Swimming Pool Estimate
Swimming Pool Estimate
SUMMARY OF COSTS
Project Name : Preparation of Detailed project report of Children Park
Location:Laljhadi-05, Kanchanpur
Page 1 900743298.xlsx
Laljhadi Rural Municipality
Office of Rural Municipality Executive
Sudurpaschim Province
Piping works( PVC pipe -Overflow pipe, Fill tube and emergency washout
12 rm 3.350 285.77 957.33
pipe etc.)
Steel Staircase (100-150mm riser height with black pipe post 38mm&
13 rm 3.150 10,844.18 34,159.17
20mmx20mm square pipe ,600-750mm width)
2 H.P. Electrical motor water pump Multi stage coupled pump
14 nos 1.000 28,939.75 28,939.75
(Crompton)
Open Slide build through a sandwich of resin fiberglass and geal coat ,
15 nos 1.000 100,000.00 100,000.00
and for your final finish sky color will be used
Total 2,046,184.21
Vat(13%) 266,003.95
Contingencies(4%) 81,847.37
Grand Total 2,394,035.53
CONCRETE WORKS
4 P.C.C.(1:3:6) Works
swimming pool
Left Portion Swimming Pool(Lvl -1.4m) 1 area= 77.36 0.075 5.80
Righ Portion Swimming Pool(Lvl -0.6m) 1 area= 31.59 0.075 2.37
Top&bottom portion swimming pool(-0.47m) 1 area= 4.05 0.075 0.30
Footway 1 area= 36.40 0.075 2.73
Sill Beam
Perimeter of building 1 42.51 0.25 0.200 2.13
Mid portion of swimming pool 1 8.00 0.25 0.200 0.40
Top portion of swimming pool 1 4.00 0.25 0.200 0.20
Page 4 of 209
S.N. DESCRIPTION NO. LENGTH(m)BREADTH(m)
HEIGHT(m) TOTAL UNIT
Top portion swimming pool(-0.47m) 1 area= 4.05 4.05
Footway 1 area= 36.40 36.40
Vertical Surface
Left portion of swimming pool circular wall 1 27.51 1.100 30.261
Right portion of swimming pool circular wall 1 15.00 0.750 11.25
Perpendicular wall 1 8.00 0.590 4.72
Top portion of swimming pool 1 4.00 0.470 1.88
Page 5 of 209
Government of Nepal
Ministry of Education, Science and Technology
Center for Education and Human Resource Development
Sanothimi, Bhaktapur
Project Name: Conduct Detailed Assessment of the Educational and Physical Infrastructure of
the Proposed Model School, and Prepare School-Specific Multi-Year Coasted Master Plan
###
Location:Laljhadi-05, Kanchanpur
Type of Job: Electrification Works
Ite
Total Amount
m Description of Works Unit Rate Remarks
Quantity (NPR)
No.
A Panel & Distribution Boards
1 Distribution board
Distribution board 12 way SPN made of mild
1.1 steel sheet double cover lockable Geco or Set 4.00 4,358.73 17,434.92
eqvt. Flush type etc all complete
Distribution board 8 way SPN made of mild
1.2 steel sheet double cover lockable Geco or Set 3.00 7,762.85 23,288.55
eqvt. Flush type etc all complete
6-32 Amps SP MCB Geco, North west, ISI or
1.4 Nos 30.00 379.50 11,385.00
eqvt. For light and power supply
6-32 Amps DP MCB Siemens, Geco,Legrend
1.5 Nos 6.00 1,238.43 7,430.58
or eqvt. For main
B Mains,Sub-Mains,Cables & Wires - -
(2*6+1*1.5) sq.mm multistrand flexible cu
1 wire for main in 3/4" HDPE polythene pipe Rm 12.80 250.00 3,200.00
from sub DB to DB etc, all complete
C CIRCUIT CUM POINT WIRING - -
General Service Light/Fan/Exhaust Fan/
Call bell Point Wiring
Supply,installation,testing and commissioning
of light point /fan point wiring from DB to
various points with 2.5 sqmm multistrand
flexible cu wire through 1/2" internal dia
1 Point 108.00 900.00 97,200.00
HDPE conduit concealed via junction box and
switch as per drawing and specification
including cost of circular box and junction box
and switch. Notes : 1)
Average lenght per point = 12.5m
Approximately
2 Power Socket Point Wiring - -
Supply, storing,assembling,installation,testing
and commissioning of wall/ceiling ,
surface/recessed,suspended types CFL/LED
1 - -
lighting fixtures including lamp,power factor
improvement capacitor,electronics ballast,
controle gear, LED driver etc
3 Earthback Filling
Filling Upto Ground Level
For Footing of column
F1 4.00 3.100 12.400 3.100 1.800 69.192
F2 1.00 4.250 4.250 4.250 1.800 32.512
F3 3.00 3.900 11.700 3.900 1.800 82.134
F4 2.00 3.500 7.000 3.500 1.800 44.100
CF1 2.00 5.250 10.500 4.000 1.800 75.600
CF2 1.00 7.400 7.400 4.900 1.800 65.268
CF3 1.00 7.400 7.400 4.600 1.800 61.272
CF4 1.00 7.400 7.400 4.300 1.800 57.276
Foundation of beam and wall
Along Grid A-A 1.00 4.940 4.940 0.450 1.625 3.612
Along Grid B-B 1.00 1.815 1.815 0.450 1.475 1.204
Along Grid C-C 1.00 2.190 2.190 0.450 1.525 1.502
Along Grid D-D 1.00 2.190 2.190 0.450 1.525 1.502
