M5 - CTSSS
M5 - CTSSS
Cofferdams
A cofferdam is a temporary structure built to enclose an area of water for the purpose of creating a dry work
environment, typically in construction, repair, or maintenance activities. Cofferdams are commonly used in
marine construction, bridge foundations, dam repairs, and other projects where work must be done below
water level or in submerged areas. The structure typically holds back water, allowing workers to perform
tasks such as excavation, foundation installation, or repairs in a dry environment.
Types of Cofferdams
1. Earth-Fill Cofferdams:
o Made from earthen materials such as sand, gravel, or clay, often reinforced with a layer of
impervious material.
o Typically used for smaller, shallow water bodies.
o Relatively cost-effective but may not be suitable for large-scale projects or areas with high
water pressure.
2. Rock-Fill Cofferdams:
o Constructed using large stones or rocks to create a barrier that can resist water pressure.
o Used when more stability is required, such as in riverbeds or areas with strong currents.
o More durable than earth-fill cofferdams but more expensive and labor-intensive to build.
3. Sheet Pile Cofferdams:
o Consist of interlocking steel, concrete, or wooden sheets driven into the ground to form a
watertight barrier.
o Suitable for deepwater areas or places with limited space for construction.
o Provides a more reliable, watertight solution and is often used in urban areas or near existing
structures.
4. Cellular Cofferdams:
o Made of multiple connected cells (usually constructed from interlocking steel plates or sheet
piles) to form a watertight enclosure.
o Often used for large-scale projects, such as bridge foundations or harbor structures.
o The multiple cells act as a load-bearing structure, providing more strength and stability.
5. Concrete Cofferdams:
o Constructed with reinforced concrete for projects that require a very strong and durable
structure.
o Used in very deep water or for long-term projects where a permanent or semi-permanent
solution is needed.
o Provides excellent water resistance but is expensive and time-consuming to build.
6. Combination Cofferdams:
o A mixture of different materials (such as sheet piles and earth or rock fill) to form a stable and
watertight structure that can resist varying water pressures.
o Used when specific site conditions require a combination of strength and flexibility.
Applications of Cofferdams
1. Bridge Foundations:
o Cofferdams are commonly used to create a dry working environment for the construction of
bridge piers and foundations in rivers or lakes.
2. Dam Construction and Repair:
o In the construction or repair of dams, cofferdams are used to divert water from the work area,
allowing engineers to work on the structure without being affected by water pressure or flow.
3. Maritime and Marine Construction:
o Cofferdams are used for the construction of docks, piers, and other maritime structures,
providing a dry work environment for the installation of foundations or other substructures.
4. Hydroelectric Projects:
o Cofferdams are used to divert water temporarily during the construction of hydroelectric
plants, turbines, and other infrastructure along rivers and dams.
5. Water Treatment Plants:
o Cofferdams are used to create dry conditions for the construction of water intake and treatment
facilities, especially in locations where the intake structure is submerged.
6. Environmental Projects:
o In environmental remediation or containment projects, cofferdams can be used to isolate
contaminated areas and prevent water from spreading pollutants into surrounding ecosystems.
Advantages of Cofferdams
1. Effective Water Control: Cofferdams are highly effective at controlling water and providing a dry
working environment in areas that are submerged or flooded.
2. Flexibility: Cofferdams can be used in a variety of environments, from rivers and lakes to coastal
regions, making them suitable for many different types of projects.
3. Cost-Effective: Cofferdams can be a cost-effective solution for temporary water control, especially
when compared to alternative methods like diversions or tunnels.
4. Safety: Cofferdams provide a safe working environment by preventing flooding, water pressure, or
other hazards during construction activities.
5. Minimal Environmental Impact: When designed and constructed properly, cofferdams can minimize
environmental disruption by containing water and preventing erosion or soil disturbance.
Disadvantages of Cofferdams
1. High Initial Cost: The construction of cofferdams, especially large or complex ones, can be costly
due to the materials, labor, and equipment required.
2. Time-Consuming: The installation of cofferdams can take a significant amount of time, especially in
deep or challenging environments.
3. Maintenance: Regular monitoring and maintenance are necessary to ensure the cofferdam remains
effective throughout the construction process.
4. Limited Durability: Cofferdams are temporary structures and may not be suitable for long-term use
unless specially designed for extended periods.
5. Environmental Risks: If not properly constructed or maintained, cofferdams can cause environmental
damage, such as soil erosion, sedimentation, or disruption to aquatic habitats.
Single Wall Cofferdams
A single wall cofferdam is a structure made using one continuous barrier, typically constructed with sheet
piles (steel, concrete, or timber) or earth fill. This type of cofferdam is used where water pressure is relatively
low and the area to be dewatered is not very large.
Construction Steps for Single Wall Cofferdams
1. Site Survey and Design:
o A thorough site survey is conducted to determine the water depth, soil conditions, and other
site-specific factors. Based on this, a design is prepared for the cofferdam, specifying the
material, depth, and required height of the wall.
2. Excavation and Preparation:
o Before constructing the cofferdam, excavation may be required to remove loose material and
prepare the foundation. If an earth-fill cofferdam is used, the soil is excavated and compacted
in layers.
3. Installation of Sheet Piles:
o Sheet piles (steel, timber, or concrete) are driven into the ground along the perimeter of the
area to be enclosed. These piles are interlocked to form a continuous barrier to water.
o For steel sheet piles, a pile driver is used to drive the piles into the ground until they reach a
stable layer or required depth.
4. Water Control:
o Once the sheet piles are in place, dewatering pumps are used to remove the water inside the
cofferdam. The pumps continue to remove water as the water level inside the cofferdam drops.
5. Reinforcement and Sealing:
o If required, the inside of the cofferdam may be reinforced with clay liners or plastic sheets to
prevent any water seepage.
o Grouting is sometimes used to seal the joints between sheet piles and prevent any leakage.
6. Foundation Work:
o After dewatering, the area inside the cofferdam is excavated and foundation work is carried
out. This may involve digging, piling, or installing concrete bases.
7. Dismantling:
o Once the work inside the cofferdam is completed, the water is reintroduced, and the cofferdam
is dismantled. The sheet piles are removed and can be reused for other projects.
Advantages of Single Wall Cofferdams:
Cost-Effective: Suitable for shallow water environments and smaller areas where water pressure is
low.
Quick to Install: Easier to construct than more complex cofferdam designs.
Simple Design: Ideal for straightforward projects with minimal depth or complexity.
Limitations:
Limited Water Resistance: Not suitable for areas with high water pressure or deep water.
Susceptible to Leakage: Water may seep through the single barrier if not properly sealed.
Double Wall Cofferdams
A double wall cofferdam consists of two concentric walls, typically one inside the other, with a gap between
them that is filled with material (such as sand, gravel, or slurry). This design provides additional strength and
water resistance compared to single wall cofferdams. They are used in deeper water or areas where higher
water pressure is expected.
Construction Steps for Double Wall Cofferdams
1. Site Survey and Design:
o A detailed site assessment is performed to understand water depth, soil conditions, and other
environmental factors.
o The design will include two walls, with specific materials chosen for each layer (e.g., sheet
piles for the outer wall and earth or concrete for the inner wall).
2. Excavation and Preparation:
o As with the single wall cofferdam, the area may need to be excavated and prepared before
construction.
o If using earth-fill for the inner wall, the area will be compacted to ensure stability before
construction begins.
3. Outer Wall Installation:
o The outer wall of the cofferdam is constructed first. This typically involves the installation of
sheet piles (steel, timber, or concrete) along the perimeter of the enclosure.
o Pile-driving equipment is used to install the sheet piles to a sufficient depth to resist water
pressure and prevent seepage.
