Final Corrected
Final Corrected
Ahmedabad
                                Submitted for
                          T.Engg. Civil part II (ICE)
_____________________________________________________________
                                                                                57
                              ACKNOWLEDGEMENT
I would like to thank the Institution of Civil Engineers (I.C.E) for giving me an opportunity to
work on a project and gain knowledge of civil engineering and a chance to encounter real life
site issues by adding site project case study in our curriculum. I would like to pay my gratitude to
N.G.Raval Sir for giving me an opportunity to work and guide me for learning the principles of
civil engineering and how to deal with real life situations. He also shared an immense knowledge
with me on issues related to civil engineering. It helped me to bring out the task in proper shape.
And at the last but not the least, I am also very thankful to my parents and friends who have
given me moral support and encouragement.
                                                                                                       57
                                     LIST OF FIGURES
LIST OF TABLES
   1                                                                        42
          Shuttering Material required for bed room
                                                                                    57
                                           INDEX
List of figures 3
List of tables 3
CHAPTER 1: INTRODUCTION
1.1 Introduction 7
2.2 Work procedure for Reinforced & Plain Cement Concrete Works 15
CHAPTER 3: PRODUCTIVITY
3.3 Foundation 46
                                                                                     57
3.4 Concreting                                     49
3.5 Reinforcement 50
3.8 RMC 54
4.1 Conclusion 57
References 59
                                                        57
 CHAPTER 1
INTRODUCTION
CHAPTER 1
               57
1.1 Introduction
Home buyers face challenges while deciding “when” to purchase houses. While favorable
economic conditions lead to higher incomes for home buyers, it also leads to spiraling real estate
prices making it difficult for a buyer to purchase homes even given their higher incomes. On the
other hand, during economic downturns while real estate prices decline, people become skeptical
about their incomes and adopt a more cautious approach to purchases.
Affordable housing may be a good strategy to this home-buyers dilemma and can help ensure
housing across different sections of society. Affordable housing can be defined using three key
parameters viz.
   •    income level,
   •    size of dwelling unit
   •    Affordability
“Affordability” as a concept is very generic and could have different meanings for different
people based on differences in income levels.
Affordable housing refers to any housing that meets some form of affordability
1 Criterion .
Different countries have defined affordable housing to present the economic potential of an
individual buying a house. In the United States and Canada, a commonly accepted guideline for
affordable housing is that the cost of housing should not be more than 30 percent of a
household's gross income. Housing costs here include taxes and insurance for owners, and utility
costs. If the monthly carrying costs of a home exceed 30–35 percent of household income, the
housing is considered
                                                                                                       57
broadly defined affordable housing in India for Tier I, II and III cities based on three key
parameters:
Defining Affordable Housing
        Type                  Income level         Size of dwelling unit         Affordability
        EWS                <INR 1.5 lacs per           Upto 300 sq.ft.          EMI to monthly
                                 annum                                              income
         LIG               INR 1.5-3 lacs per          300-600 sq.ft.            30-40 percent
                                 annum                                     House price to Annual
        MIG                INR 3-10 lacs per           600-1200 sq.ft.           income ratio
                                 annum                                           Less than 5.1
Affordable and low-cost housing are often interchangeably used, but are quite different from
each other. Low-cost housing is generally meant for EWS category and comprises bare minimum
housing facilities while affordable housing is mostly meant for LIG and MIG and includes basic
amenities like schools, hospitals and other community facilities and services
   •   As per 2011 census, the country had a population of 1,210.98 million, out of which,
       377.10 million (31.16%) lived in urban areas.
   •   During 2001-2011, the urban population of India grew at a CAGR of 2.8%, resulting in
       the increase in level of urbanization from 27.81% to 31.16%.
   •   This growing concentration of people in urban areas has led to problems of land shortage,
       housing shortfall and congested transit and has also severely stressed the existing basic
       amenities such as water, power and open spaces of the towns and cities.
   •   According to the 2011 census, the housing stock in urban India stood at 78.48 million for
       78.86 million urban households.
                                                                                                   57
   •     Urbanisation has resulted in people increasingly living in slums and squatter settlements
         and has deteriorated the housing conditions of the economically weaker sections of the
         society.
   •     According to estimates of the Technical Group constituted by the Ministry of Housing
         and Urban Poverty Alleviation (MHUPA), the urban housing shortage in the country at
         the end of the 10th Five-Year Plan was estimated to be 24.71 million for 66.30 million
         households.
   •     The group further estimated that 88% of this shortage pertains to houses for
         Economically Weaker Sections (EWS) and another 11% for Lower-Income Groups
         (LIG).For Middle- and High-Income Groups (MIG and HIG), the estimated shortage is
         only 0.04 million
Name of the Project : New Heaven, Arvind and Smart Value Homes
                                   1. Swastik Arcade
                                   2. B.G. Mistry
                                   3. Balar Buildcone
                                   4. Priyanka construction
                                                                                                     57
Date of Completion         : JAN 2015
ARCHITECT : 99 studio
STAFF STRENGTH : 29
                                                                      57
Conventional method is not used. RCB( Reinforced Concrete Blocks) technology is used and its
load bearing structure with raft foundation
REVIEW MEETING                : Once in a week with main contractor, Internal staff meeting twice
                              a week
Connectivity Of Site          :
The site is well connected with access to highway. State transport (GSRTC) and city buses has
regular bus services to vadsar. The site is located adjacent to the ahmedabad which is the main
advantage because material and man power is easily available.