Along Grid E-E 1.00 4.940 4.940 0.450 1.625 3.612
Along Grid 1-1 1.00 10.220 10.220 0.450 1.625 7.473
Along Grid 2-2 1.00 6.420 6.420 0.450 1.575 4.550
Along Grid 3-3 1.00 6.420 6.420 0.450 1.575 4.550
4 Brick/Stone soling
4.1 Flat Brick Soling
Floors
Room between Grid A-A and B-B 1.00 12.390 12.390 6.230 77.189
Room between Grid B-B and C-C 1.00 12.390 12.390 6.230 77.189
Room between Grid C-C and D-D 1.00 12.390 12.390 4.330 53.648
Room between Grid D-D and E-E 1.00 12.390 12.390 6.230 77.189
Outside Grid 4-4 1.00 19.690 19.690 1.635 32.193
Floor of ramp 2.00 5.420 10.840 1.000 10.840
Flat Brick Soling 328.248 Sq.m
5 Sand Filling
Floors
Room between Grid A-A and B-B 1.00 12.390 12.390 6.230 0.100 7.718
Room between Grid B-B and C-C 1.00 12.390 12.390 6.230 0.100 7.718
Room between Grid C-C and D-D 1.00 12.390 12.390 4.330 0.100 5.364
Room between Grid D-D and E-E 1.00 12.390 12.390 6.230 0.100 7.718
Outside Grid 4-4 1.00 19.690 19.690 1.635 0.100 3.219
Total Sand Filling Work 31.737 Cu.m
7 Brickwork
Brick Masonry Works in 1:6 C/S
7.1 Cu.m
mortar
Upto Plinth Level
Toe wall between lower and upper tie
beam
Along Grid A-A 1.00 11.940 11.940 0.230 1.050 2.883
Along Grid B-B 1.00 11.765 11.765 0.230 0.900 2.435
Along Grid C-C 1.00 11.765 11.765 0.230 0.950 2.570
Along Grid D-D 1.00 11.765 11.765 0.230 0.950 2.570
Along Grid E-E 1.00 11.940 11.940 0.230 1.050 2.883
Along Grid 1-1 1.00 22.270 22.270 0.230 1.050 5.378
Along Grid 2-2 1.00 22.270 22.270 0.230 1.000 5.122
Along Grid 3-3 1.00 22.270 22.270 0.230 1.000 5.122
Along Grid 4-4 1.00 22.120 22.120 0.230 1.050 5.341
Outside Grid 4-4 1.00 23.705 23.705 0.350 0.300 2.489
1.00 23.705 23.705 0.230 0.450 2.453
Between Grid A-A and B-B 1.00 3.835 3.835 0.230 0.300 0.264
Between Grid D-D and E-E 1.00 7.630 7.630 0.230 0.300 0.526
Between Grid 3-3 and 4-4 1.00 6.300 6.300 0.230 0.300 0.434
Partition wall between Account room
1.00 3.380 3.380 0.230 0.300 0.233
and Exam room
Boys Toilet
Partition wall of boys toilet 1.00 5.300 5.300 0.230 0.300 1.590
5.00 1.500 7.500 0.230 0.300 2.250
Partition wall of urinal 1.00 3.325 3.325 0.230 0.300 0.997
Wall of disabled toilet 1.00 4.50 4.500 0.230 0.300 1.350
Girls Toilet
Partition wall of girls toilet 1.00 5.200 5.200 0.230 0.300 1.560
4.00 1.500 6.000 0.230 0.300 1.800
Partition wall of urinal 1.00 5.540 5.540 0.230 0.300 1.662
Wall of WC of teachers 1.00 2.360 2.360 0.230 0.300 0.708
Outside building
Stair near front lobby
Step I 1.00 4.400 4.400 0.600 0.150 0.396
Step II 1.00 4.400 4.400 0.300 0.150 0.198
Stair at backside of building
Stair
Step I 3.00 2.000 6.000 0.600 0.150 0.540
Secondary Beam
Betweeen Grid A-A & B-B 1.00 13.415 13.415 0.230 0.175 0.539
Betweeen Grid B-B & C-C 1.00 13.415 13.415 0.230 0.175 0.539
Betweeen Grid D-D & E-E 1.00 13.415 13.415 0.230 0.175 0.539
Secondary Beam
Betweeen Grid A-A & B-B 1.00 11.780 11.780 0.230 0.175 0.474
Betweeen Grid B-B & C-C 1.00 11.780 11.780 0.230 0.175 0.474
Betweeen Grid D-D & E-E 1.00 11.780 11.780 0.230 0.175 0.474
Betweeen Grid 1-1 & 2-2 1.00 22.820 22.820 0.230 0.175 0.918
Betweeen Grid 3-3 & 4-4 1.00 18.540 18.540 0.230 0.175 0.746
25.136 Cu.m
Second Floor
Main Beam
Along Grid A-A 1.00 11.940 11.940 0.350 0.425 1.776
Along Grid B-B 1.00 11.765 11.765 0.350 0.425 1.750
Along Grid C-C 1.00 11.765 11.765 0.350 0.425 1.750
Along Grid D-D 1.00 11.765 11.765 0.350 0.425 1.750
Along Grid E-E 1.00 11.940 11.940 0.350 0.425 1.776
Along Grid 1-1 1.00 22.420 22.420 0.350 0.425 3.334
Along Grid 2-2 1.00 22.270 22.270 0.350 0.425 3.312
Along Grid 3-3 1.00 22.270 22.270 0.350 0.425 3.312
Along Grid 4-4 1.00 22.120 22.120 0.350 0.425 3.290
Secondary Beam
Betweeen Grid A-A & B-B 1.00 11.780 11.780 0.230 0.175 0.474
Betweeen Grid B-B & C-C 1.00 11.780 11.780 0.230 0.175 0.474
Betweeen Grid D-D & E-E 1.00 11.780 11.780 0.230 0.175 0.474
Betweeen Grid 1-1 & 2-2 1.00 22.820 22.820 0.230 0.175 0.918
Betweeen Grid 3-3 & 4-4 1.00 18.540 18.540 0.230 0.175 0.746
25.136 Cu.m
Third Floor
Main Beam
Along Grid A-A 1.00 11.940 11.940 0.300 0.325 1.164
Along Grid B-B 1.00 11.765 11.765 0.300 0.325 1.147
Along Grid C-C 1.00 11.765 11.765 0.300 0.325 1.147
Along Grid D-D 1.00 11.765 11.765 0.300 0.325 1.147
Along Grid E-E 1.00 11.940 11.940 0.300 0.325 1.164
Along Grid 1-1 1.00 22.420 22.420 0.300 0.325 2.185