4. Inner Wall Installation:
o Once the outer wall is completed, the inner wall is built, typically using the same material or a
combination of materials (e.g., concrete, earth fill, or slurry).
o The gap between the two walls is then filled with a suitable material such as sand, gravel, or
grouting slurry, which acts as a barrier to water.
5. Water Control:
o Dewatering pumps are used to remove water from the area enclosed by the cofferdam. The
pumps maintain a dry environment as water is pumped out.
o Additional grouting or sealing materials may be used between the inner and outer walls to
ensure no water leakage occurs.
6. Foundation Work:
o Once the cofferdam is fully constructed and the work area is dry, foundation work can be
carried out in the enclosed area. This may involve deep excavation, piling, or pouring concrete
for structures such as bridges or dam foundations.
7. Dismantling:
o After the construction work inside the cofferdam is completed, water is reintroduced, and the
cofferdam is dismantled. The materials used in the construction, especially the sheet piles, can
be reused in other projects.
Advantages of Double Wall Cofferdams:
Better Water Resistance: The double barrier provides greater protection against water seepage,
making it ideal for deep water or areas with high water pressure.
Strength and Stability: The dual-wall system offers greater structural integrity, especially for large
and heavy projects.
Higher Safety: The inner wall acts as an additional safety measure, reducing the risk of failure or
water intrusion.
Limitations:
Higher Cost: Due to the additional materials and construction complexity, double wall cofferdams are
more expensive than single-wall cofferdams.
Longer Construction Time: The installation of two walls and the filling process takes more time
compared to single wall cofferdams.
Complexity: The design and construction process is more involved, requiring specialized equipment
and expertise.
Sheet Pile Cofferdam
A sheet pile cofferdam is a type of cofferdam that utilizes sheet piles (typically made of steel, concrete, or
timber) to form a watertight barrier around an area that needs to be dewatered for construction purposes. Sheet
pile cofferdams are commonly used in marine, riverine, or other waterlogged environments where work
needs to be done below water level, such as foundation installation for bridges, piers, or dam repairs.
Construction of Sheet Pile Cofferdam
Materials Used for Sheet Piling
Steel Sheet Piles: The most commonly used material for sheet piles. Steel sheet piles are durable,
strong, and can be driven to great depths.
Concrete Sheet Piles: Used for projects where steel is not suitable or when more resistance to
corrosion is needed.
Timber Sheet Piles: Typically used for smaller, less critical applications where water pressure is low
and the environment is not too harsh.
Composite Sheet Piles: A combination of materials like steel and concrete, or plastic and steel, used
for specific applications based on the strength and corrosion resistance required.
Construction Process for Sheet Pile Cofferdams
1. Site Survey and Design:
o The site is surveyed to understand the water depth, soil conditions, and other environmental
factors. Based on this, an appropriate design for the cofferdam is created, specifying the
material, type, and depth of the sheet piles.
2. Excavation and Site Preparation:
o If necessary, excavation is carried out to remove loose or unsuitable soil and to create a stable
base for the sheet piles.
Department of civil engineering, RIT, Hassan Page 4
MODULE 5 21CV72
o In shallow water, the area may be prepared by clearing debris and sediment from the
foundation level.
3. Installation of Sheet Piles:
o Driving the Piles: Steel sheet piles are installed along the perimeter of the work area using a
pile-driving hammer or vibratory pile driver. The piles are driven into the ground or seabed
until they reach a stable layer, such as hard soil or bedrock, or the required depth for water
resistance.
o The sheet piles are interlocked with each other to form a continuous barrier.
o The installation of the sheet piles may require temporary supports to hold the piles in place as
they are driven into the ground.
4. Waterproofing and Sealing:
o Once the sheet piles are in place, the joints between the individual piles are sealed to prevent
water seepage. Grouting, clay liners, or bituminous coatings may be applied to enhance the
watertightness of the cofferdam.
o In some cases, additional pressure grouting is used to fill any voids between the piles and the
surrounding soil.
5. Dewatering:
o After the sheet piles are installed and sealed, dewatering pumps are used to pump water out of
the enclosed area. The pumps continue to remove any water infiltrating the cofferdam and
maintain a dry working environment.
o As the water level inside the cofferdam drops, the work area becomes dry, allowing for
excavation, foundation work, or other construction activities to proceed.
6. Reinforcement and Strengthening:
o If necessary, the cofferdam may be reinforced by adding additional layers of sheet piles or
incorporating other materials like sand or gravel to provide extra strength and stability.
o Temporary internal bracing or tiebacks may be used to hold the walls of the cofferdam in
place, especially for deeper cofferdams or areas with high water pressure.
7. Foundation Work:
o Once the area is dry, construction activities such as excavation, piling, foundation installation,
or concrete pouring can begin. The cofferdam provides a safe and dry working space in
submerged or waterlogged areas.
8. Dismantling:
o After the construction work inside the cofferdam is completed, the area is refilled with water,
and the cofferdam is removed.
o The sheet piles can be reused on other projects depending on their condition.
Advantages of Sheet Pile Cofferdams
1. High Water Resistance: Sheet pile cofferdams provide a highly effective water barrier, ensuring
minimal leakage and water seepage.
2. Durability: Steel and concrete sheet piles are robust and can withstand high water pressure and
environmental stress, making them suitable for deep water or high-pressure applications.
3. Reusability: Sheet piles can be reused multiple times in different locations, making them a sustainable
solution.
4. Quick Installation: Sheet pile cofferdams can be constructed relatively quickly, especially when
using specialized equipment like vibratory hammers.
5. Minimal Environmental Impact: Once the cofferdam is in place, it causes minimal disruption to the
surrounding environment, especially when compared to other methods that may require more
extensive excavation or alteration of the site.
Disadvantages of Sheet Pile Cofferdams
1. High Initial Cost: The cost of steel or concrete sheet piles and the equipment required for installation
can be relatively high.
2. Limited for Extreme Depths: While sheet pile cofferdams are effective for most applications, they
may not be suitable for extremely deep water or very high water pressure environments unless
additional support or reinforcement is provided.
3. Space Constraints: Sheet pile cofferdams require sufficient space along the perimeter of the work
area for installation, which may not be feasible in confined or urban settings.
4. Maintenance: Continuous monitoring is required to ensure that the cofferdam remains sealed and
functional throughout the construction process, especially in areas where water pressure fluctuates.
Applications of Sheet Pile Cofferdams
1. Marine and River Construction:
o Used in the construction of piers, bridges, and other structures in rivers, lakes, or coastal
environments.
2. Dam and Reservoir Repair:
o Employed for dewatering and repairing dam foundations, spillways, and other structures below
the waterline.
3. Harbor and Dock Construction:
o Used to create a dry area for the construction of docks, marinas, and other port infrastructure.
4. Pipeline Installation:
o Sheet pile cofferdams can be used for installing pipelines in areas where they cross water
bodies, ensuring that the excavation area remains dry.
5. Water Treatment Plants:
o Installed around areas where water intake or treatment facilities are being constructed or
maintained.
Concrete Wall Movable Cofferdam
A movable cofferdam is a temporary structure used to enclose and dewater an area for construction purposes,
typically for underwater or near-water works such as bridge piers, dams, or waterfront structures. A concrete
wall movable cofferdam consists of large concrete segments or walls that are used to isolate an area from
surrounding water. The cofferdam is "movable" because it can be adjusted or relocated during construction to
accommodate varying water levels or different project phases.
1. Purpose and Functionality
Water Control: The primary purpose of a movable cofferdam is to create a dry working environment
by keeping water out of a construction zone.
Temporary Enclosure: It temporarily isolates a section of water, allowing for the construction of
foundations, piers, or other structural elements in a controlled, dewatered environment.
Adaptability: The design allows for movement, enabling adjustments to the cofferdam position based
on the progress of construction or changes in site conditions.
