230 kV transmission line is given below.
Access roads
At present the exact number and length of access roads is not known. But the access roads are
built within the direct AOI of the project. In some cases, the access road passes through cultivated
The main activities of the Metu – Masha 230 kV single circuit transmission line project are given below
according to the phases of this project.
The following project activities occur during the construction phase of the project. These are:
• Assembly of towers
• Supply of insulators
• Supply of conductors
• Cable stringing
The contractor will construct access roads of 4 m width. Big indigenous trees, cash crop plants
and other perennial crops will not be damaged by the construction of the access road.
After completion of the construction, EEP will be responsible for the operation and maintenance
of the 230 kV transmission line. The main activities to be carried out during the operation life of
the transmission line include surveillance of the condition of the transmission line routine,
emergency maintenance and repairs and vegetation control.
EEP is responsible for controlling future land uses within the ROW and ensuring that no new
structures are constructed. In particular, buildings must be at a minimum distance from the line
conductors. Growth of crops will be permitted, but limited to a height of 2 m or less. Growth of
vegetation on the right-of-way will be controlled to ensure safe and reliable operation of the line.
Therefore, vegetation cover will need to be cleared occasionally to ensure that vegetation does
not interfere with the operation of the lines.
Vehicular access to the ROW will be required to effect line repairs or to correct any localized
erosion or terrain instability problems that might develop.
A total of 115 plant species were recorded from the project area (Annex 15). Out of these, 38
were assessed for their conservation status while the remaining species were not assigned any of
the IUCN categories, i.e., they were not assessed. Many species with a conservation status of
Least Concern (LC) have stable populations while a small portion (about 10%) of them have a
decreasing trend of population (Figure 6-1). The project crosses Baro River and the Transition
Zone of Sheka Forest Biosphere Reserve. This Zone is used for cultivation and there are
scattered trees species, e.g., Albizia gummifera, Pouteria adolfi-friderici and exotic trees such as
Euclayptus. No species of conservation concern was recorded in this Transition Zone.
Figure 6-1. Population trend of species with an IUCN conservation status of Least Concern (LC)
6 Coffea arabica. The IUCN Red List of Threatened Species. Version 2021-3
The forest of the project area is part of the fragmented Moist Afro-montane Forest (MAF) of
Ethiopia. This type of vegetation is found in selected parts of Ethiopia (Figure 6-4). Characteristic
species MAF are Pouteria adolfi-friderici, Prunus africana, Albizia gummifera, Albizia schimperiana, Olea
welwitschia, Coffea arabica, Schfflera abyssinica, Diospyros abyssinica, etc.
Figure 6-3 presents selected profile of the forest of the study area. The salient features of the
stand of two species, Pouteria adolfi-friderici and Olea welwitchii shows the the vertical structure
of the forest. Both species form high canopy but there are also other understorey trees species
and Coffea arabica and ground vegetation mainly featuring spices such as Piper capense and
Afromomum corrorima.
Figure 6-3. Profile of selected tree species of the project area (source: Senbeta, 2016)
The project crosses modified landscape (cultivated fields and tea Estate and transition zone of
Biosphere Reserves). But a small section of the OHTL triggers forest related issues, e.g., cutting
trees. This issue has been addressed in the ESMP.
0
2000 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 2022
Similar trend was also observable in the remaining natural forest of SNNPR (Figure 6-6). In 2002,
Sheka has 229 kha of tree cover, which covers 98% 0f its land area. In 2020, it has lost 185 ha of
its tree cover amounting to 111 kt of Co2 of emissions. Furthermore, Sheka has lost a total of
2.64 kha of its humid primary forest, which is 34% of its total tree cover loss in the same period.
This has resulted in a decrease by 27% of its humid primary forest. Relatively higher loss of the
Sheka humid primary forest was recorded from 2012 – 2017. The highest loss was in 2013.
Sheka has lost 7.86 kha of tree cover from 2002 – 2020, which is 3.4% decrease in tree cover
since 2000. This is equivalent to 5.04 Mt of CO2e emission.
Figure 6-7. Management Zone of Yayu Coffee Biosphere Reserve. (Source: Motion Consultancy & Training,
2018).
This endemic species has an IUCN conservation category of Endangered (cf. below).
The following animal species were recorded from the project area.
No Scientific name Common name Remarks
1 Heterohyrax brucei(Gray, 1868) Hyrax -
Procavia capensis(Pallas, 1766
2 Cercopithecus mitis(Wolf, 1822 Blue monkey Raids crops and persecuted by
communities
3 Lepus saxatilis(Cuvier, 1823 Hare Open fields
fagani (Hoffmann and Smith 2005
4 Chlorocebus aethiops(Linnaeus, 1758) Grivet monkey Troops seen along road side.
Habituated?
5 Colobus guereza(Rüppell, 1835 Colobus monkey Frugivore in forest canopy,
6 Panthera pardus(Linnaeus, 1758 Leopoard Predator on wild and domestic
animals
7 Civettictis civetta (Schreber, 1776 Civet uncommon
Some animal species are endemic and their conservation status are given below.
a. Yalden’s Desmomys (rat) - Desmomys yaldeni
This rodent species is endemic to Ethiopia. Figure 6-9 shows the species and its geographic range
in Ethiopia. The species distribution ranges from Metu to Tepi and covers the project area as
well. It habitats are humid afro-montane forest dominated by Ficus species and undergrowth
dominated by coffee. Deforestation of the afro-montane forest may threaten this species in the
future.
Scott’s mouse-eared Bat was assessed as a Vulnerable species with regard to its conservation
status. Habitat fragmentation and conversion are the major threat to the conservation of this
species.
The elevation range of this species is 1300 – 2500 masl in Ethiopia. Part of the project area
(around Metu) falls in the geographic extent of this species (see below). But the remaining areas
of the project are outside of the geographic range of this species.
g. Plants
Octotea kenyensis
This species has a wide geographic range even outside Ethiopia. Its superior quality of hardwoods
has results in its high exploitation for timber.
This species was assessed as Vulnerable.
Generally, these four species (3 animal and 1 plant) are the biodiversity elements that have
triggered the delineation of Sheka Forest as a UNESCO Biosphere Reserve of a global
importance.
B. National Forest Priority Areas
There are three National Forest Priority Areas (NFPAs) in the project area (Figure 6-12). Another
NFPA, the Sele Anderacha NFPA lies far in the west of the project area.
Although they were designated as NFPAs, most parts of these forests are converted to
Agricultural lands (Figure 6-13). As a result, the 230 kV power transmission line passes through
these converted parts of the NFPAs. But a very small section of this power transmission line
crosses these forests. Coffee is the most dominant undergrowth in these NFPAs.
Figure 6-13. Current spatial distribution of the extent of the NFPAs of the project area.
Figure 6-14. Area of extent of Rouget’s rail. (source: Birdlife International, 2016).
Figure 6-15. Critical bird sites of Ethiopia. Colors denote level of protection of the habitats. Red = little protection
of habitats or none; Green = whole habitats protected.
But there are no critical bird habitats in the project area (Figure 6-16). The Koffee Swamp is at
the far Eastern side of the project while the Gambella National Park is further West of the project
area. None of the bird species recorded in this study were listed in the critical bird sites of
Ethiopia.
Migratory Birds
Some of the bird species of the project area are migrant while other are residents (non-migrants).
Table 6-1 gives details information on the migration of the bird species recorded from the project
area.
Table 6-1. Migration status of bird species of the project area.
7 https://birdsoftheworld.org/bow/species/rescus1/cur/introduction
White-crowned Non-migrant
robin-chat
White-browed robin- Non-migrant
chat
Red-capped robin- Non-migrant
chat
Rueppell's robin-chat Non-migrant
Abyssinian slaty Non-migrant
flycatcher
Northern black Non-migrant
flycatcher
African Dusky Non-migrant
flycatcher
White-cheeked Non-migrant
turaco
Variable sunbird Non-migrant
Olive sunbird Non-migrant
Tacazze sunbird Non-migrant
Scarlet-chested Non-migrant
sunbird
Non-forest species Non-migrant
Chestnut-naped Non-migrant
francolin
Scaly francolin Non-migrant
Nubian woodpecker Non-migrant
Abyssinian Non-migrant
woodpecker
Cardinal woodpecker Non-migrant
Western Black- Non-migrant
headed batis
Grey-headed batis Non-migrant
Brown-throated Non-migrant
wattle-eye
Black-winged Non-migrant
lovebird
Yellow-fronted Non-migrant
parrot
Common bulbul Non-migrant
Black-billed barbet Non-migrant
Yellow-fronted Non-migrant
tinkerbird
The species denoted as migrant exhibit intra-African movement. They also occur all year round
in the project area. Some breed in Africa and others in Eurasia (Palearctic migrant), e.g., Lesser
whitethroat. Their habitats are woodland or bush, forest edges, homegardens (e.g., the
palearctic Blackcap) and open woodland, homegardens, bush (e.g., African paradise Flycatcher).
That is the habitats of these migrant species are away from the zone of this high-tension
transmission line to trigger electrocution. Similarly, the resident (non-migrant) species habitats
are also inside forest, ground and homegardens. As a result, the 230 kV Metu-Mash
transmission line will not pose electrocution threat.
Bird species of the project area
Large number of bird species were recorded from the project area. Table 6-2 gives their IUCN
conservation status and their population trend8.
Table 6-2. Bird species of the project area. Keys: LC = Least concern; NT = Near threatened
8 Some species were not assessed by using IUCN conservation criteria. In this case, their population
trend is unknown.
The major threat to the conservation of the bird species of the project area are continuous
decline in extent, area and quality of their habitats. Most of the bird species if the project area
are of least conservation concern (Figure 6-17). Their foraging niches are also different, i.e., their
range from ground to canopy of big tree species like Cordia Africana, Albilzia gummifera, Pouteria
adolfi-friderici and etc. Furthermore, these bird species have different trend of their population
status. Over 25% of the bird species of the project area has a generalist feeding niches (Figure
16). Only about 9% of them feed on their respective diet at the canopy of the forest. Furthermore,
the mid-high foraging niche is about 18% but the combination of mid-high, understorey and
canopy is very small (less or equal to 4%). On the other hand, a ground foraging niche accounts
for the majority of the bird species (over 34%).
Figure 6-17. IUCN conservation status and foraging niches of bird species of the project area.
Figure 6-18. Forest dependency classes of bird species of the project area
10 http://www.ifc.org/wps/wcm/connect/115482804a0255db96fbffd1a5d13d27/
PS_English_2012_Full-Document.pdf?MOD=AJPERES
11 http://www.ifc.org/wps/wcm/connect/a359a380498007e9a1b7f3336b93d75f/ Updated_GN6-
2012.pdf?MOD=AJPERES
• Conserve ecosystems and habitats together with associated cultural values and traditional
natural resources management system;
12 https://www.iucn.org/theme/protected-areas/about/protected-areas-categories/category-vi-
protected-area-sustainable-use-natural-resources
There are 6 endemic species, i.e., 1 plant, 2 amphibians, 1 reptile 1 rodent, 1 Bat species (Annex VI).
E. Ecosystem services
The project area crosses different land use/land cover types. The agricultural system of the
project area is a mixed system where the local communities grow crops and practice coffee-
agroforestry system. Noteworthy is that the local livelihoods depend on the ecosystem services
derived from forested areas.
• Provisioning services. These include timber products for construction purposes, non-timber
forest products such as honey, spices and water supply.
• Regulating services. The forests sequester CO2, which an important regulatory factor for
climate change. The forests also regulate soil erosion.
• Cultural services. Forests aesthetic values and visual impressions promoting spiritual values
of the local communities.
• Supporting services. Forest provides habitats for important species for enhancing
agricultural production, i.e., habitats for natural enemies of pests, pollinators and etc.
Topography
The slope of the project area ranges from almost flat t0 over 45% (Figure 6-19). The slope of the
Right-of-Way of the Metu-Masha 230 kV power transmission line passes through different slope,
which falls below 25%.
35
30
30 31 31 30
29 29
Number of days
25
20 24
21
15 17
15
10
Rain days
5 9 9
0
14°c 16°c 16°c 15°c 14°c 13°c 12°c 13°c 12°c 12°c 12°c 13°c
29°c 31°c 30°c 29°c 26°c 23°c 21°c 22°c 23°c 25°c 25°c 27°c
Night
JanuaryFebruary March April May June July AugustSeptember
October
November
December Day
Metu
Metu gets rainfall for 9 months with at least 15 days in each month (Figure 6-21). Months from
May – October are with the highest number of rain days. Relatively less rain days were recorded
for January and February. With regard to temperature, the coldest night characterizes 4 months,
i.e., July, September, October and November. The highest day-time temperature was recorded
in February (31° C) and followed by March (30° C). The average temperature in January and April
is 29° C. Similar rainfall and temperature patterns characterize Gore area as well.
30
25
Axis Title
20
15
10 Rain days
0
14°c 16°c 16°c 15°c 14°c 13°c 12°c 13°c 12°c 12°c 12°c 13°c
29°c 31°c 30°c 29°c 26°c 23°c 21°c 22°c 23°c 25°c 25°c 27°c
Night
JanuaryFebruary March April May June July AugustSeptember
OctoberNovember
December Day
Elevation
The elevation of the project area ranges from 1200 – 2650 masl. (Figure 6-22). The Metu – Masha
230 kV single circuit transmission line project crosses its highest elevation around Gore area. It
has the lowest elevation at and around Masha Town.
Geology
The geology of the project area was comprised of four different types of formations in different
period (Figure 6-23). These are Archaen, late Eocene – late Oligocene, Oligocene – Miocene and
Soil
There are seven soil types in the project area (Figure 6-24). But the Metu – Masha 230 kV single
circuit transmission line project crosses only two soil types. These are Nitisols and Gleysols.
The general overview of soil erodibility in Ethiopia is given in Figure 6-25. The soil erodibility value
of Ethiopia is low. Five erodibility ranges were produced for Ethiopia. The soil erodibility
(susceptibility the soil to erosion and the rate of runoff) of the project area falls in the 0.001 –
0.135.
Air quality
The air quality of the project area is mainly dominated by naturally occurring sources. Examples are
naturally occurring whirlwind inducing dust emission to air. There are not any development activities
affecting the air quality of the project area. Therefore, the baseline air pollution due to dust emission is
considered as a function of natural event (e.g., strong wind) and almost absent in the project area.
