National Highways Authority of India
Schedule - H
                                        (See Clauses10.1 (iv) and 19.3)
                                         Contract Price Weightages
     1.1        The Contract Price for this Agreement is Rs. *****
     1.2        Proportions of the Contract Price for different stages of Construction of the Project
                Highway shall be as specified below:
                              Weightage
                            in percentage                                                          Percentage
           Item                                              Stage for Payment
                           to the Contract                                                         weightage
                                Price
            1                     2                                    3                                4
  Road works                   18.15%        A- Widening and strengthening of existing road
  including culverts,
                                             (1) Earthwork up to top of the sub-grade                       -
  widening and repair
  of culverts.                               (2) Sub-base Course                                            -
                                             (3) Non-Bituminous Base Course                                 -
                                             (4) Bituminous Base Course                                     -
                                             (5) Wearing Coat                                               -
                                             (6) Widening and repair of culverts                            -
                                             B.1- Reconstruction/New       4-lane   realignment/
                                             bypass (flexible pavement)
                                             (1) Earthwork up to top of the sub-grade                       -
                                             (2) Sub-base Course                                            -
                                             (3) Non-Bituminous Base Course                                 -
                                             (4) Bituminous Base Course                                     -
                                             (5) Wearing Coat                                               -
                                             B.2- Reconstruction/New       4-lane   realignment/
                                             bypass (Rigid Pavement)
                                             (1) Earthwork up to top of the sub-grade                       -
                                             (2) Sub-base Course                                            -
                                             (3) Dry Lean Concrete (DLC) Course                             -
                                             (4) Pavement Quality Control (PQC) Course                      -
                                             C.1- Reconstruction/ New service road/Widening
                                             and Strengthening of Existing service Road/Slip
                                             Road (Flexible pavement)
                                             (1) Earthwork up to top of the sub-grade                   8.77%
Long Term Measures for rectification of 4 nos. MoRTH identified Accident
                                                                                            H-1 | P a g e
Blackspots on Jetpur - Somnath section of NH-151 in the state of Gujarat on EPC
Basis
                                                                     National Highways Authority of India
                            Weightage
                          in percentage                                                              Percentage
          Item                                              Stage for Payment
                         to the Contract                                                             weightage
                              Price
           1                   2                                      3                                  4
                                           (2) Sub-base Course                                          19.37%
                                           (3) Non-Bituminous Base Course                               20.28%
                                           (4) Bituminous Base Course                                   27.81%
                                           (5) Wearing Coat                                             18.62%
                                           C.2- Reconstruction/ New Service Road/ (Rigid
                                           Pavement)
                                           (1) Earthwork up to top of the sub-grade                           -
                                           (2) Sub-base Course                                                -
                                           (3) Dry Lean Concrete (DLC) Course                                 -
                                           (4) Pavement Quality Control (PQC) Course                          -
                                           D- Re-Construction and New culverts on existing
                                           road, realignments, bypasses:
                                           Culverts (length < 6 m)                                       3.50%
                                           E- Widening and repair of culverts
                                           Culverts                                                      1.65%
  Minor Bridge/             11.03%         A.l- Widening and Repair of Minor bridges
  Underpasses/                             (length> 6 m and < 60 m)
  Overpasses                               Minor bridges                                                 4.64%
                                           A.2- New Minor bridges/Additional New
                                           Bridges/Reconstruction of Existing bridge (length
                                           >6 and <60 m.)
                                           (1) Foundation + Sub-structure: On completion of             27.93%
                                           the foundation work including foundations for wing
                                           and return walls, abutments, piers upto the
                                           abutment/pier cap.
                                           (2) Super-structure: On completion of the                     8.77%
                                           superstructure in all respects including wearing coat,
                                           bearings, expansion joints, hand rails, Crash barriers,
                                           road signs & markings, tests on completion etc.
                                           complete in all respect.
                                           (3) Approaches: On completion of approaches                   8.36%
                                           including Retaining walls, stone pitching, protection
                                           works complete in all respect, tests on completion in
                                           all respect and fit for use.
                                           (4) Guide Bunds and River Training Works: On
Long Term Measures for rectification of 4 nos. MoRTH identified Accident
                                                                                             H-2 | P a g e
Blackspots on Jetpur - Somnath section of NH-151 in the state of Gujarat on EPC
Basis
                                                                      National Highways Authority of India
                             Weightage
                           in percentage                                                                Percentage
          Item                                                Stage for Payment
                          to the Contract                                                               weightage
                               Price
            1                   2                                      3                                    4
                                            completion of Guide Bunds and river Training                         -
                                            Works complete in all respects
                                            B.1- Widening and Repair of underpasses/
                                            overpasses                                                           -
                                            Underpasses/ Overpasses
                                                                                                                 -
                                            B.2- New underpasses/ overpasses
                                            (1) Foundation + Sub-structure: On completion of               16.48%
                                            the foundation work including foundations for wing
                                            and return walls, abutments, piers upto the
                                            abutment/pier cap.