The nearest International airport is Ahmedabad with frequent domestic and international
flights.
                                                                                                    57
57
    CHAPTER 2
METHOD STATEMENTS
                    57
                                       CHAPTER 2
                           METHOD STATEMENTS
 Objective
    This Procedure is based on the requirements of the Approved Drawings and Technical
    Specification
    IS 1200 - Method of Measurement of building and civil engineering works. (Part – 1 Earth
    Work, Part – 27 Earthwork done by mechanical appliances)
      Resource Deployment
    The Contractor shall deploy any or all of the following resources as dictated by the volume
    and nature of excavation.
                                                                                                        57
      Procedure
     Prior to commencement of any excavation, an excavation plan shall be developed based
       on the drawing and carry out the survey of the site before excavation and set properly
       lines and establish levels at an intervals of 10 mtr for earth work. The excavation outline
       shall be chalk-marked on ground.
     Slopes and berms as required for each type of soil shall be provided to ensure safety
       against collapse. Where necessary, protective shoring shall be adopted to prevent side
       collapse.
     In case of any slip occurring, the debris shall be cleared forthwith and specific protection
       shall be arranged to prevent recurrence.
     Barricading and providing safety warning tape around the excavation area shall be done
       to warn unsuspecting passers.
     Mode of excavation (manual or mechanical) shall be decided considering site condition,
       feasibility and quantity of work involved and exigency of the job.
     Excavated earth shall be deposited in stacks at locations indicated by the Engineer-in-
       charge.
      Disposal
    All surplus materials shall be carried away from the site and disposed at a dumping site
    selected by the Engineer in charge.
      Safety precautions:
     Area should be barricaded so no one can enter the on going excavated area.
 There should be person restricting other people to enter the swing area of the poclain.
 All the workers working in the excavation pit should be with the PPES.
                                                                                                     57
2.2 Work procedure for Reinforced & Plain Cement Concrete Works
      Objective
 Reference
       This Procedure is based on the requirements of the Client / Owner’s Drawings Civil /
       Structural works and technical specification.
 Resource Deployment
       The Contractor shall deploy any or all of the following resources as dictated by the
       volume and nature of concrete work.
                                                                                                     57
     Measuring Jar.
     Bucket (Calibrated)
c) Material
     Cement to be used shall be as specified.
     Coarse aggregate & Fine aggregate shall be as per IS 383 : 1972
     Water should be as per IS 456: 2000.
     Admixture (Plasticizer) as required as per IS - 9103.
     All materials to be used for construction shall be subject to acceptance by the
       Engineer in charge.
d) Manpower
    Adequate skilled, semi-skilled and unskilled manpower shall be arranged for every
    activity described hereafter.
   Procedure
1. Pre-pour Activities
     Level, layout, formwork and formwork support system of the pouring area shall be
       checked with respect to relevant construction drawings before starting RCC.
     Reinforcement bar size and placement shall be checked with respect to relevant
       construction drawings and bar bending schedules duly approved by engineer. Where
       applicable, provision of chairs shall be checked for adequacy.
     Location, size details, level etc. of all embedment parts shall be checked.
     Any accumulated water shall be drained out / pumped out.
     Any accumulated dust, wooden pieces, other foreign materials etc within the
       formwork shall be removed by compressor/ manually as per requirement.
     All cover blocks having proper thickness shall be placed in proper location as per
       drawing.
     Cover block shall be made of same grade of concrete in which it is to be embedded.
     Tarpaulins shall be kept in readiness if there is possibility of rain.
     Proper lighting arrangement shall be made from unloading area to the placing area if
       the pouring continues through night.
     The aforesaid checks shall be jointly made with the Owner’s Engineer and pour
       clearance shall be obtained on Pre-pour Card Inspection format.
                                                                                             57
2. Production and Delivery of Concrete using Batching Plant
    Batching Plant(s) shall be pre-qualified in order to ascertain its rated capacity,
      accuracy of weighing, consistency of product etc. prior to commencement of first
      concreting. Thereafter, plant calibration shall be checked every three months.
    Batch correction for moisture content in aggregate shall be carried out daily.
    Grading of aggregates used by the plant shall be checked daily for conformity with
      design mix grading range.
    Suitable design mix shall be developed and approved by the Owner well in advance
      for each grade of concrete and for each variation of cement and admixture. Separate
      design mix shall be developed for pumpable and non-pumpable concrete of a given
      grade, depending on mode of placement.
    Only concrete of approved design mix shall be issued from the Batching Plant for
      works at site.
    Concrete from Batching Plant shall be transported by transit mixer only.
    Rate of production of Batching Plant and number of transit mixers required should be
      decided based on rate of concrete placement.
