SQL 3
SQL 3
                                                  10             0.014556
                                                  46             0.066958
                                                  20             0.029112
                                                  26             0.037846
                                                  14             0.020378
                                                  20             0.029112
                                                  32             0.046579
                                                  27             0.039301
                                                  14             0.020378
                                                  20             0.029112
                                                  32             0.046579
                                                  35             0.050946
                                                  23             0.033479
                                                  29             0.042213
                                                  54             0.078603
                                                  14             0.020378
                                                  14             0.020378
                                                  17             0.024745
                                                  28             0.040757
                                                  30             0.043668
                                                  33             0.048035
                                                  24             0.034934
                                                  29             0.042213
                                                  31             0.045124
                                                  27             0.039301
                                                  10             0.014556
                                                  12             0.017467
                                                  12             0.017467
                                                  16             0.02329
11    0.016012
710   1.033479
tion: 452 Days
 rt: 05/07/2025
ish: 12/23/2026
st: ₱ 100,000,000.00
QUIRED       :
                                            DESCRIPTION                                 NO.
                            Project Engineer                                             1
                            Site Engineer                                                1
                            Foreman                                                      2
                            Skilled                                                     25
                            Labor                                                       20
20
26
14
20
32
27
14
20
32
35
23
29
54
14
14
17
28
30
33
24
29
31
27
10
12
12
16
11
ITEM NO.                   DESCRIPTION                    % OF      UNIT
                                                          TOTA
                                                          L
   101       Pre-Construction                               0.000           L.
   201       Foundation                                    0.000           cu.
                                RC WORKS (Ground Floor)
   301        Slab on Ground                               0.000           cu.
   302        Columns (Ground Floor)                       0.000           cu.
   303        Stairs (Ground Floor)                        0.000           cu.
   304        CHB Layering (Ground Floor)                  0.000           sq.
                                RC WORKS (Second Floor)
   401        Beam & Slab (Second Floor)                   0.000           cu.
   402        Columns (Second Floor)                       0.000           cu.
   403        Stairs (Second Floor)                        0.000           cu.
   404        CHB Layering (Second Floor)                  0.000           sq.
                                 RC WORKS (Third Floor)
   501        Beam & Slab (Third Floor)                    0.000           cu.
   502        Columns (Third Floor)                        0.000           cu.
   503       CHB Layering (Third Floor)                    0.000           sq.
   504        Roof Beam                                    0.000           cu.
                Sub-total for B                                                           P
   C.                     Tot                                                             P
                          al
                          (A
   D.       Output/day +
        Name and Specifications            Quantity           Unit           Unit Cost
   E.      Materials
                L50x50x5 angle bar           185              pcs              ₱1,014.00
             Gusset Plates & Fasteners        19              sets             ₱150.00
                   Welding rods               15              kgs.             ₱200.00
                     C-purlains               10              pcs.             ₱1,200.00
                Sub-total for E
   F.       Direct Cost (C+E)
                                                                       10%
   G.           Overhead, Contingencies and Miscellaneous              per D.O 197 s 2016
   H.       Contractor's Profit                           8% per D.O 197 s
            2016 (CP)
   I.       Value Added Tax                               5% per D.O 197 s
            2016 (VAT)
   J.       Total Unit Cost
   Amount
   52800
   118800
   69300
   240,900.00
    Amount
   4,800.00
     0.00
    4,800.00
   245,700.00
Amount
  ₱187,590.00
   ₱2,850.00
   ₱3,000.00
  ₱12,000.00
   205440.00
   451,140.00
45114
   36,091.20
22,557.00
   554902.20
                                                        DETAILED UNIT PRICE ANALYSIS
PROJECT NAME           CBC DORMITORY
           Sub-total for A
           Name and Capacity                          No. of    No. of Days             Daily Ra
                                                      Equip.