                                            (2) Super-structure: On completion of the                       4.93%
                                            superstructure in all respects including wearing coat,
                                            bearings, expansion joints, hand rails, crash barriers,
                                            road signs & markings, tests on completion etc.
                                            complete             in           all           respect.
                                            Wearing Coat (a) in case of Overpass - wearing coat
                                            including expansion joints complete in all respects as
                                            specified and (b) in case of underpass- rigid
                                            pavement         including       drainage        facility
                                            complete in all respects as specified as specified.
                                            (3) Approaches: On completion of approaches                    28.89%
                                            including Retaining walls/ Reinforced Earth walls,
                                            stone pitching, protection works complete in all
                                            respect and fit for use.
  Major bridge               48.59%         A.1- Widening and repairs of Major Bridges
  (length>60 m)
                                            (1) Foundation                                                       -
  works and
  ROB/RUB/elevated                          (2) Sub- Structure                                                   -
  sections/Flyovers                         (3) Super-structure (including bearings)                             -
  including viaduct, if
                                            (4) Wearing Coat including expansion joints                          -
  any
                                            (5) Miscellaneous Items like hand rails, crash                       -
                                            barriers, road markings etc.)
                                            (6) Wing walls/return walls                                          -
                                            (7) Guide Bunds, River Training works etc.                           -
                                            (8) Approaches (including Retaining walls, stone                     -
                                            pitching and protection works)
Long Term Measures for rectification of 4 nos. MoRTH identified Accident
                                                                                                H-3 | P a g e
Blackspots on Jetpur - Somnath section of NH-151 in the state of Gujarat on EPC
Basis
                                                                   National Highways Authority of India
                            Weightage
                          in percentage                                                          Percentage
          Item                                              Stage for Payment
                         to the Contract                                                         weightage
                              Price
           1                   2                                     3                                4
                                           A.2- New Major bridges                                         -
                                           (1) Foundation                                                 -
                                           (2) Sub- Structure                                             -
                                           (3) Super-structure (including bearings)                       -
                                           (4) Wearing Coat including expansion joints                    -
                                           (5) Miscellaneous Items like hand rails, crash                 -
                                           barriers, road markings etc.)
                                           (6) Wing walls/return walls                                    -
                                           (7) Guide Bunds, River Training works etc.                     -
                                           (8) Approaches (including Retaining walls, stone               -
                                           pitching and protection works)
                                           B.l- Widening and repair of ROB/ RUB
                                           (1) Foundation                                                 -
                                           (2) Sub-structure                                              -
                                           (3) Super-structure (including bearings)                       -
                                           (4) Wearing Coat (including expansion joints                   -
                                           complete in all respects as specified)
                                           (5) Miscellaneous Items like hand rails, crash                 -
                                           barriers, road markings etc.)
                                           (6) Wing walls/return walls                                    -
                                           (7) Approaches (including Retaining walls, stone               -
                                           pitching and protection works)
                                           B.2- New ROB/ RUB
                                           (1) Foundation                                                 -
                                           (2) Sub-structure                                              -
                                           (3) Super-structure (including bearings)                       -
                                           (4) Wearing Coat (including expansion joints                   -
                                           complete in all respects as specified)
                                           (5) Miscellaneous Items like hand rails, crash                 -
                                           barriers, road markings etc.)
                                           (6) Wing walls/return walls                                    -
                                           (7)      Approaches     (including     Retaining               -
                                           walls/Reinforced Earth wall, stone pitching and
                                           protection works)
Long Term Measures for rectification of 4 nos. MoRTH identified Accident
                                                                                          H-4 | P a g e
Blackspots on Jetpur - Somnath section of NH-151 in the state of Gujarat on EPC
Basis
                                                                      National Highways Authority of India
                            Weightage
                          in percentage                                                             Percentage
          Item                                               Stage for Payment
                         to the Contract                                                            weightage
                              Price
           1                   2                                       3                                 4
                                           C.1- Widening and repair of                  Elevated
                                           Section/Flyovers/ Grade Separators
                                           (1) Foundation                                                    -
                                           (2) Sub-structure                                                 -
                                           (3) Super-structure (including bearings)                          -
                                           (4) Wearing Coat including expansion joints                       -
                                           (5) Miscellaneous Items like hand rails, crash                    -
                                           barriers, road markings etc.)