Noise quality
There are no conditions that emit high noise. The ambient noise quality is characterized as limited to the
songs of birds and noise from wildlife.
140,000.00
120,000.00
Area cover in ha
100,000.00
80,000.00
60,000.00
40,000.00
20,000.00
0.00
Farmland Plantation Forest Waterbody Settlement Grassland
1990 2020
Figure 6-28. Land use/land cover conditions of the project area in 2020.
The proposed Metu – Masha 230 kV single circuit transmission line project is located in South-
west Ethiopia Peoples and Oromia regional states of Ethiopia. The South-west Ethiopia Peoples
and Oromia regions are two of the eleven Regional National States of Ethiopia. The regions are
structured into Special Zones/Zones, Special Woredas/Woredas and kebeles.
Administratively, the proposed project overlaps two administrative zones and four Woredas.
Accordingly, Table 6-5 shows lists of administrative set-ups by regions, zones, woredas and kebeles.
Table 6-5. Lists of administrative set-ups affected by the envisaged project
Knowing the number of populations provides the basis to understand and to design the
development projects like electric power transmission line and distribution substations. It is also
important for the wise use of resources according to the size of population. The total population
of Illubabor zone is estimated to be 987, 191 both in rural and urban areas. Of this most of the
population, i.e., 858,423 (87%) lives in rural parts of the zone (Table 6-6). This implies that if the
project electrifies the rural parts of the area, it will have more customers as it is a cash crop
producing area.
Table 6-7 shows that gender wise the population of the project area is almost equally distributed
indicating that half segments of the community are women population and they should get
emphasis in the project. The average family size is 5 persons in the zones. The dependency ratio
ranges from 30.01% at zonal level to 94.13% in Alle woreda in Illubabor zone. The later shows
that 94 inactive persons depend on every 100 economically active /productive/ people in the area.
Table 3 also shows that the population density of the zone varies from 52.1 people per KM 2 in
Didu woreda to 133 people per KM2 in Ale woreda. As to housing characteristics, 99% of housing
types in the urban areas are made of corrugated iron roofing while in rural areas they are entirely
tukuls, i.e., almost 85%.
Table 6-7. Percentages of project area population by gender and place of residence, density, household size and
dependency ratio
Source: Socio-economic Profile Report of the Respective Zones and own calculations, 2021
There are several ethnic groups in Ethiopia based on the national census of the Central Statistical
Agency of Ethiopia (2007). These are presented below.
Illuabor Zone:
• Oromo
• Amhara
• Tigrayan
But the ethnic groups in the project area are Oromo and some Amhara.
Sheka Zone:
Agriculture
Agriculture is the dominant livelihood strategy in Ilubaror and Sheka zones in which the project
is going to be implemented. More specifically, in Illubabor zone 87% of the population are engaged
in the agricultural sector which is greater than the national average. In so doing there is crop
production and livestock rearing as the major economic activities for subsistence means of
livelihood in the project affected areas particularly in the rural areas. As to crop production, there
are annual and perennial crops grown in the area. The major annual crops produced in the area
are cereals, pulses and oil seeds. Cereals mainly include teff, sorghum and maize. Table 6-8 shows
that 115,951 hectares of land were covered by cereals in 2020 with an average productivity of
nearly 39 quintals per hectare in Illubabor zone. The major perennial or cash crops are coffee,
mango, lemon, orange, papaya, banana, avocado, sugarcane, and chats. Table 6-8 also shows that
12,620 hectares of land were covered by cash crops in 2020 with an average productivity of
nearly 133 quintals per hectare in Illubabor zone. Table 6-8 also shows that 9041hectares of land
were covered by cereals in 2020 with an average productivity of 35 quintals per hectare in Sheka
zone. The major perennial or cash crops are coffee, lemon, banana, and apple. Table 6-8 also
shows that 2,626 hectares of land were covered by cash crops in 2020 with an average
productivity of 200 quintals per hectare in Sheka zone. Farmers in the proposed project area
produce crops using traditional farming system mainly by hoe cultivation system using oxen for
ploughing. Moreover, farmers are not using different machineries important for their mainly crop
production and preparation due to lack of power. However, if the proposed project is going to
be implemented in the area, farmers can also use modern technologies to produce surplus and
earn additional income from their crop production. Though most farmers practice sedentary
crop production there is also shifting cultivation which involves clearing of the forest and burning
the thrash before cropping. This practice affects the forest since after some years of cropping the
land is left fallow in order to restore the fertility of soil and farmers will clear other areas of
forests for similar purposes of cultivation and such practice continues.
Table 6-9 shows Illubabor and Sheka Zone farmers land holding size and more than 60% of farmers
own less than 2 hectares in Illubabor zone. On the other hand, average household size of the
zone is 5 and there is low productivity per hectare in the proposed project areas which in turn
affects their endeavour of fulfilling livelihood security. This shows that modern technologies
should be introduced and practiced in order to increase productivity through different
mechanisms. One of the important infrastructures in introducing and practicing modern
technologies is the supply of power. Hence, the implementation of this project will highly benefit
the local communities.
Table 6-9. Farmers land holding size in Illubabor and Sheka zones
Livestock
Off-Farm Activities
Projected affected people practice off-farm activities in addition to their on-farm activities of crop
production and livestock rearing. Most of the income generation activities of the communities
are traditional, similar and mostly practiced to meet their daily demands. Some of the activities
widely undertaken include petty trade, sell of fuel wood, and gathering wild honey from the forest
they have preserved. This shows that there is low awareness in creation and implementation of
other businesses, lack of skill and experience in income generating activities, limited number and
capacity of the private sectors to absorb the growing number of unemployed youths, weak saving
culture of the community to create employment opportunities, and shortage of credit and saving
facilities in the project area. One of the reasons for such kinds of problems is lack of power and
the implementation of the proposed project to some extent will address most of the problems.
Education Service
Education is a backbone of development in general and a principal means of improving the lives
of individuals in particular. Accordingly, the government and its partners have made great efforts
to make accessible for pre-primary, primary, secondary, college and university education at the
proximity of the students in Ethiopia. As a result, the numbers of educational institutions have
increased highly in all over the country including the project area though there is a problem of
offering quality education in those institutions. Table 6-12 shows that a significant number of
students learn in different levels of education in Illubabor zone. Of these, 3,104 students learn
in 30 pre-primary schools, 179,960 students learn in 438 primary schools and 33,600 students
learn in 55 secondary schools with a net enrollment ratio (NER) of 54.7 and 37.7 in primary and
secondary educations respectively. However, Table 6-12 also shows that there are 3.8% and 8.5%
dropouts in primary and secondary education respectively. There are also 193, 6890 and 1664
teachers in pre-primary, primary and secondary schools respectively. This implies that all these
students, teachers and schools are eagerly waiting for access to electricity from this project
especially for those which are not still getting the service.
Table 6-12. Education in Illubabor zone, 2021
13
Federal Democratic Republic of Ethiopia: Poverty and Economic Growth Analysis (Planning and Development
Commission, 2018)
Stakeholder and public consultation participants have pointed out that most health institutions
are suffering from shortage or lack of power. Thus, the implementation of this project will solve
their problem and they will get access for electricity so that they will be able to function
successfully. On the other hand, the residents of the project area are suffering from top 10
diseases (Table 6-14) and these diseases demands power to investigate them. Hence, this project
Institutions and physical infrastructures are crucial for socio-economic development in a given
country. Hence, the Ethiopian Government is striving to construct different institutions and
physical infrastructures throughout the country including the project area. Accordingly, the
existing institutions and physical infrastructures mainly pure water supply and sanitation,
transportation and communication networks, waste disposal management and recreational
services are assessed in the proposed project area.
Water Supply
The proposed project area gets water from different sources such as shallow well, hand dug well,
spring development, river diversion, gravity spring, and SPDD (Table 6-15). However, most of
them are not functional; one of the reasons for such non-functionality is lack/shortage of power.
Thus, the implementation of the proposed project will improve the supply of water in the project
areas.
Table 6-15. Water sources with their functionality and non-functionality in Illubabur Zone
Transport: Transportation is crucial for the movement of human beings and moving materials
from place to place. Thus, the existence of transportation infrastructure such as roads and
vehicles are very important for achieving development in a certain locality. Accordingly,
transportation facilities are paramount for the construction and implementation of the proposed
project in the area.
Telecommunication: Telecommunications services such as internet, cable and satellite
television services, wireless communication services like cellular telephony, paging, and telephony
which are important for facilitation of development activities in a certain area. In so doing, there
is expansion of those telecom services in the proposed project area though it is not enough due
to lack of power and other factors. Hence, the construction an implementation of the proposed
project will help Ethio-telecom to maximize its efforts in the expansion and provision of its
services for both urban and rural communities in the area.
Banks and Other Financial Institutions
Banks: There are totally 30 branches of banks in 2020 belonging to Development Bank of
Ethiopia, Commercial Bank of Ethiopia, Oromia International Bank, Oromia Cooperative Bank,
Awash Bank, Dashen Bank, Wagagen Bank and Hibret Bank in Illubaor zone. The availability or
access to financial resources and institutions is a key to provision and expansion of goods and
services, promoting credit and savings, and accelerating rural and urban investment. However,
most of these financial institutions suffer from lack or shortage of power supply.
Saving and credit associations: There are different types of saving and credit institutions in
the zone which initiate saving and facilitate credit for business activity and economic development
Gender Issues
Projects should be gender sensitive to create equal access for services and resources especially
if people are going to be displaced due to the proposed project. On the other hand, during
public consultation it was raised that women suffered during delivery due to lack of power, health
problems due to indoor pollution in cooking foods and other domestic activities in project areas.
Moreover, women participation in development as compared to men is low though there are
improvements nowadays. This implies that the burden of the work in the family makes women
not to participate in outdoor development activities as like as men. Hence the implementation of
the project will reduce the load/burden of women by letting them for getting access to electricity
in the project area which in turn makes the local women to participate in different socio-
economic developments equally like men by completing their domestic activities easily using
electric power.
Vulnerable Groups
There might be vulnerable groups in the project areas such as disabled people, old people,
lactating women, pregnant women, and children who are going to be affected by the proposed
project. Therefore, during the preparation of resettlement action plan such groups of people
should be seriously identified and taken into considerations for appropriate compensations.
Though Ethiopia is endowed with various historical, cultural as well as natural tourist attractions,
there are no any historical, cultural and archaeological sites in this project site. However, there
might be religious institutions, burial places and others. Hence, such kinds of issues should be
taken into considerations.
In ESIA process, Stakeholder and Public Consultations are paramount importance and mandatory
practices, in accordance to the requirements, as set forth in national and WB policy and legal
frameworks on ESIA procedures and course of actions, as well as, on public consultation and
participation.
Public and stakeholder consultations are useful for gathering environmental data, understanding
likely impacts, determining community and individual preferences, selecting project alternatives
and determine community and individual preferences, designing viable and sustainable mitigation
and compensation plans. Public and stakeholder consultations in the ESIA process is undertaken
at all stages of project phases (the project planning, design, implementation and operation phases).
The aim is to provide information to interested and affected parties, solicit their views and consult
on sensitive issues. Hence, stakeholder and public consultations are important components of
development projects. Thus, the same holds true for the proposed 230 kV Electric Power
Transmission Line Project, which will be implemented from Metu-Mesha in South-west Ethiopia
Peoples and Oromia regional states.
Stakeholder’s consultations were held at three Government administrative layers. The types of
stakeholders are given below accordingly.
Zone level
• Administrator
• Vice Administrator
• Advisor to the Administrator
• Ruling Party Head
• Road Construction head
• Forest, Environment and Climate Change Head
• Urban and Rural Development Head
• Education Head
• Agriculture Head
• Land Administration Head
• Women, Youth and Children Head
• Government Communication Affairs Head
• Finance Head
• Oromia Wildlife and Forest Enterprise Head
• Investment Office Head
• Administrator
• Ruling Part Office Head
• Agriculture office Head
• Investment Office Head
• Finance office Head
• Agriculture Head
• Health office Head
• Forest and Environment protection Head
• Land Administration Head
• Livestock office representative
Town Administration
• Mayor
• Municipality Office representative
• Advisor to the Mayor
• Ruling Party Office Head
• Urban and Rural House Office Head
• Trade Office
• Agriculture
• Health Office head
• Environmental protection head
• Women, Youth and Children Office Head
• Land Administration Office Head
• Water supply Office Manager
• Investment Office head
• Livestock team representative
Kebele Level
• Chairman
• Vice chairman
• Kebele Council representative
• General Manager
• Security Head
Stakeholders at Illubabor Zone were conducted regarding Metu – Masha 230 kV single circuit
transmission line project (Figure 7-1). They are familiar with the project and raised various benefits
and some negative effects of the project on those projects affected peoples (PAPs) as like as any
other projects. More specifically they have pointed out that the project has many benefits such
as getting access for electric power for those who haven’t and providing power without
interruption for those who have access before. On the other hand, since 87 percent of the
residents of the zone are farmers, the project has negative effect on the PAPs as it affects their
cash crops, forests and fruits. Moreover, they have indicated that both the local government and
community benefit from the forest equally with 50 percent each sharing from the income of the
forest. After a detail discussion, the participants have reached at consensus that the PAPs should
be compensated based on Ethiopian Proclamation No 1161/2019 and Regulation No 472/2020
and the project should be implemented as soon as possible.
Since the expansion of Metu distribution station and the erection of some electric towers for
transmission affect some people in Metu town, stakeholders under Metu town administration
were also consulted about Metu – Masha 230 kV single circuit transmission line project (Figure
7-2). In so doing, participants have raised different benefits of the project and their concerns
about PAPs. As to the benefit, the participants have argued that the project will benefit both the
Metu and Masha towns and many small towns and rural areas all the way from Metu to Masha.
However, it will have also negative effects on especially PAPs since it might affect their plots of
land, house, cash crops and others. Accordingly, the participants said that the PAPs should be
compensated based on appropriate proclamations and regulations. More importantly, the Metu
town Mayor has pointed out that the town administration will give a plot of land for those PAPs
if their land and/or house are affected by the project. Moreover, he pointed out that town housing
Stakeholders at Metu woreda administration were also consulted about Metu – Masha 230 kV
single circuit transmission line project (Figure 7-3). The participants argued that any project has
benefits and some negative effects and the same holds true for this project. Previously, the
participants have argued that we were not consulted as a result not able to answer the
questions/concerns raised by the proposed PAPs such as loss of their plots of land and house.