Along Grid 2-2 1.00 22.270 22.270 0.300 0.325 2.171
Along Grid 3-3 1.00 22.270 22.270 0.300 0.325 2.171
Along Grid 4-4 1.00 22.120 22.120 0.300 0.325 2.156
Secondary Beam
Betweeen Grid A-A & B-B 1.00 11.930 11.930 0.230 0.175 0.480
Betweeen Grid B-B & C-C 1.00 11.930 11.930 0.230 0.175 0.480
Betweeen Grid D-D & E-E 1.00 11.930 11.930 0.230 0.175 0.480
Betweeen Grid 1-1 & 2-2 1.00 23.020 23.020 0.230 0.175 0.926
Betweeen Grid 3-3 & 4-4 1.00 18.690 18.690 0.230 0.175 0.752
17.570 Cu.m
Secondary Beam
Betweeen Grid B-B & C-C 1.00 7.260 7.260 0.230 0.125 0.208
Betweeen Grid 3-3 & 4-4 1.00 10.330 10.330 0.230 0.125 0.296
4.958 Cu.m
Total RCC for beam 147.308 Cu.m
Slab
Ground Floor
Entire blocks slab 1.00 25.870 25.870 15.890 0.125 51.384
Deduction for staircase portion -1.00 5.140 -5.140 4.40 0.125 -2.827
48.557 Cu.m
First Floor
Entire blocks slab 1.00 375.096 0.125 46.887
Deduction for staircase portion -1.00 5.140 -5.140 4.40 0.125 -2.827
44.060 Cu.m
Second Floor
Entire blocks slab 1.00 380.690 0.125 47.586
Deduction for staircase portion -1.00 5.140 -5.140 4.40 0.125 -2.827
44.759 Cu.m
Third Floor
Entire blocks slab 1.00 384.470 0.125 48.058
Deduction for staircase portion -1.00 5.140 -5.140 4.40 0.125 -2.827
45.231 Cu.m
Fourth Floor
Entire blocks slab 1.00 12.835 12.835 9.535 0.125 15.297
15.297 Cu.m
Total RCC for slab 197.904 Cu.m
Staircase
Ground Floor
First Flight
First landing slab 1.00 2.100 2.100 0.485 0.200 0.203
Waist slab 1.00 3.360 3.360 2.100 0.200 1.411
Second Landing slab 1.00 1.890 1.890 2.200 0.200 0.831
Riser 5.00 2.100 10.500 0.300 0.150 0.472
Second Flight
Landing slab 1.00 2.275 2.275 2.200 0.200 1.001
Waist slab 1.00 3.360 3.360 2.100 0.200 1.411
Riser 5.00 2.100 10.500 0.300 0.150 0.472
5.801 Cu.m
First Floor
First Flight
First landing slab 1.00 2.100 2.100 0.485 0.200 0.203
Waist slab 1.00 3.360 3.360 2.100 0.200 1.411
Second Landing slab 1.00 1.890 1.890 2.200 0.200 0.831
Riser 5.00 2.100 10.500 0.300 0.150 0.472
Second Flight
Landing slab 1.00 2.275 2.275 2.200 0.200 1.001
Waist slab 1.00 3.360 3.360 2.100 0.200 1.411
Riser 5.00 2.100 10.500 0.300 0.150 0.472
5.801 Cu.m
Second Floor
First Flight
First landing slab 1.00 2.100 2.100 0.485 0.200 0.203
Waist slab 1.00 3.360 3.360 2.100 0.200 1.411
Second Landing slab 1.00 1.890 1.890 2.200 0.200 0.831
9 FORMWORKS
For column
For Column upto Top Tie Beam
Column(450*450) 8.00 1.800 14.400 1.800 25.920
Column(500*500) 9.00 2.000 18.000 1.800 32.400
Column(550*500) 3.00 2.200 6.600 1.800 11.880
70.200 Sq.m
Ground Floor
Column(450*450) 8.00 1.800 14.400 3.000 43.200
Column(500*500) 9.00 2.000 18.000 3.000 54.000
Column(550*550) 3.00 2.200 6.600 3.000 19.800
117.000 Sq.m
First Floor
Column(450*450) 8.00 1.800 14.400 3.000 43.200
Column(500*500) 9.00 2.000 18.000 3.000 54.000
Column(550*550) 3.00 2.200 6.600 3.000 19.800
117.000 Sq.m
Second Floor
Column(450*450) 8.00 1.800 14.400 3.000 43.200
Column(500*500) 9.00 2.000 18.000 3.000 54.000
Column(550*550) 3.00 2.200 6.600 3.000 19.800
117.000 Sq.m
Third Floor
Column(450*450) 8.00 1.800 14.400 3.000 43.200
Column(500*500) 9.00 2.000 18.000 3.000 54.000
Column(550*550) 3.00 2.200 6.600 3.000 19.800
117.000 Sq.m
Fourth Floor
Short Column(450*450) 8.00 1.800 14.400 1.000 14.400
Column(500*500) 9.00 2.000 18.000 3.000 54.000
Column(550*550) 3.00 2.200 6.600 3.000 19.800
88.200 Sq.m
Fourth Floor
Short Column(500*500) 6.00 2.000 12.000 1.000 12.000
Short Column(550*550) 3.00 2.200 6.600 1.000 6.600
18.600 Sq.m
Total formwork for column 645.000 Sq.m
For Beam
For Foundation Beam
Along Grid A-A 1.00 9.960 9.960 0.700 6.972
Along Grid B-B 1.00 9.835 9.835 0.700 6.884
Along Grid C-C 1.00 9.835 9.835 0.700 6.884
Along Grid D-D 1.00 9.835 9.835 0.700 6.884
Along Grid E-E 1.00 9.960 9.960 0.700 6.972
Along Grid 1-1 1.00 22.420 22.420 0.700 15.694
Along Grid 2-2 1.00 22.270 22.270 0.700 15.589
Secondary Beam
Betweeen Grid A-A & B-B 1.00 13.415 13.415 0.580 7.780
Betweeen Grid B-B & C-C 1.00 13.415 13.415 0.580 7.780
Betweeen Grid D-D & E-E 1.00 13.415 13.415 0.580 7.780
Betweeen Grid 1-1 & 2-2 1.00 22.820 22.820 0.580 13.235
Betweeen Grid 3-3 & 4-4 1.00 18.540 18.540 0.580 10.753
234.294 Sq.m
First Floor
Main Beam
Along Grid A-A 1.00 11.940 11.940 1.200 14.328
Along Grid B-B 1.00 11.765 11.765 1.200 14.118
Along Grid C-C 1.00 11.765 11.765 1.200 14.118