                                           (6) Wing walls/return walls                                       -
                                           (7)      Approaches     (including     Retaining                  -
                                           walls/Reinforced Earth wall, stone pitching and
                                           protection works)
                                           C.2-New Elevated Section/Flyovers/ Grade
                                           Separators
                                           (1) Foundation                                                3.91%
                                           (2) Sub-structure                                             4.57%
                                           (3) Super-structure (including bearings)                      7.30%
                                           (4) Wearing Coat including expansion joints                   0.28%
                                           (5) Miscellaneous Items like hand rails, crash               16.76%
                                           barriers, road markings etc.)
                                           (6) Wing walls/return walls                                       -
                                           (7)      Approaches     (including     Retaining             67.19%
                                           walls/Reinforced Earth wall, stone pitching and
                                           protection works)
      Other works           20.57%         (i) Toll Plaza                                                    -
                                           (ii) Road side drains                                        22.56%
                                           (iii) Highway Lighting                                        7.98%
                                           (iv) Road signs, markings, km stones, safety devices         12.42%
                                           (Road Studs, Flexible Median Marker, Solar Blinker,
                                           Traffic Impact Attenuators, Kerb, etc)
                                           (v) Thrie Metal Beam Crash barrier                           16.05%
                                           (vi) Pedestrian Guard Rail                                   15.49%
                                           (vii) Project Facilities
Long Term Measures for rectification of 4 nos. MoRTH identified Accident
                                                                                             H-5 | P a g e
Blackspots on Jetpur - Somnath section of NH-151 in the state of Gujarat on EPC
Basis
                                                                         National Highways Authority of India
                             Weightage
                           in percentage                                                                   Percentage
          Item                                                  Stage for Payment
                          to the Contract                                                                  weightage
                               Price
            1                    2                                         3                                   4
                                            (a) Bus Bays with Passenger Shelter                                2.47%
                                            (b) Truck lay-byes                                                 1.32%
                                            (c) Rest Area
                                            (d) Others (Separator, Raised Footpath, Retaining                 13.55%
                                            wall, Toe wall etc)
                                            (viii) Roadside plantation
                                            (ix) Repair of protection works other than approaches                   -
                                            to the bridges, elevated sections/ flyovers/grade
                                            separators and ROBs/ RUBs
                                                                                                               1.38%
                                            (x) Safety      and        traffic   management       during
                                            construction
                                            (xi) Junction Development                                          6.79%
                               1.67%        (i) EHT line                                                            -
                                            (ii) EHT crossings                                                      -
   Electrical Utilities                     (iii) HT/LT Line                                                  90.50%
  and Public Health                         (iv) HT/LT crossings                                               9.17%
    Utilities (Water
                                            (v) Water pipeline                                                      -
  Pipelines & Sewage
         Lines)                             (vi) Water pipeline crossings                                      0.34%
                                            (vii) Sewage lines                                                      -
                                            (viii) Sewage line crossings                                            -
     1.3    Procedure of estimating the value of work done.
      1.3.4 Road works. Procedure for estimating the value of road work done shall be as follows:
                                            Table 1.3.1
                 Stage of Payment                     Weightage                     Payment Procedure
                          1                                 2                                 3
 A- Widening and strengthening of existing road
 (1) Earthwork up to top of the sub-grade                          -      --NA--
 (2) Sub-base Course                                               -
 (3) Non-Bituminous Base Course                                    -
Long Term Measures for rectification of 4 nos. MoRTH identified Accident
                                                                                                   H-6 | P a g e
Blackspots on Jetpur - Somnath section of NH-151 in the state of Gujarat on EPC
Basis
                                                                 National Highways Authority of India
                 Stage of Payment                   Weightage              Payment Procedure
                          1                             2                           3
 (4) Bituminous Base Course                                  -
 (5) Wearing Coat                                            -
 (6) Widening and repair of culverts                         -   --NA--
 B.1- Reconstruction/New 4-lane realignment/
 bypass (flexible pavement)
 (1) Earthwork up to top of the sub-grade                    -   --NA--
 (2) Sub-base Course                                         -
 (3) Non-Bituminous Base Course                              -
 (4) Bituminous Base Course                                  -
 (5) Wearing Coat                                            -
 B.2- Reconstruction/New 4-lane realignment/
 bypass (Rigid Pavement)
 (1) Earthwork up to top of the sub-grade                    -   --NA--
 (2) Sub-base Course                                         -
 (3) Dry Lean Concrete (DLC) Course                          -
 (4) Pavement Quality Control (PQC) Course                   -
 C.1- Reconstruction/ New service road/Widening
 and Strengthening of Existing service Road/Slip
 Road (Flexible pavement)
 (1) Earthwork up to top of the sub-grade               8.77% Unit of measurement is linear length.