However, from now onwards the participants stated that we are familiar with the project and
will follow up and monitor its implementation together with the concerned bodies. Moreover,
the participants have emphasized on the appropriate compensation of PAPs based on the right
proclamations and regulations. Furthermore, they have indicated that there are two categories
of land holdings those with green card and those with a plan done by GPS, and two of them are
legal and they are entitled for compensation if there are any such PAPs.
Stakeholders in Ale woreda are consulted and they have pointed out that they know well the
project that includes the expansion of Metu distribution station, construction of Masha
distribution station, and construction of Metu – Masha 230 kV single circuit transmission line
project (Figure 7-4). They also indicated that the project gives access to electric power not only
to urban areas but also to rural areas to their vicinity on which the distribution stations are going
to be constructed and/or upgraded. On the other hand, the project has a negative effect on some
people as project uses 400m2 of their land, forest, houses, cash crops and others for the erection
of each tower. Thus, as much as possible the project should try its best to minimize the
destruction of the households’ properties and their natural resources. However, taking all the
necessary measures if there are households’ properties and their natural resources to be
destructed by the project, they should be compensated based on the new proclamation and
regulation. Moreover, when estimation of compensation is made it should be clear based on
proclamation and regulation. Furthermore, the participants have mentioned that if the PAPs are
compensated properly, they will develop a sense of belongingness to the project. If not, they may
complain as like the Masha – Gore road project that does not still pay the compensation for PAPs
by arguing that we have lost our land, natural resources and other properties without being
compensated properly and also not getting electric power that passes through our land. This
negatively affects the success and sustainability of the project.
Didu woreda stakeholders are consulted about Metu – Masha 230 kV single circuit transmission
line project (Figure 7-5). They know the project and even recommended to be implemented more
of on the farmland rather than on forest areas since the lives of the community mainly depends
on the forest, cash crops in the forest, beehives and others. The project has many benefits for
both urban and rural areas. The participants of the woreda said that they are happy in the project
but when it passes on their woreda if it makes us access to electric power from particularly the
nearest newly constructed Masha distribution station, we will be happier. They have indicated
that Didu woreda is connected to Metu distribution station with a distance of nearly 60 KMs.
However, they get electricity once in a week and even when the light comes it does not have a
power even to lighten the bulb. As result almost all the residents of the woreda uses fuel wood
which indirectly affects the forest in their locality. Thus, if this project is implemented, they hope
that they will have access of a good power from the newly constructed Mash distribution station
which is less than 30 KMs distance from Didu woreda. On the other hand, the project affects the
forest which is one of the livelihood sources of the local people, cultivable land, houses, cash
crops, traditional beehives and others that affects some of the local people. Hence, the
participants have argued that the PAPs should be compensated based on appropriate
proclamation and regulation after the estimation is done properly.
Sheka zone stakeholders have said that we all know well the Metu – Masha 230 kV single circuit
transmission line project and we are waiting for its implementation eagerly and we all are worried
about its delay since we are living without electric power (Figure 7-6). The project has a significant
benefit for the zone in general and Masha town in particular since these areas are far from Addis
Ababa or the center without the necessary infrastructures. Thus, if these areas get electric power,
it will contribute a lot to bring socioeconomic development. The participants have argued that
residents of the zone are suffering from lack of electric power as a result the local people are
using fire wood for cooking food by deforesting the forest which in turn affects their health due
to indoor pollution, students are not learning and studying well, mothers are not getting even the
minimum services during their delivery, youths are not getting or creating employment
opportunities, and people are not able to have access to mills and the like. Hence, having access
to electric power in these areas will solve and/or minimize these problems. On the other hand,
the project may have some negative effects on the forest, cultivable lands, houses, cash crops and
others since 400M2 lands are required to erect each electric tower. This implies that individuals
using such resources will be affected by the project, and those PAPs should be compensated
properly using the appropriate proclamation and regulation after the estimation is done properly
by the estimation committee established by incorporating professionals, local elders and other
concerned bodies. Participants have also argued that the local people is willing to accept the
compensation done by the committee as long as it is estimated properly and paid timely and make
free the area for the project and the zonal stakeholders will work towards that day and night.
Finally, the stakeholders make emphasis on timely payment of the compensation for the PAPs
and they will follow up for its action and the zone together with the town will give a plot of land
for PAPs to reconstruct their affected houses.
The stakeholders of the town have argued that they are waiting eagerly for Metu – Masha 230
kV single circuit transmission line project implementation since the town has no electric power
(Figure 7-7). Participants have said that though there is distribution line connected from Metu
substation it is better to say that there is no light or power because the light comes once or
twice in a week and when it comes it works for few hours. Even the light that comes during those
few hours let alone to use for other purposes it does not lighten the bulbs. As a result, there is
very limited socioeconomic development in the town. Consequently, youths do not have access
to employment opportunities, students are studying by torches and candles, women are forced
to use totally fuel wood for cooking that in turn affects their health, and mothers are not
delivering in health institutions due to lack or shortage of power. However, though all town
residents will be benefited with this project directly or indirectly, there are some PAPs, and they
should be compensated for their properties based on appropriate compensation proclamation
and regulation. Moreover, stakeholders indicated that the town administration will follow up
whether the compensation is made properly and paid timely. Furthermore, the town
administration will offer a plot of land for those PAPs on the other parts of the town.
Masha woreda stakeholders know well Metu – Masha 230 kV single circuit transmission line
project and they are following up for its implementation (Figure 7-8). The participants have said
that electric power is very important for everything both in urban and rural areas. It creates
employment opportunities for youths, lets the students to learn and study well, mothers can get
better services during their delivery in health institutions, and women can use electric stoves and
others for cooking food. On the other hand, when the distribution substation is built in Masha
town and towers are erected in Keja and Wollo rural kebeles of the woreda, some people will
be affected, and those PAPs should be compensated based on the newly revised proclamation
and regulation after a proper estimation is made by the committee. The woreda stakeholders will
follow the proper and timely payment of the compensation for PAPs and also make free the
compensated land/area for the project by working day and night within a short period of time.
Moreover, the woreda administration will work together with other concerned organs to offer
a plot of land for those PAPs if their house is damaged totally and they do not have a land to
reconstruct their house both in rural and urban areas.
Project affected people of both gender groups living in Kola Korma kebele of Metu woreda were
consulted about expansion of Metu distribution substation and Metu – Masha 230 kV single circuit
transmission line project (Figure 7-9). The participants have indicated that they know the project
and it will benefit both the local people and government. While the local people benefit from
electric power for different purposes, the government will get sales revenue by selling electric
services. However, the participants have argued that we will be affected by the project if our
small plot of land which is 10m by 20m is going to be used for the expansion of Metu distribution
A B
Figure 7-9. Consultation with Project Affected People (PAPs). A, consultation with project affected male and
female; B, consultation with project affected females
Project affected people of both gender groups living in Sagi kebele of Ale woreda were consulted
about Metu – Masha 230 kV single circuit transmission line project (Figure 7-10). The participants
have indicated that they know the project and it has various benefits for those rural and urban
areas which have no access for electricity and some negative effects on some people like us
especially if we are not compensated appropriately. Accordingly, the participants have hotly
discussed about the issue of compensation. They argue that the properties of the PAPs who were
affected by the Masha – Gore Road project in their locality were not appropriately valuated and
even the estimated compensation that was signed by the PAPs is not paid till now though the
Masha – Gore Road project is underway. The participants added that when they are asking for
their payment and if that is not the case the project should not be started, they are beaten by the
Project affected people of both gender groups living in Keja and Wollo kebeles of Masha woreda
were consulted about the construction of Masha distribution substation and the Metu – Masha
230 kV single circuit transmission line project (Figure 7-11). The participants have indicated that
they know the project and it has various benefits and some negative effects on some people like
us particularly if we are not appropriately compensated. Some of the benefits of the projects are
creating employment opportunities for youths, letting the students to learn and study well,
rescuing the forest from being deforested for fuel wood, keeping the health of women/mothers
The summary of key issues raised by stakeholders of the Metu – Masha 230 kV single circuit
transmission line project, and the responses provided by the project team are summarized below:
Table 7-1. Key issues raised by stakeholders and responses
The IFC Guidance Note 1 (GN 25) requires the examination of technically and economically
feasible project alternatives and documentation of the rationale for selecting a particular course
of action. The core objective of the Metu – Masha 230 kV power transmission line is to supply
power to Masha town and its surrounding areas. This section outlines how the project represents
an optimal route that is environmentally and socially feasible through minimizing impacts of these
receptors. It also starts with no or zero option and thoroughly evaluate details of three alternative
routes. Based on these detailed analyses, the optimal route will be selected for further impact
assessment, mitigation measures and Environmental and Social Management Plan. These
alternatives are described below and Annex 13.5 for further details.
Given that the location of the Masha substation was fixed, no location alternatives were examined
for the substation. Thus, alternatives assessment is based on transmission line route alternatives.
The present ESIA Update revises the selection of Alternative I which was made at the 2016 ESIA
and examines Alternative 2, which is a clear improvement over Alternative 1, in the sense that
the crossing of large, dense forest areas is avoided at the expense of crossing cultivated areas and
tea farm areas. Alternative 3 offers a further improvement of Alternative 2, by minimizing the
impact to tea farms, using existing tracks as far as possible. Alternatives are examined for a section
of 34.3 km of the transmission line route, which presented the greatest challenges in terms of
forest and biodiversity loss. The parts of the route before and after this section are common for
all alternatives.
Details are provided in the following paragraphs and in Figure 8-1 at the end of this section.
In the No-project option, there are not anticipated impacts due to the implementation of the
Metu – Masha 230 kV power transmission line, i.e., it entails the maintenance of the status quo.
That is no 24 hours/week power supply to Masha Town. This project option, however, has
impacts on the local economy and livelihoods of the communities of Masha Town and its
surrounding areas such as Woredas of the Sheka Zone. It is anticipated that the new sub-station
at Masha could serve as a springboard for at least the electrification of Woreda towns of the
Sheka Zone. This project also enables the students to study their subject longer than usual by
clean energy source. Masha Town currently uses Diesel run generator for power supply and the
Metu – Masha 230 kV power transmission line helps the town to reduce cost. Furthermore, more
local economic activities and investments will be triggered by the implementation of the Metu –
Masha power transmission line. In view of these factors, the No-project option was
dismissed.
This alternative passes through both cultivated areas and large section of forests. In this case,
large trees of highly valued tree species will be removed. Some of these tree species are Pouteria
adolfi-friderici, Cordia africana, Albizia gummifera, Prunus africana, Milletia ferruginea, Schefflera
abyssinica (an important resource for honey), Syzygium guinese and etc. These trees have a
diameter of more than 1 m and it has taken 100 of years for them to get to this size. Cutting
these indigenous trees along the ROW of the Metu – Masha 230 kV single circuit transmission
line project negatively affects the biodiversity of the project area. Furthermore, these mature
tree species are also habitats for epiphytic plants and their removal will also result in the loss of
these epiphytic plants. Table 8-1 shows some features of Alternative 1.
Table 8-1. Characteristics of Alternative 1.
Furthermore, Blue Monkey, Cercopithecus mitis, lives in the canopy of these high trees. This species
is of least conservation concern, but its population is decreasing. Therefore, the removal of a long
stretch of forest area and forest disturbance create open spaces and could potentially affect this
species having a decreasing population trend. Due to the high negative impacts of Alternative 2
on the biodiversity, this option was not selected for further ESIA study.
8.4. Alternative 2
This project alternative passes through cultivated fields avoiding forests. A total length of this
alternative is 69.7 km and a large forest area will fall in the RoW of the Metu – Masha 230 kV
single circuit transmission line project in this alternative. There are tree species along this RoW.
By avoiding forest of the project area, which are also designated as National Forest Priority Areas,
14 Previous studies in moist Afro-montane Forest, which is close to the project area, has resulted in several new
records of rare Bryophytes and new species of the same group. Since there is little information on this group of
plant biodiversity, a removal of their hosts (tree species) for a long stretch will have potentially adverse impact
them (cf. Hylander et al, 2010; Hylander et al., 2013)
8.5. Alternative 3
This alternative is meant to reduce the damage to the tea Estate and use existing foot tracks of
the Estate for ancillary activities such as depositing and mixing construction materials for tower
foundation. The total length of this alternative is 1.4 km longer than Alternative 2. Due to its
significantly low level of forest disturbance, conservation of key indigenous tree species, reduced
adverse impacts on Tea Estate, Alternative 3 was selected for further ESIA study.
A summary comparison of route alternatives is provided below:
Criteria Alternative 1 Alternative 2 Alternative 3
Length of section 69 km 69.7 km 71.1 km
Accessibility Good Excellent Excellent
Terrain conditions Mountainous, sloppy, Hilly, waterways and flat Hilly, waterways and flat
deep waterways, flat areas areas
areas
Dense forest crossed 21 km 6 km 4 km
Scattered forest crossed 5 km 12 km 12 km
Farm and open land 8 km 19 km 18 km
Loss of biodiversity Clearing of mature trees Significantly improved Significantly improved
of Cordia abyssinica, Fiucs footprint in terms of footprint in terms of
sycomoros and Coffee biodiversity loss, due to biodiversity loss, due to
shade trees; avoiding crossing dense avoiding crossing dense
Removal of vulnerable forest; forest; reduced adverse
species such as Prunus Significant damage to tea impacts on tea farm
africana and a flagship farms
plant species of the
forests, i.e., Pouteria adolfi-
friderici
The Metu – Masha 230 kV single circuit transmission line project has the following beneficial
impacts.
i. Employment opportunity
ii. Development of different enterprises and trades
iii. Boost investment, e.g., coffee mill
iv. Improve quality of life
v. Improve education delivery systems and students study norm
The anticipated adverse environmental and social impacts of the project are given below
according to the different phases of the project.
