Schedule B
Schedule B
Schedule B
Long Term Measures for rectification of 4 nos. MoRTH identified Accident Blackspots
B-1 | P a g e
on Jetpur - Somnath section of NH-151 in the state of Gujarat on EPC Basis
National Highways Authority of India
Schedule - B
Development of the Project Highway shall include design and construction of the Project Highway as
described in this Schedule-B and in Schedule-C.
Four lane divided carriageway with paved shoulder shall include new construction as described in
Annex-I of this Schedule-B and in Schedule-C.
The Project Highway shall be designed and constructed in conformity with the Specifications and
Standards specified in Annex-I of Schedule-D.
Long Term Measures for rectification of 4 nos. MoRTH identified Accident Blackspots
B-2 | P a g e
on Jetpur - Somnath section of NH-151 in the state of Gujarat on EPC Basis
National Highways Authority of India
Annex – I
(Schedule – B)
The project work includes Long Term Measures for rectification of 4 nos. of MoRTH identified
Accident Blackspots on Jetpur-Somnath section of NH-151 in the state of Gujarat on EPC Basis. The
details of location are Sorath at Ch.13+255 Km, Keshod at Ch. 64+077 Km, Gadu at Ch. 97+800 and
98+000 Km and Santipara Patiya from Ch. 100+700 to Ch. to 103+195 Km.
The Project Highway shall generally follow the horizontal alignment shown in the plan specified in
Annex- III of Schedule-A, unless otherwise specified by the Authority. Notwithstanding anything to
the contrary contained in this Agreement or IRC:SP:84 -2019, the proposed plan & profile, locations of
different structures/drains/service & slip road/RE walls, chainages of different structures/drains/service
& slip road/RE walls, length of different structures/drains/service & slip road/RE walls etc. of the
project highway as indicated in the Schedule A, Schedule B, Schedule C and their Annexures shall be
treated as minimum requirement. Based on site/design requirement, the EPC Contractor shall finalize
their Detailed Designs (Development Stage) including plan & profile of the project highway and submit
the same to Authority & its Engineer for its Consent/Approval and Safety Audit by Safety Auditor /
Expert, before the start of the execution of project. The designs so approved shall not be in
contradiction with the scope of project. For avoidance of doubt, the provisions mentioned in schedule B
& C cannot be changed, only the design of the components is to be submitted for consent/ approval.
a) Four Lane with paved side shoulders shall be undertaken. The paved Carriageway width shall be as
per TCS drawings/ schedule given in Appendix B1.
b) Except as otherwise provided in this Agreement, the width of the paved carriageway and cross-
sectional features shall conform to paragraph above.
c) The entire cross-sectional elements shall be accommodated in the available/proposed ROW. If
required, suitable retaining structures shall be provided to accommodate the highway cross section
within the available/ proposed ROW and the same shall not constitute a Change of Scope, save and
except any variations in the length arising out of a Change of Scope expressly undertaken in
accordance with the provisions of Article 13 of the EPC Contract Agreement.
Long Term Measures for rectification of 4 nos. MoRTH identified Accident Blackspots
B-3 | P a g e
on Jetpur - Somnath section of NH-151 in the state of Gujarat on EPC Basis
National Highways Authority of India
a) The width of median including kerb shyness shall be 2.5/3/5 meter as per TCS drawings given
in Appendix B1.
b) A minimum of 0.5 metre width adjacent to carriageway in either direction shall be paved.
c) Median shall be paved with PCC of minimum thickness of 75mm along with sand filling as per
applicable TCS.
Note:
• Carriageway width of slip roads or service road shall be as per this Schedule. The width of bus
bays, Truck lay-bye shall as be mentioned in Schedule C.
• Proper tapering shall be provided at merging and diverging points (Start and End) as per fig
2.1A and 2.1C of IRC: SP:84-2019 and relevant MoRT&H circulars. Any structure falling
within these stretches shall be widened to required width.
• The width of carriageway in case of structure shall be as per this Schedule B and GADs
provided in Annex-III of Schedule A.
(i) General:
Geometric design and general features of the Project Highway shall be in accordance with IRC: SP:84-
2019.
In general, the contractor shall adopt ruling design speed (i.e100kmph) for designing the project
highway in conformity with the provisions of the manual & as specified in the Plan and Profile
drawings of Annex-III of Schedule-A and in Annex-I of Schedule D. Minimum design speed shall be
adopted for the stretches indicated as deviation in Schedule D.
a) In the sections, where improvement of the existing road geometrics to the prescribed standards
is not possible, the existing road geometrics shall be improved to the extent possible within the
given right of way and appropriate road signs, pavement markings and safety measures shall be
provided.
Long Term Measures for rectification of 4 nos. MoRTH identified Accident Blackspots
B-4 | P a g e
on Jetpur - Somnath section of NH-151 in the state of Gujarat on EPC Basis
National Highways Authority of India
b) The entire cross-sectional elements shall be accommodated in the available /proposed ROW. If
required, suitable full height retaining structures shall be provided to accommodate the highway
cross section within the available/proposed ROW.
c) Realignments/Curve Improvement:
The existing road shall be improved to the standards as specified in the manual at the following
locations:
d) Bypasses:
The existing road shall be bypassed to the standards as specified in the manual at the following
locations:
Details of Right of Way are given in Annex– II of Schedule-A. However, details of proposed Right of
Way along main carriageway are given below.
Long Term Measures for rectification of 4 nos. MoRTH identified Accident Blackspots
B-5 | P a g e
on Jetpur - Somnath section of NH-151 in the state of Gujarat on EPC Basis
National Highways Authority of India
For junction improvement locations, additional land shall be acquired as per design in accordance with
applicable IRC/MORTH specifications and prevailing NHAI/MORTH policy guidelines in the matter.
a) The Design Specification of paved shoulder shall conform to the requirements specified in
paragraph 5.10 of the manual.
b) Paved shoulders and strip on median side shall be of same specification and pavement
composition as of main carriageway.
c) The overlay on the main carriageway pavement and on the paved shoulders shall be uniform in
thickness and composition.
e) Design and specifications of paved shoulders shall conform to the requirements specified in the
relevant Manual.
a) In case of VUP/ LVUP, the proposed structure, the finish road level in VUP/ LVUP shall be kept
150 mm above the bituminous/paved cross road to ensure that these VUP/ LVUP don’t become
Long Term Measures for rectification of 4 nos. MoRTH identified Accident Blackspots
B-6 | P a g e
on Jetpur - Somnath section of NH-151 in the state of Gujarat on EPC Basis
National Highways Authority of India
water accumulation points. However, in case of unpaved cross roads (track roads), the finish road
level shall be kept minimum 450mm above the existing ground/cross road level. (Clause No. 2.10
of IRC: SP:84-2019)
b) Lateral and vertical clearances at underpasses / flyovers and provision of guardrails/crash barriers
shall be as per Schedule D. Lateral clearance: The width of the opening at the vehicular
underpasses/Fly overs shall be as per clause 2.ix of Schedule B Annex-I.
Note: LVUP at ch.98+000 shall be provided with minimum of 4.5m of Vertical Clearance.
a) Lateral and vertical clearances for overpasses shall be as per paragraph 2.11 of the Manual and
this schedule. (Clause No. 2.11 IRC: SP:84-2019)
b) Lateral clearance: The width of the opening at the Overpasses shall be as follows:
Nil
(MCW – main carriageway, LHS – Left Hand Side and RHS – Right Hand Side)
b) The Service roads/Slip Road shall be constructed at the locations & for the lengths indicated
below:
Long Term Measures for rectification of 4 nos. MoRTH identified Accident Blackspots
B-7 | P a g e
on Jetpur - Somnath section of NH-151 in the state of Gujarat on EPC Basis
National Highways Authority of India
1. The length of service road and slip road mentioned above are minimum and including length of
the acceleration, deceleration lane and taper which shall be provided as per the Provisions of
IRC-SP: 84 2019. Exact location may be finalized in consultation with Authority Engineer which
shall not be treated as change in scope of work.
2. The Acceleration, deceleration lane, right turning storage lane, entry/exit lanes, taper shall be
constructed which shall be deemed to be part of the scope and no Change of Scope shall be
considered for the same. (Clause No. 2.12.2 IRC: SP:84-2019).
3. In addition to above mentioned width, bus bay if applicable shall be provided as per Schedule C.
4. Paved Carriageway and other cross-sectional elements shall be accordance to TCS enclosed in
Appendix B1
Grade separated structures shall be constructed as per paragraph 2.13 of the Manual. Proposed levels at
structure locations as shown in plan & profile specified in Annex-III of schedule A are minimum
requirement and only for guidance and any increase in levels shall not constitute any change of scope.
RCC barrier shall start from start of valley curve and end after grade separator at end of valley curve.
The sub-structure shall be continued in the median portion with RCC barrier wherever superstructure
has not been proposed in median portion. (Clause 7.1 (vii) IRC: SP:84-2019).
50m long MBCB Safety barriers on structure approaches shall be provided on all four faces of each
structure. MBCB provided towards median side of each structure shall be joined on ends in semi-
circular shape. (Clause No. 4.3.5 and 4.9, IRC 119).
Sufficient width of footpaths shall be provided at grade intersection below structures for each direction
of pedestrian movement.
Long Term Measures for rectification of 4 nos. MoRTH identified Accident Blackspots
B-8 | P a g e
on Jetpur - Somnath section of NH-151 in the state of Gujarat on EPC Basis
National Highways Authority of India
Width of median /
Minimum Vertical
Type of Structure
Configuration (m)
Type of Crossing
Design Chainage
clearance(m)
Skewangle
(Square)
Sl. No
(Km)
Deck
Remarks
Keshod Location
Flyover proposed
for four lane
PSC 1x16.816 + carriageway
1 64+077 Y Junction Precast I 1x27.805 + - 2 x 10.350 2.0 5.5 catering traffic
Girder 1x16.848 direction from
Jetpur to
Somnath
Gadu Location
Flyover proposed
for four lane
PSC carriageway
1x15 +
2 97+800 T Junction Precast I - 2 x 10.250 0.5 5.5 catering traffic
1x25 +1x15
Girder direction from
Jetpur to
Somnath
Width of median
Design Chainage
Configuration
clearance (m)
Skewangle
Minimum
Structure
(Square)
Vertical
Type of
Sl. No
(Km)
Deck
(m)
Remarks
Sorath Location
Pre-Cast
1 13+255 T junction RCC I 1 x 20 - 2 x 10.250 3.0 5.5 VUP
Girder
Gadu Location
RCC
2 98+000 T Junction 1 x 12 - 1 x 21.000 - 4.5 LVUP
Box
Note:
Long Term Measures for rectification of 4 nos. MoRTH identified Accident Blackspots
B-9 | P a g e
on Jetpur - Somnath section of NH-151 in the state of Gujarat on EPC Basis
National Highways Authority of India
1. Project Location is near to the Coastal region, all the structures shall be designed
considering the ‘Very Severe’ Exposer Condition. Hence, preventive measures shall be
considered for the structures for prevention from corrosion in steel, erosion of concrete and
other materials, etc. To prevent corrosion in steel strictly FE500D (Fusion Bonded Epoxy
Coated steel shall be used) confirming to IS: 13620-1993/ IRC 112-2020 specification along
with Galvanized coated binding wire, and minimum grade of concrete M40 shall be adopted
for structures. For Additional details, notes mentioned in GADs shall be referred.
2. To prevent early corrosion in reinforcement, steel bars shall be used with Fusion Bonded Epoxy
Coated confirming to IS : 13620-1993, MoRTH specification 1009.3.2.1 and IRC 112-2020.
Minimum grade of concrete shall be M-40 for all structures.
3. The minimum vertical clearance from cross road in case of all VUP, LVUP, & Flyover structures
shall be as mentioned above.
4. Open to sky median shall be cover by fiberglass roofing sheet along with appropriate frame
structure.
5. The total width excludes the clear gap between two super structures, which will be directed by
the roadway width.
7. Locations given in the above table are tentative, subjected to site condition. No change of scope
due to change in location shall be given.
8. Chainages may be adjusted according to location of structures as per drawings.
9. In case of grade separated structures like VUP/LVUP, the proposed structure, the finish road
level in VUP/LVUP shall be kept 150mm above the ground level/service road/cross road
(whichever is higher) to ensure that these VUP/LVUP don’t become water accumulation points.
Profile of the cross roads shall be corrected accordingly within proposed RoW.
10. The proposed span arrangement as suggested in table shall be adopted. Any change in proposed
span arrangement, RE Wall length shall be finalized in consultation with AE/NHAI. Any Change
in span arrangement shall not be treated as change of scope, except any variations in the length
arising out of a Change of Scope expressly undertaken in accordance with the provisions of
Article 13
11. Wherever liquefaction is observed in Open / Raft structures, Ground improvement (densification/
ground replacement with suitable soil) shall be done to compact the soil to increase its
penetration resistance and satisfy clause 8.4.4 (v) of IRC 114.8. In the case of Grade Separated
Structures, the type of structure and the level of the Project Highway and the crossroads shall be
as per levels (NGL, FRL etc.) given in Plan & Profile. The height of grade separator will be
decided as per the levels of the existing crossroad.
Long Term Measures for rectification of 4 nos. MoRTH identified Accident Blackspots
B-10 | P a g e
on Jetpur - Somnath section of NH-151 in the state of Gujarat on EPC Basis
National Highways Authority of India
All intersections and grade separators intersections shall be as per Section 3 of IRC: SP: 84-2019.
Long Term Measures for rectification of 4 nos. MoRTH identified Accident Blackspots
B-11 | P a g e
on Jetpur - Somnath section of NH-151 in the state of Gujarat on EPC Basis
National Highways Authority of India
The service road pavement composition shall be continued on crossroads of the intersections for
the length specified for at-grade and grade separated intersections.
Properly designed intersections shall be provided at the locations and of types and features given in
the tables below:
Junction Type
crossroad (m)
Carriageway
Category of
Cross Road
Length of
width of
Design
Sl. crossroad to be
developed Proposal
No. Left Right
LHS RHS
Nil
b) Minor Intersections:
Length
Carriageway
Design of crossroad
Sr. Junction Leads Category of Width of
Chainage Side to be
No. Type Towards Road Cross Road
(Km) developed
(m)
(m)
Sorath Location
1 12+870 Y Pipalva Village Village Road Left 3.50 50
2 13+030 Y Farm Village Road Left 3.50 20
3 13+140 Y Akala Village Village Road Left 5.50 50
Keshod Location
4 63+600 T Farm Village Road Right 4.00 20
5 63+580 T Cow Farm Village Road Left 5.00 20
6 63+660 T School Village Road Right 5.00 20
7 64+060 T Farm Village Road Left 3.50 20
8 64+160 T Farm Village Road Right 3.50 20
9 64+660 T Farm Village Road Right 3.50 20
Gadu Location
10 97+060 Y Farm Village Road Right 3.50 20
11 97+440 T Khera Village Village Road Right 3.50 50
12 97+650 T Gadu Village Village Road Right 4.00 50
13 97+740 T Station Village Road Left 4.00 50
14 98+380 T Side Road Village Road Left 4.00 20
15 98+440 T Side Road Village Road Left 9.00 20
16 98+620 T Side Road Village Road Left 7.00 20
17 98+660 Y Side Road Village Road Left 3.50 20
Santipara Patiya Location
18 100+730 Y Side Road Village Road Left 3.50 20
19 100+800 T Farm Village Road Right 3.50 20
Long Term Measures for rectification of 4 nos. MoRTH identified Accident Blackspots
B-12 | P a g e
on Jetpur - Somnath section of NH-151 in the state of Gujarat on EPC Basis
National Highways Authority of India
Length
Carriageway
Design of crossroad
Sr. Junction Leads Category of Width of
Chainage Side to be
No. Type Towards Road Cross Road
(Km) developed
(m)
(m)
20 100+960 T Farm Village Road Right 3.50 20
21 101+230 T Simar Village Village Road Right 3.50 50
Santipara
22 101+260 T Village Road Left 3.50 50
Village
23 101+480 T Side Road Village Road Left 3.50 20
Santipara
24 101+530 T Village Road Left 3.50 50
Village
25 102+030 T Side Road Village Road Right 3.50 20
Santipara
26 102+070 T Village Road Left 4.00 50
Village
27 102+170 T Side Road Village Road Left 4.00 20
Santipara
28 102+620 T Village Road BS 3.50 50
Village
29 102+680 T Side Road Village Road Left 4.00 20
30 102+910 Y Farm Village Road Right 4.00 20
31 103+020 Y Farm Village Road Right 4.00 20
Santipara
32 103+060 T Village Road Left 5.50 50
Village
Vinoba Vidhya
33 103+060 T Village Road Right 3.50 50
Mandir
34 103+140 T Kindarva Village Road Left 3.50 50
At grade intersection to be constructed shall be as per layout mentioned in Appendix B-II and as per
manual.
The grade separated intersection shall be developed as specified in paragraph 2.ix of Annex-I of
schedule B.
Road Leading to
Carriageway
Length of
Category of
Cross Road
crossroad
Chainage
Junction
width of
crossroad to
Design
(Km)
Type
Sl.
(m)
be developed Proposal
No. Left Right
LHS RHS
Sorath “VUP” in
Village
1 13+255 T - Choki 7 - 50 Sorath
Road
Village Location
“Flyover” in
Keshod
2 64+077 Y - NH 7 50 - Keshod
City
Location
Road Leading to
Carriageway
Length of
Category of
Cross Road
crossroad
Chainage
Junction
width of
crossroad to
Design
(Km)
Type
Sl.
(m)
be developed Proposal
No. Left Right
LHS RHS
Location
“LVUP” in
Khorsa/
4 98+000 T - SH 5.5 50 - Gadu
Gir
Location
(iii) Interchanges
1. The contractor shall take up ‘Detailed Engineering study’ to ascertain further details of all
intersections and treatment of the intersections shall be designed in accordance with the latest
guidelines mentioned out in section-3 of IRC: SP:84-2019. The same shall not constitute a
Change of Scope, save and except any variations arising out of a Change of Scope expressly
undertaken in accordance with the provisions of Article 13.
2. Junction improvement under grade separators shall be carried out as per IRC: SP:84-2019 with
proper entry/exit to cross roads and slip/service roads.
3. Locations of grade-separated structures are indicative. Exact location may be decided in
consultation with Authority Engineer.
4. The proposed span arrangements of the structures over water/gas pipeline are tentative and
subject to change as per availability of RoU/ requirement of the owning agency or approved
GAD by concerned authority. Any change in the span arrangement and length shall neither form
the basis for change of scope of work nor qualified for variation.
5. All charges payable to the Owning agency, like supervision, insurance etc. shall be borne by the
Contractor.
6. The Cross road at the junctions which are having at level difference from the main carriageway
are to be improved at the level of main carriageway for the length of 50 meter and then to be
merged with the crossroad at the gradient not more than 1:50
7. For Minor /Major layout for left in /left out arrangement with physical islands with hazard
marking. Where there is pace constraint to provide physical islands, the effect of junction kept
wide opened can be avoided by ghost island with marking.
Long Term Measures for rectification of 4 nos. MoRTH identified Accident Blackspots
B-14 | P a g e
on Jetpur - Somnath section of NH-151 in the state of Gujarat on EPC Basis
National Highways Authority of India
In case of realignment stretches/full reconstruction of existing stretches (if the existing road has
been overtopped in past during rains/ floods), the bottom of subgrade shall be 1500mm above
highest flood level (HFL)/ground water table/ original ground level (ground level achieved after
clearing & grubbing)/ pond level, whichever is higher.
Embankment slope protection shall conform to the clause 4.4 and 6.4 of IRC: SP:84-2019.
Notwithstanding anything to the contrary contained in this Agreement or IRC: SP:84-2019, the
proposed profile of the project highway as indicated in the Annex-III of Schedule A shall be
deemed to be part of this Schedule B. Based on site/design requirement the contractor shall
design the alignment plans and profiles of the project highway based on site/design requirement
mentioned in schedule B with approval from the Authority Engineer/Authority within the
available Right of Way.
The side slopes shall not be steeper than 2H:1V. In case, there is a ROW constraint than, suitable
soil retaining structures shall be provided. (Clause No. 4.2 IRC: SP:84-2019)
For stability of slope up to 3-meter height the turfing can be adapted. For the slope from 3-6
meter suitable, geocell, geo-grid, geo-green etc. can be provided with suitable drainage chutes as
per IRC 56. For the slope more than 6-meter height, a complete slope stability analysis as per
IRC:75 shall be done, and the slopes shall be compulsory protected with stone pitching within
stone masonry grid structure of 4x4 meter and suitable drains/chutes etc. shall be provided for
effective drainage of the water.
5 Pavement design
(i) Pavement design shall be carried out in accordance with section 5 of the Manual IRC: SP 84
2019, & IRC: 37 2018 referred in schedule-D. No stage construction shall be permitted.
(ii) Type of Pavement (Clause No. 5.4 IRC: SP:84-2019)
The pavement shall be flexible for the entire length of project highway as specified in this
schedule.
Long Term Measures for rectification of 4 nos. MoRTH identified Accident Blackspots
B-15 | P a g e
on Jetpur - Somnath section of NH-151 in the state of Gujarat on EPC Basis
National Highways Authority of India
Flexible pavement shall be designed for a minimum design period of 20 years. Stage construction
shall not be permitted.
Note:
1) The Pavement crust composition shall be designed in accordance with latest guidelines of
IRC 37.
2) Soil stabilization shall be adopted as per site requirement to obtain the effective CBR as
mentioned below.
• Main Carriageway:
Notwithstanding anything to the contrary contained in this Agreement or IRC: SP 84 2019, the
Contractor shall design the pavement for minimum design traffic of 80 MSA with 8% of
maximum Effective CBR.
• Service Road:
The pavement for service road shall be designed for Minimum projected traffic of 20 MSA with
8% of maximum Effective CBR.
In order to meet the intended functional requirement of respective pavement layers on main
carriageway, the minimum thickness of respective pavement layers for main carriageway and
connecting crossroads/ service roads/ slip roads/ entry/exit locations, acceleration/ deceleration
lane, right turning lanes shall, however, in no case be less than as given below:
Main carriageway, paved shoulder, median side paved strip, entry/ exit locations,
acceleration/ deceleration lane, right turning lanes:
Minimum Crust
Pavement Composition Remarks
Thickness (mm)
Subgrade 500
Granular Sub Base (GSB) 230
WMM in two layers with one
layer of Polypropylene Geo Grid
Reinforced WMM 250
as sandwich between WMM
layers
DBM(VG-40) 65
BC (Modified Bitumen) 50
Long Term Measures for rectification of 4 nos. MoRTH identified Accident Blackspots
B-16 | P a g e
on Jetpur - Somnath section of NH-151 in the state of Gujarat on EPC Basis
National Highways Authority of India
Bituminous Mix for Overlay at Main carriageway and Service Road in addition to required camber
corrective coarse (Clause No.5.9.8 IRC: SP:84-2019)
For Main carriageway, minimum thickness of overlay shall be kept 50mm BC (Modified Bitumen) at
near end of approaches, merging and diverging sections.
The following stretches of the existing Service Road shall be provided Minimum bituminous overlay as
follows:
Notes
1. To ensure internal drainage of the pavement structure, the granular sub-base layer shall extend
to full width across the shoulders in the embankment. The pavement layers of the paved
shoulder shall be same as that of the adjacent carriageway.
2. The width of the service road to be overlay varies throughout the length.
3. Reconstruction of service road wherever required shall be constructed.
4. The pavement composition and crust thickness of acceleration/ deceleration lanes running
parallel to the main carriageway should be same as that of main carriageway.
5. The pavement crust composition shall be designed in accordance with the latest guidelines of
IRC 37-2018, Manual in accordance with the approval of Authority Engineer.
The following stretches of the existing road shall be reconstructed. These shall be designed as
per new Pavement.
Design Chainage (Km)
Sl. No. Remarks
From To
Nil
6 Roadside Drainage
Drainage system including surface and subsurface drains for the Project Highway including
crossroads shall be provided as per section 6 of the IRC: SP: 84-2019 and Schedule D. Unlined
Long Term Measures for rectification of 4 nos. MoRTH identified Accident Blackspots
B-17 | P a g e
on Jetpur - Somnath section of NH-151 in the state of Gujarat on EPC Basis
National Highways Authority of India
Drains shall be provided in the entire project length which gets terminated at all crossroad
locations.
The contractor shall design the drainage along the highway as per drainage plan. The drainage
plan provided with the tender documents is indicative only. After award of work, the contractor
shall get prepared the proper drainage plan of the project based on contours of the area, outlet
availability and discharge requirements including discharge at the outfall from drains of local
bodies. The drainage plan prepared by the contractor shall be approved by AE.
The drainage plan will also be vetted by road safety expert so that these drains do not hinder
free flow of traffic. Further, the drainage plan will be checked through joint inspection with the
engineers of local bodies/development authority so that drainage plan is totally integrated with
the local body drainage plan. The drain cover should be strong enough to withstand weight of
light commercial vehicle wherever required.
Preferably undergrounds drain with well seized and well-spaced manholes may be provided to
take care of cleaning. Wherever possible, self-cleaning cross-section of drains may be adopted.
RCC Drain cum footpaths shall conform to the cross- sectional features and other details as
given in Annexures to Schedule-B and shall be provided as under:
Design Chainage
Sr. Length Net Length Width of
(Km) Side TCS Details
No. (m) (m) Drain (m)
From To
1 12+980 13+520 Both 540.0 1080.0 1.5 TCS-1 Sorath location
2 63+629 64+691 Both 1062.0 2124.0 1.5 TCS-2 Keshod Location
3 97+020 98+640 Both 1620.0 3240.0 1.5 TCS-3 Gadu Location
100+700 103+200 LHS 2500.0 2500.0 1.5 Santipara Patiya
4 TCS-4
100+695 103+200 RHS 2505.0 2505.0 1.5 Location
b) Unlined Drains
Unlined Drains other than above mentioned locations shall be provided in the entire project
length which gets terminated at all crossroad locations.
c) Median Drain
Draining of storm water from one carriageway to another carriageway is not permitted. the
Contractor shall design the median drain based on site/design requirement mentioned in
Schedule D with approval from the Authority Engineer and shall be connected with the
nearest culvert/ outfall. (Clause No. 6.3 IRC: SP:84-2019). Median Drain at super elevated
sections shall be provided at following sections.
Long Term Measures for rectification of 4 nos. MoRTH identified Accident Blackspots
B-18 | P a g e
on Jetpur - Somnath section of NH-151 in the state of Gujarat on EPC Basis
National Highways Authority of India
A suitable drainage arrangement for draining storm water of the main carriageway shall be
provided. Storm water of main carriageway to service road is not permitted. (Clause No.
2.15 IRC: SP:84-2019)
A suitable drainage arrangement for draining storm water from deck slab shall be provided.
Water shall not fall on any surface of the structures or remain standing or flowing over the
road below the structure. (Clause No. 6.8. IRC: SP:84-2019)
A suitable drainage arrangement for draining storm water from the Underpass shall be
provided. (Clause No. 6.8.3. IRC: SP:84-2019)
Vertical Drop-down drainage pipes with suitable cleaning provision shall be provided at
suitable interval. Drainage fixtures and dropdown pipes shall be of rigid, corrosion
resistant material not less than 100mm dia. The Storm water of main carriageway draining
on service road is not permitted.
Note: -
Further, for drainage along the highway, NHAI policy circular no. 18.48 dated 8/07/2020 shall have to
be complied with by the contractor without any change of scope.
Above mentioned lengths are minimum, exact length may be finalized in consultation with Authority
Engineer which shall not be treated as change in scope of work RCC Drain cum Footpath/ Unlined
drain/ lined drain (as shown in TCS) on both sides shall be constructed as per hydrological
requirement.
Long Term Measures for rectification of 4 nos. MoRTH identified Accident Blackspots
B-19 | P a g e
on Jetpur - Somnath section of NH-151 in the state of Gujarat on EPC Basis
National Highways Authority of India
Hume Pipe culvert of 1.2m dia shall be provided in each side of major crossroad with head wall and
parapet. At minor crossroad, only 1.2m dia pipe shall be provided to maintain longitudinal drainage.
7 Design of Structures
(i) General
a) All bridges, culverts and structures shall be designed and constructed in accordance with the
provision of the relevant Manual and shall conform to the cross-sectional features and other
details specified therein.
b) The width of carriageway of bridges and structures shall be in accordance with Specifications
and standard provided in relevant Manual and latest policy guidelines referred in Schedule-D.
d) For width of carriageway of structures and bridges refer clause 2 (ix), 7 iii (a), 7 iv (b).
e) All bridges, culverts and structures shall be designed for IRC class Special Vehicle (SV)
loading as per IRC: 6 and constructed in accordance with section-7 of the manual and shall
conform to the cross-sectional features and other details specified therein.
f) The Safety Barrier on Bridges shall continue on approaches. The footpath shall be provided
with paved surface and Railing till the embankment height is more than 3m. (Clause No. 7.17.
IRC: SP:84-2019)
g) The width of paved & earthen shoulders and width of structures shall be adopted as per 4 lane
manual (IRC: SP-84:2014) as per Bharatmala circular Reference No.143430 dated 30.10.2019.
The new structures of less than 60-meter length along main carriageway and slip/service roads
The following structures of Both side Service Road shall be provided with footpaths:
All new bridges shall be designed for utility services (OFC, telephones, electrical etc.) to be
carried over. However, any other utility to be carried over as per site condition shall be
identified in consultation with Authority Engineer.
Long Term Measures for rectification of 4 nos. MoRTH identified Accident Blackspots
B-20 | P a g e
on Jetpur - Somnath section of NH-151 in the state of Gujarat on EPC Basis
National Highways Authority of India
i) Cross section of the new culverts and bridges at deck level for the Project Highway shall
conform to the typical cross sections given in Section 2.10 of the Schedule-B and as per
Schedule D.
a) Overall width of all culverts shall be equal to the roadway width of the approaches. The
location and vent size of all the culverts proposed for irrigation purposes shall be decided in
consultation with concerned/irrigation department.
The overall width of culverts shall include the width of main carriageway and service roads /
Acceleration/Deceleration lanes, etc. All culverts shall also be continued in median and in gap
between main carriageway and service road.
The existing culverts at the following locations shall be re-constructed as new culverts:
All existing culverts which are not to be reconstructed shall be widened to the roadway width of the
Project Highway and service road as per the typical cross section given in the provision of relevant
Manual. Repairs and strengthening of existing structures where required shall be carried out.
(Clause No. 7.3 iii. IRC: SP:84-2019)
Hume
1 101+135 101+135 3 x 1.2 dia Hume Pipe 3 x 1.2 dia Widening
Pipe
Hume
2 101+495 101+495 3 x 1.2 dia Hume Pipe 3 x 1.2 dia Widening
Pipe
Long Term Measures for rectification of 4 nos. MoRTH identified Accident Blackspots
B-21 | P a g e
on Jetpur - Somnath section of NH-151 in the state of Gujarat on EPC Basis
National Highways Authority of India
Hume
3 103+260 103+260 4 x 1.2 dia Hume Pipe 4 x 1.2 dia Widening
Pipe
d) New culverts (given in table below) shall be constructed for width equal to the proposed
roadway width of the Project Highway & as per typical cross-section given in schedule B. The
details are given as under:
Span / Opening
Culvert
Sl. Culvert (No. x Length in m Skew
Crossing Remarks
No. Location x height in m)/ dia Angle
Type
in m
Nil
Chainage (Km)
Crossing Type
Existing Type
Service Road
Existing Size
Proposed Type
Stream, etc)
Skew Angle
Proposed Size
(Balancing/
Proposal for
Proposed
Remark
Culvert
Existing
S. No
(m)
(m)
Nil
Note:
i. In addition to the above, new pipe culverts of NP-4 type 2x600mm (min) diameter shall be
provided across the highways for local canal/field canal/utility crossing as per site
requirements. Location and size of such utility shall be finalized in consultation with AE and
NHAI.
ii. The length of all culverts shall be for full width as per site condition and applicable skew
including Acceleration Lane /Deceleration Lane/ Bus Bay/ Truck lay-bye as per manual with
floor protection measures.
iii. The location of the above culverts are indicative. The exact location of these culverts shall be
decided in consultation with Authority Engineer.
Long Term Measures for rectification of 4 nos. MoRTH identified Accident Blackspots
B-22 | P a g e
on Jetpur - Somnath section of NH-151 in the state of Gujarat on EPC Basis
National Highways Authority of India
iv. Vent way/Span arrangements are minimum specified. The actual vent way/span arrangement of
culverts shall be determined on the basis of detailed investigation by the contractor in
accordance with the specification and standards.
v. Contractors may construct precast cement concrete Box culvert units as per policy circular of
Ministry RW/NH34049/01/2020-S&R (B) dated 08.04.2022 to improve the quality of concrete.
g) Repairs / replacements of railing / parapets, flooring and protection works of the existing
culverts shall be undertaken as follows:
h) Floor protection works shall be as specified in the relevant IRC Codes and Specifications.
(iii) Bridges
a) Existing bridges to be re-constructed/widened:
(i) Existing bridges proposed for reconstruction as new structures: (Clause No. 7.3 iv(a). IRC:
SP:84-2019)
Sorath Location:
On Main
1 13+110 13+110 2x8 44.50 RCC Box Fig. 7.2 Carriageway and
Service Road
(Both Side)
(ii) Existing narrow bridges proposed to be retained and widened: (Clause No. 7.3 iv. IRC: SP:84-
2019)
Extent of
Sl. Location Existing Widening (m) Span Arrangement
Location
No (km) Width (m) (m)
LHS RHS
1 102+055 1 x 7.30 9.0 9.0 1 x 7.30 Santipara Patiya
Additional new bridges at the following locations on the Project Highway shall be constructed. GADs
for the new bridges are attached in the drawings folder. (Clause No. 7.3 ii. IRC: SP:84-2019)
Long Term Measures for rectification of 4 nos. MoRTH identified Accident Blackspots
B-23 | P a g e
on Jetpur - Somnath section of NH-151 in the state of Gujarat on EPC Basis
National Highways Authority of India
Existing Bridge to be
retained and
1 x 20.284 (SQ) LHS: 10.500 additional new bridge
1 64+691 32.03o
1 x 23.924 (SK) RHS: 10.500 shall be provided on
both side of service
road
Note: -
1. Project Location is near to the Coastal region, all the structures shall be designed
considering the ‘Very Severe’ Exposer Condition. Hence, preventive measures shall be
considered for the structures for prevention from corrosion in steel, erosion of concrete and
other materials, etc. To prevent corrosion in steel strictly FE500D (Fusion Bonded Epoxy
Coated steel shall be used) confirming to IS: 13620-1993/ IRC 112-2020 specification along
with Galvanized coated binding wire, and minimum grade of concrete M40 shall be adopted
for structures. For Additional details, notes mentioned in GADs shall be referred.
2. The Deck level of the Major/Minor Bridge on River stream and Nalla should be governed by
HFL of stream/Navigational HFL and Clearance as per guidelines of Inland Waterways
Authority of India, wherever applicable.
3. The Deck level of the Major/Minor Bridge on canal should be governed by Full supply level of
Canal.
4. The span arrangements and vertical clearance are tentative and the same shall be followed as
per approved GAD by the concern Irrigation Authority and any change shall not be treated as
change in scope of work.
5. Wherever liquefaction is observed in Open foundation and Raft Structures, Ground
improvement (densification/ground replacement with suitable soil) shall be done to compact the
soil to increase its penetration resistance and satisfy clause 8.4.4 (v) of IRC114.
6. A minimum vent height for proposed Minor Bridges shall be provided as indicated in respective
GAD as part of the contract, i.e., proposed FRL minus structure depth and Ground level and
other adjustments (camber etc.).
c) The railings of existing bridges shall be replaced by crash barriers at the following locations:
Design Chainage
Sr. No Length (km) Remarks
From To
Nil
Long Term Measures for rectification of 4 nos. MoRTH identified Accident Blackspots
B-24 | P a g e
on Jetpur - Somnath section of NH-151 in the state of Gujarat on EPC Basis
National Highways Authority of India
d) The existing bridges/ RoB/ Grade Separators/ RUB retained on the project highway shall be
upgraded and rehabilitation measures/proposals shall be specified as follows:
An effective drainage system for bridge decks shall be provided as specified in the Manual.
The following bridges shall be constructed with structures like cable stayed suspension
bridge or with special techniques.
The following bridges shall be constructed with required clearances as per Inland
Waterways Authority of India
b) Road over bridges (road over rail) shall be provided at the following location as per
approved GAD.
Long Term Measures for rectification of 4 nos. MoRTH identified Accident Blackspots
B-25 | P a g e
on Jetpur - Somnath section of NH-151 in the state of Gujarat on EPC Basis
National Highways Authority of India
NIL
i. The proposed span arrangements of the ROBs are tentative and subject to change as per
availability of railway boundaries/ requirement of the railways or approved GAD by
railway authority. Any change in the span arrangement and length shall neither form the
basis for change of scope of work nor qualified for variation.
ii. ROBs shall be designed, constructed, and maintained as per the requirements of Railway
authorities. The construction plans shall be prepared in consultation with the concerned
railway authority.
iii. The ROBs shall be constructed and maintained by the Contractor under supervision of the
Railways.
iv. All charges payable to the Railways like D&G, Capitalized maintenance, signaling, cabling,
OHE modification, earthing etc. except P&E charges shall be borne by the Contractor.
c) Road under bridges (road under railway line) shall be provided at the following level
crossings, as per approved GAD:
The grade separated structures shall be provided at the locations and of the type and length
specified in this Annex-I.
Long Term Measures for rectification of 4 nos. MoRTH identified Accident Blackspots
B-26 | P a g e
on Jetpur - Somnath section of NH-151 in the state of Gujarat on EPC Basis
National Highways Authority of India
(i) Traffic control devices and road safety works shall be provided in accordance with Section 9 of
the IRC: SP:84: 2019
a) Traffic Signs:
Traffic signs shall be provided as per IRC 67 as mentioned in Schedule-C. Traffic signs include
roadside signs, overhead signs, and curb mounted signs along the entire Project Highway. The details
are provided in Schedule C. The numbers and location of signs shown in traffic signage plan shall be
treated as tentative and minimum specified. The actual numbers and location shall be determined by the
contractor in accordance to manual with prior approval from AE and the authority. Any increase shall
not be constituted as change of Scope.
b) Pavement Marking:
Pavement markings shall be provided as per IRC 35 as mentioned in Schedule-C. Pavement markings
shall cover road marking for the entire Project Highway including service roads.
c) Safety Barrier:
Thrie Metal beam crash barrier shall be provided along the project highway at the locations as given in
clause 9.7 of IRC: SP: 84-2019 and this Schedule. RCC crash barrier shall be provided as given in
GADs, on RE wall and retaining wall.
Metal beam/RCC crash barrier shall be provided as per TCS given in Schedule B Appendix B-I. Metal
beam (thrie) crash barrier to be provided at the shoulder side and at median side as mentioned in
Schedule C.
End Treatment of Steel barriers/Rope Barrier shall be specified i.e. MELT or P-4 confirming to EN
1317-4, TT, MBCB barrier to Concrete Barrier (Clause No. 9.7.2 (b) IRC: SP:84-2019)
End Treatment to Concrete barrier shall be done as specified in Clause No. 9.7.3 (b) IRC: SP:84-2019.
Long Term Measures for rectification of 4 nos. MoRTH identified Accident Blackspots
B-27 | P a g e
on Jetpur - Somnath section of NH-151 in the state of Gujarat on EPC Basis
National Highways Authority of India
All Sign shall be of micro prismatic grade sheeting corresponding to class C sheeting as per
ASTMD 4956 Type XI (Clause no 9.2.3 IRC SP 84: 2019 and IRC 67: 2022).
9 Roadside Furniture
(i) Roadside furniture shall be provided in accordance with the provisions of the relevant
Manual and Schedule C.
Pedestrian facilities: Provide pedestrian crossing facilities as per Manual and as per
schedule C.
Pedestrian guardrail: Provide pedestrian guardrail at each bus shelter/stop location as per
the applicability of the TCS.
(iii) Delineators: Delineators for the entire Project Highway at the locations as suggested in the
relevant Manual and Schedule C.
(iv) Road Studs: Road Studs shall be provided all along the shoulder edge line, median edge
line, curves, approaches to bridges/grade separated structures and junction influence area as per
requirement of Manual and MoRTH standards & specifications.
(v) The traffic impact attenuators shall be provided as per clause 9.6, and 10.4.3 of IRC:
SP:84-2019.
(vi) MS Railing: MS Railing for separation of main carriageway and the service road/ Slip
Road shall be provided as per the given TCS.
(vii) Antiglare Screens: Suitable antiglare shall be provided at the center of median to reduce
headlight glare from opposite traffic at suitable locations in consultation with AE.
10 Hazardous Locations
The safety barriers shall be provided at the following hazardous location such as ponds, well, electric
sub-station, Electric tower, spilt carriageway, etc.
Nil
Long Term Measures for rectification of 4 nos. MoRTH identified Accident Blackspots
B-28 | P a g e
on Jetpur - Somnath section of NH-151 in the state of Gujarat on EPC Basis
National Highways Authority of India
11 Special Requirement:
The RCC Retaining wall/ RE wall/Toe wall/Breast wall shall be provided in the following locations.
c) Toe wall
The toe wall shall have minimum surface reinforcement with an 8mm dia steel bar. The location
of toe wall shall be provided as per site requirement in order to fit TCS within available RoW.
The actual length shall be determined on the basis of detailed investigations in accordance with
Specification and standards defined in Schedule D. No Change of Scope shall be provided for
construction of any length of Toe Wall / Retaining wall.
Note:
The length of RE Wall is inclusive of structure length and exclusive of cross length at abutment which
shall be provided.
The toe wall shall have minimum surface reinforcement with 8mm dia FBEC bar.
The location of RCC Retaining wall and toe wall mentioned above shall be treated as tentative and
minimum requirement. The actual length shall be determined on the basis of detailed investigations in
accordance with Specification and standards define in Schedule D. Any additional length as per site
requirement shall not be treated as change of Scope.
The Open well shall be identified and appropriate treatment shall be provided.
Long Term Measures for rectification of 4 nos. MoRTH identified Accident Blackspots
B-29 | P a g e
on Jetpur - Somnath section of NH-151 in the state of Gujarat on EPC Basis
National Highways Authority of India
Nil
13 Utility Corridor
A strip of land at the extreme edge of ROW on each side shall be kept for accommodating utilities as
per TCS.
14 Shifting of Utilities
The existing utilities to be relocated in consultation and direction of respective/ concerned utility owing
agencies are given in Appendix A-II of Schedule A.
The EPC Contractor shall undertake the work of shifting of any utility (including electric lines, water
pipes, gas pipelines and telephone cables) to an appropriate location or alignment, in accordance with
the provisions of EPC Agreement.
The traffic diversion plans shall be prepared as per IRC SP 55 for smooth flow of traffic and safety. A
location specific diversion plan shall be prepared by EPC Contractor and shall be approved by the AE/
Authority before commencement of work.
16 Removal of structures
The existing structure if any within the project corridor shall be removed by the contractor.
Tree felling
Felling of trees within the ROW, staking, transportation from the project site to Forest department/
authority where the space is available shall be done as per requirement of Authority/ concerned
department. The cost of the same shall be borne by the Authority.
17 Change of Scope
The length of structures and bridges except for Major Bridge cum Viaduct, ROB cum Viaduct and
structures over existing water bodies like ponds, lakes etc. as mentioned in Schedule B shall be treated
as an minimum. The actual lengths as required on the basis of detailed investigations shall be
determined by the Contractor in consultation with Authority Engineer and in accordance with the
Specifications and Standards. Any variations in the lengths specified in this Schedule-B shall not
constitute a Change of Scope, save and except any variations in the length arising out of a Change of
Scope expressly undertaken in accordance with the provisions of Article 13.
Long Term Measures for rectification of 4 nos. MoRTH identified Accident Blackspots
B-30 | P a g e
on Jetpur - Somnath section of NH-151 in the state of Gujarat on EPC Basis
National Highways Authority of India
Appendix B-I
Following Typical Cross Sections of project location are enclosed. Indicative Start and end of the
stretches (Chainages) applicable for each type of cross sections are given in the Table below.
Long Term Measures for rectification of 4 nos. MoRTH identified Accident Blackspots
B-31 | P a g e
on Jetpur - Somnath section of NH-151 in the state of Gujarat on EPC Basis
National Highways Authority of India
Long Term Measures for rectification of 4 nos. MoRTH identified Accident Blackspots
B-32 | P a g e
on Jetpur - Somnath section of NH-151 in the state of Gujarat on EPC Basis
National Highways Authority of India
Long Term Measures for rectification of 4 nos. MoRTH identified Accident Blackspots
B-33 | P a g e
on Jetpur - Somnath section of NH-151 in the state of Gujarat on EPC Basis
National Highways Authority of India
Long Term Measures for rectification of 4 nos. MoRTH identified Accident Blackspots
B-34 | P a g e
on Jetpur - Somnath section of NH-151 in the state of Gujarat on EPC Basis
National Highways Authority of India
RHS
Long Term Measures for rectification of 4 nos. MoRTH identified Accident Blackspots
B-35 | P a g e
on Jetpur - Somnath section of NH-151 in the state of Gujarat on EPC Basis
National Highways Authority of India
Appendix B-1
Note:
1. TCS schedule as given above shall be treated as an approximate assessment. The actual length
of the TCS schedule shall be prepared by the contractor based on detailed investigations and
site requirements. Any variation in length of respective TCS specified in Schedule B shall not
constitute a change of scope, save and except any variations in the length arising out of a
change of scope expressly undertaken in accordance with the provisions of Article 13.
2. The Lengths mentioned in the above list for cross section types concerned to structures are
inclusive of structure length.
3. The width of carriageway for all structures shall be as mentioned in this schedule and GAD.
4. If the paved carriageway width at structure is more than the carriageway width given in TCS,
proper pavement tapering (as per manual) shall be provided. Suitable transition as per Manual
shall be provided between two types of sections. The flare shall be provided in the narrow
section.
5. Retaining wall/ RE wall shall be provided for full height on all structures. (clause No. 7.1 (iv)
IRC: SP:84-2019).
6. A minimum 2m wide strip of land at the extreme edge of ROW shall be kept for
accommodating utilities as per TCS.
7. In addition to width mentioned in TCS, bus bay, Truck lay-bye shall be provided as per
Schedule C.
8. The applicable TCS for the minor structures shall be as per this schedule B
10. Intermediate Sight Distance (Desirable Minimum Sight Distance) shall be followed for design
of all vertical curves (Summit and Valley Curves) including structures as well as highways.
(Clause No. 2.9.5 IRC: SP:84-2019).
Long Term Measures for rectification of 4 nos. MoRTH identified Accident Blackspots
B-37 | P a g e
on Jetpur - Somnath section of NH-151 in the state of Gujarat on EPC Basis
National Highways Authority of India
Appendix-B-II
A. Major Junction:
Road Leading to
Sl. Design Junction
Proposal
No. Chainage (Km) Type Left Right
B. Minor Junction
Length
Carriageway
Design of crossroad
Sr. Junction Leads Category of Width of
Chainage Side to be
No. Type Towards Road Cross Road
(Km) developed
(m)
(m)
Sorath Location
1 12+870 Y Pipalva Village Village Road Left 3.50 50
2 13+030 Y Farm Village Road Left 3.50 20
3 13+140 Y Akala Village Village Road Left 5.50 50
Keshod Location
4 63+600 T Farm Village Road Right 4.00 20
5 63+580 T Cow Farm Village Road Left 5.00 20
6 63+660 T School Village Road Right 5.00 20
7 64+060 T Farm Village Road Left 3.50 20
8 64+160 T Farm Village Road Right 3.50 20
9 64+660 T Farm Village Road Right 3.50 20
Gadu Location
10 97+060 Y Farm Village Road Right 3.50 20
11 97+440 T Khera Village Village Road Right 3.50 50
12 97+650 T Gadu Village Village Road Right 4.00 50
13 97+740 T Station Village Road Left 4.00 50
14 98+380 T Side Road Village Road Left 4.00 20
15 98+440 T Side Road Village Road Left 9.00 20
16 98+620 T Side Road Village Road Left 7.00 20
17 98+660 Y Side Road Village Road Left 3.50 20
Santipara Patiya Location
18 100+730 Y Side Road Village Road Left 3.50 20
19 100+800 T Farm Village Road Right 3.50 20
20 100+960 T Farm Village Road Right 3.50 20
Long Term Measures for rectification of 4 nos. MoRTH identified Accident Blackspots
B-38 | P a g e
on Jetpur - Somnath section of NH-151 in the state of Gujarat on EPC Basis
National Highways Authority of India
Length
Carriageway
Design of crossroad
Sr. Junction Leads Category of Width of
Chainage Side to be
No. Type Towards Road Cross Road
(Km) developed
(m)
(m)
21 101+230 T Simar Village Village Road Right 3.50 50
Santipara
22 101+260 T Village Road Left 3.50 50
Village
23 101+480 T Side Road Village Road Left 3.50 20
Santipara
24 101+530 T Village Road Left 3.50 50
Village
25 102+030 T Side Road Village Road Right 3.50 20
Santipara
26 102+070 T Village Road Left 4.00 50
Village
27 102+170 T Side Road Village Road Left 4.00 20
Santipara
28 102+620 T Village Road BS 3.50 50
Village
29 102+680 T Side Road Village Road Left 4.00 20
30 102+910 Y Farm Village Road Right 4.00 20
31 103+020 Y Farm Village Road Right 4.00 20
Santipara
32 103+060 T Village Road Left 5.50 50
Village
Vinoba Vidhya
33 103+060 T Village Road Right 3.50 50
Mandir
34 103+140 T Kindarva Village Road Left 3.50 50
All the balancing culverts where track/cart roads are crossing under the project highway to be
constructed as per gravel road standard within PROW and to be provided with required safety devices
including marking, signage and other road safety furniture as per IRC: SP:84-2019, IRC:67, IRC:35 and
other relevant policy documents/circulars published by MoRTH/NHAI. Traffic island and separators
between main carriageway and slip road shall be constructed with raised kerb and top surface shall be
treated with concrete tile flooring. All at grade intersection shall be developed as per manual
requirement and typical layout drawings as per MoRTH type Design. The typical layout of Major
junctions as listed above is as follows.
Long Term Measures for rectification of 4 nos. MoRTH identified Accident Blackspots
B-39 | P a g e
on Jetpur - Somnath section of NH-151 in the state of Gujarat on EPC Basis
National Highways Authority of India
Long Term Measures for rectification of 4 nos. MoRTH identified Accident Blackspots
B-40 | P a g e
on Jetpur - Somnath section of NH-151 in the state of Gujarat on EPC Basis
National Highways Authority of India
Flyover at Ch. 64+077 km, Span: 1x15 + 1x25 + 1x15 (Keshod Location)
Long Term Measures for rectification of 4 nos. MoRTH identified Accident Blackspots
B-41 | P a g e
on Jetpur - Somnath section of NH-151 in the state of Gujarat on EPC Basis
National Highways Authority of India
Flyover at Ch. 97+800 km, Span: 1x15 + 1x25 + 1x15 (Gadu Location)
Long Term Measures for rectification of 4 nos. MoRTH identified Accident Blackspots
B-42 | P a g e
on Jetpur - Somnath section of NH-151 in the state of Gujarat on EPC Basis
National Highways Authority of India
Long Term Measures for rectification of 4 nos. MoRTH identified Accident Blackspots
B-43 | P a g e
on Jetpur - Somnath section of NH-151 in the state of Gujarat on EPC Basis
National Highways Authority of India
Appendix-B-III
Traffic Signs
Traffic Signs: Traffic sign boards as per details given Schedule C and Annex III to Schedule A (the
signage plan) shall be provided in the project highway in accordance to manual. The signage plan
indicated in this Schedule deemed to be part of this Schedule-B. The type, numbers, and location of
Traffic Signages shown in Traffic Signage Plan as indicated in this Schedule are tentative and minimum
specified. The actual numbers and location of Traffic Signages shall be determined by the Contactor in
accordance with the Manual with approval from the IE/ AE. Any increase in the number and type of
road sign shall not constitute a Change of Scope.
Long Term Measures for rectification of 4 nos. MoRTH identified Accident Blackspots
B-44 | P a g e
on Jetpur - Somnath section of NH-151 in the state of Gujarat on EPC Basis
National Highways Authority of India
Annexure I
Utility Shifting:
Note: -
(b) The supervision charges at the rates/charges applicable of the Utility Owning Department shall be
paid directly by the Authority to the Utility owning Department as and when Contractor furnishes
demand of Utility Owning Department along with a copy of estimated cost given by the letter.
(c) The dismantled material /scrap of existing Utility to be shifted/dismantled shall belong to the
Contractor who would be free to dispose-off the dismantled material as deemed fit by them unless the
Contractor is required to deposit the dismantled material to utility owning department as per the norms
and practice and, in that case the amount of credit for dismantled material may be availed by the
Contractor as per the estimate agreed between them.
(d) The utilities shall be handed over after shifting work is completed to Utility Owning Department to
their entire satisfaction. The maintenance liability shall rest with the Utility Owning Department after
handing over process is complete as far as utility shifting works are concerned.
Long Term Measures for rectification of 4 nos. MoRTH identified Accident Blackspots
B-45 | P a g e
on Jetpur - Somnath section of NH-151 in the state of Gujarat on EPC Basis