Along Grid D-D 1.00 11.765 11.765 1.200 14.118
Along Grid E-E 1.00 11.940 11.940 1.200 14.328
Along Grid 1-1 1.00 22.420 22.420 1.200 26.904
Along Grid 2-2 1.00 22.270 22.270 1.200 26.724
Secondary Beam
Betweeen Grid A-A & B-B 1.00 11.780 11.780 0.580 6.832
Betweeen Grid B-B & C-C 1.00 11.780 11.780 0.580 6.832
Betweeen Grid D-D & E-E 1.00 11.780 11.780 0.580 6.832
Betweeen Grid 1-1 & 2-2 1.00 22.820 22.820 0.580 13.235
Betweeen Grid 3-3 & 4-4 1.00 18.540 18.540 0.580 10.753
222.390 Sq.m
Second Floor
Main Beam
Along Grid A-A 1.00 11.940 11.940 1.200 14.328 0.425
Along Grid B-B 1.00 11.765 11.765 1.200 14.118
Along Grid C-C 1.00 11.765 11.765 1.200 14.118
Along Grid D-D 1.00 11.765 11.765 1.200 14.118
Along Grid E-E 1.00 11.940 11.940 1.200 14.328
Along Grid 1-1 1.00 22.420 22.420 1.200 26.904
Along Grid 2-2 1.00 22.270 22.270 1.200 26.724
Along Grid 3-3 1.00 22.270 22.270 1.200 26.724
Along Grid 4-4 1.00 22.120 22.120 1.200 26.544
Secondary Beam
Betweeen Grid A-A & B-B 1.00 11.780 11.780 0.580 6.832
Betweeen Grid B-B & C-C 1.00 11.780 11.780 0.580 6.832
Betweeen Grid D-D & E-E 1.00 11.780 11.780 0.580 6.832
Betweeen Grid 1-1 & 2-2 1.00 22.820 22.820 0.580 13.235
Betweeen Grid 3-3 & 4-4 1.00 18.540 18.540 0.580 10.753
222.390 Sq.m
Third Floor
Main Beam
Along Grid A-A 1.00 11.940 11.940 0.950 11.343 0.325
Along Grid B-B 1.00 11.765 11.765 0.950 11.176
Along Grid C-C 1.00 11.765 11.765 0.950 11.176
Along Grid D-D 1.00 11.765 11.765 0.950 11.176
Along Grid E-E 1.00 11.940 11.940 0.950 11.343
Along Grid 1-1 1.00 22.420 22.420 0.950 21.299
Along Grid 2-2 1.00 22.270 22.270 0.950 21.156
Along Grid 3-3 1.00 22.270 22.270 0.950 21.156
Along Grid 4-4 1.00 22.120 22.120 0.950 21.014
Secondary Beam
Betweeen Grid A-A & B-B 1.00 11.930 11.930 0.580 6.919
Betweeen Grid B-B & C-C 1.00 11.930 11.930 0.580 6.919
Betweeen Grid D-D & E-E 1.00 11.930 11.930 0.580 6.919
Betweeen Grid 1-1 & 2-2 1.00 23.020 23.020 0.580 13.351
Betweeen Grid 3-3 & 4-4 1.00 18.690 18.690 0.580 10.840
185.787 Sq.m
Fourth Floor
Main Beam
Along Grid B-B 1.00 6.835 6.835 0.950 6.493
Along Grid C-C 1.00 6.835 6.835 0.950 6.493
Along Grid D-D 1.00 6.835 6.835 0.950 6.493
Along Grid 2-2 1.00 10.160 10.160 0.950 9.652
Along Grid 3-3 1.00 10.160 10.160 0.950 9.652
Along Grid 4-4 1.00 10.060 10.060 0.950 9.557
Secondary Beam
Betweeen Grid B-B & C-C 1.00 7.260 7.260 0.580 4.210
Betweeen Grid 3-3 & 4-4 1.00 10.330 10.330 0.580 5.991
10 REINFORCEMENT Kg
11.4.2 On floor
Ground Floor
Boys Toilet 1.00 6.300 6.300 5.200 32.760
Janitor 1.00 1.670 1.670 1.270 2.120
Girls Toilet 1.00 6.300 6.300 5.200 32.760
WC for teachers 1.00 1.305 1.305 1.225 1.598
First Floor
WC for teachers 1.00 1.500 1.500 1.200 1.800
Total tile on floor 71.038 Sq.m
12 PLASTERING WORKS
12mm thick cement plaster in (1:3) in
12.1 Sq.m
ceiling ,beams etc
Ground Floor
Ceiling
Headmaster's room 1.00 6.300 6.300 5.200 32.760
Teacher's room 1 1.00 6.300 6.300 5.200 32.760
ECD 1.00 6.300 6.300 5.200 32.760
Account room 1.00 3.700 3.700 3.380 12.506
Exam room 1.00 3.700 3.700 3.380 12.506
Corridor and staircase portion 1.00 61.385 61.385
Front lobby 1.00 4.400 4.400 1.900 8.360
Lobby outside headmaster's room 1.00 4.860 4.860 3.835 18.638
Female Toilet 1.00 6.300 6.300 5.200 32.760
Male Toilet 1.00 6.300 6.300 5.200 32.760
Janitor room 1.00 1.670 1.670 1.600 2.672
WC 1.00 1.305 1.305 0.955 1.246
Projected slab 1.00 18.400 18.400 1.635 30.084
1.00 52.910 52.910 0.550 29.100
Main beam
Along Grid A-A 1.00 3.275 3.275 0.850 2.783 2 sides
Along Grid
1.00 3.090 3.090 0.850 2.626
B-B Along Grid
1.00 3.430 3.430 0.850 2.915
C-C
Along Grid
1.00 10.750 10.750 0.850 9.137
D-D
Along Grid
1.00 8.685 8.685 0.850 7.382
E-EGrid
Along
1.00 3.400 3.400 0.850 2.890
2-2
Along Grid
1.00 12.940 12.940 0.850 10.999
3-3
Along Grid
1.00 6.030 6.030 0.850 5.125
4-4
Secondary Beam
Betweeen Grid A-A & B-B 1.00 13.305 13.305 0.350 4.656
Betweeen Grid B-B & C-C 1.00 13.555 13.555 0.350 4.744
Betweeen Grid D-D & E-E 1.00 13.555 13.555 0.350 4.744
Betweeen Grid 1-1 & 2-2 1.00 22.820 22.820 0.350 7.987
Betweeen Grid 3-3 & 4-4 1.00 18.540 18.540 0.350 6.489
Staircase
Waist slab 1.00 3.360 3.360 2.100 7.056
Sides 1.00 3.360 3.360 0.350 1.176
Second Landing slab 1.00 1.660 1.660 2.100 3.486
Second Flight
Landing slab 1.00 2.045 2.045 2.100 4.294
Waist slab 1.00 3.360 3.360 2.100 7.056