The activities of the project during the pre-construction phase include workforce mobilization
and vegetation clearing by the contractor. The mobilization of workforces for clearing vegetation
and cutting trees is one of the major activities of the project, which leads to environmental and
Project Activity
Public health
Solid wastes
Livelihoods
Settlement
Population
Air quality
growth
Fauna
Flora
Workforce x x x x x x x x
mobilization
Vegetation x x x
clearing
along RoW
and access
road
Land x x
Acquisition
Pre-construction phase
for Tower
foundations
Acquisition x x x
of Assets
inside the
RoW
Conclusion:
The duration and magnitude of this impact is low and reversible. Applying the mitigation measure will reduce this impact to negligible
in the case of HIV/AIDS and STDs. The dust emission due to the activities of the workforce could also be reduced to an acceptable
level if the mitigation measures is strictly used, i.e., prior orientation of the workforce. There will be an increase in the ambient noise
level of the project area but the impact is temporary.
Details of the impacts associated with workforce mobilization are given below.
reversibility
Cumulative
occurrence
Probability
Objective/
magnitude
subjective
perceived
Adverse/
beneficial
duration
intensity
Direct/
Actual/
indirect
Spatial
effect
scale
of
Workforce Population
mobilization growth local Short-term low none certain low reversible adverse direct objective Actual
Public Health
(HIV/AIDS_ local Short-term low none probable low reversible adverse direct objective perceived
Occupational
health &
Safety local Short-term low none probable low reversible adverse direct objective perceived
This activity of the project results in the emission of dust to the environment. It also potentially leads to potential injuries, which in
turn triggers occupational health & safety. Detailed studies of the plant species of the Row and access road revealed that most species
occurring in these areas are of least conservation concerns and some are vulnerable (e.g., Prunus africana) or with decreasing trend of
populations. Furthermore, some tree species are even not locally abundant (e.g., Pouteria adolfi-friderici and Olea welwitschii). The tree
species of the project area provide habitats for other species (epiphytes) and ant nests for Crematogaster (useful organisms for coffee
pest control). During this activity of the project, a large quantity of used plastic bottles could be left in the project area uncollected.
There will be an increase in the ambient noise level of the project area but it has a temporary impact on the social environment.
The details of the type and number of indigenous and cash crop trees that are adversely impact due to the removal of vegetation along
the RoW of the project is given in
Kebele CA FS DA SE EU CM SG AD SA OW PA Pad PR AA AG MF GR CL EB EC PF
Jeto 208 21 27 124 7750 202 0 22 0 0 0 0 100 0 254 0 110 106 105 0 0
Gebre Dima 50 12 61 205 2308 236 0 62 0 0 0 0 0 0 32 0 4691 81 0 0 0
Doha 96 31 0 283 16002 441 0 94 302 0 0 40 0 0 45 0 0 281 0 0 0
Kolo Korma 0 0 0 0 966 0 0 0 0 0 0 0 0 0 0 0 0 91 0 0 0
Chatu &
Kawo 44 0 0 0 1202 73 0 0 0 0 0 0 0 0 124 0 54 3 0 0 0
Gaba Guda 58 0 0 0 66 90 0 0 0 0 0 0 0 0 106 0 23 5 0 0 0
Gagi Bicha 209 0 0 0 658 168 0 0 0 0 4 0 0 0 235 0 667 79 0 0 0
Key:
CA = Cordia africana; Ficus sycomorus; DA: Diospyros abyssinica; SE: Sapium ellipticum; EU: Eucalyptus species; CM: Croton macrostachyus; SG: Syzygium guineese; AD: Apodytes
dimidiata; SA: Schefflera abyssinica; OW: Olea welwitschii; PA: Prunus africana; Pad: Pouteria adolfi-friderici; PR: Phoenix reclinata; AA = Acacia abyssinica; AG: Albizia gummifera;
MF: Millettia ferruginea; GR: Grevillea robusta; CL: Cupressus lustanica; EB: Erythrina brucei……; EC: Ekebergia capensis; PF: Polyscias fulva
There is a high number of Eucalyptus trees that are adversely affected by the project across different Kebele of Masha Woreda (Table
9-4). A total of 30 mature individuals of the vulnerable Prunus africana and 10 of the scattered mature individuals of Pouteria adolfi-
friderici will be removed along the Row of the project in different Kebeles of Masha Woreda. A handful of coffee shade trees, e.g.,
Albizia gummifera and Millettia ferruginea will be removed. Furthermore, important trees for honey production, i.e., Syzygium guineese
and Schefflera abyssinica will be also permanently removed from the RoW of the project.
Table 9-4. Types and number of tree species removed from the RoW in different Kebeles of Masha Woreda, Sheka Zone of the Metu – Masha 230 kV
power transmission line.
Kebele CA FS DA SE EU CM SG AD SA OW PA Pad PR AA AG MF GR CL EB EC PF
Wolo 0 8 0 0 1250 5 17 0 4 0 2 0 0 0 0 1 0 7 0 1 1
Keja 12 38 0 0 11113 76 8 0 0 3 28 10 0 0 30 25 56 0 0 0 57
Masha 02 0 0 0 0 15025 4 18 0 0 0 0 0 0 0 0 0 0 1 0 0 0
• Apply all requirements of the Occupational Health & Safety Management Plan
reversibility
Cumulative
occurrence
Probability
Objective/
magnitude
subjective
perceived
Adverse/
beneficial
duration
intensity
Direct/
Actual/
indirect
Spatial
effect
scale
of
Vegetation
clearing along
RoW Air quality local temporary low none certain low reversible adverse direct objective Actual
Total Flora local permanent high none certain high irreversible adverse direct objective Actual
Noise local temporary low none certain low reversible adverse direct objective Actual
Tree species local permanent high none certain high irreversible adverse direct objective Actual
Crematogaster
nests local Permanent high none certain high irreversible adverse direct objective perceived
Fauna local temporary negligible none probable negligible reversible adverse direct objective perceived
Occupational
health &
safety local temporary low none probable low reversible adverse direct objective perceived
Vegetation
clearing along
access roads Air quality local temporary low none certain low reversible adverse direct objective Actual
Noise quality local temporary low none certain low reversible adverse direct objective Actual
Total flora
Tree species local permanent medium none certain medium irreversible adverse direct objective actual
Crematogaster
nests local permanent high none certain high irreversible adverse direct objective actual
Fauna local temporary negligible none probable negligible reversible adverse direct objective perceived
Occupational
Health &
Safety local temporary low none probable low reversible adverse direct objective perceived
• Apply all provisions of the Resettlement Action Plan of the Metu – Masha 230 kV power transmission line
reversibility
Cumulative
occurrence
Probability
Objective/
magnitude
subjective
perceived
Adverse/
beneficial
duration
intensity
Direct/
Actual/
indirect
Spatial
effect
scale
of
Tower foundation Coffee shrubs local permanent medium none certain medium irreversible adverse direct objective Actual
Spice
plants15 local permanent high none certain high irreversible adverse direct objective Actual
Households’
income local permanent high none certain high irreversible adverse direct objective Actual
Tea shrubs local permanent high none certain high irreversible adverse direct objective Actual
15 The density of spice plants inside these forest areas for Tower foundations is noticeable. They are also important economic sources of
household as coffee shrubs are.
16 The coffee shade trees such as Albizia gummifera, Cordia africana, Ficus sycomorus and others are inside the RoW of the Metu- Masha power
transmission line. These coffee shade trees will be cut. Since the coffee shrubs need the shade of these trees, cutting these trees will affect coffee
production of the smallholder farmers. Therefore, the client need to acquire the land falling in its project’s RoW.
• Payment of compensation for permanent and temporary loss of assets of the PAPs.
reversibility
Cumulative
occurrence
Probability
Objective/
magnitude
subjective
perceived
Adverse/
beneficial
duration
intensity
Direct/
Actual/
indirect
Spatial
effect
scale
of
Houses local permanent high none certain high irreversible adverse direct objective Actual
Scattered
trees at the
new
substation local permanent negligible none certain negligible irreversible adverse direct objective Actual
reversibility
Cumulative
occurrence
Probability
Objective/
magnitude
subjective
perceived
Adverse/
beneficial
duration
intensity
Direct/
Actual/
indirect
Spatial
effect
scale
of
Coffee shade
trees local permanent high none certain high irreversible adverse direct objective Actual
Coffee shrubs local permanent high none certain high irreversible adverse direct objective Actual
Cash tree
crops local permanent high none certain high irreversible adverse direct objective Actual
Household
livelihood local permanent high none certain high reversible adverse direct objective Actual
Basic public
services, e.g.
education and
provisions of
utilities17 local temporary high none certain high reversible adverse direct objective perceived
Social
cohesion18 local permanent negligible none probable negligible reversible adverse direct objective perceived
Traditional
community
associations,
e.g. Idir19 local permanent low none probable low reversible adverse direct objective perceived
17 If the members of the current community are relocated to new places far from their current location, household should change schools for their kids. If these
areas are new with less developed basic public services such as water and power, these PAPs will be highly affected. This impact may be temporary since these
utilities will be developed sooner or later.
18 If the members of the current local community are relocated to different places
19 If the members of the current local community are relocated to different places
This phase of the project is where most of the activities of the project take place. Table 9-5 gives the list
of project activities and their receiving environmental and social environments
Table 9-5. Environmental and social Impacts of the project during the construction phase. Key: x denotes impacts
on concerned bio-physical and social conditions that will be triggered by the project activity.
Project Activity
and
health & safety
Occupational
Noise quality
Public health
employment
Solid wastes
Livelihoods
Settlement
Population
Air quality
Economy
growth
Fauna
Flora
Soil
Labor influx x x
Excavation of x x x x x x x
Tower
Foundations
Access road to x x x x x
Tower
Construction phase
foundations to
transport
construction
materials
Stringing x x x
• Risk of social tension: Conflicts may arise between the local community and the construction workers, which may be related
to differences due to competition for local resources. Tensions may also arise between different groups within the labor force,
and pre-existing conflicts in the local community may be exacerbated.
• Increased risk of illicit behavior and crime: The influx of workers and service providers into communities may increase
the rate of crimes and/or a perception of insecurity by the local community. Such illicit behavior or crimes can include theft,
physical assaults, and substance abuse. Local law enforcement may not be sufficiently equipped to deal with the temporary
increase in local population.
• Increased burden on and competition for public service provision: Presence of construction workers and service
providers (and in some cases family members of either or both) can generate additional demand for the provision of public
services, such as water, electricity, medical services, transport, education and social services. This is particularly the case when
the influx of workers is not accommodated by additional or separate supply systems.
• Increased risk of communicable diseases and burden on local health services: The influx of people may bring
communicable diseases to the project area, including sexually transmitted diseases (STDs), or the incoming workers may be
exposed to diseases to which they have low resistance. This can result in an additional burden on local health resources.
Workers with health concerns relating to substance abuse, mental issues or STDs may not wish to visit the project’s medical
facility and instead go anonymously to local medical providers, thereby placing further stress on local resources. Local health
and rescue facilities may also be overwhelmed and/or ill- equipped to address the industrial accidents that can occur in a large
construction site.
• Gender-based violence: Construction workers are predominantly younger males. Those who are away from home on the
construction job are typically separated from their family and act outside their normal sphere of social control. This can lead
to inappropriate and criminal behavior, such as sexual harassment of women and girls, exploitative sexual relations, and illicit
sexual relations with minors from the local community.
• Child labor and school dropout: Increased opportunities for the host community to sell goods and services to the incoming
workers can lead to child labor to produce and deliver these goods and services, which in turn can lead to enhanced school
dropout.
• The Contractor will prepare the construction camp management plan which, in addition to other components, will include the
labor influx management plan. This will be reviewed and approved by EEP and the World Bank.
• The Contractor will select the specific work shift for the construction activities particularly near the settlements, to cause least
disturbance to the local population, particularly women.
• The Contractor will take due care of the local community and observe sanctity of local customs and traditions by his staff.
Contractor will warn the staff strictly not to involve in any unethical activities and to obey the local norms and cultural
restrictions.
• During construction activities, if privacy of the nearby households is affected, the Contractor will inform the house owner to
make particular arrangements. Similarly, Contractor will take care as much as possible that the construction activities should
not affect the privacy.
• The contractor will also ensure that solid waste and wastewater is disposed of in an environmentally friendly manner in
designated areas and by approved methods only. Contractor will ensure that soil and water is not contaminated by improper
disposal of solid waste and waste water.
• The contractor will explore alternative water sources and ensure that water usage by the project does not affect or compete
with water requirements of the local community.
• The Contractor will also ensure that noise and light pollution from the labor camp is kept at minimal levels especially at night.
• The contractor will be required to provide qualified key personnel to address the specific risks identified in the project including
Sexual Exploitation and Abuse risks. Contractors will specify key staff with the technical skill and experience to implement the
recommendations and mitigations included in this ESIA.
• The bidders will be required to submit Codes of Conduct (CoCs) with their bids. The CoCs will set clear boundaries for
acceptable and unacceptable behaviors of all individuals and companies and will be signed by companies, managers and
individuals.
• The contractor will be required to establish anti-sexual harassment policies that governs conduct in the workplace.
• The contractor will be required to provide mandatory and repeated training to workers on sexual exploitation and abuse and
HIV/AIDS prevention and on the content and obligations derived from the code of conduct
• Provisions will be set in contracts for dedicated payments to contractors for SEA prevention activities (e.g., training) against
evidence of completion.
• The Contractor will ensure the implementation of the recommendations and mitigations related to SEA risks included in this
ESIA. The implementation will be regularly reported by the Contractors and internally monitored by EEP. Implementation of
these recommendations and mitigations will also be monitored by the third-party M&E Consultant and presented in its
monitoring reports.
• The contractor will make all PPEs (face masks, hand sanitizers etc.) available at site and should also arrange for Covid vaccination
at site when required. All the employees of the contractors (including skilled and non-skilled) must be vaccinated and their
certificates should be checked before their mobilization/engagement.
Conclusion
The scale of these impacts is local, and temporary. Their magnitude, however could be medium to high. With the appropriate mitigation
measues, as described above, and with continuous monitoring, the residual impacts are considered low.