2. Components of a Concrete Wall Movable Cofferdam
a. Concrete Walls
Precast or Cast-In-Situ: Concrete walls may be precast in large segments or poured in place at the
site.
Waterproofing: Concrete walls are designed to be impervious to water, often with additional coatings
or membranes for enhanced waterproofing.
b. Structural Frame
Steel Frames: The concrete walls are typically supported by steel frames or girders that allow for easy
movement and alignment.
Guide Tracks: Steel tracks or rail systems are often used to guide the concrete walls along a path,
ensuring precise movement and proper alignment.
c. Bottom Seal
Sealing System: A flexible bottom seal, such as rubber gaskets, is used to create a watertight seal
between the cofferdam and the riverbed or seabed.
Weighting: The cofferdam may be weighted down by the concrete’s mass or additional ballast to
prevent floating or shifting while under water pressure.
d. Anchor and Support Mechanism
Anchor Points: The cofferdam is anchored to the ground using steel cables or other support
mechanisms to hold it in place.
Adjustable Mechanism: Hydraulic or mechanical systems may be used to adjust the position of the
walls as the construction progresses or water levels change.
3. Construction Process
a. Site Preparation
Excavation: The area where the cofferdam will be placed is cleared and excavated to a level that
supports the structure.
Foundation: A foundation or base slab is prepared if required, or the cofferdam may rest directly on
the existing bedrock or soil.
b. Wall Installation
Precast Wall Placement: If using precast concrete segments, these are lifted into place using cranes
or other lifting equipment.
Cast-In-Situ Wall Construction: For walls poured on-site, formwork is assembled, and concrete is
poured in sections.
Alignment: The walls are aligned along guide tracks or beams to ensure accurate positioning.
c. Sealing and Ballasting
Waterproofing: The base of the cofferdam is sealed using a rubber or flexible material that conforms
to the substrate.
Ballast: Additional weight may be added to the bottom to keep the cofferdam in place and prevent
floating.
d. Dewatering
Once the cofferdam is in place, pumps are used to dewater the enclosed area, lowering the water level
within the cofferdam to create a dry working environment.
e. Relocation or Adjustment
As the construction progresses, the cofferdam may be relocated or adjusted. Concrete walls can be
moved along the guide tracks or rails to accommodate shifting water levels or changing construction
needs.
4. Advantages of Concrete Wall Movable Cofferdams
Reusability: The cofferdam can be moved and reused for different parts of the project or for future
projects, making it cost-effective.
High Strength: Concrete provides excellent durability and resistance to water pressure, ensuring
reliable performance.
Minimal Environmental Impact: Unlike pile-driven cofferdams, the impact on the surrounding
environment is lower.
Adaptability: The design can be easily modified to suit different site conditions, water depths, and
project requirements.
Safety: Provides a secure and stable environment for workers, reducing risks associated with working
in water.
5. Disadvantages
High Initial Cost: The construction of a movable cofferdam can be costly due to the materials, labor,
and machinery required.
Complex Installation: The installation process can be complex, requiring precise alignment, sealing,
and weight distribution.
Limited Use in Deep Water: This type of cofferdam is best suited for shallow to moderately deep
water applications.
6. Applications
Bridge Foundations: Used in the construction of bridge piers and abutments in rivers or lakes.
Marine Structures: Suitable for the construction of jetties, piers, and other waterfront infrastructure.
Dams and Locks: Used to construct dam foundations, lock chambers, and other water control
systems.
Harbor Construction: Can be used for dry-docking ships or constructing facilities in harbors.
7. Design Considerations
Water Depth and Pressure: The design must take into account the depth of water and pressure
exerted on the cofferdam walls.
Soil Conditions: The nature of the underlying soil or seabed must be considered to ensure proper
sealing and stability.
Construction Phases: The cofferdam’s design should allow for easy relocation and adjustment as
construction progresses.
Anchor Systems: The cofferdam must be securely anchored to prevent movement due to water
currents or waves.
Safety Features: Proper safety measures, including fall protection, must be in place for workers
during installation and operation.
Land Cofferdams
A land cofferdam is a temporary structure designed to enclose a construction site on land, protecting it from
water intrusion and providing a dry working area for construction activities. Unlike sheet pile cofferdams
used in waterlogged or submerged environments, land cofferdams are typically used in areas where
groundwater or surface water may be present, such as in flood-prone areas, low-lying land, or along the banks
of rivers and streams.
Land cofferdams are often made from earth materials, rock fill, or sheet piling, and they are used to create a
barrier against rising water levels, preventing water from entering the construction site.
Types of Land Cofferdams
1. Earthfill Cofferdams:
o Constructed by using soil, sand, or gravel to build an embankment that forms a barrier around
the construction site.
o These cofferdams are typically used where water levels are moderate, and the soil is available
locally for embankment creation.
2. Rockfill Cofferdams:
o Made by using large stones or rocks to create a barrier. These are often used in locations where
water is expected to exert significant pressure, and a more robust structure is needed.
3. Sheet Pile Cofferdams:
o As mentioned earlier, sheet piles (often steel or concrete) can be used to construct a cofferdam
on land in locations where the water level is high, or the soil conditions are challenging.
4. Combination Cofferdams:
o These combine earth embankments with sheet piles or other materials for added strength and
water resistance. For example, a rockfill outer layer combined with an earthfill core could be
used in flood-prone zones.
Construction Process for Land Cofferdams
1. Site Survey and Design:
o A detailed site survey is conducted to assess the water level, soil conditions, and groundwater
conditions. Based on the survey, the cofferdam design is developed, specifying the materials
and construction methodology.
o The design should account for the expected water levels, the area to be enclosed, the type of
soil, and the required height and strength of the cofferdam.
2. Excavation and Site Preparation:
o Excavation is carried out to clear the site of any debris, vegetation, or loose material. This
ensures that the cofferdam has a stable foundation.
o If necessary, drainage systems may be set up to manage groundwater or surface runoff during
the construction process.
3. Building the Cofferdam:
o Earthfill Cofferdam: Soil or sand is placed in layers, compacted, and built up around the
perimeter of the construction site. A proper slope is maintained to ensure stability and prevent
failure.
o Rockfill Cofferdam: Larger rocks or stone are placed along the perimeter, and smaller
materials may be used to fill any gaps. The rockfill provides a durable, water-resistant barrier.
o Sheet Pile Cofferdam: Steel or timber sheet piles are driven into the ground along the
perimeter of the site, interlocking to form a continuous barrier. The sheet piles are sealed at the
joints to prevent water seepage.
4. Waterproofing and Sealing:
o The joints between earthfill or rockfill material and any adjacent structures should be carefully
sealed to prevent water infiltration.
o Grouting or other sealing methods may be applied to improve the watertightness of the
cofferdam, especially in areas where the ground is permeable or where high water pressures are
expected.
5. Dewatering the Site:
o Dewatering pumps are used to remove any water from the construction site inside the
cofferdam. The water can come from groundwater infiltration, rainwater, or surface runoff.
o The pumps continuously remove water to maintain a dry environment for the construction
activities. In the case of high groundwater pressure, additional measures may be taken to
prevent water from entering the cofferdam.
6. Foundation or Construction Work:
o Once the site is dry, construction activities such as excavation, foundation pouring, or
installing supports can begin. The cofferdam provides a safe, dry area for these activities,
ensuring that they can proceed without interference from water.
7. Dismantling the Cofferdam:
o Once construction is completed, the cofferdam is dismantled. This involves removing the earth,
rockfill, or sheet piles, and allowing the water to return to the site.
o In some cases, the cofferdam materials may be reused, especially sheet piles, which can be
lifted and stored for future projects.
Advantages of Land Cofferdams
1. Effective Water Control: Land cofferdams are particularly useful in managing surface water,
groundwater, and floodwaters to keep the construction site dry.