                                                              Payment of each stage shall be made on
 (2) Sub-base Course                                   19.37%
                                                              pro rata basis on completion of a stage in
 (3) Non-Bituminous Base Course                        20.28% full length or One km length, whichever is
 (4) Bituminous Base Course                            27.81% less.
 (5) Wearing Coat                                      18.62%
 C.2- Reconstruction/ New Service Road/ (Rigid
 Pavement)
 (1) Earthwork up to top of the sub-grade                    -   --NA--
 (2) Sub-base Course                                         -
 (3) Dry Lean Concrete (DLC) Course                          -
 (4) Pavement Quality Control (PQC) Course                   -
 D- Re-Construction and New culverts on existing
 road, realignments, bypasses:
 Culverts (length < 6 m)                                3.50% Cost of each culvert shall be determined
                                                              on pro rata basis with respect to the total
 E- Widening and repair of culverts                     1.65%
                                                              number of culverts. Payment shall be
                                                              made on the completion of equivalent
Long Term Measures for rectification of 4 nos. MoRTH identified Accident
                                                                                        H-7 | P a g e
Blackspots on Jetpur - Somnath section of NH-151 in the state of Gujarat on EPC
Basis
                                                                       National Highways Authority of India
                 Stage of Payment                       Weightage                   Payment Procedure
                           1                                   2                            3
                                                                       width of 2 lane carriageway .
    @. For example, if the total length of bituminous work to be done is 100 km, the cost per km of
    bituminous work shall be determined as follows:
    Cost per km = P x weightage for road work x weightage for bituminous work x (1/L)
    Where    P= Contract Price
             L = Total length in km
    Similarly, the rates per km for other stages shall be worked out accordingly.
    Note:
       The length affected due to law-and-order problems or litigation during execution due to
       which the Contractor is unable to execute the work, may be deducted from the total project
       length for payment purposes. The total length calculated here is only for payment purposes
       and will not affect and referred to in other clauses of the Contract Agreement.
    1.3.2    Minor Bridges and Underpasses/Overpasses.
    Procedure for estimating the value of Minor bridge and Underpasses/Overpasses shall be as stated in
    table 1.3.2:
                                                 Table 1.3.2
               Stage of Payment               Weightage                      Payment Procedure
                       1                           2                                    3
     A.l- Widening and Repair of Minor
     bridges (length> 6 m and < 60 m)
     Minor bridges                                 4.64% Cost of each minor bridge shall be determined on pro
                                                         rata basis with respect to the total linear length of the
                                                         minor bridges. Payment shall be made on the
                                                         completion of widening & repair works of a minor
                                                         bridge.
     A.2- New Minor bridges/Additional
     New Bridges/Reconstruction of
     Existing bridge (length >6 and <60
     m.)
     (1) Foundation + Sub-structure: On          27.93% Foundation + Sub-Structure: Cost of each minor
     completion of the foundation work                  bridge shall be determined on pro- rata basis with
     including foundations for wing and                 respect to the total linear length (m) of the minor
     return walls, abutments, piers upto                bridges. Payment against foundation +sub-structure
     the abutment/pier cap.                             shall be made on pro-rata basis on completion of a
                                                        stage i.e. not less than 25% of the scope of foundation
                                                        +Sub structure of each bridge subject to completion of
                                                        at least two foundations along with sub-structure up to
                                                        abutment/ pier cap level of each bridge.
Long Term Measures for rectification of 4 nos. MoRTH identified Accident
                                                                                                H-8 | P a g e
Blackspots on Jetpur - Somnath section of NH-151 in the state of Gujarat on EPC
Basis
                                                                    National Highways Authority of India
              Stage of Payment                Weightage                  Payment Procedure
                       1                          2                                3
                                                       In case where load testing is required for foundation,
                                                       the trigger of first payment shall include load testing
                                                       also where specified.