Details of the impacts associated with workforce mobilization are given below.
reversibility
Cumulative
occurrence
Probability
Objective/
magnitude
subjective
perceived
Adverse/
beneficial
duration
intensity
Direct/
Actual/
indirect
Spatial
effect
scale
of
Workforce
mobilisation Public health local temporary medium none probable low reversible adverse direct objective perceived
Occupational
health & safety local temporary high none probable high reversible adverse direct objective perceived
Competition
on resources local temporary Medium none Probable Medium reversible adverse direct objective perceived
SEA and GBV local temporary High None probable high reversible adverse direct objective perceived
Solid waste local temporary high none probable high reversible adverse direct objective perceived
• Spread excess soil around the tower foundation evenly and use the cleared vegetation as mulch to minimize soil erosion
• Prepare Resettlement Action Plan (RAP) and apply all of its requirements
• Restrict all excavation activities to the tower foundation areas and access roads
• Apply all requirements of the Occupational Health & Safety Management Plan
reversibility
Cumulative
occurrence
Probability
Objective/
magnitude
subjective
perceived
beneficial
Adverse/
intensity
duration
indirect
Direct/
Actual/
effect
of
Excavation of
tower foundation
and construction
of access roads Air quality local temporary low none certain low reversible adverse direct objective actual
Soil erosion local temporary medium none certain medium reversible adverse direct objective actual
Occupational
health & safety local temporary low none probable low reversible adverse direct objective perceived
Biodiversity
components local permanent high none certain high irreversible adverse direct objective actual
local
Spatial scale
permanent
duration
high
intensity
none
Cumulative
effect
Probability
of
certain
occurrence
high
magnitude
P a g e | 152
irreversible
reversibility
Adverse/
adverse
beneficial
Direct/
direct
indirect
Objective/
objective
subjective
actual
Actual/
perceived
9.2.3. Operation Phase
I. Soil
During the operation phase, the location of tower foundations and access roads will be
revegetated naturally. As a result, a significant soil erosion is not anticipated.
II. Air quality
Once the construction phase is completed, no significant impacts on air quality is anticipated.
III. Noise and vibration
Once the construction phase is completed, no significant impacts on noise level is anticipated.
IV. Flora and Forest
There will be adverse impact on the vegetation during the operation phase, i.e., vegetation
clearance for maintenance purposes. Since the vegetation in the RoW are cleared, a significant
impact is not anticipated. But there is a chance for the germination of seeds of big indigenous
trees in the surrounding forest inside the RoW corridor. Although these seedlings require many
years to become a mature tree, they may not pose risks to the Metu – Masha 230 kV single circuit
transmission line project. Maintenance activities also provide an enabling environment for the
introduction of invasive species into the project area. If invasive species produce seeds, these
seeds stay in soil as soil seedbank and results in a permanent risk for their spread to other areas
in the project area. Due to the presence of forested areas in the surrounding, the operation
phase impact on flora and forest is low. It is, however, permanent since the Metu – Masha 230
kV single circuit transmission line project operates for a couple of years.
Mitigation measures
• Transplant any seedlings of tree species of the forest that are growing inside the RoW
• Identify invasive species and clear them (uproot the seedlings) before reaching maturity
(seed production stage).
V. Fauna
During the operation phase, bird collision with the transmission line could occur. There is no
migratory route in the project area. Furthermore, the project area is not known as a
steppingstone habitat for migratory birds. The impact on migratory bird is anticipated to be not
significant.
VI. Economy and employment
The project creates opportunities for employment creating positive impacts on the livelihood
income. At a national level, the operation of the Metu – Masha 230 kV single circuit transmission
Mitigation measures
• Monitor and follow-up to support households to restore their livelihoods during the
operation phase. That is the details of the Livelihood Restoration Plan (LRP) details this
aspect.
• Maintain the functionality of the Grievance Redress Mechanism (GRM) developed for
Resettlement Action Plan (RAP) for the construction phase to create enabling
environment for communities to voice their concerns.
VIII. Land and livelihoods
During the operation phase, lands will be permanently lost to tower foundations. But cultivation
of cereal crops including Enset and growing tea shrubs are allowed. The incomes from the land
Mitigation measures
• Strictly follow-up PAPs, especially those in the urban area with only 200 square meter of
land, to provide support to restore their livelihoods in the operation phase
• The requirements of Livelihoods Restoration Plan developed for the construction phase
should apply for the operation phase as well.
IX. Community health and safety impacts from exposure to Electromagnetic Fields
(EMF)
The Electromagnetic Fields are usually emitted by electric devices such as transmission lines and
any other electric equipment. These invisible forces pose health risks such as chronic health
effects. They also cause acute public health effects. Although there are public health risks due to
high voltage OHTL, the IFC Guidelines for electric power distribution states that there is
empirical data to support that there is chronic public health concern from power transmission
lines and equipment. On the other hand, the International Commission on Non-ionizing
Radiation Protection (ICNIRP) Guidelines state that the existence of well-established cases of
acute health effects of exposure to low frequency of EMF. The RoW of the Metu – Masha 230
kV single circuit transmission line project crosses cultivated fields, tea Estate and some part of
Mitigation measures
• The Client should measure exposure levels once the Metu – Masha 230 kV single circuit
transmission line project is operational to ensure that the exposure of the public to EMF
is within the accepted limit.
• Awareness creation of the effects of EMF for the public by the Client
• Annual monitoring the RoW to make sure that no new houses are built inside the 40 m
corridor.
X. Worker’s health and safety
During the operation phase, there will be maintenance of the Metu – Masha 230 kV single circuit
transmission line project. Workers will be exposure to EMF and potential risks of electrocution.
The workers should be provided with PPE to mitigate the impact. It is anticipated that this impact
is not significant.
XI. Religious sites
There is no significant impact on the religious site due to the Metu – Masha 230 kV single circuit
transmission line project.
Currently, there is Masha – Gore Asphalt Road construction project. This project crosses
through the forest. Lots of indigenous trees were falling to expand the width of the road. Large
areas of forest have been cleared. Big trees such as Pouteria adolfi-frifderici, Polycias fulva, Olea
welwitchi, Cordia africana and etc. have been clear. Since the clearing is wide, this activity negatively
impact forest integrity and tree density.
Agricultural expansion (circled areas; these are labeled for year 2020 in Figure 44) is one of the
major factors affecting the forest cover of the project area (Figure 10-1). An estimate of
agricultural expansion from 1984 – 2020 is given in Table 10-1. Three sites (Figure 10-1: A1, A2
and A3) were randomly selected to show the impacts of agricultural expansion on the forests of
the project area.
Table 10-1. A quantitative estimate of the length of agricultural expansion from one forest edge to the other
from 1984 – 2020.
The forest cover (cf. circled area) was disturbed in 1984 but the forest in the surrounding area
was intact. (Figure 10-2). This intact forest has been gradually converted into tea Estate. Currently,
the size of the tea Estate has increased significantly.
A summary of the cumulative effects of other activities on the selected VEC is given in Table 10-2.
The cumulative impacts are of a high-risk level. But the current Masha – Gore Road Project is
rated as moderate considering the full implementation of its ESMP by the Contractor.
Table 10-2. Significance of cumulative effects on the selected VECs
Natural Habitats Agricultural Likely: the past trend High impact: the H
and Biodiversity expansion shows that there is an aerial extent and
increase in the quality of the
expansion of natural habitats
agricultural fields will decline
triggered by an leading to
increase in population depauperated
of the project area. biodiversity and
With the current compromised
20 The risk level will be moderate if the Road Contractor plants seedlings of these tree species in the
project area as part of implementing the requirements of the ESIA of the Road project
The Ethiopian Electric Power (EEP) will procure the services of contractors for construction the
proposed the Metu - Masha OHTL. It is likely that the main contractor will procure local services
of sub-contractors mainly for certain project activities. The responsibilities of major parties of
are outlined below.
• Ethiopian Environmental Protection Authority (EPA). The EPA will review and
approve ESIA reports of the Metu – Masha 230 kV single circuit transmission line project.
It is also a sole authority for providing environmental clearance for the implementation of
the project. Furthermore, EPA is responsible for monitoring the implementation of the
provisions of ESMP.
• Ethiopian Electric Power (EEP). EEP is the project proponent and will contract a
consultant (Project Implementation Consultant, PIC) to supervise the implementation of
the proposed Metu – Masha 230 kV OHTL project. The PIC will supervise and monitor
the implementation of the provisions of the ESMP and will report to EEP on a regular
basis. EEP will also assign own experts (Project Implementation Unit, PIU) to monitor the
implementation of all requirements of the ESMP of this project.
• Zonal and Woreda Forest and Environmental Protection Offices. They are
expected to get involved in the monitoring of the implementation of the ESMP of the
project.
• Contractors. The Contractor is mainly responsible for the implementation of all of the
mitigation measures outlined in the ESIA to avoid or minimize environmental, health &
safety and social impacts of the project. Besides, the Contractor should have an
Environment, and Social Management (E&S) Unit, which is solely responsible for the
implementation, management and monitoring of all the environmental and social
mitigation measures according to the ESMP. This Unit should have at a minimum one
Environmentalist, one Forester and one Sociologist/Social expert. The Contractor is
responsible for ensuring its subcontractors are in compliance with the international and
national environmental and social standards. The Contractor will submit weekly reports
and monthly reports to EEP.
The Contractors will comply with requirements within the scope of work. This ESMP requires
all contractors to develop a detailed Environmental, Social, Health and Safety Plan in accordance
with their own policy framework and management system to foster environmental and social
sustainability of the project. The following sections provide the EHS requirements of civil works
(construction works).
All wastes including used plastic water bottles should be sorted on site and deposited at
designated areas. Wastes of any types should be removed on time and regular basis.
Solid Waste includes those materials which are no more used for project activities and excavated
soil materials.
The following national legislation and policy are relevant.
• The Constitution of the Federal Republic of Ethiopia.
Article 44 states that all persons have the right to clean and health environment. Article
92 tasks the Federal Government to ensure that all Ethiopians live in a clean and health
environment.
• Environmental policy of Ethiopia
This policy advocates the “polluters pay policy” and authorizes competent authorities to
close down or relocate any enterprise if its activities are considered as posing risks to
human health and the environment.
• Prevention of Industrial Pollution Regulation (159/2008)
All workforces of the • All workers are responsible for good practice waste
contractors and their management at the project sites
subcontractors
Implementation schedule • Construction phase of the project
Management Actions
• Establish a waste management procedure at the project sites which also takes domestic
solid and liquid wastes and used oils into consideration
Dispose all excavated soil wastes by using the ESMP provisions as a guide.
The extent of soil erosion during the construction phase depends on the type and physical
properties of soil, slope of the topography, vegetation cover and the duration of the construction.
The project crosses through different types of soil and slopes of topography. The slope of the
RoW of the project ranges from flat to 25%.
The Metu – Masha 230 kV single circuit transmission line project crosses two major soil types,
i.e., Nitisols and Gleysols. Soil erodibility of the project area is low but human factors and
construction activities enhance soil erosion. Both the Nitisols and Gleysoils are moderately
erodible.
The excavation of foundations and access roads to the tower foundations trigger soil erosion.
This impact likely occurs but its extent is limited to tower foundations areas and the access roads.
The impacts of these activities of the project will have a short duration, i.e., limited to the direct
zone of the AOI of the project. Given the high moisture condition of the area, vegetations growth
will cover these impact areas within a short period of time.
Responsibilities and accountability
The responsible Parties and their roles and responsibilities are given below.
Responsible parties Roles
The Contractor • Ensure that all required Environmentalist/forester are
employed
• Ensure that all management actions are implemented
• Submit its Company Soil Erosion Management
Procedures/policy for approval by the Client
Zonal and Woreda • Regular supervision of the construction activities
Environmental Protection • Regular recording of risks of the activities of the contractor
Office for triggering soil erosion
• Enforce all requirement of the soil management actions
The Ethiopian Electric Power • Regular supervision of excavation activities of the Contractor
• Record the presence of an Environmentalist/Forest at
construction sites on a regular basis
• Record activities of the Contract that pose risks for soil
erosion
• Provide corrective measures to minimize soil erosion
•
Supervision Consultants • Follow day-to-day construction activities of the Contractor
• Hire an Environmentalist/Forester to follow and guide
environmental due diligence of the Contractor
Management actions
• Minimize vegetation clearance and topsoil disturbance
• Stockpile topsoils separately from subsoil. Fill the tower foundation first with subsoil and
then topsoil.
• The implementation of the management actions to mitigate soil erosion is done by visual
inspections. Contractor’s risk footprints will be used for verification of the
implementation of this ESMP.
There are forests in the project area. Coffee agroforestry, where big indigenous trees are uses
as shade, is practiced in the project area. The Metu – Masha 230 kV single circuit transmission
line project also crosses some section of the Yayu Coffee Forest and Sheka Forest Biosphere
Reserve. The length of the Metu – Masha 230 kV single circuit transmission line project in these
sections of the Biosphere Reserves is about 700 m. But there are forest vegetation and plants
growing beneath this big vegetation.
Purpose and scope of this Management Plan
Vegetation clearance along the Row in areas where the Metu – Masha 230 kV single circuit
transmission line project crosses forested areas will likely happen. The purpose of the Forest
Management Plan is to minimize vegetation clearance and limit it to the direct impact zone of the
Project AOI. The duration of this impact is permanent since vegetation will be removed from the
RoW. Furthermore, the habitats within the RoW will be modified.
Responsibilities and accountability
Management actions
• Invasive species could be transported with construction materials, namely sand. The
forester of the Contractor should inspect the disturbed area for the seedlings of invasive
species. In this case, remove all invasive species before they mature and produce seeds.
• Vehicles should use only access roads. There should not be deviations from the access
road and damage other forest components.
There are diverse species in the project area. Most of the plant species are widely distributed in
Ethiopia and were assessed as Least Concern from conservation viewpoint. But there are
indigenous tree species such as Prunus africana, which is assigned a vulnerable IUCN status. Other
species such as Pouteria adolfi-friderici, Olea welwitschii, Apodytes dimidiata and etc. occur in the
project area. Indigenous trees of Ethiopia usually need decades to reach maturity. With regard
to avifauna, they are of least conservation concern based on IUCN assessment criteria.
Furthermore, there is no known route for migratory birds in the project area. On the other
hand, there are ants species which are important to suppress coffee pests. They usually build
their nests on these indigenous trees. Therefore, felling trees with ant nest affects these species.