2. Adaptability: They can be adapted to a range of conditions, including flood-prone areas, wetlands, or
land with high groundwater levels.
3. Cost-Effective: Earthfill and rockfill cofferdams are relatively inexpensive to construct compared to
other methods, especially when local materials are available.
4. Quick Construction: Earth and rockfill cofferdams can be constructed quickly, especially in areas
where water levels are not excessively high.
2. Flexibility: The design can be adapted to various site conditions, and it is suitable for projects of
different sizes.
3. Quick Installation: The soldier pile method can be installed relatively quickly, especially with the use
of modern pile-driving equipment.
4. Reusability: Components such as soldier piles and walings can be reused for future projects, reducing
material costs.
5. Reduced Space Requirements: Soldier pile cofferdams can be installed in tight spaces, making them
ideal for urban or constrained environments.
Disadvantages of Soldier Pile Cofferdams
1. Limited Depth: The method may not be suitable for very deep water or high-pressure environments
unless additional reinforcement (e.g., tiebacks) is used.
2. Water Seepage: While sheet piles provide a watertight barrier, soldier pile cofferdams are more prone
to seepage compared to other types of cofferdams, requiring careful sealing and maintenance.
3. Complexity of Anchoring: In deeper cofferdams or areas with high water pressure, additional
anchoring and bracing systems (e.g., tiebacks) are needed, which can increase the complexity and cost
of the construction.
4. Environmental Impact: Depending on the construction site, soldier pile cofferdams may cause
disruption to local ecosystems, especially if groundwater is altered or if materials are not properly
managed.
Applications of Soldier Pile Cofferdams
1. Bridge Foundations: Used in the construction of bridge piers and abutments, especially in areas
where water is present.
2. Dams and Spillways: Soldier pile cofferdams are useful in the construction or repair of dam
foundations or spillways, where control of water is necessary.
3. Water Treatment Plants: Employed when constructing or maintaining water treatment facilities,
particularly in flood-prone areas.
4. Marine and River Construction: Used for waterfront construction projects, such as piers, wharves,
and docks.
5. Utility Installations: Used when installing pipelines or utilities in areas with high groundwater or
water table levels.
Cofferdam Wall by ICOS Method
The ICOS Method (Incremental Construction of Open Caisson) is a construction technique used for building
cofferdam walls, particularly in marine or riverine environments. This method is commonly applied for
projects involving the construction of piers, bridges, or other waterfront structures, where the cofferdam needs
to be built around a construction site to keep water out and allow for dry working conditions.
The ICOS method is an innovative approach that combines the traditional caisson construction with
incremental vertical construction techniques, making it suitable for a variety of challenging geological and
hydrological conditions. The method helps to control water ingress and provides a stable foundation for large-
scale civil engineering projects.
Key Components of the ICOS Cofferdam Method
1. Incremental Construction of Caisson:
o The method begins with the construction of a large caisson (a watertight structure) that will act
as a barrier around the construction site.
o The caisson is installed incrementally, meaning it is built in stages or layers, with each layer
being sunk deeper into the water or soil until it reaches the required depth.
2. Steel or Reinforced Concrete Walls:
o The caisson walls are typically constructed from steel or reinforced concrete, designed to
withstand water pressure and prevent seepage.
o These walls serve as the main structure holding back water while providing a safe, dry
environment for construction work to proceed.
3. Waterproofing and Sealing:
o The ICOS method relies on waterproofing techniques, ensuring that the caisson remains
sealed and prevents water from entering the construction area. This may include using rubber
seals or grouting methods to seal the joints between sections.
4. Dewatering System:
o Once the cofferdam is in place, a dewatering system is used to pump out the water that
accumulates inside the cofferdam, maintaining a dry working space for the construction of
foundations or other structural components.
Construction Process of Cofferdam Walls Using the ICOS Method
1. Site Survey and Design:
o A detailed site survey is performed to assess the water table, soil conditions, and possible
underwater obstacles. Based on this survey, an engineering design is developed, which
includes the dimensions and materials for the caisson and the expected water depth.
2. Preparation of the Caisson:
o The caisson structure is built incrementally, often in sections. The first step involves
constructing a base or a large platform that can float and be submerged to the desired location.
o Sections of the caisson are then added one by one, using cranes or other lifting equipment, and
sunk into place, with each section interlocked or sealed to the previous one to create a
continuous watertight barrier.
3. Sinking the Caisson:
o The caisson structure is sunk progressively by either ballasting (adding weight to sink it) or
excavating the inside of the caisson to reduce buoyancy, allowing it to sink to the required
depth.
o As the caisson sinks, any gaps between the caisson and the surrounding soil or waterbed are
sealed, often by using grouting or caisson sealing systems.
4. Waterproofing and Sealing:
o The joints between the individual caisson sections are sealed to prevent water infiltration.
Waterproofing techniques such as rubber seals, caulking, or grout injection are used to
ensure that the cofferdam remains watertight.
o Depending on the water pressure and soil conditions, additional reinforcement may be added to
ensure the structural integrity of the cofferdam.
5. Dewatering:
o After the caisson is fully sunk, the construction area inside the cofferdam is dewatered using
pumps. This step involves removing any groundwater or surface water that may have seeped
inside the cofferdam.
o The cofferdam provides a dry environment for construction, where foundation work, piling, or
other structural elements can be built.
6. Construction of the Permanent Structure:
o Once the area inside the cofferdam is dry, construction begins on the permanent structure, such
as a bridge pier or foundation.
o The cofferdam provides a safe environment for workers and equipment, and the construction of
the structure proceeds without the need to worry about water intrusion.
7. Dismantling the Cofferdam:
o After the permanent structure has been completed, the cofferdam is removed, or parts of it may
be left in place as part of the foundation.
o The cofferdam may be dismantled in stages, with the sections being pulled up from the water
or excavated, depending on the design.
o Steel or Concrete Piles: The primary structural element in this type of cofferdam is piles,
which are driven into the ground or seabed to form a barrier. Steel, concrete, or composite piles
can be used depending on the soil conditions, water depth, and project specifications.
o Touching Arrangement: The piles are positioned so that they are placed very close together
or interlocked, effectively creating a watertight seal. This arrangement provides the necessary
resistance against water penetration and can be adapted for various site conditions.
2. Waling Beam:
o Horizontal waling beams are often used to connect the tops of the piles, providing additional
lateral support and distributing the forces acting on the cofferdam. They help maintain the
stability of the cofferdam structure during construction.
3. Dewatering System:
o A dewatering system is typically employed inside the cofferdam to pump out any water that
seeps through the piles. This ensures a dry working area, which is necessary for the
construction of foundations or other structures inside the cofferdam.
4. Waterproofing (Optional):
o In some cases, additional waterproofing methods, such as sheet piling, grouting, or rubber
seals, are used between the piles to enhance the water-tightness of the cofferdam and prevent
seepage.
Construction Process of Cofferdam with Touching Piles
1. Site Survey and Design:
o A detailed survey of the site is performed to assess soil and water conditions, such as the water
table, soil type, and possible underwater obstacles. Based on the survey, the design of the
cofferdam and pile arrangement is finalized, ensuring that the piles are spaced appropriately to
create a continuous barrier.
2. Pile Driving:
o Piles are driven into the soil or seabed around the perimeter of the construction site. Depending
on the water depth and soil conditions, this can be done using a pile driver or an auger.
o The piles are positioned close enough to each other so that their edges or tops "touch," forming
a barrier. This arrangement provides continuous support against water pressure.
3. Connection of Piles (Optional):
o If necessary, waling beams or tie rods are installed at the top of the piles to provide additional
structural support. These beams help to resist horizontal forces and ensure that the piles remain
in place as the cofferdam is constructed.