    BEquipment, (2014 ACEL Rates)
                          Sub-total for B
   C.                     Total (A+B)
                              480.00
   D.    Output/day
      Name and Specifications                        Quantity        Unit              Unit Co
   E.    Materials
                        Main Busbar                       1          set                  ₱17,4
                       Panel Busburs                      3         sets                  ₱10,5
                 Neutral & Ground Busbars                 6         sets                  ₱7,0
                       Phase Busbars                      9         sets                  ₱7,0
                       PANEL BOARD                        3         sets                  ₱1,2
             MAIN SAFETY BREAKER(100 AMP)                 3         sets                  ₱1,5
                CIRCUIT BREAKER (30 AMP)                 18         sets                   ₱38
                CIRCUIT BREAKER (20 AMP)                  9         sets                   ₱35
                CIRCUIT BREAKER (15 AMP)                 15         sets                   ₱30
             2.0 MM SQ. THWN COPPER WIRE                 11         rolls                 ₱2,2
             5.5 MM SQ. THWN COPPER WIRE                  6         rolls                 ₱2,7
             3.0 MM SQ. THWN COPPER WIRE                 11         rolls                 ₱2,3
                   PVC CONDUIT (15 MM)                  1700          m                     ₱50
                   PVC CONDUIT (30 MM)                  600           m                     ₱80
                 JUNCTION BOX W/ SCREW                   70         sets                    ₱25
                        UTILITY BOX                      80         sets                    ₱25
                      ELECTRICAL TAPE                    90         pcs                     ₱30
                   KILOWATT HOUR METER                    1         pcs                   ₱1,2
            Sub-total for E
   F.       Direct Cost (C+E)
   G.       Overhead, Contingencies and Miscellaneous
                                                                            10%per D.O 197 s
                                                                            201
H.   Contractor's Profit (CP)   8% per D.O 197 s 2016
I.   Value Added Tax (VAT)      5% per D.O 197 s 2016
J.   Total Unit Cost
te           Amount
0             22400
0             50400
0             29400
            102,200.00
     P       Amount
te
               0.00
     P         0.00
     P      102,200.00
st Amount
00.00    ₱17,400.00
00.00    ₱31,500.00
00.00    ₱42,000.00
00.00    ₱63,000.00
50.00    ₱3,750.00
70.00    ₱4,710.00
5.00     ₱6,930.00
0.00     ₱3,150.00
0.00     ₱4,500.00
60.00    ₱24,860.00
00.00    ₱16,200.00
19.00    ₱25,509.00
.00      ₱85,000.00
.00      ₱48,000.00
.00      ₱1,750.00
.00      ₱2,000.00
.00      ₱2,700.00
50.00    ₱1,250.00 384209.00
         486,409.00
         48640.9
6
38,912.72
24,320.45
598283.07
                                                      DETAILED UNIT PRICE ANALYSIS
PROJECT NAME           CBC DORMITORY
           Sub-total for A
           Name and Capacity                         No. of      No. of Days           Daily Ra
                                                     Equip.
    BEquipment, (2014 ACEL Rates)
                          Sub-total for B
   C.                     Total (A+B)
                              480.00
   D.    Output/day
      Name and Specifications                       Quantity          Unit             Unit Co
   E.    Materials
                    1-1/2" gate valve                  9              pcs                 ₱25
                   150 ф PVC riser pipe                4              pcs                 ₱30
                       3" riser pipe                   4              pcs                 ₱40
                     1-1/2 " CWL pipe                 65              rolls               ₱30
                   1-1/2 " tee threaded               11              pcs                 ₱81
               1-1/2 " 90D elbow threaded             20              pcs                 ₱61
                     150 ф PVC pipe                   63              pcs                 ₱30
                     100 ф PVC pipe                   53              pcs                 ₱10
                 100 ф PVC tee threaded               29              pcs                 ₱81
               100 ф sanitary tee threaded            38              pcs                 ₱82
                100 ф 45D elbow threaded              22              pcs                 ₱50
                100 ф 90D elbow threaded              35              pcs                 ₱50
             100 ф PVC couplings threaded             25              pcs                 ₱50
             150 ф PVC 90D elbow threaded             32              pcs                 ₱50
            Sub-total for E
   F.       Direct Cost (C+E)
   G.       Overhead, Contingencies and Miscellaneous Contractor's Profit (CP)
            Value Added Tax (VAT) Total Unit Cost                      10% per D.O 197 s 201
   H.                                                                  8% per D.O 197 s 2016
   I.                                                                  5% per D.O 197 s 2016
   J.