     (2) Super-structure: On completion of       8.77% Super-structure: Payment shall be made on pro-rata
     the superstructure in all respects                basis on completion of a stage i.e., completion of
     including wearing coat, bearings,                 super-structure of at least one span in all respects as
     expansion joints, hand rails, Crash               specified in the column of “Stage of Payment” In this
     barriers, road signs & markings, tests            sub-clause excluding any payment made in pursuance
     on completion etc. complete in all                to              here             in               under:
     respect.                                          If precast girders/segments are used, on casting of all
                                                       such girders and segments for at least one span and on
                                                       submission of Indemnity Bond by the Contractor,
                                                       40% of the actual cost of such precast
                                                       girders/segments determined based on SoR prevalent
                                                       on the Base date within 30 days of submission of the
                                                       bill therefor. In case the Contract Price is lower/
                                                       higher than the Estimated Project Cost as per RFP,
                                                       then the SOR rates shall be reduced/ increased in the
                                                       same proportion accordingly. Balance payment shall
                                                       be after erection of / launching of these elements as
                                                       per stage payment stipulations.
     (3) Approaches: On completion of            8.36% Approaches: Payment shall be made on pro-rata
     approaches     including Retaining                basis on completion of a stage i.e. completion of
     walls, stone pitching, protection                 approaches in all respect as specified in the column of
     works complete in all respect, tests              “Stage of Payment” in this sub-clause.
     on completion in all respect and fit
     for use.
     (4) Guide Bunds and River Training               -   --NA--
     Works: On completion of Guide
     Bunds and river Training Works
     complete in all respects
     B.1- Widening and Repair of
     underpasses/ overpasses
     Underpasses/ Overpasses                          -   --NA--
     B.2- New underpasses/ overpasses
     (1) Foundation + Sub-structure: On         16.48% Foundation +Sub- Structure: Cost of each
     completion of the foundation work                 Underpass/Overpass shall be determined on pro
     including foundations for wing and                rata basis with respect to the total linear length
     return walls, abutments, piers upto               (m)        of     the      Underpasses/Overpasses.
     the abutment/pier cap.                            Payment against foundation + sub- structure shall be
                                                       made on pro-rata basis on completion of a stage i.e.
                                                       not less than 25% of the scope of foundation + sub-
                                                       structure of each Underpasses/Overpasses subject to
Long Term Measures for rectification of 4 nos. MoRTH identified Accident
                                                                                            H-9 | P a g e
Blackspots on Jetpur - Somnath section of NH-151 in the state of Gujarat on EPC
Basis
                                                                    National Highways Authority of India
              Stage of Payment                Weightage                  Payment Procedure
                       1                          2                                3
                                                       completion of at least two foundations along with
                                                       sub-structure up to abutment/pier cap level each
                                                       underpass/                                    overpass.
                                                       In case where load testing is required for foundation,
                                                       the trigger of first payment shall include load testing
                                                       also where specified.
     (2) Super-structure: On completion of       4.93% Super-structure: Payment shall be made on pro-rata
     the superstructure in all respects                basis on completion of a stage i.e., completion of
     including wearing coat, bearings,                 super-structure of at least length equivalent to two
     expansion joints, hand rails, crash               lane width carriageway as specified in the column of
     barriers, roadsigns & markings, tests             “Stage of Payment” In this sub-clause excluding any
     on completion etc. complete in all                payment made in pursuance to here in under:
     respect.                                          If precast girders/segments are used, on casting of all
     Wearing Coat (a) in case of Overpass              such girders and segments for at least one span and on
     - wearing coat including expansion                submission of Indemnity Bond by the Contractor,
     joints complete in all respects as                40% of the actual cost of such precast
     specified and (b) in case of                      girders/segments determined based on SoR prevalent
     underpass- rigid pavement including               on the Base date within 30 days of submission of the
     drainage                      facility            bill therefor. In case the Contract Price is lower/
     complete in all respects as specified             higher than the Estimated Project Cost as per RFP,
     as specified.                                     then the SOR rates shall be reduced/ increased in the
                                                       same proportion accordingly. Balance payment shall
                                                       be after erection of / launching of these elements as
                                                       per stage payment stipulations.
     (3) Approaches: On completion of           28.89% Approaches: Payment shall be made on pro-rata
     approaches      including Retaining               basis on completion of a stage i.e. completion of one
     walls/ Reinforced Earth walls, stone              side approach of at least one structures approaches in
     pitching, protection works complete               all respect as specified excluding any payment made
     in all respect and fit for use.                   in pursuance to here in under: If Reinforced Earth
                                                       Wall is used with Fascia Panels/Blocks, on casting of
                                                       all the Fascia Panels/Blocks of all approaches and on
                                                       submission of Indemnity Bond by the Contractor,
                                                       40% of the actual cost of such precast
                                                       girders/segments determined based on SoR prevalent
                                                       on the Base date within 30 days of submission of the
                                                       bill therefor. In case the Contract Price is
                                                       lower/higher than the Estimated Project Cost as per
                                                       RFP, then the SOR rates shall be reduced/ increased
                                                       in the same proportion accordingly. Balance payment
                                                       shall be after erection of/ launching of these elements
                                                       as per stage payment stipulations.