4. Waterproofing and Sealing:
o To enhance the watertightness of the cofferdam, additional sealing measures may be employed
between the piles. This can include grouting between the pile joints, the use of waterproof
membranes, or rubber seals to prevent water from leaking through the gaps.
5. Dewatering:
o A dewatering system is activated to pump out any water that enters the cofferdam. This may
involve using deep wells, wellpoints, or sump pumps to lower the water table inside the
cofferdam and keep the construction area dry.
6. Foundation Work:
o Once the cofferdam is fully installed and the water has been removed, construction work can
proceed inside the dry area. This may include excavating the site for foundations, piling, or
other construction activities necessary for the project.
7. Completion and Dismantling:
o After the permanent structure has been built, the cofferdam may be dismantled, or some
elements may be left in place as part of the permanent foundation or structure. The piles used
in the cofferdam may be retained if they are integrated into the final design.
the ground around the construction area to form a watertight enclosure. The interlocking piles fit together like
puzzle pieces, creating a continuous and stable barrier that prevents water from entering the work area.
This type of cofferdam is commonly used for bridge foundations, tunnel shafts, piers, and other construction
projects where excavation is required in areas prone to water ingress, such as rivers, lakes, or marshy ground.
1. Key Components of a Cofferdam with Interlocking Piles
a. Interlocking Piles
Material: Interlocking piles are generally made of steel (such as sheet piles or H-piles) or concrete.
o Steel Sheet Piles: Thin, flat steel piles that have edges designed to interlock with neighboring
piles. These are the most common type used for interlocking cofferdams due to their flexibility
and ease of installation.
o Concrete Piles: These are sometimes used in situations where higher strength and resistance to
corrosion are required. Concrete piles may have interlocking joints or be arranged with a
tongue-and-groove system.
Types of Interlocking Mechanisms:
o Tongue-and-Groove: One edge of the pile has a "tongue" (a protruding part), and the other
has a "groove" (a recessed part), allowing the piles to interlock tightly.
o Z-Interlocking: Z-shaped edges are used, allowing the piles to fit together and form a
continuous barrier.
b. Lagging or Sealing Material
Waterproofing: While interlocking piles provide a significant degree of watertightness, additional
sealing material, such as rubber gaskets, bentonite slurry, or sealant, is often used to ensure there is
no water seepage between the interlocked piles.
Lagging: In some cases, lagging materials such as timber or concrete panels are used to fill the gaps
between the piles, especially in taller cofferdams where additional support is needed.
c. Tiebacks (Optional)
Purpose: Tiebacks are installed to provide additional lateral stability to the cofferdam. These are steel
cables or rods anchored into stable soil or rock behind the cofferdam to prevent it from shifting under
the pressure of the water.
Installation: Tiebacks are drilled into the ground behind the cofferdam and tensioned to stabilize the
interlocking piles.
2. Construction Process for Cofferdam with Interlocking Piles
a. Site Preparation
Clearing the Area: The site is cleared of any debris, vegetation, or other obstructions. The area where
the cofferdam will be constructed is also leveled if necessary.
Surveying: The exact positioning of the cofferdam is surveyed to ensure that the interlocking piles are
placed correctly.
b. Pile Installation
Driving or Drilling:
o Driven Piles: Steel sheet piles or other types of interlocking piles are driven into the ground
using a pile driver. The piles are driven into the seabed, riverbed, or soil, depending on the
project location.
o Drilled Piles: In some cases, piles are drilled into the ground and then grouted in place. This is
often used in rock or very hard soils.
Interlocking: As each pile is driven, it is interlocked with the adjacent piles. The interlocking edges
create a continuous barrier, and the piles are fitted tightly together to form a stable structure.
Water Pressure: The design must account for the expected water pressure in the area, ensuring that
the piles and interlocking system can withstand these forces.
Soil Conditions: Soil type, cohesion, and the depth of the cofferdam influence the design and pile
installation method. For example, more robust piles may be needed in rocky or dense soil.
Pile Spacing: The spacing between piles must be determined based on the load-carrying capacity,
water pressure, and type of soil.
Tiebacks: The use of tiebacks and their design is crucial in ensuring the structural stability of the
cofferdam, particularly in high-water-pressure situations.
Environmental Considerations: The design should include measures to minimize environmental
impact, especially in sensitive ecosystems like marine or river environments.
Cofferdam with Diaphragm Wall
A cofferdam with a diaphragm wall is a type of temporary structure used to create a dry working
environment for construction projects in areas where water is present, such as rivers, lakes, or coastal
locations. This construction method combines the use of a diaphragm wall (a thick, reinforced concrete wall)
with a cofferdam to effectively seal off the construction area from water intrusion. It is particularly useful for
underwater or marine constructions, such as bridge piers, tunnels, and waterfront buildings.
The diaphragm wall serves as the primary structural element in the cofferdam, providing a watertight barrier
that resists the pressure of the surrounding water and soil. This construction method ensures the safety and
stability of the project while creating a dry environment for excavation and foundation work.
Key Components of Cofferdam with Diaphragm Wall
1. Diaphragm Wall:
o A diaphragm wall is a reinforced concrete wall constructed below ground level. It is typically
built using a slurry trenching method or continuous piling technique and is designed to
withstand high water pressure and provide a watertight barrier.
o The diaphragm wall is often built in sections that are interconnected and sealed to form a
continuous barrier around the construction site.
2. Soldier Piles (Optional):
o Soldier piles may be used in conjunction with the diaphragm wall to provide additional lateral
support and prevent movement.
o These vertical steel or concrete piles are driven into the ground around the perimeter of the
excavation and are connected to horizontal walings for structural stability.
3. Waterproofing:
o Waterproofing techniques are essential to prevent seepage through the diaphragm wall. These
may include bentonite slurry, rubber seals, or grouting methods to seal joints and gaps.
4. Dewatering System:
o Once the diaphragm wall is in place, a dewatering system is installed inside the cofferdam to
remove any water that seeps into the excavation. This ensures that the construction area
remains dry and safe for workers.
Construction Process of Cofferdam with Diaphragm Wall
1. Site Survey and Design:
o A detailed geotechnical survey is conducted to understand the soil conditions, groundwater
levels, and potential water pressures. Based on this data, the design of the cofferdam and
diaphragm wall is determined, including the depth, thickness, and reinforcement requirements.
2. Excavation and Preparation:
o The construction site is prepared by excavating the area to the required depth. This may
involve dredging or removing loose soil to make room for the diaphragm wall installation.
o Temporary supports, such as sheet piles or soldier piles, may be used to stabilize the
excavation.
3. Construction of the Diaphragm Wall:
o The diaphragm wall is constructed using a trenching method. A trench is excavated to the
required depth, and a bentonite slurry or waterproof slurry is used to support the trench
walls.
o Reinforcement cages (steel bars) are lowered into the trench, and concrete is poured to form
the wall. The concrete is poured in stages to build the continuous diaphragm wall.
o The wall is typically constructed in sections, and each section is connected and sealed to form a
watertight barrier.
4. Waterproofing and Sealing:
o Once the diaphragm wall is in place, waterproofing methods are applied to ensure that no
water can infiltrate through joints or gaps. This may include grouting, rubber seals, or
applying waterproof membranes to the exterior of the diaphragm wall.
5. Installation of Soldier Piles (if applicable):
o If additional lateral support is required, soldier piles are driven into the ground around the
perimeter of the diaphragm wall. These piles are connected to walings (horizontal beams) that
help distribute the load and provide extra stability to the structure.
6. Dewatering:
o A dewatering system is activated once the diaphragm wall is in place to remove any water that
has seeped into the excavation. The system typically includes pumps, wellpoints, or deep
wells to lower the water level inside the cofferdam, keeping the area dry for construction
activities.