te             Amount
 0              22400
 0              33600
0               24500
       P       80,500.00
te             Amount
                 0.00
       P         0.00
       P       80,500.00
st Amount
1.00          ₱2,259.00
0.00          ₱1,200.00
0.00          ₱1,600.00
0.00          ₱19,500.00
.00            ₱891.00
.00           ₱1,220.00
0.00          ₱18,900.00
7.00          ₱5,671.00
.00           ₱2,349.00
.00           ₱3,116.00
.00           ₱1,100.00
.00           ₱1,750.00
.00           ₱1,250.00
.00           ₱1,600.00
               62406.00
              142,906.00
6          14290.6
               11,432.48
                7,145.30
               175774.38
                                                       DETAILED UNIT PRICE ANALYSIS
PROJECT NAME                CBC DORMITORY
                Sub-total                                                                 P
                    for B
   C.                                                                                     P
   D.       Output/da
                   480.00
            y
              Sub-total
                   for E
   F.       Direct
            Cost
            (C+E)
                                                                       10%
   G.           Overhead, Contingencies and Miscellaneous                    per D.O 197 s
                2016
H.   Contractor   8% per D.O 197 s 2016
     's Profit
     (CP)
I.   Value        5% per D.O 197 s 2016
     Added
     Tax (VAT)
J.   Total
     Unit
     Cost
     Amount
      52800
      79200
        0
    132,000.00
Amount
54,064.00
       0.00
     54,064.00
186,064.00
Amount
    ₱8,640.00
    ₱1,190.00
    ₱1,178.32
₱234.84
    ₱10,500.00
    ₱6,540.00
    ₱8,750.00
    ₱8,640.00
    ₱9,300.00
    ₱12,600.00
    ₱15,400.00
82973.16
269,037.16
26903.716
21,522.97
13,451.86
330915.71
Item                              : 701(1) Tile Works (Ground
No./Description                   Floor)
Unit of                           : sq.m.
Measurement
Output per hour                   :
Quantity             :   1457.6
                         4
                   Sub-total for B                                                                  P
   C.                    Total                                                                      P
                         (A+B)
   D.       Output/day
                                  480.00
                   Sub-total for E
   F.       Direct Cost (C+E)
                                                                              10%
   G.             Overhead, Contingencies and Miscellaneous                     per D.O 197 s 2016
   H.       Contractor's Profit                                     8% per D.O 197 s
            2016 (CP)
   I.       Value Added Tax                                         5% per D.O 197 s
            2016 (VAT)
   J.       Total Unit Cost
                                             DETAILED UNIT PRICE
PROJECT NAME        CBC DORMITORY
                                             ANALYSIS
Amount
        0.00
        0.00
      151,200.00
Amount
    ₱194,700.00
   ₱10,205,000.00
    ₱20,700.00
     ₱7,440.00
     ₱5,915.00
    ₱207,390.00
    ₱68,400.00
    10709545.00
   10,860,745.00
1086074.5
     868,859.60
543,037.25
     13358716.35
             TILE WORKS
  AREA      40 CM      60 CM 30X60          30 CM    CEME      SAND ADHESI
       28     176.4          CM                      NT 12.6        0.7 VE
                                                                        4.666667
     6.44    40.572                                     2.898    0.161 1.073333
1457.636              4081.381                      655.9362 36.4409 242.9393
55.82002              156.2961                      25.11901 1.395501 9.303337
9.530001                         53.36801           4.288501 0.23825 1.588334
1557.4 216.97 4237.6 53.36                   0      700.84 38.935 259.57
3      2      8      8                              2      7      1
 GROU
 T 2.52
   0.5796
87.45816
3.349201
   0.6671
94.574
1
Item                              : 701(2) Tile Works (Second
No./Description                   Floor)
Unit of                           : sq.m.