The impact of the project on the biodiversity of the area is likely to occur. The impact is
permanent since trees will be removed along the RoW and access roads.
Although the project area is not located within the flyways of migratory birds, there is a potential
collusion of these birds and bats of the area with this new power transmission line. This results
in an electrocution of birds and bat species in the project area.
Purpose and scope of this Management Plan
• Tree species of the project area are used by Crematogaster ants to build their nest. These
ant species are critical for the integrity of pest-predator communities of the ecosystem of
the project areas. The personnel of the Contractor will be given an orientation not to
destroy these ant nests. When trees with ant nest fell, the Contractor personnel will
mechanically detach the nest and attach it to other tree of the same species, under the
supervision of the project environmentalist / biologist.
• For each impacted individual indigenous tree, plant 10 new individual seedlings of the same
species
• Birds and bats of the project area could potentially collide with the power transmission
line. To minimize or avoid the electrocution of birds and bats install visibility enhancement
objects such as “Aviation” or marker balls and diverters following the World Bank EHS
guidelines21.
Monitoring and verification
• Visual inspection of the types and number of trees impacted will be used to quantify
impacts.
• Counting the number and types of trees felled and planted to mitigate the adverse impacts.
• Evidence of the activities of the Contractor to either establish new Nursery sites or work
with the existing one.
• Visual inspection and counting the number cut trees with ant nests
All vehicles entering and leaving the project sites should be covered except when they are loading.
Dust suppression methods such as spraying water on access and internal roads should be
practiced by the Contractors on timely and regular basis in accordance with the ESMP.
The following national legislation and policy are relevant for the air quality management.
21
Environment, Health and Safety Guidelines for Electric Power Transmission and Distribution (IFC – World Bank
Group 2007)
• National guidelines
The Environmental Standards for industrial Pollution Control in Ethiopia. The contents of
this Standard limit the emission of pollutants to the atmosphere.
The overall accountability for the implementation of the air quality management plan lays on the
Contractors and their subcontractors. The table below provides roles and responsibilities of all
concerned parties for the implementation of air quality management.
Responsible Parties Roles and responsibilities
Project Manager Ensure the availability of resources and authority
for the implementation of the air quality
management as specified in the ESMP
Environmental and Social experts Enforce the management and monitoring of air
quality
Management actions
Dust emission and be controlled and managed by implementing the following actions during the
implementation of the project.
The Contractor shall submit a traffic safety plan to be reviewed by the representatives of the
Client before commencing the work. This plan should specify key responsibilities and speed limit
of vehicles it operates in accordance with the ESMP. Furthermore, the contractor should also
develop a plan for on-site parking of cars.
The activities of the project during the construction and operation phase triggers certain issues
with regard to potential traffic accidents. An increased movement of vehicles could lead to
potential impacts on the livestock of the local communities.
Objectives
The objectives of the Traffic Management Plan (TMP) are as follow.
• Avoid potential traffic accidents due to the movements of vehicles due to the opening of
this new road
Purpose and scope of the Traffic Management Plan
The purpose of this Management Plan is to guide the contractor to avoid potential traffic accidents
during the construction phase by using designated access roads. The scope of this Management
Plan includes the construction and operation phases of the project.
The following national policies and legislations are relevant with regard to this TMP.
• The Constitution of the FDRE
• Policy on Public health
Project Manager
Management Actions
• The Environmentalist of the contractor should take the lead in guiding the implementation
of the TMP
The contractor shall submit an Occupational Health and Safety (OHS) Plan to be reviewed by the
representatives of the client before commencing the work. The plan should include at least the
following:
• Description of hazards and risks to the safety and health of the workers which arise from
the working environment – including occupational health and safety hazards specific to
electric power transmission and distribution projects, such as working close to live power
lines; working at height; electric and magnetic fields; and exposure to chemicals.
• Identification of sources of injury and harm with preventive measures to avoid these
injuries and harms
Management actions
• Heath education for communicable diseases such as HIV/AIDS and STDs. This activity will
enhance personal protection and behavior to avoid this health risk
• The Contractors shall adhere to the following key Workforce Code of Conduct
o Forbidding sale or purchase of alcohol
o Forbidding sale or purchase of drugs
• Ensure that there is a free access to first aid stations for minor treatments
The labor management of the Contractors should comply with the national labor and
employment law. Details should such payments of wage, working hours and treatment provisions
in cases of accidents. The contractors should employ local laborers and develop a procedure for
equitable selection of laborers.
The contractors should maintain accurate records in relation to:
Health and safety officer (First Aid Expert) Ensure that all provisions in relation to OHS are
implemented and workers are provided with PPE
Implementation schedule Construction phase of the project
Management actions
• Ensure that all standards provisions, including PPE, are implemented to enhance the OHS
issues
• Develop workers’ OHS awareness program
• Develop a worker code of conduct in applying OHS requirements, including the use of
PPE and monitoring system to enhance workplace health and safety
The following national legislation and policy are relevant for ensuring the occupational health and safety
of the workers.
• Labor law. This specifies provisions for ensuring workers’ rights, for example, minimum
wages, collective bargaining rights and rights to association.
• Prevention of Industrial Pollution Regulation (159/2008). Sections of this Regulation state
the need for emergency response systems and environmental safety monitoring.
The table below provides responsible parties and their roles and responsibilities.
Responsible Parities Roles and Responsibilities
Management actions
All incidents shall be registered and reported accordingly for further actions. A standard checklist
shall be used for this purpose. Incidents can be of the following categories.
• Environmental incidents
• Injuries of workers
• Injuries of people
• Security breach
Monitoring and verification
The Health and Safety officer (First aid expert) is tasked the responsibilities for supervising the
implementation of the Emergency Response Plan of the Contractors and their subcontractors.
This officer shall report incidents monthly to be reviewed by the representatives of the client.
The communities of the project area are smallholder farmers who entirely depended on incomes
generated from their lands. The impacts of the project during construction and operation phases
are given below.
Construction phase Operation phase
• High household income due to • Permanent loss of land to tower
compensation payment from their foundations
lands
• More household income due to
employment opportunity
• Displacement of physical structure,
e.g., houses and cash crop trees
Houses
Access control to the site shall be arranged to foster accountability of all personnel. This policy
should apply during the construction phase of the project.
The contractors and its personnel should interact with the local communities in such a way that
promotes good relationship. Local norms and values should be observed and maintained by the
contractors and all personnel. The contractors bear the sole responsibility for any damage to
public properties that may occur outside the project area. This policy should apply during the
construction phase of the project.
During operation phase of the project, regular maintenance of the right-of-way to control
vegetation growth will be implemented. This may involve the use of mechanical methods, such as
mowing or pruning machinery, in addition to manual hand clearing and herbicide use. Such
activities may disrupt wildlife and their habitats. However, given the size of the RoW, the impact
is not considered significant. Care will be taken during maintenance to remove fauna species likely
to be present in the RoW.
The cost of mitigation measures is given in Table 11-1. The calculation of costs is based on
background information such as the cost of one seedling for Biodiversity Management.
Furthermore, the frequency of awareness creation was set as 2 times per Kebele with a total
turnout of 50-60 participants and a publication of information leaflets. In other cases, lumpsum
amounts are given. Employment of staff of the Environmental Unit of the Contractor was
estimated based on current earnings for similar jobs (short-term employment for development
projects).
Table 11-1. Summary of the Environmental and social mitigation measures
Impact source Mitigation Responsible body Amount in ETB ESMP to be Time schedule
measures addressed
Removal of Plant 10 The Contractor 6,250,000.00 Biodiversity Construction
mature seedlings for Management phase
indigenous trees each removed Plan; Soil
tree. Erosion
It is anticipated Management
that close to Plan
25,000
seedlings will
be planted
Felling of trees Transplant the The Contractor 500,000.00 Forest Construction
with ant nests nest onto Management phase
another tree Plan
of the same
species
Air quality: Dust The Contractor 100,000.00 Air Quality Construction
emission of dust suppression by Management phase
watering Plan
access roads
Public exposure Awareness The Contractor 250,000.00 Community and Construction
to EMF raising Health Safety phase
Management
Plan;
workers/Labour
Management
Plan
Public health Health The Contractor 250,000.00 Solid Waste Construction
risks: HIV/AIDs education Management phase
and STDs Plan; Emergency
Response Plan
Occupational Short-training The Contractor 1,000,000.00 Workers/labour Construction
health and safety on first aid for Management phase
the Plan; Emergency
contractor’s Response Plan
workforce;
Provision of
PPE
First aid kits
Workforce Transfer of • Orientation of the workforce by the contractor prior to Contractor PIC, PIU
Mobilization responsibility for ESHS commencing duties
compliance to • Health education for the workforce and awareness creation for
Contractor HIV/AIDS and other STDs
• Apply the best industry practice and applicable law and regulation
of Ethiopia for employing workers
• Collect all used plastic water bottles and dispose them at
designated areas
• Apply all requirements of the Solid Waste Management Plan
• Apply all requirements of Occupational Health and Safety
Management Plan
• Apply all requirements of Air Quality Management Plan
• Apply all requirements of the Forest Management Plan
• Apply all requirements of Biodiversity Management Plan
RoW clearance Impact on wildlife • Provide workers with personal protective equipment (PPE) Contractor PIC, PIU
habitats due to RoW • Avail first aid kits at the work places
clearance • Undertake vegetation clearing in the presence of an
Occupational H&S risks Environmentalist or a Forester
• Prepare and execute a tree plantation program to compensate for
the environmental loss of the trees felled
• Suppress dust emission by watering the work areas on a regular
basis
• Apply all requirements of Biodiversity Management Plan
• Apply all requirements of the Air Quality Management Plan
• Apply all requirements of the Occupational Health & Safety
Management Plan
• Apply all requirements of the Emergency Response Plan
• Collect used plastic water bottles
Land • Loss of approx. 1.8 ha • Apply all provisions of the Resettlement Action Plan (RAP) of the Contractor PIC, PIU
acquisition for of land as well as loss Metu – Masha 230 kV power transmission line
tower of cultivations within • Payment for permanently lost coffee shrubs and spices plants
foundations the RoW • Payments for permanent loss of assets of PAPs due to Tower
foundation
Removal of Loss of residential • Apply all requirement of the Resettlement Action Plan (RAP) Contractor PIC, PIU
structures from structures and means • Payment of compensation for permanent and temporary loss of
RoW of livelihood assets of the PAPs.
• Apply all provisions of the Livelihood Restoration Plan of this
project
• Enable the PAPs at Kolo Korma get new plots of land to construct
new houses at least close to where they are living now to ensure
social cohesion and their traditional social activities.
B. CONSTRUCTION STAGE
Labor influx Stress on local The Contractor will prepare the construction camp management plan, Contractor PIC, PIU
resources and services including the labor influx management. This will be reviewed and approved
by project staff by EEP and World Bank
The Contractor will select the specific work shift for the construction
activities particularly near the settlements, to cause least disturbance to the
local population, particularly women.
Contractor will take due care of the local community and observe sanctity
of local customs and traditions by his staff. Contractor will warn the staff
strictly not to involve in any unethical activities and to obey the local norms
and cultural restrictions.
During construction activities, if privacy of the nearby households is affected,
the Contractor will inform the house owner to make particular
arrangements. Similarly, Contractor will take care as much as possible that
the construction activities should not affect the privacy.
Social and gender The contractor will provide qualified personnel to address the specific risks Contractor PIC, PIU
impacts created by identified in the project including Sexual Exploitation and Abuse (SEA) risks
project staff due to the and implement the recommendations and mitigations included in this ESIA
unawareness of local
The bidding documents will include specific requirements that minimize the
customs and norms
use of expatriate workers and encourage hiring of local workers through
skill development program, thereby minimizing labor influx.
The bidders will be required to submit Codes of Conduct (CoCs) with their
bids. The CoCs will set clear boundaries for acceptable and unacceptable
behaviors of all individuals and companies and will be signed by companies,
managers and individuals.
The contractor will be required to establish anti-sexual harassment policies
that govern conduct in the workplace.
The contractor will be required to provide mandatory and repeated training
to workers on sexual exploitation and abuse and HIV/AIDS prevention and
on the content and obligations derived from the code of conduct.
Provisions will be set in contracts for dedicated payments to contractors for
SEA prevention activities (e.g., training) against evidence of completion.
The Contractor will ensure the implementation of the recommendations and
mitigations related to SEA risks included in this ESIA. The implementation
will be regularly reported by the Contractors and internally monitored by
the PIU. Implementation of these recommendations and mitigations will also
be monitored by the third party M&E Consultant and presented in its
Covid-19 The contractor will make all PPEs (face masks, hand sanitizers etc.) available Contractor PIC, PIU
at site and should also arrange for Covid vaccination at site when required.
All the employees of the contractors (including skilled and non-skilled) must
be vaccinated and their certificates should be checked before their
mobilization/engagement.
Excavation of Management of spoil • Water the project area on a regular basis to suppress dust Contractor PIC, PIU
tower generated due to the emission
foundations, excavation works; • Spread excess soil around the tower foundation evenly and use the
tower erection, cleared vegetation as mulch to minimize soil erosion
Risk of soil pollution
stringing of • Prepare Resettlement Action Plan (RAP) and apply all of its
and soil erosion;
conductors, requirements
other works Risk of water • Restrict all excavation activities to the tower foundation areas and
contamination; access roads
Dust and air pollution • Provide workers with PPE
from construction • Apply all requirements of Biodiversity Management Plan
activities; • Apply all requirements of Waste Management Plan
• Avail first aid kits
Noise and vibration
• Apply all requirements of the Air Quality Management Plan
from construction
activities; • Apply all requirements of the Occupational Health & Safety
Management Plan
Generation of solid • Apply all requirements of the Emergency Response Plan
waste and hazardous • Avoid excavation of religious sites (graveyards and others)
waste
TL RoW Impacts from tree • Identify seedlings of indigenous tree species before clearing the EEP PIU
Maintenance cutting during O/M vegetation
activities • Transplant any seedlings of tree species of the forest that are
growing inside the RoW
• Identify invasive species and clear them (uproot the seedlings)
before reaching maturity (seed production stage).