Sides 1.00 3.360 3.360 0.350 1.176
Ground Floor
Around Building 1.00 96.856 96.850 2.875 278.443
Wall on side of door 2.00 1.700 3.400 1.000 3.400
Column 1.00 1.800 1.800 2.875 5.175
Ramp support wall 2.00 10.840 21.680 0.350 0.225 4.878
Flower bed near front lobby
Flower bed 1 1.00 5.570 5.570 0.600 3.342
Flower bed 2 1.00 11.040 11.040 0.600 6.624
Flower bed at backside of building
Flower bed 1 1.00 3.310 3.310 0.600 1.986
Flower bed 2 1.00 6.075 6.075 0.600 3.645
Flower bed near ramp 1.00 10.160 10.160 0.600 6.096
Deduction for openings
W1(1800*1200) -9.00 1.800 -16.200 1.200 -19.440
W2(1800*1750) -1.00 1.800 -1.800 1.750 -3.150
W3(2100*875) -1.00 2.100 -2.100 0.875 -1.837
V1(1800*1200) -2.00 0.600 -1.200 1.200 -1.440
V2(1800*1200) -2.00 2.400 -4.800 1.200 -5.760
V3(1800*1200) -1.00 1.000 -1.000 1.200 -1.200
DW1(2000*2450) -1.00 2.000 -2.000 2.450 -4.900
D2(1500*2450) -1.00 2.000 -2.000 2.450 -4.900
D3(1000*2450) -3.00 2.000 -6.000 2.450 -14.700
Ground Floor
D5(1100*2450) 5.00 0.974 4.870 2.037 9.920
First Floor
D5(1100*2450) 12.00 0.974 11.688 2.037 23.808
Second Floor
D5(1100*2450) 13.00 0.974 12.662 2.037 25.792
Third Floor
D5(1100*2550) 13.00 0.974 12.662 2.037 25.792
Fourth Floor
D5(1100*2550) 2.00 0.974 1.948 2.037 3.968
Total solid core flush door shutter 89.280 Sq.m
14.4 Window/ventilation
14.3.1 Supplying and fitting metal window Sq.m
Ground Floor
W1(1800*1200) 9.00 1.800 16.200 1.200 19.440
W2(1800*1750) 2.00 1.800 3.600 1.750 6.300
W3(2100*875) 1.00 2.100 2.100 0.875 1.837
V1(600*600) 2.00 0.600 1.200 0.600 0.720
V2(2400*600) 2.00 2.400 4.800 0.600 2.880
V3(1000*600) 1.00 1.000 1.000 0.600 0.600
First Floor
W1(1800*1200) 13.00 1.800 23.400 1.200 28.080
W2(1800*1750) 2.00 1.800 3.600 1.750 6.300
W3(2100*875) 1.00 2.100 2.100 0.875 1.837
V1(600*600) 1.00 0.600 0.600 0.600 0.360
Second Floor
W1(1800*1200) 13.00 1.800 23.400 1.200 28.080
W2(1800*1750) 2.00 1.800 3.600 1.750 6.300
W3(2100*875) 1.00 2.100 2.100 0.875 1.837
Third Floor
W1(1800*1200) 13.00 1.800 23.400 1.200 28.080
W2'(1800*1850) 2.00 1.800 3.600 1.850 6.660
W3'(2100*975) 1.00 2.100 2.100 0.975 2.047
Fourth Floor
W1(1800*1200) 5.00 1.800 9.000 1.200 10.800
Total metal window 152.158 Sq.m
16 Railing work
Staircase railing
Ground Floor 1.00 7.275 7.270 7.270
First Floor 1.00 7.275 7.270 7.270
Second Floor 1.00 7.275 7.270 7.270
Third Floor 1.00 7.275 7.270 7.270
Fourth Floor 1.00 2.100 2.100 2.100
Ramp railing
Ground Floor 2.00 5.420 10.840 10.840
1.00 2.200 2.200 2.200
Total railing for staircase and ramp 44.220 Rm
Ground Floor
On walls
Boys Toilet
Inner toilet 5.00 5.20 26.000 1.20 31.200
Inside disabled toilet 1.00 9.650 9.650 1.20 11.580
Outside boys toilet and disabled toilet 1.00 23.310 23.310 1.20 27.972
Floor 1.00 6.300 6.300 5.200 32.760
1.00 1.670 1.670 1.270 2.120
19 GRILL WORK
Ground Floor
W1(1800*1200) 10.00 1.800 18.000 1.200 21.600
W2(1800*1750) 2.00 1.800 3.600 1.750 6.300
W3(2100*875) 1.00 2.100 2.100 0.875 1.837
First Floor
W1(1800*1200) 13.00 1.800 23.400 1.200 28.080
W2(1800*1750) 2.00 1.800 3.600 1.750 6.300
W3(2100*875) 1.00 2.100 2.100 0.875 1.837
Second Floor
W3(2100*875) 1.00 2.100 2.100 0.875 1.837
Third Floor
W3'(2100*975) 1.00 2.100 2.100 0.975 2.047
Total Grill work 69.838 Sq.m
PCC
Base of Foundation -9 1.20 1.20 0.10 -1.30
Trench Plan
Along Grid A, B, C -3 7.30 0.45 0.05 -0.49
Along Grid 1,2 and 3 -3 11.80 0.45 0.05 -0.80
Side of Ramp -2 6.23 0.45 0.05 -0.28
Drain -1 13.40 0.63 0.08 -0.63
Foundation Tie Beam
Along Grid A, B, C -3 7.70 0.25 0.30 -1.73
Along Grid 1,2 and 3 -3 12.20 0.25 0.30 -2.75
Column Below Ground level
Along A, B, C -9 0.40 0.40 0.85 -1.22
Stone Masnory Below Ground Lvl
Along Grid A, B, C -3 7.70 0.35 0.85 -6.87
Along Grid 1 and 3 -2 12.20 0.35 0.85 -7.26
Side of Ramp -2 6.23 0.45 0.68 -3.78
Plinth beam(250x300)
Along Grid A, B, C 3 7.70 0.25 0.30 1.73
Along Grid 1,2 and 3 3 12.20 0.25 0.30 2.75
E Lintel Bands
Along Grid A, B, C/(1-2) 3 5.60 0.25 0.13 0.53
Along Grid 1,2/(A-C) 2 11.20 0.25 0.13 0.70
B Beam
Footing beam(250x300)
Along Grid A, B, C 3 7.70 0.60 13.86
Along Grid 1,2 and 3 3 12.20 0.60 21.96
Plinth beam(250x300)
Along Grid A, B, C 3 7.70 0.60 13.86
Along Grid 1,2 and 3 3 12.20 0.60 21.96
Wall
Internal wall of internal room 2 38.90 2.10 163.38
Walls of T-Shaped 2 6.38 2.10 26.78
Internal Walls 2 6.99 2.10 29.36