Measurement
Output per hour                   :
Quantity             :   1495.6
                         5
                   Sub-total for B                                                                  P
   C.                    Total                                                                      P
                         (A+B)
   D.       Output/day
                                  480.00
                   Sub-total for E
   F.       Direct Cost (C+E)
                                                                              10%
   G.             Overhead, Contingencies and Miscellaneous                     per D.O 197 s 2016
   H.       Contractor's Profit                                     8% per D.O 197 s
            2016 (CP)
   I.       Value Added Tax                                         5% per D.O 197 s
            2016 (VAT)
   J.       Total Unit Cost
                                             DETAILED UNIT PRICE
PROJECT NAME        CBC DORMITORY
                                             ANALYSIS
Amount
        0.00
        0.00
      162,000.00
Amount
    ₱194,700.00
   ₱10,230,000.00
    ₱21,600.00
     ₱7,500.00
     ₱5,915.00
    ₱208,940.00
    ₱68,400.00
    10737055.00
   10,899,055.00
1089905.5
     871,924.40
544,952.75
     13405837.65
            TILE WORKS
  AREA     40 CM    60 CM 30X60        30 CM    CEME       SAND ADHESI
   34.569 217.7847          CM                  NT
                                               15.55605  0.864225 VE5.7615
     6.44   40.572                                 2.898     0.161 1.073333
1461.074           4091.008                    657.4834 36.52685 243.5124
55.82002           156.2961                    25.11901 1.395501 9.303337
9.530001                    53.36801           4.288501 0.23825 1.588334
1567.4 258.35 4247.         53.36       0      705.34 39.185 261.23
3      7      3             8                  5      8      9
  GROU
 3T.11121
   0.5796
87.66445
3.349201
   0.6671
95.371
6
Item                              : 701(3) Tile Works (Third
No./Description                   Floor)
Unit of                           : sq.m.
Measurement
Output per hour                   :
Quantity             :   1495.6
                         5
                   Sub-total for B                                                                 P
   C.                    Total                                                                     P
                         (A+B)
   D.       Output/day
                                  480.00
                   Sub-total for E
   F.       Direct Cost (C+E)
                                                                             10%
   G.             Overhead, Contingencies and Miscellaneous                    per D.O 197 s 2016
   H.       Contractor's Profit                                    8% per D.O 197 s
            2016 (CP)
   I.       Value Added Tax                                        5% per D.O 197 s
            2016 (VAT)
   J.       Total Unit Cost
                                             DETAILED UNIT PRICE
PROJECT NAME        CBC DORMITORY
                                             ANALYSIS
Amount
        0.00
        0.00
      162,000.00
Amount
    ₱265,100.00
   ₱10,297,500.00
    ₱21,960.00
     ₱7,560.00
     ₱5,980.00
    ₱210,800.00
    ₱70,200.00
    10879100.00
    11,041,100.00
 1104110
     883,288.00
552,055.00
     13580553.00
            TILE WORKS
  AREA     40 CM    60 CM 30X60        30 CM    CEME       SAND ADHESI
   38.125 240.1875          CM                  NT
                                               17.15625  0.953125 VE
                                                                   6.354167
     6.44   40.572                                 2.898     0.161 1.073333
1471.029           4118.882                    661.9632 36.77573 245.1716
55.82002           156.2961                    25.11901 1.395501 9.303337
9.530001                    53.36801           4.288501 0.23825 1.588334
1580.9 280.7 4275.1 53.36               0      711.42 39.523 263.49
4      6     8      8                          5      6      1
  GROU
 3T.43125
   0.5796
88.26176
3.349201
   0.6671
96.288
9
Item                              : 801(1) Ceiling (Ground
No./Description                   Floor)
Unit of                           : sq.m.
Measurement
Output per hour                   :
Quantity             :   1309.7
                         2
                   Sub-total for B                                                               P
   C.                    Total                                                                   P
                         (A+B)
   D.       Output/day
                                  480.00
                   Sub-total for E
   F.       Direct Cost (C+E)
                                                                           10%
   G.             Overhead, Contingencies and Miscellaneous                  per D.O 197 s 2016
   H.       Contractor's Profit                                  8% per D.O 197 s
            2016 (CP)
   I.       Value Added Tax                                      5% per D.O 197 s
            2016 (VAT)
   J.       Total Unit Cost
                                              DETAILED UNIT PRICE
PROJECT NAME       CBC DORMITORY
                                              ANALYSIS
Amount
        0.00
        0.00
      152,400.00
Amount
     ₱432,715.00
     ₱256,700.00
     ₱51,340.00
     ₱166,440.00
     ₱23,600.00
     ₱136,500.00
    1067295.00
   1,219,695.00
121969.5
     97,575.60
60,984.75
     1500224.85
 CEILING WORKS
                                                                T
  AREA CHANN FURRI WALL                 CLIP    BOAR LIND
         EL
1309.716 779.5929 NG
                  2338.779 ANGLE
                            2566.179            D
                                       5457.15 454.7625 RIVE
                                                         94288.49
                   Sub-total for B                                                               P
   C.                    Total                                                                   P
                         (A+B)
   D.       Output/day
                              480.00
                   Sub-total for E
   F.       Direct Cost (C+E)
                                                                           10%
   G.             Overhead, Contingencies and Miscellaneous                  per D.O 197 s 2016
   H.       Contractor's Profit                                  8% per D.O 197 s
            2016 (CP)
   I.       Value Added Tax                                      5% per D.O 197 s
            2016 (VAT)
   J.       Total Unit Cost
     Amount
      0.00
      0.00
    165,100.00
Amount
   ₱362,415.00
   ₱232,600.00
   ₱91,420.00
   ₱139,065.00
   ₱23,200.00
   ₱114,275.00
    962975.00
   1,128,075.00
112807.5
    90,246.00
56,403.75
    1387532.25
 CEILING WORKS
                                                                 T
  AREA CHANN FURRI WALL                 CLIP     BOAR LIND
         EL
1096.934 652.9371 NG
                  1958.811 ANGLE
                            2325.164   4570.56   D380.88 RIVE
                                                          84774.59
                   Sub-total for A                                                                       P
            Name and Capacity                           No. of       No. of Days            Daily Rate
                                                        Equip
   B          Equipment, (2014 ACEL Rates)              .
                     Sub-total for B                                                                     P
   C.                      Total                                                                         P
                           (A+B)
   D.         Output/day
                                    480.00
                     Sub-total for E
   F.         Direct Cost (C+E)
                                                                                   10%
   G.               Overhead, Contingencies and Miscellaneous                        per D.O 197 s 2016
   H.         Contractor's Profit                                        8% per D.O 197 s
              2016 (CP)
   I.         Value Added Tax                                            5% per D.O 197 s
              2016 (VAT)
   J.         Total Unit Cost
     Amount
      0.00
      0.00
    165,100.00
Amount
   ₱455,100.00
   ₱274,500.00
   ₱114,780.00
   ₱174,835.00
   ₱21,800.00
   ₱143,500.00
    1184515.00
   1,349,615.00
134961.5
    107,969.20
67,480.75
    1660026.45
 CEILING WORKS
                                                              T
  AREA CHANN FURRI WALL               CLIP    BOAR LIND
         EL
1377.152 819.7334 NG
                   2459.2 ANGLE               D
                           2744.013 5738.134 478.1778 RIVE
                                                       100651.5
                              Sub-total for B
     C.                       Total (A+B)
                                  480.00
      D.    Output/day
            Sub-total for E
     F.     Direct Cost (C+E)
     G.     Overhead, Contingencies and Miscellaneous Contractor's Profit (CP)
            Value Added Tax (VAT) Total Unit Cost                      10% per D.O 197 s 201
     H.                                                                8% per D.O 197 s 2016
     I.                                                                5% per D.O 197 s 2016
     J.
te           Amount
0            43200
0            32400
0            18900
            94,500.00
     P       Amount
te
               0.00
     P         0.00
     P      94,500.00
st Amount
00.00     ₱173,600.00
00.00     ₱76,000.00
50.00     ₱23,800.00
00.00     ₱140,600.00
00.00      ₱9,600.00
         423600.00
         518,100.00
         51810
6        41,448.00
         25,905.00
         637263.00
Item No./Description    : 1001 (1) Paintworks (Ground
Floor) Unit of Measurement     : sq.m.
Output per hour                       :
Quantity                 :    1,480.185
                  Sub-total                                                     P
                      for B
   C.                                                                           P
   D.         Output/da
                     480.00
              y
  22400
  33600
  19600
 75,600.00
Amount
 4,800.00
   0.00
 4,800.00
80,400.00
Amount
₱203,250.00
₱51,375.00
₱87,000.00
₱58,500.00
₱11,400.00
    411525.00
491,925.00
49192.5
39,354.00
24,596.25
    605067.75
Item No./Description    : 1001 (2) Paintworks (Second
Floor) Unit of Measurement     : sq.m.
Output per hour                         :
Quantity                 :    1645.24
                  Sub-total                                                       P
                      for B
   C.                                                                             P
   D.         Output/da
                     480.00
              y
                  Sub-total
                      for E
  F.      Direct                          DETAILED UNIT PRICE
          Cost                            ANALYSIS
PROJECT NAME         CBC DORMITORY
          (C+E)
                                                               10%
  G.       Overhead, Contingencies and Miscellaneous               per D.O 197 s
  H.       2016
         Contractor                               8% per D.O 197 s 2016
         's Profit
         (CP)
  I.     Value                                   5% per D.O 197 s 2016
         Added
         Tax (VAT)
  J.     Total
         Unit
         Cost
 Amount
  24000
  36000
  21000
 81,000.00
Amount
 4,800.00
   0.00
 4,800.00
85,800.00
Amount
₱224,930.00
₱56,855.00
₱96,280.00
₱64,740.00
₱12,920.00
455725.00
    541,525.00
54152.5
43,322.00
27,076.25
    666075.75
Item No./Description    : 1001 (3) Paintworks (Third
Floor) Unit of Measurement     : sq.m.
Output per hour                         :
Quantity                 :    1576.24
                  Sub-total                                                       P
                      for B
   C.                                                                             P
   D.         Output/da
                     480.00
              y
  24000
  36000
  21000
 81,000.00
Amount
 4,800.00
   0.00
 4,800.00
85,800.00
Amount
₱214,090.00
₱54,115.00
₱91,640.00
₱61,620.00
₱12,160.00
    433625.00
519,425.00
51942.5
41,554.00
25,971.25
    638892.75
                                                       DETAILED UNIT PRICE ANALYSIS
PROJECT NAME          CBC DORMITORY
                      Sub-total for B
C.                    Total (A+B)
                        480.00
D.      Output/day
        Sub-total for E
F.      Direct Cost (C+E)
G.      Overhead, Contingencies and Miscellaneous
                                                                              10%   per D.O 197 s 201
H.   Contractor's Profit (CP)                              8% per D.O 197 s 2016
I.   Value Added Tax (VAT)                                 5% per D.O 197 s 2016
J.   Total Unit Cost
0             25600
0             76800
0             33600
            136,000.00
     P       Amount
te
               0.00
     P         0.00
     P      136,000.00
st Amount
0.00        ₱1,080.00
0.00        ₱3,040.00
0.00        ₱6,240.00
7.00       ₱10,275.00
0.00       ₱20,700.00
99.00      ₱41,998.00
9.00        ₱5,890.00
.00         ₱1,470.00
60.00      ₱81,880.00
50.00      ₱25,250.00
40.00      ₱15,520.00
10.00      ₱117,990.00
4.00       ₱15,466.00
1.00        ₱2,510.00
1.00        ₱4,016.00
         353325.00
         489,325.00
         48932.5
6
39,146.00
24,466.25
601869.75
                                         DETAILED UNIT PRICE ANALYSIS
PROJECT NAME          CBC DORMITORY
       Sub-total for A
       Name and Capacity                                No. of         No. of Days                Daily Ra
                                                        Equip.
BEquipment, (2014 ACEL Rates)
a. Excavators218.0027,032.0
b. Payloader218.0013,864.0
c. Compactor36.0013,865.0
d. Bulldozer218.0013,864.0
e. Dumptruck518.0011,360.0
f. Circle Saw Bar cutter314.00400
                        Sub-total for B
C.                      Total (A+B)
                          480.00
D.       Output/day
         Sub-total for E
F.       Direct Cost (C+E)
G.       Overhead, Contingencies and Miscellaneous
                                                                                    10%   per D.O 197 s 201
H.   Contractor's Profit (CP)   8% per D.O 197 s 2016
I.   Value Added Tax (VAT)      5% per D.O 197 s 2016
J.   Total Unit Cost
te                  Amount
 0                  60800
 0                  136800
0                   93100
       P           290,700.00
te                  Amount
0                  973,152.00
0                  166,368.00
0             249,570.00
0                  499,104.00
0                 1,022,400.00
.00                 16,800.00
                      0.00
       P          2,927,394.00
       P          3,218,094.00
st Amount
₱15,750.00
0.00
₱16,500.00
00.00
₱74,000.00
00.00
₱62,000.00
00.00
₱108,000.00
5.00
₱887,500.00
8.00
₱83,276.00
                       54.6
49                     36.4
63                       28
                       53.2
         3831280.00
        7,049,374.00
6    704937.4
563,949.92
352,468.70
8670730.02