Restrictions Impacts to livelihood of • Monitor and follow-up to support households to restore their EEP PIU
within the smallholder farmers livelihoods during the operation phase. That is the details of the
RoW Livelihood Restoration Plan (LRP) details this aspect.
• Maintain the functionality of the Grievance Redress Mechanism
(GRM) developed for Resettlement Action Plan (RAP) for the
construction phase to create enabling environment for
communities to voice their concerns.
Land loss Impacts due to the land • Strictly follow-up PAPs, especially those in the urban area with only EEP PIU
occupied by the towers 200 square meter of land, to provide support to restore their
livelihoods in the operation phase
• The requirements of Livelihoods Restoration Plan developed for
the construction phase should apply for the operation phase as
well.
TL operation Community H&S risks • Avoid installation of transmission line above densely occupied EEP PIU
due to exposure to settlements.
EMF • The Client should measure exposure levels once the Metu – Masha
230 kV single circuit transmission line project is operational to
ensure that the exposure of the public to EMF is within the
accepted limit.
• Awareness creation of the effects of EMF for the public by the
Client
• Annual monitoring the RoW to make sure that no new houses are
built inside the 40 m corridor.
The monitoring of the construction practices and mitigation measures will be based on visual
inspections. Table 13-1 give a monitoring plan of the project with key measures to be considered.
It is to be noted that the contractors shall undertake self-monitoring their compliance with the
ESMP and EHS plan. The contractors should perform regular monitoring inspections by using pre-
developed checklists and prepare monthly report to be reviewed by the representative of the
client (Engineering Consultant) and submitted to the competent authority, the Ethiopian
Environmental Protection Authority, MoPD. The contractor should establish an Environmental
Management Unit (EMU) comprised of one Environmentalist, one Forester and one Sociologist
Monthly report
The Contractors shall prepare a monthly report with regard to the environmental and social performance
and their compliance to the ESMP. This report should be submitted the representatives of the client for
review and further actions. The contents of this report shall be based on the monitoring results of the
EMU of the contractors.
Annual Reporting
The Contractors shall prepare an annual environmental and social performance report and overall
compliances with the ESMP. This report shall be reviewed by a supervision Consultant, who is also the
representative for the EEP. This annual report should be submitted by EEP to the Ethiopian Environmental
Protection Authority for a review and approval.
The Ethiopian Electric Power (EEP) has planned to construct Metu – Masha 230 kV single circuit
transmission line project. This entails the construction of an extension of the Metu sub-station
and a new sub-station at Masha. Masha town is currently without power. The Metu – Masha 230
kV single circuit transmission line project crosses modified landscape for most of its length and a
very small length of it crosses forests. It is anticipated that the construction of this power
transmission line and new sub-station at Masha stimulates local economic activities and attracts
investments. The ESIA study has recorded a case where an investor in coffee processing in Sheka
Zone has constructed all physical structures but did not start work because of the lack of power.
Furthermore, this project will improve quality of life for Masha and its surrounding communities.
Currently, the local communities use traditional means of flour milling. The implementation of
the project attracts investors to establish flour mills and other related activities. It is anticipated
that several business activities will come up with power, which in turn improve household
incomes.
It is expected that any development project affects the status quo environmental and social
conditions. The ESIA study has recorded the following impacts.
Biological conditions and natural habitats
The project area is a site where part of the remaining moist Afro-montane Forest is located. This
forest is characterized by keystone species such as Pouteria adolfi-friderici, Cordia africana, Prunus
africana, Olea welwitchi and etc. Coffee grows under the canopy of these trees. Furthermore,
spices such as Piper capense and Afromomum corrorima grows as herbaceous layer of this forest
and provide additional household incomes. IUCN conservation assessment was conducted for a
handful of the flora and fauna of the project area. For example, Prunus Africana as assessed as
Vulnerable and other are of Least Concern from the IUCN assessment perspectives. But at a
national level, there are tree species which have low number of individuals in the forest and need
to be protected. Examples are Pouteria adolfi-friderici, Olea welwitchii, Cordia africana and etc.
Noteworthy is also that it takes decades for these tree species to reach maturity. A natural
regeneration of some of these tree species is a challenge since young seedling survival is affected
by wildlife browsing.
Different fauna species were investigated in this ESIA study. Selected amphibians, reptile, birds
and mammals were studies. There are endemic amphibians, reptiles and a mammal species. But
these are widely distributed and were not recorded along the RoW of the project. They occur
in the Moist Afro-montane Forest in the surrounding area of the project. As a result, there is no
direct impact by the activities of the project. The ESIA has also revealed that there is no Important
Bird Area and known bird migratory route in the project area. Furthermore, the bird species are
of least conservation concerns and there is no immediate threat to their long-term persistence.
Conclusion
• The project triggers biodiversity issues such as cutting indigenous trees inside the 40 m
corridor of the RoW. It also restricts the planting of high trees inside this same area. But
the impacts are mitigable and ESMP has been developed for environmental receptors
receiving these impacts.
• Although there are Biosphere Reserves in the project area, the Metu – Masha 230 kV
single circuit transmission line project crosses their transition zone, which are highly
modified (agriculture and settlement). The ESIA study has revealed that there are no
Critical Habitats that are triggered by this project. There are also National Priority Forest
Areas lying on the RoW of the project. But these have been converted to agriculture and
settlement long time ago.
• Some project activities trigger soil erosion but the impact can be mitigated. An ESMP has
been develop.
• The socio-economic impacts of this project are significant. It triggers physical displacement
of houses and cutting of crop trees. RAP and LRP studies should be conducted to mitigate
these impacts.
Generally, the impacts of the project on bio-physical and socio-economic environments can be
mitigated. The ESMP was also developed for these impacted receptors. Therefore, for the project
to proceed the following conditions should be fulfilled. These are:
(1) all requirements of each ESMP are implemented in full;
(2) the ESMP is improved and adjusted to new emerging conditions which are not captured
during the ESIA study; and
(3) Resettlement Action Plan and Livelihood Restoration Plan are conducted and
implemented.
Recommendation
Therefore, the proposed project is environmentally and socially feasible to be implemented
provided that all the requirements of the ESMP are implemented by the contractor and the
project proponent (project owner, EEP). The regulatory bodies, i.e., EPA and Zonal and Woreda
Office for Forests and Environmental Protection and other government bodies should participate
in ensuring the implementation of all the proposed mitigation measures for the impacts of Metu
– Masha 230 kV single circuit transmission line project.
Hedberg, I. and Edwards, S.1995. Flora of Ethiopia and Eritrea, Vol 7, Poaceae (Gramineae).The
National Herbarium, Addis Ababa University, Addis Ababa and Uppsala.
Hedberg, I., Edwards,S. and Sileshi Nemomissa.2003. Flora of Ethiopia and Eritirea, Vol 4, Part
1.Apiaceae to Dipsacaceae.The National Herbarium Addis Ababa University, Addis Ababa and
Uppsala.
Hedberg, I., Ensermu, Kelbessa, Edwards,S., SebsebeDemissew and Eva, P.2006.Flora of Ethiopia
and Eritrea, Vol 5, Gentianaceae to Lamiaceae. The National Herbarium Addis Ababa University,
Addis Ababa and Uppsala.
Hedberg, I., Friis, I. and Eva, P.2009. General part and index, Vol 8.The National Herbarium, Addis
Ababa University, Addis Ababa and Uppsala.
Hedberg, I., Friis,I. and Pearson, E. 2001. Flora of Ethiopia and Eritirea, Vol 1, Lycopodiaceae to
Pinaceae.The National Herbarium, Addis Ababa University, Addis Abeba.
Hedberg, S. and Edwards, S. 1989.Flora of Ethiopia and Eritirea, Vol 3, Pittosporaceae to
Araliaceae. The National Herbarium, Addis Ababa University, Addis Abeba, Asmara and Uppsala.
Ib Friis, Sebsebe Demissew & Paulo van Breugel. 2012. Atlas of the Potential Vegetation of
Ethiopia. Copenhagen: The Royal Danish Academy of Sciences and Letters in Biologiske
Skrifter58. 2010. 307 pp. including 29 colour map plates (1:2 000 000). ISSN 0366 3612, ISBN
97887 7304 347 9. 400 DKK Published online by Cambridge University Press: 16 February 2012
International Labour Organisation (ILO). C087 - Freedom of Association and Protection of the
Right to Organise Convention, 1948 (No. 87). Convention concerning Freedom of Association
and Protection of the Right to Organise (Entry into force: 04 Jul 1950).
International Labour Organisation (ILO). C105 - Abolition of Forced Labour Convention, 1957
(No. 105) Convention concerning the Abolition of Forced Labour (Entry into force: 17 Jan
1959).
International Labour Organisation (ILO). C111 - Discrimination (Employment and Occupation)
Convention, 1958 (No. 111). Convention concerning Discrimination in Respect of Employment
and Occupation (Entry into force: 15 Jun 1960).
International Labour Organisation (ILO). C138 - Minimum Age Convention, 1973 (No. 138)
Convention concerning Minimum Age for Admission to Employment (Entry into force: 19 Jun
1976).
International Labour Organisation (ILO). C182 - Worst Forms of Child Labour Convention,
1999 (No. 182). Convention concerning the Prohibition and Immediate Action for the
Elimination of the Worst Forms of Child Labour (Entry into force: 19 Nov 2000).
International Labour Organisation (ILO). Convention against Torture and Other Cruel,
Inhuman or Degrading Treatment or Punishment: 1987.
International Labour Organisation (ILO). Convention on the Elimination of All Forms of
Discrimination against Women: 1981 (CEDAW).
International Labour Organisation (ILO). Convention on the Rights of the Child: 1990. Adopted
and opened for signature, ratification and accession by General Assembly resolution 44/25 of 20
November 1989
IUCN. 2013. IUCN Red List of Threatened Species (ver. 2013.2). Available at:
http://www.iucnredlist.org
The ESIA was prepared by IRIS Consult PLC (Ethiopia) under the supervision of intec- GOPA
(Germany). The ESIA team comprised the following.
Name Expertise
Prof. Sileshi Nemomissa Team leader and Senior Environmentalist
Prof. Feyera Senbeta Forester
Prof. Seyoum Mengistou Zoologist
Dr. Endalew Addis Senior sociologist
Mr. Girma Demissie Socio-economist
Mrs Semira Berhanu Gender Expert
Mr. Amanuel Kumsa GIS Expert
A. Illubabor Zone
i. Ilubabor Zonal Administration
Population
S/N Species name Family Habit IUCN Category Trend Remark
1 Abutilon longicuspe Hoehst. ex A. Rich. Malvaceae Shrub Not assessed Indigenous
2 Acacia abyssinica Hochst. ex Benth. Fabaceae Tree Not assessed Indigenous
3 Acanthus eminens C.B.Cl Acanthaceae Shrub Not assessed Indigenous
4 Acanthus polystachyus Delile. Acanthaceae Shrub Not assessed Indigenous
5 Aframomum corrorima (Braun) Jansen Zingiberaceae Herb LC Unknown Indigenous
6 Albizia gummifera (J. F. Gmel.) C.A.Sm. Fabaceae Tree LC Unknown Indigenous
7 Albizia schimperiana Oliv. Fabaceae Tree LC Stable Indigenous
8 Allophylus abyssinicus (Hochst.) Radlk. Sapindaceae Tree Not assessed Indigenous
9 Amorphophallus abyssinicus (A. Rich.) N.E. Br. Araceae Herb Not assessed Indigenous
10 Anthocleista schweinfurthii Gilg Loganiaceae Tree LC Stable Indigenous
11 Apodytes dimidiata E. Mey. ex Am. Icacinaceae Tree LC Decreasing Indigenous
12 Asplenium aethiopicum (Burm. F.) Becherer Aspleniaceae Fern Not assessed
13 Asplenium sandersonii Hook Aspleniaceae Fern Not assessed Indigenous
14 Bersama abyssinica Fresen. Melianthaceae Tree/ Shrub LC Stable Indigenous
15 Bidens biternata (Lour.) Merr. & Sherff Asteraceae Herb Not assessed Indigenous
16 Bidens pilosa L. Asteraceae Herb Not assessed Indigenous
17 Bridelia micrantha (Hochst.)Baill. Euphorbiaceae Tree Not assessed Indigenous
18 Buddleja polystachya Fresen. Loganiaceae Tree Not assessed Indigenous
19 Caesalpinia decapetala (Roth)Alston Fabaceae Shrub Not assessed Indigenous
20 Catha edulis (Vahl) Forssk. ex Endl. Celastraceae Shrub Not assessed Indigenous
21 Celtis africana Buerm.f. Ulmaceae Tree Not assessed Indigenous
22 Clausena anisata (Willd). Benth. Rutaceae Shrub Not assessed Indigenous
23 Clerodendrum myricoides (Hochst.) Vatke Lamiaceae Shrub Not assessed Indigenous
24 Coffea arabica L. Rubiaceae Shrub EN Decreasing Endemic
25 Colocasia esculenta (L.) Schott Araceae Herb LC Unknown Indigenous
26 Combretum paniculatum Vent. Combretaceae Climber Not assessed Indigenous
Forest condition in 1984 before the large-scale investment (cf. the circled area)
Critical habitats are areas that contain features that are vital for conservation of species. These are habitats of conservation concern
and require targeted management and conservation. The IFC Performance Standard 6 define critical habitats as “Habitat is defined
as a terrestrial, freshwater, or marine geographical unit or airway that supports assemblages of living organisms and their
interactions with the non-living environment.” These habitats are of high biodiversity value22 and meet the one or more of the
following criteria23. These criteria are:
vi. Criterion 1: Critically endangered (CR) and/or Endangered (EN) species
vii. Criterion 2: Endemic or restricted-range species
viii. Criterion 3: Migratory or congregatory species
ix. Criterion 4: Highly threatened and/or unique ecosystem
x. Criterion 5: Key evolutionary processes
Where the project falls inside IUCN’s Protected Areas Categories 1a, 1b and II, IFC guidance note 6 (Biodiversity Conservation and
Sustainable Natural Resources Management, G9 stipulates that a Biodiversity Management Plan to be prepared. A critical habitats
assessment will be carried out in such case. The project area falls under IUCN’s Protected Areas Category VI (protected area with
sustainable use of natural resources). Category VI protected areas24:
• Conserve ecosystems and habitats together with associated cultural values and traditional natural resources management
system;
22 http://www.ifc.org/wps/wcm/connect/115482804a0255db96fbffd1a5d13d27/ PS_English_2012_Full-Document.pdf?MOD=AJPERES
23 http://www.ifc.org/wps/wcm/connect/a359a380498007e9a1b7f3336b93d75f/ Updated_GN6-2012.pdf?MOD=AJPERES
24 https://www.iucn.org/theme/protected-areas/about/protected-areas-categories/category-vi-protected-area-sustainable-use-natural-
resources
Criterion 1: Critically Endangered / Endangered Species (The species included in the assessment consist of the strictly protected species
a. Areas that support globally important concentrations of an IUCN Red-listed EN or CR species (≥ 0.5% of the global population AND ≥ 5
reproductive unitsGN16 of a CR or EN species).
b. Areas that support globally important concentrations of an IUCN Red-listed Vulnerable (VU) species, the loss of which would result in the change
of the IUCN Red List status to EN or CR and meet the thresholds in GN72(a).
