3. $$$: Additional Fixed Charge of Rs.
250 per 10 kW load or part thereof above 10 kW
load shall also be payable.
4. #: Street lighting having 'automatic timers' for switching 'on/off' would be levied
Demand Charges on the lower of the following:
a) 50% of the Contract Demand
b) Actual Recorded Demand
The detailed computation of category-wise revenue with revised tariffs for FY 2018-19 is
set out at Annexure I of this Order.
The approved Tariff Schedule for FY 2018-19 is given at Annexure III of this Order.
7.11 REVISED TARIFFS EFFECTIVE FROM 1 APRIL, 2019 (FY 2019-20)
Fixed/ Wheeling Regulatory
Energy
Consumer Category & Demand Charges Asset
Sl. Charge
Consumption Slab Charge per (Rs / Charge
(Rs/kWh)
month kWh) (Rs/kWh)
LT Category
1 LT I - Below Poverty Line Rs. 10 1.00 1.57 0.27
LT -I Residential
0-100 Rs. 65$$ 3.00 1.57 0.20
101-300 6.02 1.57 0.32
Rs. 105 $$
301-500 7.15 1.57 0.36
500 and above Rs. 130 $$ 8.90 1.57 0.46
2 LT II - LT Commercial
(A) ≤ 20 kW load Rs. 365 6.75 1.57 0.44
(B) > 20 kW and ≤ 50 kW load Rs. 305 per 6.85 1.57 0.45
(C) > 50 kW load kVA 7.15 1.57 0.47
3 LT III - LT Industry
(A) Upto 20 kW load Rs. 365 6.55 1.57 0.39
Rs. 305 per
(B) Above 20 kW 6.75 1.57 0.44
kVA
Rs. 305 per
4 LT IV – Public Water Works 5.45 1.57 0.41
kVA
LT V - Advertisement &
5 Rs. 585 6.65 1.57 0.51
Hoardings
Rs. 305 per
6 LT VI – Streetlights 5.65 1.57 0.41
kVA #
7 LT VII – Temporary Supply
TSR – Temporary Supply -
(A) Rs 305 5.25 1.57 0.36
Religious
TSO – Temporary Supply -
(B) Rs 585$$$ 7.90 1.57 0.51
Others
Case No. 200 of 2017 – Mid Term Review Order for RInfra-D Page 417 of 499
Fixed/ Wheeling Regulatory
Energy
Consumer Category & Demand Charges Asset
Sl. Charge
Consumption Slab Charge per (Rs / Charge
(Rs/kWh)
month kWh) (Rs/kWh)
LT VIII – Crematoriums and
8 Rs 305 4.90 1.57 0.28
Burial Grounds
9 LT IX – Public Services
Government Hospitals &
(A) Rs 365 6.00 1.57 0.34
Educational Institutions
(B) Others Rs 365 6.40 1.57 0.39
10 LT X - Agriculture
Rs 40 per
(A) Pumpsets 3.40 1.57 0.08
HP
Rs. 95 per
(B) Others 4.80 1.57 0.33
kW
LT XI: Electric Vehicle
Rs. 70 per
11 Charging Stations (New 3.48 1.57 0.45
kVA
Category)
TOD Tariffs (in addition to
above base tariffs) –
compulsory for LT II (B) and
(C), LT III (B), LT IV, LT IX
(A) and (B), and LT X
categories, and optional for LT
II (A) and LT III (A) categories
0600 hours to 0900 hours 0.00
0900 hours to 1200 hours 0.50
1200 hours to 1800 hours 0.00
1800 hours to 2200 hours 1.00
2200 hours to 0600 hours -0.75
110/132 kV Category
Rs. 305 per
1 HT V (A) - HT Metro & Monorail 6.70 - 0.79
kVA
33 kV Category
Rs. 305 per
2 HT V (B) - HT Metro & Monorail 6.70 0.72 0.79
kVA
11 kV Category
Rs. 305 per
3 HT I: HT-Industry 7.75 0.72 0.81
kVA
Rs. 305 per
4 HT II: HT- Commercial 7.95 0.72 0.76
kVA
HT III: HT-Group Housing Rs. 305 per
5 7.30 0.72 0.86
Society kVA
Rs. 305 per
6 HT IV: HT -Public Water Works 6.60 0.72 0.80
kVA
HT VI (a):PS - Govt. EI & Rs. 305 per
7 6.80 0.72 0.82
Hospitals kVA
Case No. 200 of 2017 – Mid Term Review Order for RInfra-D Page 418 of 499
Fixed/ Wheeling Regulatory
Energy
Consumer Category & Demand Charges Asset
Sl. Charge
Consumption Slab Charge per (Rs / Charge
(Rs/kWh)
month kWh) (Rs/kWh)
Rs. 305 per
8 HT VI (b):PS - Others 7.65 0.72 0.82
kVA
Rs. 585 per
9 HT VII: Temporary Supply 8.45 0.72 0.89
connection
HV VIII: Electric Vehicle Rs. 70 per
10 4.02 0.72 0.76
Charging Stations kVA
TOD Tariffs (in addition to
above base tariffs) for HT I, HT
II, HT IV, HT VI (A) and (B),
and HT VIII categories
0600 hours to 0900 hours 0.00
0900 hours to 1200 hours 0.50
1200 hours to 1800 hours 0.00
1800 hours to 2200 hours 1.00
2200 hours to 0600 hours -0.75
Notes:
1. Fuel Adjustment Cost will be applicable to all consumers and will be charged over the
above tariffs, on the basis of the FAC formula specified by the Commission, and
computed on a monthly basis.
2. $$: Fixed Charge of Rs. 130 per month will be levied on residential consumers availing
3 phase supply. Additional Fixed Charge of Rs. 130 per 10 kW load or part thereof
above 10 kW load shall be payable.
3. $$$: Additional Fixed Charge of Rs. 280 per 10 kW load or part thereof above 10 kW
load shall also be payable.
4. #: Street lighting having 'automatic timers' for switching 'on/off' would be levied
Demand Charges on the lower of the following:
a) 50% of the Contract Demand
b) Actual Recorded Demand
The detailed computation of category-wise revenue with revised tariffs for FY 2019-20 is
set out at Annexure II of this Order.
The approved Tariff Schedule for FY 2018-19 is given at Annexure IV of this Order.
Case No. 200 of 2017 – Mid Term Review Order for RInfra-D Page 419 of 499