    Concrete shall be unloaded from the transit mixer on a leveled plat form / concrete
      Pump / Bucket as per the requirement and availability.
    Concrete shall be conveyed to the actual pouring area by manual mode / through
      concrete Pump / Bucket as per the requirement & availability.
    Suitable chute shall be used, wherever required, to convey the concrete by gravity, in
      order to avoid segregation of the mix.
                                                                                              57
    Concrete from the mixture shall be discharged on a platform.
    Concrete shall be transported manually to the actual pouring point.
4. Laying of Concrete
    Concrete shall be placed in its final position within 90 minutes of its production or
       well before initial setting time, so as to leave sufficient time for proper compaction.
    Concrete shall be placed in layers having a thickness of maximum of 300 mm.
       Generally the pour height of columns and wall shall be restricted to 2.4 m. With
       special formwork and support arrangement to prevent segregation and keeping access
       for vibration, casting of columns and walls for greater heights (even full height) can
       also be planned.
    Before laying any subsequent layer of concrete, the previous layer shall be fully
       compacted and there shall not be any initial setting in the previous layer.
    Bedding planes shall be kept horizontal & care shall be taken so that cold joints are
       not formed.
       When manual pour of PCC is contemplated, any visible segregation of concrete
       unloaded from transit mixer on to the receiving platform, shall be remixed manually
       by spade & shovel before placement by head load.
    Concrete shall be well-compacted using immersion vibrator.
    Concrete shall be leveled & finished in proper level as per the requirement of the
       drawing.
    Slumps shall be checked & cubes shall be taken as per Quality Assurance Plan.
    Concrete shall be cured for at least 10 days by water spraying / ponding. Jute cloth
       shall be provided over the vertical surface to facilitate for keeping the surface wet.
    In case of pre-cast concrete, the pre-cast block shall be removed as per the
       instructions given in the drawing.
                                                                                                 57
   pockets of coarse aggregate or of entrapped air and the concrete fits tightly against all
   form surfaces and embedded materials.
                                                                                                57
    The vibrator shall penetrate full in the layer being placed and also penetrate the layer
      below by about 50 mm while it is still plastic, to ensure good bond and homogeneity
      between the two layers and prevent the formation of cold joints.
    Care shall be taken to prevent contact of vibrators against reinforcement steel.
      Vibrators shall not be brought in contact with reinforcement steel after start of initial
      set. Vibrators shall not be allowed to come in contact with forms or finished surfaces
      and embedments.
    Form-attached vibrators shall be used wherever feasible.
    The use of surface vibrators shall not be permitted for compaction of concrete under
      ordinary conditions. However, for thin slabs, surface vibration by specially designed
      vibrators may be permitted upon approval of the Owner’s Engineer.
    The formation of stone pockets or mortar pondage in corners and against face of
      forms shall not be permitted. Should these occur, they should be dug out, reformed
      and refilled to sufficient depth and shape for thorough bonding.
6. Construction Joints and Keys
    When concrete placement is to be interrupted, horizontal and vertical construction
      joints and bonding keys shall be located and shall conform in detail to the
      requirements of the plans. In case of water retaining structures, containment
      structures and other structures water stops of approved material shall be provided as
      mentioned in the drawing. Construction joints shall be provided in positions as shown
      or described in the drawings.
    In a column, the joint shall be formed below the lowest soffit of the beams framing in
      to it, joint location being determined by the relevant drawings. Concrete in a beam
      shall be placed throughout, without a joint but if the provision of a joint is
      unavoidable, joint location shall be determined by the relevant drawings. Before
      fresh concrete is placed, the cement skin or any loose or porous material of partially
      hardened concrete shall be thoroughly removed and cut back until the solid face is
      exposed and surface made rough by hacking using manual chisel / pneumatic tool.
      The rough surface shall be thoroughly wetted for about two hours and shall be dried
      and coated with 1:1 freshly mixed cement sand slurry, immediately before placing the
                                                                                                  57
           new concrete. Special care shall be taken to see that the first layer of concrete is
           placed after a construction joint is thoroughly rammed against the existing layer.
 Objective
      Resource Deployment
       The Contractor shall deploy any or all of the following resources as dictated by the
volume and nature of work.
 Iron Pans.
 Spade.
 Trowel.
 Measuring Tape.
 Line Thread.
                                                                                                     57
       Procedure Details
    Prior to commencement of the work the surface shall be clean from dust, oil and loose
    particles.
     The height of masonry units shall not exceed either its length or 1 m with adjacent or
        diagonally.
     Concrete blocks shall be sound, free of cracks, chipping or other defects which impair the
        strength or performance of the construction.
     For preparing mortar, the ingredients shall first be mixed thoroughly in dry condition.
        Water shall then be added and mixing continued to give a uniform mix of required
        consistency. The mortar thus mixed shall be used as soon as possible preferably with in
        30 minutes from the time water is added to cement.
     Any mortar partially set shall be rejected and shall be removed forthwith from the site.
        Droppings of mortar shall not be re-used.
     The thickness of cement mortar shall not be less than 10 mm and not more than 12 mm in
        both the vertical & horizontal joints.
     The first layer shall be laid carefully, ensuring that it is properly aligned, leveled and
        plumb since this will facilitate in laying succeeding courses to obtain a straight and truly
        vertical wall.
     For horizontal / bedding joint, mortar shall be spread over the entire top surface except
        hollow part of the block including front and rear shells as well as the webs to a uniform
        thickness of 10 mm.
     For vertical joints, the mortar shall be applied on the vertical edges of the front and rear
        shells of the block.
     The mortar may be applied either to the unit already placed on the wall or an edge of the
        succeeding unit when it is standing vertically and then placing it horizontally, well
        pressed against the previously laid unit to produce a compacted vertical joint.
     The mortar shall be racked to a depth of 10 mm as each course as laid to ensure good
        bond for the plaster.
                                                                                                       57
       The blocks should be wetted before laying in walls. Blocks should be laid dry except
        slightly moistening their surface on which mortar is to be applied to avoid absorption of
        water from the mortar.
     As per design requirements and to effectively control cracks in the masonry, RCC bond
        beams / studs, joint reinforcement shall be provided at locations as per details indicated in
        the construction drawings.
     At every 1.2 m a vertical 16mm# bar is provide and at every 2 layer 18 gauge G.I wire is
        laid horizontally.
Mode of measurement
Safety Measures
     Proper precautions should be taken during masonry work i.e. workmen should wear PPE
     like safety belt, safety shoe, helmet, goggles while working on scaffolding at high altitude.
 Objective
 Resource Deployment
    The Contractor shall deploy any or all of the following resources as dictated by the type of
    formwork.
                                                                                                        57
   Tools & tackles
          Carpenter’s Kit
          Masking tape / putty
   Plant & Machineries
          Tractor / Trailer
          Builder’s hoist
   Material
          Timber, Plywood, Steel, Plastic or Concrete formwork depending upon the type
    of finish specified in shapes and sizes as required.
          Sliding forms & Slip form shall be used with the approval of Engineer.
          Fabricated steel formwork in shapes and sizes as required
          Scaffolding pipes with clamps
          H-frame
          MS pipe with adjustable props
          MS section soldiers / runners
          Hardwood battens
          Steel trestles
          Stirrups, turnbuckles.
   Consumables
          Wire nails
          Form Oil except for surfaces to be painted later.
 Manpower
    Adequate skilled, semi-skilled and unskilled manpower shall be arranged for every
    activity described hereafter.
 Procedure
    The form work shall consist of but not limited to shores, bracings, sides of beams,
    columns, walls, rafts and bottom of slabs including ties, anchors, inserts, hangers, false
                                                                                                 57
    work, wedges etc. complete, which shall be properly planned for the work. For the
    floors, supports can be taken from the floors down below with prior permission of the
    Owner’s Engineer. Wherever required provision shall be made to support the floor
    shuttering by means of trusses, which shall be spanned from the near by walls/ columns.
   Formwork
     Formwork shall be designed to fulfill the following requirements:
     a)    Sufficiently rigid and tight to prevent loss of grout or mortar from the concrete at
     all stages and appropriate to the methods of placing and compacting.
     b)    Made of suitable materials.
     c)    Capable of providing concrete of the correct shape and surface finish within the
     specified tolerance limits.
     d)    Capable of withstanding without deflection the worst combination of self-weight,
     reinforcement and wet concrete weight, all loads and dynamic effects arising from
     construction and compacting activities, wind and weather forces.
     e)    Capable of easily striking without shock, disturbance or damage to the concrete.
     f)    Soffit forms capable of imparting a camber if required.
     g)    Soffit forms and supports capable of being left in position if required.
     h)    Capable of being cleaned and or coated if necessary immediately prior to casting
     the concrete; design temporary openings where necessary for these purposes and to
     facilitate the preparation of construction joints.
     i)    All horizontal forms shall be constructed for pressures from the dead load of the
     concrete and embedments and a minimum live load of 200 kg/m 2. For any additional
     loads, the formwork shall be suitably designed.
   Support Structure
     The following loading shall be considered for design of the supporting structure.
      Dead Load
     Concrete load                                            --   2500 kg/cum. (set concrete)
     Self weight                                         --        as per design.
                                                                                                  57
     Top formwork                                       --      as per design
     Reinforcement in Un-concreted area                 --      200 Kg/sqm on plan area
       Live Load
 Centering of Formwork
    Centering using steel, H frames, built-up sections, with provisions to adjust the heights of
    the props shall be used and they shall be to true levels and rigid. They shall be adequately
    braced horizontally and vertically. For shuttering supported on floors below, vertical
    props shall be so supported on wedges or other measures shall be taken whereby the
    props can be gently lowered vertically while striking the shuttering. Bamboos and
    wooden poles shall not be used as props or cross bearers.
 Tie Rods
    As far as possible MS / Reinforcement tie rods left in type shall be used for supporting all
    forms. Retrievable type can also be used with the prior approval of the Engineer. Tie
    rods shall have provision for removal of a section of each rod at surface of the concrete to
    a depth of approximately 50mm. All holes left by the removal of conical nuts / PVC
    Conduit or other removable fixtures embedded in the face of the concrete shall be filled
    and finished with cement-sand mortar in a manner specified in the finishing specification.
    Threaded inserts embedded on each face of the wall shall be cut for attaching the forms to
    previously placed concrete.
                                                                                                   57
      Through Tie rods shall be permitted only upon approval of the Engineer and when
      permitted shall be cut off flush with the face of the concrete, or the countersunk, filled
      and finished, as required by the Engineer, in the manner specified under the finishing
      specification. Measures shall be taken to prevent rust stains on concrete.
 Form Oil
      Only non-staining mineral oil or other approved oil shall be applied before placing
      reinforcing steel and embedded parts. Form oil shall not be used on the surfaces requiring
      painting. Form oil shall be insoluble in water and not injurious to concrete and shall not
      become flaky or be removed by rain or wash water. Form oils that retard the setting of
      concrete shall not be used.
      All excess oil on the form surface and any oil on metal or other parts to be embedded in
      the concrete shall be carefully removed. Before treatment with oil, forms shall be
      thoroughly cleaned of dried splatter of concrete from placement of previous lift.
 Joints
      Joints in forms shall be truly horizontal or vertical unless otherwise specified and shall be
      sufficiently tight to prevent any leakage of cement slurry to avoid formation of fine or
      blemish. Faulty joints shall be sealed as directed by the Engineer. Suitable devices shall
      be used to hold adjacent edges together in accurate alignment. Sealing tapes / cotton
      waste packing shall be used to avoid leakage of slurry through the formwork joints. On
                                                                                                      57
      the removal of forms, marks left by sealing tapes / cotton waste shall be finished so as to
      merge with other concrete surface. Care shall be taken to maintain symmetry in
      formwork in slabs, walls, columns etc. so as to give a pleasant appearance to finish
      concrete surface. All forms shall be so made that they can be removed without
      hammering or prying against the concrete.
 Reuse of Forms
      Before reuse, all forms shall be thoroughly scrapped, cleaned, examined and when
      necessary, repaired and re-oiled before resetting. Formwork shall not be used / reused, if
      declared unfit or unserviceable by the Engineer.
   Working Platform
      Safe working platform shall be provided for workmen, when working above ground
      level. Safe method of approach shall be provided to reach locations above ground level.
      Hanging platforms shall have safety net provisions. All ladders shall have handrails and
      shall not be kept vertical. All platforms, ladders handrails etc. shall be firmly secured to
      ground or on supports. No loosely supported ladders, platforms shall be used in the
      works.
 Removal of Forms
      In the determination of time for removal of forms, consideration shall be given to the
      location and character of the structure, the weather and other conditions including the
      setting and curing of the concrete and materials used in the mix.
      Forms and their supports shall not be removed without the approval of the Engineer.
      Improper methods of removal of formwork likely to cause overstressing or damage to the
      concrete shall not be used. Supports shall be removed in such a manner as to permit the
      concrete to uniformly and gradually take the stresses due to its own weight.
                                                                                                     57
The minimum period for removal of forms shall be as mentioned in the table given
hereafter. However, seven day test results shall be as per IS: 456 (latest revision). If the
strength requirements are not met with, the formwork shall be removed as per the
instruction of the Engineer.
Striking shall be done slowly with utmost care to avoid any damage to concrete surfaces
or any projections on it and without shock or vibrations, by gently easing the wedge. If
after removing the formwork, it is found that timber has been embedded in the concrete,
it shall be removed and made good as approved.
                                                                                               57
         Tie rods, clamps form bolts etc., which must be entirely removed from the walls or
         similar structure shall be loosened not sooner than 24 hours after the concrete was
         deposited.
 Safety Procedures:
         All the workers should wear the PPES.Proper handling of the materials while working on
         height.
         While deshuttering there sould be a person guiding all the persons not to pass through
         that area with the proper barrication of that area.
 Objective
     Resource Deployment
      The Contractor shall deploy any or all of the following resources as dictated by the volume
      and nature of work.
 Iron Pans.
 Spade.
 Trowel.
 Measuring Tape.
                                                                                                       57
        Line Thread.
 Procedure
         The masonry surface is rendered first and washed with clean water to remove all
           dirt, loose materials etc. Concrete surface is being hacked for proper adhesion of
           plaster and the surface shall be evenly wetted to provide the correct suction. The
           masonry surfaces should not be too wet but only damp at the time of plastering. The
           dampness shall be uniform to get uniform bond between the plaster and the
           masonry surface.
         The proportion of cement mortar for interior plain faced surface shall be 1:4 (one
           part of cement to four parts of sand).The average thickness of plaster is 13mm.
         The proportion of cement mortar for soffit of concrete slab shall be 1:3 (one part of
                cement to three parts of sand). The average thickness of plaster is 6mm.
 Cement and sand shall be mixed thoroughly with water (in the mixer machine or on
         The mortar shall be dashed against the prepared surface with a trowel. The dashing
          of the coat shall be done using a strong whipping motion at right angles to the face
          of the wall. The coat shall be trowelled hard and tight forcing it to surface
          depressions to obtain a permanent bond and finished to smooth surface. Interior
          plaster shall be carried out on jambs, lintel and sill faces etc. as shown in the
          drawing.
                                                                                                  57
           Mortar once prepared, should not be used after 30 minutes.
 Steel wire fabric will be used at the junction of brick masonry and concrete.
          Now the finishing is made with the help of trowel, line thread, level ruler and plumb
           bob to maintain proper line, level and thickness as per drawing and technical
           specification.
          Curing of plaster shall be started as soon as the applied plaster has hardened
           sufficiently so as not to be damaged when watered. Curing shall be done by
           continuously applying water in a fine spray and shall be carried out for atleast 7
           days.
 Mode of measurement
    Mode of measurement shall be in square meter. A joint protocol shall be maintained by the
    engineer concerned at execution.
 Safety Measures
    Proper precautions should be taken during plastering work i.e. workmen should wear PPE
    like safety belt, safety shoe, helmet, while working on scaffolding at high altitude.
 Objective
                                                                                                     57
   SCOPE
    This procedure is applicable for cement plastering work as per approved drawings, technical
         specification and is-1661,is-2402 and is-1542
   RESOURCE DEPLOYMENT
    The Contractor shall deploy any or all of the following resources as dictated by the volume
    and nature of work.
 Iron Pans.
 Spade.
 Trowel.
 Measuring Tape.
 Line Thread.
 Procedure
          The masonry surface is rendered first and washed with clean water to remove all dirt,
           loose materials etc. Concrete surface is being hacked for proper adhesion of plaster
           and the surface shall be evenly wetted to provide the correct suction. The masonry
                                                                                                   57
    surfaces should not be too wet but only damp at the time of plastering. The dampness
    shall be uniform to get uniform bond between the plaster and the masonry surface.
   The plaster shall be applied in 2 coats.The first coat shall be 14 mm thick with the
    mix proportion of 1:4 and the second coat shall be 6 mm thick with the mix
    proportion of 1:3 with addition of approved water curing compound.These coats shall
    be applied as stipulated in clause .However,only approved white quality sand shall be
    used for second coat and for the finishing work.Sand sor the finishing work shall be
    coarse and of even size and shall be dashed against the surface and sponged.The
    mortar proportion for the first and second coats shall be as specified in the respective
    items of work.
   Wherever more than 20mm thick plaster has been specified, which is intended for the
    purpose of providing beading ,bands,etc.this work shall be carried out in two or three
    coats as directed by the ENGINEERS duly satisfying the requirement of curing each
    coat (rendering/floating)for a minimum period of 2 days and curing the finished work
    for atleast 7 days.
   Cement and sand shall be mixed thoroughly with water (in the mixer machine or on
    the nonabsorbent platform as per engineer’s instruction) in the required ratio
    mentioned above until the uniform mix of required consistency is achieved.
    The mortar shall be dashed against the prepared surface with a trowel. The dashing
     of the coat shall be done using a strong whipping motion at right angles to the face
     of the wall. The coat shall be trowelled hard and tight forcing it to surface
     depressions to obtain a permanent bond and finished to smooth surface. Interior
     plaster shall be carried out on jambs, lintel and sill faces etc. as shown in the
     drawing.
 Steel wire fabric will be used at the junction of brick masonry and concrete.
                                                                                               57
          Now the finishing is made with the help of trowel, line thread, level ruler and plumb
           bob to maintain proper line, level and thickness as per drawing and technical
           specification.
          Curing of plaster shall be started as soon as the applied plaster has hardened
           sufficiently so as not to be damaged when watered. Curing shall be done by
           continuously applying water in a fine spray and shall be carried out for atleast 7
           days.
 Mode of measurement
    Mode of measurement shall be in square meter. A joint protocol shall be maintained by the
    engineer concerned at execution.
 Safety Measures
    Proper precautions should be taken during plastering work i.e. workmen should wear PPE
    like safety belt, safety shoe, helmet, while working on scaffolding at high altitude.
                                                                                                   57
 CHAPTER 3
PRODUCTIVITY
               57
                                           CHAPTER 3
The productivity of workers is worked out based on the actual output at the site.
       Masonry work of building 5 (S.G.MISTRY) on 1st floor was going on and person
         available were:
         -   2 masons
         -   2 helpers
         -   1 person for cutting blocks
         -   1 helper to cutter person
         -   Shifting of blocks were done through crane
         -   1 person to keep blocks from crane
         -   Masonry work of 292 blocks were done in 1 day
         -   So total work done = (292*0.390*0.190 )*0.2
                                 = 4.32 cu.m
         -   This work was done by 2 pair, so total work done by 1 pair ( 1mason+2 helper) in 1
             day
                   = 4.32/2 = 2.16cu.m
                                                                                                  57
 Similarly total work done in building 19 of BALAR BUILDCON by 2 pair was 248
   blocks = (248*0.390*0.190)*0.2 = 3.67 cu.m
 So work done by 1 pair = 1.83 cu.m
 Similarly total work done in building 35 of PRIYANKA CONSTRUCTION by 5 pair
   was 350 blocks = (350*0.390*0.190)*0.2 = 5.187cu.m
 So work done by 1 pair = 1.0374 cu.m
 Similarly total work done in building 31 of PRIYANKA CONSTRUCTION by 3 pair
   was 325 blocks = (325*0.390*0.190)*0.2 = 4.8164 cu.m
 So work done by 1 pair = 1.6054 cu.m
 The variation in output per pair was observed due to skill of labour, use to with this
   technology and level of working i.e ground floor, 1st floor etc..
 The thumb rule for masonry work is that 1 pair should do the 2.5cu.m for main wall and 5
   cu.m for partition wall in 1 day.
                                                                                             57
3.2 FORMWORK FOR SLAB
                                                                                                         57
-   Bedroom area (2.830*2.711=7.672 sqm)
                                                                                         57
-   Drawing room = 2.100*2.160 + 2.600*4.310 = 15.73 sqm
                                                                                  57
     Props/wall plate      1.50/0.6 = 2.5              2                     2
          Batten            1.50/0.3 = 5               4                     6
-   Total plysheet required for toilet, bath and area near bath = 2.5 plysheet of
    standard size mentioned above.
-   Total khila of 1.5 inch required are = 50 to 60
-   3 inch 5 per every 2.24m for beam.
-   For beams support plysheet required are = 17.854/2.71 = 6.58 = 7 plysheet
                                                                                      57
   Description            Estimated             Actual in            Actual in
                                                building 5           building 6
   Wall plate (chavi)     1.2/1 = 1.2           2(acro span)         2 (acro span)
   Props/wall plate       9.752/1 = 9.752       3(acro span)         3(acro span)
   Battern                9.752/0.3 = 32.50     23                   26
   Plysheet               11.70 sqm ( 4.3 plysheets of size 1.210*2.240 are
                          required)
   Khila                  220 (1.5 inch)        3 inch 5 per every 2.24m for beam
 So total material required for casting the slab of half floor of 8-core of area:
       -     Area = 15.71*11.9 = 186.949 sqm.
       -     186.949 - 2*5.3*1 - 2*.91*.90 - 5.958*1.2
             = 186.949 - 10.6 - 1.638 - 7.149
             =167.553 sqm.
 Following material is required:
 For 170 sqm area 4 pair of carpenter i.e. 1 carpenter and 1 helper worked and
   completed in 7 days in building-6
       -     Work done by 1 pair = 170/4 = 42.49 sqm
       -     Work done by 1 pair/day = 42.49/7 = 6.071 sqm
       -     The output was comparatively low because new material was brought
             and cutting and all done at the site.
                                                                                         57
          For 170 sqm area 3 pair of carpenter i.e. 1 carpenter and 1 helper worked and
             completed in 5 days in building-5
                 -   Work done by 1 pair = 170/3 = 56.67 sqm
                 -   Work done by 1 pair/day = 56.67/5 = 11.33 sqm
                 -
3.3 Foundation
          Excavation
                 -   L= 34.832 + 0.5(raft face) + 0.1(pcc face) + 0.3(working area) = 35.732
                 -   B= 12.404 + 0.5(raft face) + 0.1(pcc face) + 0.3(working area) = 13.304
                 -   Total area= 35.732*13.304 = 475.37 sqm.
                                                                                               57
57
Fig 2 shuttering for raft foundation.
                                            57
                     Fig 4 grade slab after soil compaction at FPL.
                                                                                        57
     In architectural drawings dotted line known as grid is shown on each raft wall so similar
     walls are picked and quantity is calculated.
   6.9 ton steel was used for 8 core foundation 152.2716 cum concrete
   So steel required for 1 cum = 6.9/ 152.2716 = 0.045314 = 45.31kg
3.4 CONCRETING
   Levelling procedure:
         -   At 1 m from the previous slab or floor level marking is done on the wall
                                                                                                 57
         -   Then from that level shuttering bottom is kept.
         -   From the marking another marking at 2m+slab thickness+300mm is done on the
             vertical bar
         -   A rope is tied at that marking and shuttering top level is checked whether it is on
             level or not.
         -   If it is in level then only concreting is started.
   To complete the slab of 28 m3 22 person took 12.30 hours
   So productivity of concreting per hour = 2.27 m3
   To complete it in 1 working day i.e 8 hours we can either increase 1 concrete mixer or
     persons to 34 from 22.
3.5 REINFORCEMENT
                                                                                                   57
  Beam size         No. of           Ring            No. of   Total            Total
                    rings            length          beam     length of        length of
                                                              rings            horizontal
                                                                               bars
  5.9*0.2*0.325 29.5                 27.435          3        82.305           70.8
  9.9*0.2*0.325 49.5                 46.03           1        46.03            39.6
  3.5*0.2*0.325 17.5                 16.27           1        16.27            14
  4.8*0.2*0.325 24                   22.32           2        44.64            38.4
  1.6*0.2*0.325 8                    7.44            2        14.88            12.8
  2.6*0.2*0.325 13                   10.79           1        10.79            10.4
  2.5*0.2*0.325 12.5                 10.37           1        10.37            10
                             Total                            225.29           196
                                                                                            57
          So total work done by 2 pair = 598.8 * 0.395 = 236.52 kg
          Work done by 1 pair = 118.26 kg
          At every two layers 18 mm gauge G.I wire is used as a reinforcement.