The project area crosses cultivated areas for most of its length. These cultivated areas have been developed over a couple of years of deforestation of
National Forest Priority Areas, e.g., Gebre Dima. It also crosses a small portion of the transition zone of the Yayu UNESCO Biosphere Reserve. Just shortly
before crossing the Baro River and shortly after that, a small part of the project area (about 700 m) crosses the transition Zone25 of the Sheka Forest
UNESCO Biosphere Reserve.
There are endemic plants and fauna in the project area. But they are all widely distributed in Ethiopia and across Africa. As a result, the project area cannot
be considered critical to their long-term persistence. Furthermore, the project crosses cultivated areas, which are already highly disturbed over years. On
the other hand, some plant species, e.g., Prunus africana, were assessed as vulnerable and the project adversely affect some individuals of these species.
There are no important Bird Areas and intact forests adversely affected by the project.
25
The Transition Zone of a Biosphere Reserve, Sheka Forest in this case, is area with human settlements and farming activities. In this study, tree species in the
Transition Zone are common across the study area and have no conservation concerns. These are scattered trees of Albizia gummifera, Pouteria adolfi-friderici
and etc.
Flora
Prunus africana The population It occurs in different parts of Ethiopia and several African • This is a widely distributed species
status of this countries; Ethiopia, Angola, Benin, Botswana, Burkina Faso, occurring throughout Ethiopia and in
species is Cameroon, Chad, Comoros, Cote d'Ivoire, Gambia, Ghana, Africa.
unspecified, VU Guinea, Guinea-Bissau, Kenya, Lesotho, Liberia, Madagascar,
Mali, Mauritania, Mozambique, Namibia, Niger, Nigeria, Sao • This species is not concentrated in the
Tome & Principe, Senegal, Sierra Leone, South Africa, project area
Tanzania, Togo, Uganda
• The geographic distribution of the specie
is of a large extent and thus, landscape is
unlikely to support >0.05% of the global
population
Afromomum Population status It is extensively distributed in the southwestern parts of • Widely distributed in Ethiopia and Eastern
corrorima unknown, LC Ethiopia: Keffa, Illubabor, Sidamo and Wollega floristic regions Africa.
of Ethiopia): Sudan, Uganda, Tanzania
• The species is not concentrated in the
project area
Albizia Population status It is widely distributed in Ethiopia, Nigeria, Kenya, Zimbabwe, • Widely distributed in Ethiopia and Africa.
gummifera unknown, LC Mozambique, Madagascar
• The species is not concentrated in the
project area
Albizia Population status is It is widely distributed in Ethiopia, DRC, Sudan, Zimbabwe, • Widely distributed in Ethiopia and Africa.
schimperiana stable, LC Mozambique
• The species is not concentrated in the
project area
Anthocleista Population status is It is widely distributed in Ethiopia, Nigeria, Tanzania, • Widely distributed in Ethiopia and Africa.
schweinfurthii stable, LC Zimbabwe, Angola
• The species is not concentrated in the
project area
Apodytes Population status It is widely distributed in Ethiopia, Sudan, Kenya, Tanzania, • Widely distributed in Ethiopia and Africa.
dimidiata decreasing, LC Uganda, Central Africa, Angola, South Africa and Australia
• The species is not concentrated in the
project area
Bersama Population status It is widely distributed in Ethiopia, Guinea Bissau, most of • Widely distributed in Ethiopia and Africa.
abyssinica stable, LC West Africa, Eritrea, Angola, Zambia, Zimbia, Zimbabwe,
Mozambique • The species is not concentrated in the
project area
Cordia africana Population status It is widely distributed in Ethiopia, Guinea, Eritrea, Kenya, • Widely distributed in Ethiopia and Africa.
stable, LC Angola, Zimbabwe, Mozambique, South Africa
• The species is not concentrated in the
project area
Croton Population status It is widely distributed in Ethiopia and throughout Africa • Widely distributed in Ethiopia and Eastern
macrostachyus stable, LC Africa.
Cyathea Population status It is widely distributed in southwestern Ethiopia, Malawi, • Widely distributed in Ethiopia and Africa.
manniana stable, LC Mozambique, Zimbabwe, DRC, Cameroun, Gunea Bissaou
• The species is not concentrated in the
project area
Dracaena Population status It is widely distributed in Ethiopia, Kenya, Uganda, Tanzania, • Widely distributed in Ethiopia and Africa.
afromontana stable, LC DRC, Rwanda, Burundi, Malawi
• The species is not concentrated in the
project area
Dracaena Population status Ethiopia, Kenya, Uganda, Burundi, Sudan, Malawi, DRC, • Widely distributed in Ethiopia and Africa.
steudneri stable, LC Zimbabwe, Mozambique, Rwanda
• The species is not concentrated in the
project area
Ehretia cymosa Population trend Ethiopia, Cameroun, Zimbabwe, Tanzania, Nigeris, Yemen, • Widely distributed in Ethiopia, Africa and
decreasing, LC Soudi Arabia, Madagascar, Comoros, Central African Republic Asia
Ensete Population status Ethiopia, Kenya, Uganda, Tanzania, Mozambique, South Africa, • Widely distributed in Ethiopia and Africa
ventricosum stable, LC DRC
• The species is not concentrated in the
project area
Ekebergia Population status Ethiopia, Eritrea, Botswana, South Africa, Senegal • Widely distributed in Ethiopia and Africa
capensis stable, LC
• The species is not concentrated in the
project area
Ficus Population status Ethiopia, Senegal, Djibouti, Mozambique, Angola, Yemen, • Widely distributed in Ethiopia, Africa and
exasperata stable, LC India, Sri Lanka Asia
Ficus sur Population status Ethiopia, widespread in tropical Africa, west to Senegal, Cape • Widely distributed in Ethiopia and Africa
stable, LC Verde Islands, South Africa
• The species is not concentrated in the
project area
Ficus thonningii Population status Widespread in Ethiopia and tropical Africa, West to Senegal, • Widely distributed in Ethiopia and Africa
stable, LC Zambia
• The species is not concentrated in the
project area
Ficus vasta Population status Widespread in Ethiopia, Kenya, Sudan, Somalia, Tanzania and • Widely distributed in Ethiopia, Africa and
stable, LC Yemen Yemen
Galiniera Population status Widespread in Ethiopia, Sudan, Kenya, Tanzania, Uganda, • Widely distributed in Ethiopia and Africa
saxifraga stable, LC Burundi, Rwanda, Zambia, DRC
• The species is not concentrated in the
project area
Hallea Population status Ethiopia, Tanzania, Rwanda, Malawi, Burundi, DRC, Uganda •
rubrostipulata stable, LC
Ilex mitis Population trend Ethiopia, Kenya, Eritrea, Sierra Leone, South Africa, Lesotho • Widely distributed in Ethiopia and Africa
decreasing, LC
• The species is not concentrated in the
project area
Macaranga Population status Ethiopia, Sudan, Zimbabwe, Mozambique, South Africa • Widely distributed in Ethiopia and Africa
capensis stable, LC
• The species is not concentrated in the
project area
Maesa Population stable, Ethiopia, Cameroun, DRC, South Africa, Mozambique, • Widely distributed in Ethiopia, Africa and
lanceolata LC tropical Africa, Arabia Asia
Ocotea Population status Ethiopia, Kenya, DRC, Rwanda, Uganda, Tanzania, Zimbabwe, • Widely distributed in Ethiopia and Africa
kenyensis unknown, VU Mozambique, South Africa
• The species is not concentrated in the
project area
Olea capensis L. Population status Ethiopia, Burundi, Cameroon, South Africa, Comoros, • Widely distributed in Ethiopia and Africa
ssp. macrocarpa stable, LC Guinea, Gulf of Guinea Is., Ivory Coast, Kenya, Liberia,
Madagascar, Malawi, Nigeria, Rwanda, Sierra Leone, Somalia, • The species is not concentrated in the
Sudan, Swaziland, Tanzania, Uganda, DRC project area
Piper capense Population status Ethiopia, Guinea, Angola, Mozambique, South Africa • Widely distributed in Ethiopia and Africa
stable, LC
• The species is not concentrated in the
project area
Polyscias fulva Population status Ethiopia and Kenya, Angola, Zimbabwe and Mozambique, • Widely distributed in Ethiopia and Africa
stable, LC Guinea
• The species is not concentrated in the
project area
Pouteria adolfi- Population status Ethiopia, DRC, Sudan, Zimbabwe • Widely distributed in Ethiopia and Africa
friederici stable, LC
• The species is not concentrated in the
project area
Syzygium Population status Ethiopia, Somalia, Senegal, Namibia, Botswana, South Africa • Widely distributed in Ethiopia and Africa
guineense stable, LC
• The species is not concentrated in the
project area
Trichilia Population status Ethiopia, Tanzania, Guinea, Cameroun, Côte d’Ivoire, • Widely distributed in Ethiopia and Africa
dregeana stable, LC Cameroon, in Congo, DRC, Angola, South Africa
• The species is not concentrated in the
project area
Birds
Silvery- Population trend Ethiopia, Kenya, Tanzania, Uganda, Malawi, Mozambique, • Widely distributed in Ethiopia and Eastern
cheeked decreasing, LC Zimbabwe and southeastern Africa
hornbill
• The species is not concentrated in the
project area
Crowned Population trend Ethiopia, Kenya, Tanzania, Uganda, Malawi, Mozambique, • Widely distributed in Ethiopia and Africa
hornbill decreasing, LC Zimbabwe, South Africa, Angola, Namibia, DRC
• The species is not concentrated in the
project area
African olive- Population trend Ethiopia, Kenya, Uganda, Tanzania, DRC, Mozambique, • Widely distributed in Ethiopia and Eastern
pigeon decreasing, LC Zimbabwe, South Africa, Botswana, Arabia and southeastern Africa and Arabia
African Dusky Population trend Ethiopia, Kenya, Tanzania, Uganda, DRC, Zambia, Zimbabwe, • Widely distributed in Ethiopia and Eastern
flycatcher decreasing, LC Mozambique, South Africa and southeastern Africa
Abyssinian Population trend Ethiopia, Eritrea • Widely distributed in Ethiopia and Eritrea
slaty flycatcher decreasing, LC
• The species is not concentrated in the
project area
Rouget’s rail Population trend Ethiopia and Eritrea • Widely distributed in Ethiopia and Eritrea
decreasing, NT
• The species is not concentrated in the
project area
Scaly francolin Population trend Ethiopia, Kenya, Tanzania, Uganda, Rwanda, Burundi, Malawi, • Widely distributed in Ethiopia and Eritrea
decreasing, LC DRC, Angola, Equatorial Guinea, Gabon Cameroun, Central
African Republic, Nigeria • The species is not concentrated in the
project area
Abyssinian Population trend Ethiopia, Eritrea, Kenya • Widely distributed in Ethiopia, Eritrea and
woodpecker decreasing, LC Kenya
Western Black- Population trend Ethiopia, Kenya, Uganda, Rwanda, Burundi, Somalia, DRC, • Widely distributed in Ethiopia and tropical
headed batis decreasing, LC Central African Republic, Gabon, Eritrea, Cameroun Africa
Willow warbler Population trend Widely distributed • Widely distributed in Ethiopia and East
decreasing, LC and central Africa
(source: https://ebird.org/species/wlwwar)
African hill Population trend Ethiopia, Kenya, Tanzania, DRC, Zambia, Mozambique, Angola • Widely distributed in Ethiopia and tropical
babbler decreasing, LC africa Abyssinian ground-thrush
Abyssinian Population trend Ethiopia, Kenya, Tanzania, Uganda, Rwanda, Burundi • Widely distributed in Ethiopia, East and
ground-thrush decreasing, LC Central Africa
Amphibians
Common reed Population trend Ethiopia, Kenya, Uganda, Tanzania, DRC, Burundi, Rwanda, • Widely distributed in Ethiopia and tropical
Frog unknown, LC Sudan, Central African Republic Africa
Speckle-lipped Population status Ethiopia, Sudan, Kenya, Uganda, Tanzania, Mozambique, • Widely distributed in Ethiopia and tropical
Mabuya stable, LC Malawi, DRC, Rwanda, Burundi, Gabon, Cameroon, Central Africa
African Republic, Ivory Coast, Guinea Conakry, Nogeria,
Ghana • The species is not concentrated in the
project area
Striped Skink Population status Ethiopia, Kenya, Tanzania, Malawi, Mozambique, Zambia, • Widely distributed in Ethiopia and tropical
unknown Angola, Namibia, DRC, Rwanda, Burundi Africa
Five-lined Population status Ethiopia, Sudan, Egypt, Kenya, Uganda, Chad, Nigeria, Mali, • Widely distributed in Ethiopia and tropical
Skink stable, LC Cameroon Africa
Whalberg’s Population stauts Ethiopia, Somalia, Kenya, Tanzania, DRC, Zambia, South • Widely distributed in Ethiopia and tropical
snake-eyed unknown, LC Africa Africa
skink
• The species is not concentrated in the
project area
Smooth Population status Ethiopia, Kenya, Tanzania, Uganda, Burundi, Rwanda, DRC, • Widely distributed in Ethiopia and tropical
Chameleon stable, LC Cantal African Republic, Cameroon, Sudan, Chad, Nigeria Africa
Time:………………………..