Deductions for Half Brick walls
-1 0.9 2.1 -1.89
-1 0.9 2.1 -1.89
Half brick wall both sides
Water Tough Floor 2 6.25 0.625 7.81
Elevation Portion 2 2.8 0.925 5.18
2 2.8 0.775 4.34
Total of TERRAZO CAST IN-SITU DADO 303.11 sq.m
6 ROOFING/ TERRACING WORKS
6.1 Metal Works
Total
Description Nos length Kg/m Total
Length
A Truss
Top Chord NB40M 10 3.37 3.61 121.66
Bottom Chord NB40M 5 6.30 3.61 113.72
Struts NB32M 5 4.15 3.14 65.16
Side Post NB 40M 5 1.904 3.61 34.37
King Post NB40M 10 0.94 3.61 33.93
Purlin NB 40M 10 14.60 3.61 527.06
Bracing NB 40M 16 3.23 3.61 186.56
Runner NB 40M 2 14.60 3.61 105.41
25% Wastes for Nuts and Bolts 1187.87 296.97
Total of Truss 1,485.00 k.g
Slab Deductions
Along grid 3 -1 12.50 0.15 -0.94
Along grid 2-External face -1 12.50 0.15 -0.94
Along Grid A, B, C/(2-3) -3 2.33 0.15 -0.52
slab
Along corridor 2 6.575 2.33 30.64
Total of ON CEILING (1:4) 64.00 sq.m
7.2 ON OUTER WALL (1:6):
External Plaster on Walls/Beam/Column
Building edge columns 4 3.00 0.95 11.40
Along grid B 2 3.00 0.45 2.70
1 3 0.30 0.90
Exterior edge column 2 1.95 1.35 5.27
2 1.05 1.60 3.36
Beam Plaster
Along grid 1 1 12.50 0.43 5.38
Along grid 3 1 12.50 0.48 6.00
Along grid A, C/(1-2) 2 6.25 0.43 5.38
Along Grid A, C/(2-3) 2 2.33 0.48 2.24
Slab Side Face
2 0.55
Total of Area on
External Plaster 1.10
Walls/Beam/Column 44.00
7.2.1 BAND PLASTER
Lintel Bands
Along Grid A, B, C/(1-2) 3 5.60 0.13 2.18
Along Grid 1,2/(A-C) 2 11.20 0.13 2.91
0.00
Along Grid A, B, C/(1-2) 3 5.60 0.13 2.18
Along Grid 1,2/(A-C) 2 11.20 0.13 2.91
Deductions 0.00
Door(1000 wide) -2 1.00 0.13 -0.26
Door(900 wide) -2 0.90 0.13 -0.23
Sill Bands
Along Grid A, B, C/(1-2) 3 5.60 0.08 1.34
Along Grid 1,2/(A-C) 2 11.20 0.08 1.79
Deductions
Door(1000 wide) -2 1.00 0.08 -0.16
Door(900 wide) -2 0.90 0.08 -0.14
Total of BAND PLASTER 13.00 r.m
7.3 DISTEMPER PAINT
As Per Internal Plaster on Walls 1.00 200.25 200.25
2 CONCRETE WORKS
2.1 P.C.C. Works
2.1.1 P.C.C.(1:3:6) Works
For Isolated Foundation
Footing F1 16 1.50 1.50 0.10 3.60
Footing F2 2 1.70 1.70 0.10 0.58
For Lower Tie Beam
Along Grid A, C and F 3 5.90 0.45 0.05 0.40
Along Grid B,E 2 5.70 0.35 0.05 0.20
Along Grid D 1 5.90 0.35 0.05 0.10
Along grid 1 and 3 2 21.25 0.45 0.05 0.96
Along grid 2 1 21.25 0.35 0.05 0.37
Total of P.C.C.(1:3:6) Works 6.21 cu.m
2.1.2 P.C.C.(1:2:4) Works
Below Plinth Beam
Along grid 1 and 3 2 23.25 0.35 0.05 0.81
Along Grid A, C and F 3 8.60 0.35 0.05 0.45
Below Ground Floor
Principal Room 1 5.25 6.75 0.08 2.84
Administration 1 6.75 5.28 0.08 2.85
ECD and Store 2 6.75 5.25 0.08 5.67
Corridor 1 25.63 2.25 0.08 4.32
Below Stairs, Store below Landing and Lobby 1
7.10 3.20 0.08 1.70
Secondary beam(250x425)
Along Grid 1a 1 24.00 0.25 0.43 2.55
Along Grid A1, B1, D1, E1 4 8.65 0.25 0.43 3.68
Landing Beam 250 x 380 1 3.05 0.25 0.38 0.29
Slab deduction
Main beam(300x525)
Along grid 1,2,3 -3 23.25 0.30 0.15 -3.14
Along grid A,B,C,D,E and F -6 8.60 0.30 0.15 -2.32
Secondary beam(250x425)
Along Grid 1a -1 24.00 0.25 0.15 -0.90
Along Grid A1, B1, D1, E1 -4 8.65 0.25 0.15 -1.30
C Column
Ground floor plan
Total columns(450x450) 18 0.45 0.45 3.00 10.94
E Staircase
Landing A 1 1.45 2.13 0.15 0.46
Landing B 1 3.20 1.80 0.15 0.86
Waist Slab 2 3.37 1.45 0.15 1.47
Steps 19 0.0225 Area 1.45 0.62
F Lintel Bands
Ground floor level
Along grid 1 1 20.20 0.25 0.125 0.63
Partition 1 5.25 0.13 0.125 0.09
Along grid 2 1 20.20 0.25 0.125 0.63
Along grid A,B,C,D,E, F 6 6.55 0.25 0.125 1.23
H Small Pillars for Metal Work in Corridor 10 0.50 0.250 0.250 0.31
J Soak Pit
RCC slab 1 2.84 Area 0.13 0.37
Total of R.C.C Works M20 140.65 cu.m
Secondary beam(250x425)
Along Grid 1a 1 24.00 1.15 27.60
Along Grid A1, B1, D1, E1 4 8.65 1.15 39.79
Landing Beam 250 x 380 1 3.05 1.01 3.08
Slab deduction
Main beam(300x525)
Along grid 1,2,3 -3 23.25 0.250 -17.44
Along grid A,B,C,D,E and F -6 8.60 0.250 -12.90
Secondary beam(250x425)
Along Grid 1a -1 24.00 0.250 -6.00
Along Grid A1, B1, D1, E1 -4 8.65 0.250 -8.65
G Sill Bands
Ground floor level
Along grid 1 2 23.25 0.075 3.49
Partition 2 5.25 0.075 0.79
Along grid 2 2 20.20 0.075 3.03
Along Grid A and F 4 6.55 0.075 1.97
Along grid B,C,D, E 8 6.55 0.075 3.93
for Store Below Landing 2 3.05 0.075 0.46
Additional formwork in grid 1 1 23.25 0.075 1.74
Additional formwork in grid A and F 2 6.55 0.075 0.98