7. Foundation Work:
o With the cofferdam structure in place and the water removed, the construction of the
permanent structure (e.g., foundation, piers, etc.) begins inside the dry space created by the
diaphragm wall.
o The cofferdam provides a stable, dry environment for workers to perform excavation, piling,
and other foundation-related tasks.
8. Dismantling:
o Once the construction inside the cofferdam is completed, the diaphragm wall and any
associated temporary supports (such as soldier piles) may be left in place as part of the
permanent foundation, depending on the project.
o Alternatively, the diaphragm wall can be dismantled or removed after the structure has been
completed, although this is less common due to the cost and complexity involved.
Advantages of Cofferdam with Diaphragm Wall
1. Effective Water Control:
o The diaphragm wall provides a robust and effective barrier to water, ensuring that the
construction area remains dry and safe, even in high-water pressure environments.
2. Flexibility for Deep Excavations:
o The method is well-suited for deep excavations, such as those required for bridge piers,
tunnels, or other underwater structures, where traditional cofferdams may not be feasible.
3. Minimal Impact on the Surrounding Environment:
o Since the diaphragm wall is constructed below ground, the cofferdam structure minimizes its
impact on the surrounding environment, especially in sensitive or urban areas.
4. Durability:
o The diaphragm wall is a permanent structure that can remain in place as part of the final
foundation, providing long-term stability and resistance to water pressure.
5. Safety:
o The watertight nature of the diaphragm wall reduces the risks associated with working in
waterlogged conditions, improving safety for workers.
Disadvantages of Cofferdam with Diaphragm Wall
1. High Cost:
o The construction of a diaphragm wall is expensive due to the complexity of the process,
including the use of specialized equipment, materials, and skilled labor.
2. Time-Consuming:
o The installation of the diaphragm wall and the associated dewatering and waterproofing
systems can be time-consuming, potentially delaying the overall project timeline.
3. Complexity:
o The method requires careful planning and execution, especially in terms of waterproofing,
dewatering, and structural support, making it a complex solution for certain projects.
4. Limited Flexibility for Shallow Projects:
o While effective for deep excavations, this method may be over-engineered for projects with
shallow foundations or where simpler cofferdam systems are sufficient.
Applications of Cofferdam with Diaphragm Wall
1. Bridge Construction: Often used to create dry spaces for the foundation of bridge piers in rivers or
coastal areas.
2. Dam and Lock Construction: Used for constructing dams or lock structures where water control is
essential.
3. Marine and Waterfront Construction: Suitable for constructing waterfront buildings, ports, and
other structures where water intrusion needs to be controlled.
4. Underwater Tunnels: Used in tunnel construction projects where waterproof barriers are necessary to
maintain a dry excavation area.
Caissons
A caisson is a large, watertight chamber or structure used in underwater or waterlogged construction projects
to create a dry working environment, typically for building foundations or other submerged structures. The
term "caisson" can refer to both the structure itself and the process of using such a structure in construction.
Caissons are commonly used in bridge pier foundations, underwater tunnels, and other projects requiring
excavation below water or the ground level.
1. Types of Caissons
There are several types of caissons, each designed for specific conditions and construction needs. The most
common types include open caissons, box caissons, floating caissons, and compressed-air caissons.
a. Open Caissons
Description: Open caissons are large, hollow, box-like structures with a flat base and open top. They
are used for foundations in waterlogged or underwater environments.
Structure: The caisson is typically made of reinforced concrete or steel. The bottom of the caisson is
open to allow excavation to occur inside, and water is pumped out to create a dry working space.
Installation: The caisson is sunk into the ground or water by the weight of the structure itself.
Excavation within the caisson helps it sink further until it reaches the desired depth.
Applications: Open caissons are often used for foundations in rivers, lakes, or coastal areas where the
water depth is not too deep and the soil conditions are suitable for excavation.
b. Box Caissons
Description: Box caissons are similar to open caissons but are fully enclosed on all sides.
Structure: Made of reinforced concrete or steel, box caissons are rectangular or square in shape and
are used to create a dry environment for foundation work.
Installation: The caisson is floated to the construction site and then sunk into position, often using
ballasting or controlled flooding to adjust its buoyancy. Once in place, the caisson is pumped dry, and
excavation occurs inside to reach the required foundation level.
Applications: Box caissons are typically used for pier foundations, deep underwater construction, and
offshore platforms.
c. Floating Caissons
Description: Floating caissons are large, buoyant structures that are floated to the construction site and
then sunk into place.
Structure: Floating caissons are generally large, hollow structures made of steel or concrete, designed
to float until they are positioned at the required site.
Installation: After reaching the site, the caisson is sunk by ballasting or removing buoyancy, and it
then becomes anchored at the desired location.
Applications: This type is often used in deep water where traditional sinking methods (like open
caissons) would be impractical. Floating caissons are commonly used in the construction of offshore
structures or for large bridge foundations.
d. Compressed-Air Caissons
Description: Compressed-air caissons are used in deep water and soft soil conditions where
excavation below the water table is required.
Structure: The caisson is fitted with an air-tight seal and an air supply system, allowing workers to
work in a pressurized environment inside the caisson.
Installation: The caisson is lowered to the desired depth, and compressed air is pumped into the
chamber to maintain an elevated internal pressure, preventing water from entering. Workers inside the
caisson excavate the soil to reach the required depth for the foundation.
Applications: Compressed-air caissons are used in deep-water foundations, such as those for bridges,
piers, and tunnels.
2. Construction Process for Caissons
a. Site Preparation
Surveying: The construction site is surveyed to determine the exact location where the caisson will be
installed.
Excavation (if required): In some cases, preliminary excavation is done to prepare the foundation
area, especially if the caisson will be set on land or in shallow water.
b. Caisson Fabrication
Materials: Caissons are typically made from reinforced concrete or steel. The type of material
depends on the depth of the water, the soil conditions, and the load-bearing requirements.
Construction: The caisson is either constructed at the site or fabricated in a dry dock or a special
construction area. In some cases, the caisson may be constructed on land and then floated to the site.
c. Sinking the Caisson
Open Caissons: The caisson is typically sunk using its own weight. Excavation inside the caisson
helps it sink further, and water is pumped out to keep the working area dry.
Box and Floating Caissons: These caissons are floated to the site and then sunk using ballast or by
removing buoyancy. Once at the desired depth, the caisson is positioned and anchored into place.
Compressed-Air Caissons: The caisson is lowered into the water, and compressed air is pumped into
the chamber to prevent water from entering. Workers inside excavate the soil to allow the caisson to
sink.
d. Excavation and Foundation Work
Water Removal: Once the caisson is in position, water is pumped out to create a dry workspace.
Excavation: Workers inside the caisson excavate the soil at the base to reach the required depth for
the foundation. The excavation process may involve the removal of rock, soil, or other materials.
Foundation Construction: After the desired depth is reached, the foundation work, such as pouring
concrete for piers or other structural elements, is carried out.
e. Finalizing the Caisson
Filling: Once the foundation is complete, the caisson may be filled with concrete to provide additional
stability or support.
Sealing: In some cases, the caisson is sealed to ensure water-tightness, especially if it will remain
submerged.
3. Advantages of Using Caissons
Waterproofing: Caissons provide a dry working environment in waterlogged areas, allowing for safe
excavation and construction.
Adaptability: Different types of caissons can be used in various water depths, soil conditions, and
project types.
Safety: Compressed-air caissons provide a safe work environment for workers by pressurizing the
internal atmosphere and preventing water from entering.
Structural Stability: Caissons can support heavy loads and form the foundation for large, complex
structures, such as bridges, dams, and offshore platforms.
4. Disadvantages
Cost: Caisson construction can be expensive due to the materials and specialized equipment needed
for fabrication, installation, and excavation.
Complexity: The installation process can be challenging, particularly in deep water or soft soil
conditions.