     1.3.3   Major Bridge works ROB/RUB and Structures.
             Procedure for estimating the value of Major Bridge works, ROB/RUB and Structures
Long Term Measures for rectification of 4 nos. MoRTH identified Accident
                                                                                          H-10 | P a g e
Blackspots on Jetpur - Somnath section of NH-151 in the state of Gujarat on EPC
Basis
                                                                         National Highways Authority of India
             shall be as stated in table 1.3.3:
                                                  Table 1.3.3
              Stage of Payment                    Weightage                    Payment Procedure
                          1                            2                                 3
     A.1- Widening and repairs of
     Major Bridges
     (1) Foundation                                         -   --NA--
     (2) Sub- Structure                                     -   --NA--
     (3)     Super-structure     (including                 -   --NA--
     bearings)
     (4) Wearing Coat including expansion                   -   --NA--
     joints
     (5) Miscellaneous Items like hand                      -   --NA--
     rails, crash barriers, road markings
     etc.)
     (6) Wing walls/return walls                            -   --NA--
     (7) Guide Bunds, River Training                        -   --NA--
     works etc.
     (8) Approaches (including Retaining                    -   --NA--
     walls, stone pitching and protection
     works)
     A.2- New Major bridges
     (1) Foundation                                         -   --NA--
     (2) Sub- Structure                                     -   --NA--
     (3)     Super-structure     (including                 -   --NA--
     bearings)
     (4) Wearing Coat including expansion                   -   --NA--
     joints
     (5) Miscellaneous Items like hand                      -   --NA--
     rails, crash barriers, road markings
     etc.)
     (6) Wing walls/return walls                            -   --NA--
     (7) Guide Bunds, River Training                        -   --NA--
     works etc.
     (8) Approaches (including Retaining                    -   --NA--
     walls, stone pitching and protection
     works)
     B.l- Widening and repair of ROB/
     RUB
     (1) Foundation                                         -   --NA--
     (2) Sub-structure                                      -   --NA--
Long Term Measures for rectification of 4 nos. MoRTH identified Accident
                                                                                               H-11 | P a g e
Blackspots on Jetpur - Somnath section of NH-151 in the state of Gujarat on EPC
Basis
                                                                   National Highways Authority of India
              Stage of Payment                Weightage                  Payment Procedure
                         1                        2                                3
     (3)     Super-structure     (including           -   --NA--
     bearings)
     (4)    Wearing      Coat    (including           -   --NA--
     expansion joints complete in all
     respects as specified)
     (5) Miscellaneous Items like hand                -   --NA--
     rails, crash barriers, road markings
     etc.)
     (6) Wing walls/return walls                      -   --NA--
     (7) Approaches (including Retaining              -   --NA--
     walls, stone pitching and protection
     works)
     B.2- New ROB/ RUB
     (1) Foundation                                   -   --NA--
     (2) Sub-structure                                -   --NA--
     (3)     Super-structure     (including           -   --NA--
     bearings)
     (4)    Wearing      Coat    (including           -   --NA--
     expansion joints complete in all
     respects as specified)
     (5) Miscellaneous Items like hand                -   --NA--
     rails, crash barriers, road markings
     etc.)
     (6) Wing walls/return walls                      -   --NA--
     (7) Approaches (including Retaining              -   --NA--
     walls/Reinforced Earth wall, stone
     pitching and protection works)
     C.1- Widening and repair of
     Elevated Section/Flyovers/ Grade
     Separators
     (1) Foundation                                   -   --NA--
     (2) Sub-structure                                -   --NA--
     (3)     Super-structure     (including           -   --NA--
     bearings)
     (4) Wearing Coat including expansion             -   --NA--
     joints
     (5) Miscellaneous Items like hand                -   --NA--
     rails, crash barriers, road markings
     etc.)
