Project:                            Renovation of Swimming Pool – LIV32
PRE-INSPECTION CHECK LIST
Description:
          Key Pre-Requisites Before Filling the Pool                           Date:
 Item #                  Activity / ACCEPTANCE CRITERIA                            Yes      No   N/A   Remarks
           Concrete Curing: Ensure that the pool shell has completed its
    1
           curing period
           Surface Inspection: Check for cracks, holes, or imperfections in
    2
           the pool structure that may cause leaks.
           Waterproofing Inspection: Verify that the waterproofing
    3
           membrane or coating has been properly applied and is intact.
    4      Pressure Testing: Conduct a pressure test on all plumbing lines
           Pipe Integrity: Ensure that all pipes, joints, and valves are
    5
           properly sealed and functional.
           Pump and Filtration System: Ensure that the pump, filter, and
    6
           circulation system are installed and operational.
           Drain Covers & Safety Features: Verify that drain covers,
    7      skimmers, and safety grates comply with safety regulations and
           are securely fixed.
           Lighting System: Test all underwater and surrounding lights to
    8
           confirm proper installation and insulation.
           Expansion Joint Sealing: Ensure that all expansion joints are
    9
           sealed properly to prevent water leakage.
           Tile and Grouting Inspection: Check for missing or damaged
   10
           tiles and grout to avoid water seepage.
           Grounding and Bonding: Verify that all electrical installations
   11      (lights, pumps, etc.) are properly grounded and bonded
           according to safety standards.
           Control Panel Functionality: Ensure that the control panel and
   12
           automation systems (if any) are working correctly.
           Safety Barriers & Fencing: Confirm that safety barriers, fencing,
   13
           and handrails are installed per local regulations.
           Debris Removal: Remove any construction debris, dust, and
   14
           loose particles from the pool structure.
           Surface Cleaning: Ensure that the pool surface is clean to
   15
           prevent contamination during water filling.
   Checked By:        Name:                                                    Signature: