0% found this document useful (0 votes)
17 views1 page

Material Approval Request (Mar) : Subconstructor Ceec Owner Sinopec Qa/Qc Qa/Qc Name

The document is a Material Approval Request (MAR) for the Al Shuaibah 2 PV Solar Project, submitted by CEEC EPC JV. It includes details about flood lighting fixtures and sign board lighting fixtures, along with their specifications and manufacturer information. The material has been approved for use, with comments to be complied with by the contractor.

Uploaded by

Awais Ali Shah
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
17 views1 page

Material Approval Request (Mar) : Subconstructor Ceec Owner Sinopec Qa/Qc Qa/Qc Name

The document is a Material Approval Request (MAR) for the Al Shuaibah 2 PV Solar Project, submitted by CEEC EPC JV. It includes details about flood lighting fixtures and sign board lighting fixtures, along with their specifications and manufacturer information. The material has been approved for use, with comments to be complied with by the contractor.

Uploaded by

Awais Ali Shah
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 1

MATERIAL APPROVAL REQUEST (MAR)

Project Al Shuaibah 2 PV Solar Project Doc. NO. ASB2-GEN-OTH-ICL-GF-003-0

Owner AL SHUAIBAH HOLDING MAR NO. ASB-MAR-PVS-GEN-PVT-FQE-LS-121-1

Contractor CEEC EPC JV OF AL SHUAIBAH PV PROJECT-KSA AREA PVS

Submission Date 17/9/2023 Approval Date

Material Description

FLOOD LIGHTING FIXTURE ON LP, LCM, GANTRY, (200W, 200-240/50/60Hz) L65(outdoor)

SIGN BOARD LIGHTING FIXTURE, 200-240/50/60Hz LED, OT-07 (Outdoor)

Manufacturer / Supplier

NLC

Enclosed Reference Documents

Company Profile, Data Sheet, Drawing

Material Use For:

Mechanical
✔ Electrical Civil

Inspection Result:

Material Approved. The contractor is allowed to use

Material Approved with comments. The contractor is allowed to use provided owner comments are complied

Rejected

Remarks/ Comments:

Subconstructor CEEC
Owner
SINOPEC QA/QC QA/QC

Name

Signature

Date