     (6) Wing walls/return walls                      -   --NA--
Long Term Measures for rectification of 4 nos. MoRTH identified Accident
                                                                                         H-12 | P a g e
Blackspots on Jetpur - Somnath section of NH-151 in the state of Gujarat on EPC
Basis
                                                                  National Highways Authority of India
              Stage of Payment              Weightage                    Payment Procedure
                         1                      2                                 3
     (7) Approaches (including Retaining            -    --NA--
     walls/Reinforced Earth wall, stone
     pitching and protection works)
     C.2-New Elevated Section/Flyovers/
     Grade Separators
     (1) Foundation                             3.91% Foundation: Cost of each structure shall be
                                                      determined on pro rata basis with respect to the total
                                                      linear length (m) of the structure. Payment against
                                                      foundation shall be made on pro-rata basis on
                                                      completion of a stage i.e. not less than 25% of the
                                                      scope of foundation of the structure subject to
                                                      completion of at least two foundations of the
                                                      structure.
                                                      In case where load testing is required for foundation,
                                                      the trigger of first payment shall include load testing
                                                      also where specified.
     (2) Sub-structure                          4.57% Sub-Structure: Payment against Sub-Structure shall
                                                      be made on pro-rata basis on completion of a stage
                                                      i.e. not less than 25% of the scope of sub- structure of
                                                      the structure subject to completion of at least two sub-
                                                      structures of abutments/piers up to abutment/pier cap
                                                      level of the structure.
     (3)    Super-structure    (including       7.30% Super-structure: Payment shall be made on pro-rata
     bearings)                                        basis on completion of a stage i.e., completion of
                                                      super-structure of at least one span equivalent to two
                                                      lane width of carriageway in all respects as specified
                                                      in the column of “Stage of Payment” In this sub-
                                                      clause excluding any payment made in pursuance to
                                                      here in under: If precast girders/segments are used, on
                                                      casting of all such girders and segments for at least
                                                      one span and on submission of Indemnity Bond by the
                                                      Contractor, 40% of the actual cost of such precast
                                                      girders/segments determined based on SoR prevalent
                                                      on the Base date within 30 days of submission of the
                                                      bill therefor. In case the Contract Price is lower/
                                                      higher than the Estimated Project Cost as per RFP,
                                                      then the SOR rates shall be reduced/ increased in the
                                                      same proportion accordingly. Balance payment shall
                                                      be after erection of / launching of these elements as
                                                      per stage payment stipulations.
     (4) Wearing Coat including expansion       0.28% Wearing Coat: Payment shall be made on completion
     joints                                           of wearing coat including expansion joints complete
                                                      in all respects as specified
     (5) Miscellaneous Items like hand         16.76% Miscellaneous: Payments shall be made on
Long Term Measures for rectification of 4 nos. MoRTH identified Accident
                                                                                        H-13 | P a g e
Blackspots on Jetpur - Somnath section of NH-151 in the state of Gujarat on EPC
Basis
                                                                        National Highways Authority of India
                   Stage of Payment             Weightage                      Payment Procedure
                          1                          2                                  3
     rails, crash barriers, road markings                  completion of all miscellaneous works like hand rails,
     etc.)                                                 crash barriers, road markings etc. complete in all
                                                           respects as specified.
     (6) Wing walls/return walls                         - Wing walls/return walls: Payments shall be made on
                                                           completion of all wing walls/return walls complete in
                                                           all respects as specified.
     (7) Approaches (including Retaining            67.19% Approaches: Payments shall be made on completion
     walls/Reinforced Earth wall, stone                    of at least one approaches including stone pitching,
     pitching and protection works)                        protection works, etc. complete in all respects as
                                                           specified excluding any payment made in pursuance
                                                           to here in under:
                                                           If Reinforced Earth Wall is used with Facia
                                                           Panels/Blocks, on casting of all the Facia
                                                           Panels/Blocks of all approaches and on submission of
                                                           Indemnity Bond by the Contractor, 40% of the actual
                                                           cost of such precast girders/segments determined
                                                           based on SoR prevalent on the Base date within 30
                                                           days of submission of the bill therefor. In case the
                                                           Contract Price is lower/ higher than the Estimated
                                                           Project Cost as per RFP, then the SOR rates shall be
                                                           reduced/ increased in the same proportion
                                                           accordingly. Balance payment shall be after erection
                                                           of / launching of these elements as per stage payment
                                                           stipulations.
     1.3.4    Other works.
                   Procedure for estimating the value of other works done shall be as stated in table
                   1.3.4:
                                                         Table 1.3.4
                         Stage of Payment          Weightage                           Payment Procedure
                          1                              2                               3
  (i) Toll Plaza                                               -   --NA--
  (ii) Roadside drains                                   22.56% Unit of measurement is linear length in km.