Time-Consuming: Sinking caissons and excavating the foundation to the required depth can be a slow
process.
Safety Concerns: Workers inside compressed-air caissons face risks such as decompression sickness
(the bends) due to the high-pressure environment.
5. Applications of Caissons
Bridge Foundations: Caissons are often used to create the foundations for bridge piers, especially in
rivers, lakes, or coastal areas where the foundation needs to be placed underwater.
Offshore Oil Platforms: Floating caissons are commonly used in offshore oil and gas projects to
provide a stable base for drilling rigs and platforms.
Piers and Docks: Caissons are used to build piers, jetties, and docks for marine transportation or
leisure activities.
Tunnels and Subsea Projects: Caissons can be used as part of tunnel construction, especially for
underwater tunnels or those that need to be built under challenging conditions.
Well Foundation: Overview and Construction
A well foundation is a type of deep foundation commonly used in areas with soft or loose soil, where the
load-bearing capacity of the surface soil is insufficient for supporting heavy structures. Well foundations are
used to support large structures such as bridges, piers, and other heavy constructions, particularly in riverbeds,
coastal areas, and other locations where the underlying soil is weak or waterlogged.
Well foundations are generally made of concrete and consist of a large, circular or square shaft that extends
deep into the ground or water to reach stable soil or bedrock. They are effective in transferring the load of the
structure to deeper, more stable layers of soil.
1. Types of Well Foundations
There are several types of well foundations, each designed to suit specific conditions and project needs.
a. Open Well Foundations
Description: Open well foundations consist of a large, hollow shaft with an open bottom that is dug
down to a stable soil layer. The shaft is filled with concrete or masonry once the desired depth is
reached.
Structure: These wells are typically cylindrical or rectangular and have no roof or cover. The
excavation is done within the well, and the material removed is used to create the foundation.
Applications: Open wells are used in shallow water or where the groundwater table is not too high.
They are often used for small to medium-sized structures such as piers, small bridges, and buildings.
Deep Load Distribution: Well foundations can transfer loads to deeper, more stable soil or bedrock,
making them suitable for heavy constructions such as bridges, piers, and marine structures.
Durability: Well foundations are made from durable materials such as concrete, brick, or stone, which
can withstand the effects of water and time.
Cost-Effective: While the initial construction of well foundations can be complex, they can be more
cost-effective than other deep foundation solutions, especially in areas with shallow or unstable
groundwater.
4. Disadvantages of Well Foundations
Complex Construction: The construction process for well foundations is labor-intensive and can be
time-consuming, particularly in underwater or deep-water conditions.
High Initial Costs: The cost of materials, equipment, and labor required for constructing well
foundations can be high, especially when specialized equipment like dredgers or pneumatic caissons is
needed.
Limited Depth: The depth of well foundations is limited by the construction method and the ability to
sink the well shaft into the ground. In extremely deep waters or soft soils, other foundation methods
may be more effective.
Safety Concerns: The excavation process, particularly in pneumatic caissons, poses safety risks to
workers, including the potential for decompression sickness (the bends) due to high-pressure
conditions.
5. Applications of Well Foundations
Bridge Foundations: Well foundations are commonly used for the construction of bridge piers,
especially in rivers, lakes, and coastal areas where the soil near the surface is weak or unstable.
Offshore Structures: Well foundations are used for constructing piers, docks, and offshore oil
platforms in shallow waters.
Dams and Locks: Well foundations are used in the construction of dams, locks, and other large water
control structures where deep, stable foundations are required.
Marine Structures: Well foundations are ideal for creating stable bases for marine constructions such
as jetties, wharves, and harbors.
6. Design Considerations for Well Foundations
Soil Conditions: The type of soil, depth of water, and the presence of rocks or other obstacles must be
considered when designing the well foundation.
Load Capacity: The well must be designed to handle the load of the structure it will support. The
thickness and reinforcement of the well shaft must be adequate to bear the weight of the structure.
Waterproofing: If the well will be submerged, waterproofing measures may be necessary to prevent
water seepage and ensure the integrity of the foundation.
Excavation Method: The method used to excavate the soil inside the well depends on the soil
conditions. In soft soils, hydraulic grabs or dredging may be used, while in rock formations, blasting
or mechanical excavation may be necessary
Design and Construction of Pneumatic Caissons
A pneumatic caisson is a type of caisson that uses compressed air to keep water out and provide a dry, safe
working environment for workers excavating underwater or below the groundwater level. Pneumatic caissons
are particularly useful in underwater or deep foundation projects, where the excavation needs to occur below
the water table or in soft, unstable soils.
The primary advantage of pneumatic caissons is that they allow workers to excavate and build foundations at
great depths without the risk of flooding or soil collapse. However, the use of compressed air creates a
pressurized environment inside the caisson, requiring careful safety precautions to prevent issues like
decompression sickness.
1. Overview of Pneumatic Caissons
Pneumatic caissons are large, watertight, box-like structures typically made of steel or reinforced concrete.
The key feature of a pneumatic caisson is that it is pressurized to prevent water and soil from entering the
working area. The pressurized environment allows workers to safely perform excavation tasks in underwater
or low-lying soil conditions.
Pneumatic caissons are used for constructing foundations in locations such as:
Bridge piers.
Marine structures (e.g., docks, jetties, offshore platforms).
Tunnels below water level.
Foundations for large buildings or other structures in waterlogged areas.
2. Types of Pneumatic Caissons
There are generally two types of pneumatic caissons:
Open Pneumatic Caisson: This type has an open bottom, allowing excavation of soil directly beneath
the caisson.
Closed Pneumatic Caisson: This type has a sealed bottom, typically used in cases where excavation
needs to be performed on very soft or unstable soil or when the soil is too difficult to remove using
conventional methods.
3. Design of Pneumatic Caissons
a. Structural Design Considerations
Shape and Dimensions: Pneumatic caissons are typically cylindrical or rectangular in shape. The
design must ensure that the caisson can withstand the forces exerted by the water pressure, soil
pressure, and the weight of the structure being built.
o The diameter or width of the caisson depends on the load it needs to support and the depth at
which it will be sunk.
o The depth of the caisson, along with its weight, determines the stability of the structure during
installation.
Material Selection: Pneumatic caissons are typically made of steel or reinforced concrete. Steel
caissons are used for deeper foundations and those that need to withstand higher pressures, while
reinforced concrete is used for shallower or lighter-duty foundations.
o The material must be chosen to resist corrosion, especially in marine environments.
o The walls of the caisson must be thick enough to withstand both external pressure and internal
air pressure.
Pressurization System: The caisson needs to be equipped with a compressed air system to maintain
pressure inside the chamber and prevent water from entering.
o The compressed air is supplied by compressors and regulated to maintain a steady pressure that
can vary depending on the depth of the caisson.
o The air pressure must be sufficient to counteract the water pressure at the depth of the caisson.
Ventilation and Safety: Proper ventilation and safety systems must be integrated into the design to
ensure the safe operation of workers inside the caisson. These include:
o Airlocks for workers to enter and exit the pressurized environment.
o Decompression chambers to allow workers to adjust to the outside pressure after exiting.
o Escape routes and emergency equipment to ensure safety during unexpected events.
b. Depth and Excavation Considerations
Sinking Depth: The design must account for the depth at which the caisson will be sunk, which
depends on the location of stable soil or bedrock that the foundation will rest on.
o The caisson must be designed to withstand the pressure exerted by the surrounding water and
soil as it sinks to the desired depth.
o The depth also determines the amount of pressurization required inside the caisson.
Excavation Method: Inside the pneumatic caisson, workers remove soil and rock to reach the
required foundation depth. This can be done with grab buckets, dredgers, or hydraulic excavators,
depending on the soil type.
o Excavation continues until the foundation reaches the required depth for the structure.
o The caisson must be equipped with a soil removal mechanism to allow the excavation process
to take place while maintaining a stable, dry working environment.
