PERMIT TO WORK AWARENESS TRAINING
CONTRACTOR: - AL- KHONAINI
DATE: - 19/05/2025
TOTAL ATTENDEE’S: - 19
                                              Permit to Work
                                                 (PTW)
                   The Permit to Work (PTW) System and associated safety rules is a formal and controlled
                   process that ensures that appropriate precautions and control measures are implemented to
                   avoid inherent danger and for safe completion of the work. The Permit form is a declaration
                   issued by Permit Issuer (PI) to Permit Receiver (PR) that states the nature of the work to be
                   undertaken, the period during which the work may take place and the measures to be taken.
                                                                          Objective
                                                                         Flexibly to           Bridge the gap
                     Set minimum              Provide                    business line                                                         Periodic
                                              supplement                                       for gray areas        Aligned with
                     qualification                                       to develop and                                                        PTW review/
Unified permit                                document to                                      where two             SAIS,OSHA and
                     and competency                                      add additional                                                        audit on site
to work across                                identify hazards                                 proponents            international
                     for personnel                                       supplements                                                           to verify
SEC.                                          and control for                                  overlap on            best practices.
                     involved in PTW.                                    document and                                                          compliance.
                                              key operational                                  an activity or
                                                                         forms specific to     working area.
                                              activities.                their operation.
              01                   02                       03                            04                  05                      06                       07
                                                                Types of Work Permit
         01                             02                                    03                             04                               05
    Line Breaking                    Sanction                      Electrical work Permit.             Confined Space                          Hot
    Work Permit.                  for Test (SFT).                                                     Entry Work Permit.                   Work Permit.
                                                                                06
                                                                          General Work
                                                                             Permit
Excavation Work.         Working at Height.          Lifting Operations.             Diving Operations.          Working With                  Other Work
                                                                                                              Radioactive Material.            Activities.
                                                                 Type of Certificates
                                Lifting                Safeguard              Scaffolding        Hazardous            Vehicle                Road
           Isolation                                                                                                                        Closure
                              Equipment            Defeat / inhibition          Safety         Material Handling       Entry
          Certificate.                                                                                                                     Certificate.
                               Certificate.           Certificate.            Certificate.       Certificate.        Certificate.
                                                                         PTW Forms
                            Front Side of PTW form                                       Back Side of PTW form
                            cover following sections:                                    cover following sections:
                            •	 Permit General Informatio                                 •	 Joint site inspection
                            •	 Hazard Identification & Control                           •	 Additional control measures
                            •	 Mandatory Controls Based On Ptw Type                      •	 Reference standard values
                            •	 Permit Authorisation & Closure
                                        Permit to Work
                                           (PTW)
                                                    Assess If PTW Required
                                     Routine Activities                                                   Non-Routine Activities
                                                                                                              PTW Required
                                                                                                              JSA Required
       Operation                     Exempted work                    Non-Exempted work
          work                          Activities                         Activities
    No PTW Required                  No PTW Required                     PTW Required
      SOP Required                                                      JSA If Required
     JSA If Required
        PTW Flowchart                                               Key                                          All of the criteria below
                                                                 Advantages                                     must be met for the activity
                                                                                                                      to be exempted
Work Order / Work Request Creation
                                                   01                                  02
  Planning and scheduling                Emphasize on raising               Traceable work permits               The activity does not
                                       hazard recognition ability.           (i.e., coded with serial            require isolation, and
    Pre-work Controls                                                                number).                    there is no contact with
                                                                                                                 live energy.
     PTW Authorisation
                                                                                                                 The activity is a low risk
                                                   03                                  04                        in nature or not carried
   Communicate Controls                                                                                          out in a restricted area.
                                        Provide corporate control           Enhance oversight and
    & Commence Work
                                       on training and competency          PTW compliance through
                                                                                                                 The activity (including
                                              related to PTW.                audit/review at site.
                                                                                                                 maintenance) is
                                                                                                                 conducted on a regular
             XOR
                                                                                                                 basis.
                        PTW
                      Transfer,                    05                                  06                        Carried out by a single
  Work                                                                                                           discipline with no
                     Suspension         Enable full digitalizing of         Approval escalation for
Completion                                                                                                       involvement of other
                         and            permit to work process.            High Risk Activities up till
                                                                                                                 disciplines/ parties.
                      Extension                                            Dept./Division Manager.
                                                                                                                 Can be completed in less
               V                                                                                                 than a shift.
                                                                                                                 Have no impact on
  Work Completion & Closure                                                                                      operations.