          1 person can fix up to 42.12 m per day.
          Both cutting and fixing done by the same person.
   Two pairs (1 pair = 1 mason + 1 helper {semi mason} were working and mortar of 1:4
     was used.
   Worked done by 1st pair = two long wall and 1 short wall of bedroom ( 2.830 * 2.711)
         -   Hence work done = (2 * 2.830 * 3) + (1 * 2.711 * 3 – 2.85 {W}) = 13.698 +
             8.133 – 2.85 = 18.981 sqm.
   Work done by another pair = 1 long wall and 2 short wall of living room
         -   Hence work done = 4.700 * 3 – 2.52 {D} + 4.310 * 3 + 2.170 * 3 – 6.51 – 2.52
             {D} = 14.1 – 2.52 + 12.930 + 6.51 – 2.52 = 28.5 sqm.
   Total 5 cement bags were used.
   Theoretically cement consumption should be as below
         -   Ratio of mortar = 1:4 , so 1+4 = 5
         -   Dry volume = 28.5 * 0.12 + 35% of its vol. + 18.981 * 0.12 + 35% of its vol. =
             0.342 + 0.1197 + 0.228 + 0.0797 = 0.7694
         -   0.7694/ 5 = 0.15388
         -   0.15388/0.035 = 4.39 bags
   Next day 1 pair was working
         -   Work done = 1.940 * 3 – 0.85 * 2.1 + 1.940 * 3 – 0.640 * 1.1 – 0.720 * 2.1 + 2.06
             * 3 + 2.06 * 3 + 0.5 * 2.06 * 2 = 4.035 + 3.604 + 6.18 + 8.24 = 22.059 sqm.
         -   Total 2.75 bags were used.
   Theoretically cement consumption should be as below
         -   Ratio of mortar = 1:4 , so 1+4 = 5
         -   Dry volume = 22.05 * 0.12 + 35% of its vol.
             = 0.2647 + 0.09264= 0.3573
         -   0.3573/ 5 = 0.071469
                                                                                                 57
         -   0.071469/0.035 = 2.04 bags
                                                                                             57
        3.8 RMC PLANT
                                                                                               57
       for grouting
Material required for 1 bag
                              50   30   125   110   78   0.40
         cement
CHAPTER 4
CONCLUSION
                                                                57
57
                                        CHAPTER 4
                                          CONCLUSION
4.1 General
It was a wonderful learning experience at ARVIND AND SMART VALUE HOMES a joint
venture with TATA HOUSING DEVELOPMENT at projects SUBHGRIHA AND NEW
HEAVEN COMPACT. It was a great opportunity to observe and learn quality work culture and
the functionalities in almost all the departments at the site.
Things that I learn under the shade roof of our college gave us the knowledge about the things
can be done. This project taught us that how carefully the things taught in college can be
practically applied on the site.
As a student, I learned the different concepts that attributes to the theoretical side of construction
and management. During this project, I was encouraged to think lifelike and apply those
theoretical concepts which I had learnt, in practical situations. The staff shared their past
experiences and work which made me learn many technical & managerial aspects. It helped me
to learn various safety and quality aspects and synchronized my theoretical knowledge with the
practical knowledge of the huge scale project of an affordable housing.
Overall the project helped me to strengthen my engineering and management concepts. I hope
this experience will surely help me in my future and also in shaping my career. Above all this
project has improved my thinking power and increased my eye sight, fair observation.
 Proper planning and its tracking is the key to complete project within time with quality.
                                                                                                         57
 Proper Safety Environment helps employees and works to perform their duties and
   responsibilities very well.
 Proper planning of materials is necessary for huge project like this. So, systems like SAP
   helps to achieve it.
 Checklist helps engineers to check & approve work done by contractors and minimizes
   possibility of errors.
 Safety and Quality should not be compromised with respect to work progress.
 Daily, Weekly, Monthly Meetings are necessary to check status of project and to take in
   time remedial actions.
 Latest technology and software should be used; it minimizes efforts and reduces errors in
   work.
                                                                                               57
REFERENCES
agnew, Spencer. "The impact of affodable housing oncommunities and household." Minnesota
housing finance agency (2010): 1-26.
Berry, Prof. Mike. "Affordable Housing Project back ground paper." Brotherhood of st.
Laurence (2002): 1-17.
Deven Carlson, Robert Haveman. "Long-Term Effects of Public Low-Income Housing Vouchers
on Labor Market Outcomes." Institute for Research on Poverty (2009): 1-46.
http://www.worksafety.act.gov.au/publication/view/1140
http://accessengineeringlibrary.com/browse/building-design-and-construction-handbook-sixth-
edition
http://wbpwd.gov.in/pdfs/IndianStandardsforBuildingWorks-74to83.pdf
http://www.ctbuh.org/download/Tall_Buildings_Planning_and_Construction_Guide_India.pdf
57