                                                                Payment shall be made on pro rata basis on
                                                                completion of a stage in a length of not less than
                                                                10 % (ten per cent) of the total length
  (iii) Highway Lighting                                  7.98% Payment shall be made on pro rata basis for
                                                                completed facilities.
  (iv) Road signs, markings, km stones,                  12.42% Unit of measurement is linear length in km.
  safety devices (Road Studs, Flexible                          Payment shall be made on pro rata basis on
  Median Marker, Solar Blinker, Traffic                         completion of a stage in a length of not less than
  Impact Attenuators, Kerb, etc)                                10 % (ten per cent) of the total length
Long Term Measures for rectification of 4 nos. MoRTH identified Accident
                                                                                              H-14 | P a g e
Blackspots on Jetpur - Somnath section of NH-151 in the state of Gujarat on EPC
Basis
                                                                             National Highways Authority of India
                         Stage of Payment               Weightage                            Payment Procedure
                          1                                 2                                  3
  (v) Thrie Metal Beam Crash barrier                        16.05%
  (vi) Pedestrian Guard Rail                                15.49%
  (vii) Project Facilities                                              Payment shall be made on pro rata basis for
                                                                        completed facilities.
  (a) Bus Bays with Passenger Shelter                        2.47%
  (b) Truck lay-byes                                         1.32%
   (c) Rest Area                                                    -
  (d) Others (Separator, Raised Footpath,                   13.55%
  Retaining wall, Toe wall etc)
  (viii) Roadside plantation                                        -   --NA--
  (ix) Repair of protection works other than                        -   --NA--
  approaches to the bridges, elevated
  sections/ flyovers/grade separators and
  ROBs/ RUBs
  (x) Safety and traffic management during                   1.38% Payment shall be made on pro rata basis every
  construction                                                     six months.
  (xi) Junction Development                                  6.79% Payment shall be made on pro rata basis for
                                                                   completion of development of At grade junction
                                                                   below the structures and other Major/ Minor at
                                                                   grade junctions.
     1.3.5         Electrical utilities and public health utilities (water pipelines and sewage lines)
                   Procedure for estimating the value of Electrical utilities and public health utilities (water
                   pipelines and sewage lines) done shall be as stated in table 1.3.5:
                                                         Table 1.3.5
         Stage of Payment              Weightage                                 Payment Procedure
                   1                         2                                           3
    (i) EHT line                                    -     --NA--
    (ii) EHT crossings                              -     --NA--
    (iii) HT/LT Line                         90.50% Unit of measurement is as per completed activities. Cost per
                                                    activity shall be determined on pro-rata basis as per its
                                                    weightage with reference to total cost of LT/HT line. Payment
                                                    shall be made for completed activity. (The average weightage
                                                    of major activities (only for payment purpose) in shifting work
                                                    is (i) Erection of Poles-20%, (ii) Conductor stringing including
                                                    laying of cable-30%. (iii) DTR erection (if involved)-10% and
                                                    (iv) Charging of line including dismantling and site clearance-
                                                    40% (with DTR) and 50% (without DTR)
    (iv) HT/LT crossings                      9.17% Cost of each crossing shall be determined on pro-rata basis
Long Term Measures for rectification of 4 nos. MoRTH identified Accident
                                                                                                    H-15 | P a g e
Blackspots on Jetpur - Somnath section of NH-151 in the state of Gujarat on EPC
Basis
                                                                         National Highways Authority of India
           Stage of Payment          Weightage                              Payment Procedure
                  1                       2                                          3
                                                       with reference to total no. of crossings. Payment shall be made
                                                       for not less than 25% of the crossings subject to a minimum of
                                                       10 crossings.
    (v) Water pipeline                             -    --NA--
    (vi) Water pipeline                       0.34% Cost of each crossing shall be crossing determined on pro-rata
    crossings                                       basis with reference to total no. of crossings. Payment shall be
                                                    made for not less than 25% of the crossings.
    (vii) Sewage lines                            - --NA--
    (viii) Sewage line crossings                   -   --NA--
      2.       Procedure for payment for Maintenance
      2.1      The cost for maintenance shall be as stated in Clause 14.1.1.
      2.2      Payment for Maintenance shall be made in               quarterly installments in accordance
               with the provisions of Clause 19.7.
Long Term Measures for rectification of 4 nos. MoRTH identified Accident
                                                                                                H-16 | P a g e
Blackspots on Jetpur - Somnath section of NH-151 in the state of Gujarat on EPC
Basis