First floor level
Along grid 1 2 20.20 0.075 3.03
Along grid 2 2 20.20 0.075 3.03
Along Grid A and F 4 6.55 0.075 1.97
Along grid C,D, E 6 6.55 0.075 2.95
Deduction of Doors For Sill
Ground floor level
D1 -8 1.10 0.075 -0.66
D2 -2 1.00 0.075 -0.15
D3 -2 1.10 0.075 -0.17
First floor level
D1 -8 1.10 0.075 -0.66
D2 -2 1.00 0.075 -0.15
First Floor
Beam plaster
Second floor level
Main beam(300x400)
Along grid1 1.00 23.25 0.40 9.30
Along grid 2 1.00 23.25 0.40 9.30
Along grid 3 1.00 23.25 0.70 16.28
Along grid A,F 2.00 2.05 0.70 2.87
Along grid B,C,D,E 4.00 2.05 1.10 9.02
Total of Internal Plaster on Ceiling (1:4) 335.52 sq.m
7.2 External Plaster
7.2.1 Ground Floor
For Drain 1.00 44.35 0.31 13.75
For Ramp 1.00 1.33 1.09 1.45
1.00 6.75 0.75 5.06
Bench 1.00 2.23 2.16 4.81
Beam Plaster
First floor Level
Main Beam(300 x 525)
Along grid 1, 2 and 3 3.00 23.25 0.53 36.62
Along grid A and F 2.00 8.60 0.53 9.03
Second floor Level
Main Beam(300 x 400)
Along grid 1, 2 and 3 3.00 23.25 0.40 27.90
Along grid A and F 2.00 8.60 0.40 6.88
Column Plaster
Along grid 1 and 3 2.00 4.50 6.00 54.00
Along grid 2 2.00 2.70 5.88 31.75
Drain Plaster 1.00 44.35 1.76 78.06
Total of External Plaster 269.30 sq.m
7.2.2 Band Plaster
Lintel Plaster
Ground floor level
Along grid 1 and 2 2 20.20 40.40
Along grid A, F 2 6.55 13.10
First floor level
Along grid 1 1 23.25 23.25
Along grid 2 1 20.20 20.20
Along grid A, F 2 6.55 13.10
Sill Plaster
Ground floor level
Along grid 1 1 23.25 23.25
Along grid 2 1 20.20 20.20
Along Grid A and F 2 6.55 13.10
First floor level
Along grid 1 and 2 2 20.20 40.40
Along Grid A and F 2 6.55 13.10
3 Earthback Filling
Filling Upto Ground Level
For Footing of column
F1 2.00 3.150 6.300 3.150 1.800 35.721
F2 2.00 2.850 5.700 2.850 1.800 29.241
F3 2.00 2.775 5.550 2.775 1.800 27.722
F4 4.00 2.475 9.900 2.475 1.800 44.104
F5 2.00 2.175 4.350 2.175 1.800 17.030
F6 4.00 1.650 6.600 1.650 1.800 19.602
F7 2.00 1.500 3.000 1.500 1.800 8.100
Foundation of beam and wall
H=1.8-
Along Grid A-A
0.45+0.15+
(L=6+2.5-2.175/2-2.475- 1.00 4.188 4.188 0.450 1.575 2.968
0.075=1.57
1.5/2=4.188)
5
Along Grid B-B
(L=6+2.5-2.775/2- 1.00 3.138 3.138 0.450 1.575 2.224
3.15-1.65/2=3.138)
Along Grid C-C
(L=6+2.5-2.475/2-2.85- 1.00 3.588 3.588 0.450 1.575 2.542
4 Boulder Soling
For Footing of column
F1 2.00 3.150 6.300 3.150 0.150 2.976
F2 2.00 2.850 5.700 2.850 0.150 2.436
F3 2.00 2.775 5.550 2.775 0.150 2.310
F4 4.00 2.475 9.900 2.475 0.150 3.675
F5 2.00 2.175 4.350 2.175 0.150 1.419
F6 4.00 1.650 6.600 1.650 0.150 1.633
F7 2.00 1.500 3.000 1.500 0.150 0.675
For Foundation Beam
Along Grid A-A H=0.3+1.05
1.00 7.100 7.100 0.450 0.150 0.479
=1.35
Along Grid B-B
1.00 7.100 7.100 0.450 0.150 0.479
Along Grid C-C 1.00 7.100 7.100 0.450 0.150 0.479
Along Grid D-D 1.00 7.100 7.100 0.450 0.150 0.479
Along Grid E-E 1.00 7.100 7.100 0.450 0.150 0.479
Along Grid F-F 1.00 7.100 7.100 0.450 0.150 0.479
Along Grid 1-1
1.00 25.250 25.250 0.450 0.150 1.704
Along Grid 2-2 1.00 25.250 25.250 0.450 0.150 1.704
Along Grid 3-3
1.00 25.250 25.250 0.450 0.150 1.704
Floors
Room 4.00 5.890 23.560 5.770 0.150 20.391
Staircase portion 1.00 5.890 5.890 4.400 0.150 3.887
Corridor 1.00 28.520 28.520 2.270 0.150 9.711
Ramp 1.00 6.500 6.500 1.300 0.150 1.267
Foundation
Entry porch staircase(East-South 1.00 26.100 0.150 2.349
direction) 26.100 0.600
Entry porch staircase (West direction) 1.00 2.500 2.500 0.600 0.150 0.225
Ramp support wall 1.00 9.300 9.300 0.350 0.150 0.488
Total boulder soling 61.428 Cu.m
5 Sand Filling
Floors
Room 4.00 5.890 23.560 5.770 0.050 6.797
Staircase portion 1.00 5.890 5.890 4.400 0.050 1.295
Corridor 1.00 28.520 28.520 2.270 0.050 3.237
Ramp 1.00 6.500 6.500 1.300 0.050 0.422
Total Sand Filling Work 11.751 Cu.m
7 Brickwork
Brick Masonry Works in 1:6 C/S
7.1 Cu.m
mortar
Toe wall between lower and upper tie
beam
Along Grid A-A
1.00 7.850 7.850 0.230 1.250 2.256
Along Grid B-B
1.00 7.850 7.850 0.230 1.250 2.256
Along Grid C-C 1.00 7.850 7.850 0.230 1.250 2.256
Along Grid D-D 1.00 7.850 7.850 0.230 1.250 2.256
8.2 M15
Floors
Meeting room 1.00 5.830 5.830 5.890 0.075 2.575
Teacher room 1.00 5.830 5.830 5.890 0.075 2.575
Store room 1.00 2.815 2.810 2.200 0.075 0.463
Account 1.00 2.786 2.780 3.584 0.075 0.747
Administration 1.00 2.872 2.870 5.890 0.075 1.267
Headmaster room 1.00 5.890 5.890 3.090 0.075 1.365