4. Construction Process of Pneumatic Caissons
a. Site Preparation
Survey and Location: The site is surveyed to determine the location for the caisson, ensuring it’s
positioned on stable soil or bedrock.
Dredging (if necessary): If the site is located in an area with soft or underwater soil, preliminary
dredging may be required to clear the area for the installation of the caisson.
b. Fabrication of the Caisson
Manufacturing: Pneumatic caissons are typically prefabricated in a dry dock or at the construction
site. The caisson may be assembled using steel plates or reinforced concrete sections.
Testing: The caisson is tested for structural integrity and watertightness before being floated to the
construction site.
c. Floating and Sinking the Caisson
Floating the Caisson: Once fabricated, the caisson is floated to the installation site, often using
tugboats or barges.
Sinking the Caisson: The caisson is then slowly sunk into place using a combination of its own
weight and the removal of ballast. As the caisson sinks, excavation inside the chamber begins, which
helps the caisson sink further.
o In some cases, the caisson is ballasted with material such as sand or gravel to help it sink.
o The internal air pressure is adjusted to counteract the surrounding water pressure.
d. Excavation Inside the Caisson
Excavation Process: Inside the pneumatic caisson, workers excavate soil and rock to reach the desired
foundation depth. Special tools like grab buckets or hydraulic excavators are used to remove material
from the bottom.
Pressure Control: The internal air pressure is maintained to prevent water from entering the caisson.
As workers excavate, the pressure may need to be increased or decreased depending on the depth and
water conditions.
e. Concrete Pouring and Foundation Completion
Concreting: Once the desired depth is reached and the caisson is stable, the foundation is built by
pouring concrete into the caisson. This may include pouring a concrete slab or constructing a pier or
pillar that will support the structure above.
Capping: The top of the caisson is capped with reinforced concrete, and the pressurized system is
deactivated.
Caisson Removal: Once the foundation is complete, the caisson is typically removed or left in place,
depending on the design.
5. Advantages of Pneumatic Caissons
Effective in Deep Water: Pneumatic caissons are ideal for foundation construction in deep water or
locations with high groundwater tables.
Safe Working Environment: The pressurized environment ensures that workers can safely perform
excavation in underwater or waterlogged areas.
Stability: Pneumatic caissons provide a stable, solid foundation by reaching deeper, more stable soil
or bedrock.
6. Disadvantages and Safety Considerations
Safety Risks: The use of compressed air poses risks such as decompression sickness (the bends) for
workers. Workers must undergo a gradual decompression process after leaving the pressurized
environment.
High Cost: The use of pneumatic caissons requires specialized equipment, compressed air systems,
and skilled labor, which can make the construction process costly.
Complexity: The process of installing, sinking, and excavating with pneumatic caissons is complex
and requires careful planning and precise execution.
7. Applications of Pneumatic Caissons
Bridge Foundations: Pneumatic caissons are commonly used for the foundations of bridge piers in
rivers, lakes, or coastal areas where the soil is too soft for shallow foundations.
Marine Structures: Pneumatic caissons are ideal for constructing foundations for marine structures
such as docks, jetties, and offshore platforms.
Underwater Tunnels: Pneumatic caissons are also used in the construction of underwater tunnels,
where excavation needs to occur under water or below the groundwater table.
Design and Construction of Precast Caissons
Precast caissons are large, hollow, prefabricated concrete structures used primarily in underwater or marine
construction projects, particularly for foundations in areas with deep water or soft soils. These caissons are
often employed in the construction of bridge piers, piers for docks, jetties, offshore platforms, and other
marine structures.
What is a Precast Caisson?
A caisson is a watertight structure that is used to create a dry working environment for underwater
construction. Precast caissons are made from reinforced concrete and are cast off-site in controlled conditions,
then transported to the construction site where they are sunk into place. They consist of a hollow, cylindrical,
or rectangular shape with a flat base, and they can be either open at the bottom or have an enclosed base with
a seal.
Design Considerations for Precast Caissons
1. Shape and Size:
o Precast caissons are typically cylindrical, rectangular, or box-shaped, depending on the project
requirements.
o The dimensions of the caisson are determined based on the load it will bear, the depth of water,
and the type of soil or bedrock at the installation site. The shape and size of the caisson are
designed to efficiently transfer the load to the foundation.
2. Material Selection:
o Reinforced Concrete: Precast caissons are made of reinforced concrete, which provides the
necessary strength and durability.
o High-strength Concrete: For marine applications, high-strength concrete with additives (e.g.,
marine-grade additives) is used to resist corrosion and the effects of saltwater.
3. Waterproofing and Corrosion Resistance:
o Waterproofing is crucial since caissons are used in marine environments. The concrete may
be mixed with additives to improve its resistance to water penetration.
o Corrosion protection includes the use of corrosion-resistant reinforcement and coatings to
protect the caisson from saltwater exposure.
4. Buoyancy and Ballast:
o The caisson must be designed to have sufficient buoyancy during transportation to the
construction site. Once in place, ballast is added to sink the caisson to the required depth. The
ballast typically consists of gravel, sand, or concrete.
5. Load-Bearing Capacity:
o The design must account for the loads that will be applied during construction (e.g., wind,
waves, and the weight of the structure supported by the caisson), as well as the final load once
the structure is complete.
6. Interior and Exterior Design:
o The interior of the caisson is generally hollow to reduce weight and facilitate easy transport. It
may be equipped with features like ladders, hatches, or shafts to provide access for workers
during installation.
o The exterior is designed to be smooth to reduce water resistance during transportation and
sinking.
7. Safety Features:
o Since caissons are used in underwater construction, safety features such as ventilation
systems, escape routes, and waterproof seals are incorporated into the design.
Construction Process for Precast Caissons
1. Precasting the Caisson:
o Formwork: The first step in the construction of a precast caisson is the creation of the
formwork. The formwork defines the shape of the caisson and is used to hold the reinforcing
steel bars during the pouring of concrete.
o Reinforcement: Steel reinforcement bars (rebar) are placed in the formwork to provide tensile
strength and prevent cracking. The reinforcement is designed based on the expected loads and
environmental conditions.
o Concrete Pouring: High-strength concrete is poured into the formwork. The concrete is
usually poured in sections to ensure proper curing and prevent air pockets or voids in the
concrete.
o Curing: After pouring, the concrete is allowed to cure for a specified period to achieve the
necessary strength. Curing typically takes place in a controlled environment, such as a curing
chamber or an outdoor area with proper protection from extreme weather conditions.
2. Transportation of Precast Caisson:
o Once the caisson has cured, it is transported to the construction site. This is typically done
using barges, cranes, or other lifting equipment.
o During transport, the caisson is kept afloat using buoyancy aids, such as air-filled chambers or
external floats. The caisson is positioned carefully to avoid damage and ensure it remains
upright.
3. Sinking the Caisson:
o Once at the installation site, the caisson is positioned over the desired foundation location.
o Ballasting is done to sink the caisson to the required depth. Ballast is added to the interior of
the caisson, typically consisting of sand or gravel. The weight of the ballast gradually sinks the
caisson to the seabed.
o In some cases, water pumping is used to control the sinking process, allowing for precise
positioning.
4. Excavation Inside the Caisson:
o Once the caisson is in place, it is excavated from the inside to create a dry working space for
workers. This is done by pumping out water from the caisson, which allows workers to
excavate the soil beneath the caisson to the required depth.
o The excavation is typically done in stages, starting from the bottom and moving upward as the
caisson sinks further into the soil.
5. Foundation Construction:
o The final step involves the construction of the foundation inside the caisson. This can include
pouring concrete for the foundation base or installing additional structural elements to support
the desired superstructure, such as a bridge pier, dock, or offshore platform.