Store room 1.00 5.890 5.890 2.800 0.075 1.236
Counselling room 1.00 3.000 3.000 2.045 0.075 0.460
Staircase portion 1.00 5.890 5.890 4.400 0.075 1.943
Corridor 1.00 29.250 29.250 2.200 0.075 4.826
Ramp 1.00 6.500 6.500 1.300 0.075 0.633
Total M15 (1:2:4) PCC 18.090 Cu.m
8.3 M20
For Column footing
Rectangular Section
F1 2.00 3.150 6.300 3.150 0.150 2.976
F2 2.00 2.850 5.700 2.850 0.150 2.436
F3 2.00 2.775 5.550 2.775 0.150 2.310
F4 4.00 2.475 9.900 2.475 0.150 3.675
F5 2.00 2.175 4.350 2.175 0.150 1.419
F6 4.00 1.650 6.600 1.650 0.150 1.633
F7 2.00 1.500 3.000 1.500 0.150 0.675
Trapazoidal Section
V= h/6(A1+A2+4*mean
F1 2.00 3.150 6.300 0.750 0.250 2.620
F2 2.00 2.850 5.700 0.750 0.250 2.170
V=h/
6(A1+A2+4
Araniko S.S. Page72of209 2-Admin-8
*mean Area)
Measurement
S.N Description Nos. Quantity Unit Remarks
Length T.Length Breadth Height
F3 2.00 2.775 5.550 0.750 0.250 2.064 V=h/
6(A1+A2+4
F4 4.00 2.475 9.900 0.750 0.250 3.344 *mean Area)
F5 2.00 2.175 4.350 0.750 0.250 1.322
F6 4.00 1.650 6.600 0.700 0.250 1.604
F7 2.00 1.500 3.000 0.700 0.250 0.684
Total RCC for footing 28.932 Cu.m
Column
For Column upto Top Tie Beam
Column C1 (A2,C2,D2,F2,C3) 5.00 0.350 1.750 0.350 1.800 1.102
Column C2 (B2,E2,A3,B3,C3,E3,F3) 7.00 0.350 2.450 0.350 1.800 1.543
Column C3 (A1,B1,C1,D1,E1,F1) 6.00 0.300 1.800 0.300 1.800 0.972
3.617 Cu.m
Ground Floor
Column C1 (A2,C2,D2,F2,C3) 5.00 0.350 1.750 0.350 3.000 1.837
Column C2 (B2,E2,A3,B3,C3,E3,F3) 7.00 0.350 2.450 0.350 3.000 2.572
Column C3 (A1,B1,C1,D1,E1,F1) 6.00 0.300 1.800 0.300 3.000 1.620
6.029 Cu.m
First Floor
Column C1 (A2,C2,D2,F2,C3) 5.00 0.350 1.750 0.350 3.000 1.837
Column C2 (B2,E2,A3,B3,C3,E3,F3) 7.00 0.350 2.450 0.350 3.000 2.572
Column C3 (A1,B1,C1,D1,E1,F1) 6.00 0.300 1.800 0.300 3.000 1.620
6.029 Cu.m
Total RCC for column 15.675 Cu.m
Beam
For Foundation Beam
Along Grid A-A
1.00 7.850 7.850 0.230 0.300 0.541
Along Grid B-B
1.00 7.850 7.850 0.230 0.300 0.541
Along Grid C-C 1.00 7.850 7.850 0.230 0.300 0.541
Along Grid D-D 1.00 7.850 7.850 0.230 0.300 0.541
Along Grid E-E 1.00 7.850 7.850 0.230 0.300 0.541
Along Grid F-F 1.00 7.850 7.850 0.230 0.300 0.541
Along Grid 1-1
1.00 27.250 27.250 0.230 0.300 1.880
Along Grid 2-2 1.00 27.000 27.000 0.230 0.300 1.863
Along Grid 3-3
1.00 27.000 27.000 0.230 0.300 1.863
8.852 Cu.m
For Top Tie Beam
Along Grid A-A
1.00 7.850 7.850 0.230 0.300 0.541
Along Grid B-B
1.00 7.850 7.850 0.230 0.300 0.541
Along Grid C-C 1.00 7.850 7.850 0.230 0.300 0.541
Along Grid D-D 1.00 7.850 7.850 0.230 0.300 0.541
Along Grid E-E 1.00 7.850 7.850 0.230 0.300 0.541
Along Grid F-F 1.00 7.850 7.850 0.230 0.300 0.541
Along Grid 1-1
1.00 27.250 27.250 0.230 0.300 1.880
Along Grid 2-2 1.00 27.000 27.000 0.230 0.300 1.863
Along Grid 3-3
1.00 27.000 27.000 0.230 0.300 1.863
8.852 Cu.m
Ground Floor
Main Beam
Along Grid A-A
1.00 7.850 7.850 0.300 0.300 0.706
Along Grid B-B
1.00 7.850 7.850 0.300 0.300 0.706
Along Grid C-C 1.00 7.850 7.850 0.300 0.300 0.706
Along Grid D-D 1.00 7.850 7.850 0.300 0.300 0.706
Along Grid E-E 1.00 7.850 7.850 0.300 0.300 0.706
Along Grid F-F 1.00 7.850 7.850 0.300 0.300 0.706
Along Grid 1-1
1.00 27.250 27.250 0.300 0.300 2.452
Along Grid 2-2 1.00 27.000 27.000 0.300 0.300 2.430
Along Grid 3-3
1.00 27.000 27.000 0.300 0.300 2.430
Secondary Beam
Betweeen Grid A-A & B-B 1.00 7.900 7.900 0.230 0.175 0.317
Betweeen Grid B-B & C-C 1.00 7.900 7.900 0.230 0.175 0.317
Betweeen Grid D-D & E-E 1.00 7.900 7.900 0.230 0.175 0.317
Betweeen Grid E-E & F-F 1.00 7.900 7.900 0.230 0.175 0.317
9 FORMWORKS
Column
For Column upto Top Tie Beam
Column C1 (A2,C2,D2,F2,C3) 5.00 1.400 7.000 1.850 12.950
Column C2 (B2,E2,A3,B3,C3,E3,F3) 7.00 1.400 9.800 1.850 18.130
Column C3 (A1,B1,C1,D1,E1,F1) 6.00 1.200 7.200 1.850 13.320
44.400 Sq.m
Ground Floor
Column C1 (A2,C2,D2,F2,C3) 5.00 1.400 7.000 3.000 21.000
Column C2 (B2,E2,A3,B3,C3,E3,F3) 7.00 1.400 9.800 3.000 29.400
Column C3 (A1,B1,C1,D1,E1,F1) 6.00 1.200 7.200 3.000 21.600
72.000 Sq.m
First Floor
Column C1 (A2,C2,D2,F2,C3) 5.00 1.400 7.000 3.000 21.000
Column C2 (B2,E2,A3,B3,C3,E3,F3) 7.00 1.400 9.800 3.000 29.400
Column C3 (A1,B1,C1,D1,E1,F1) 6.00 1.200 7.200 3.000 21.600
72.000 Sq.m
Total formwork for column 188.400 Sq.m
Beam
For Foundation Beam
Along Grid A-A
1.00 7.850 7.850 0.600 4.710 2 sides
Along Grid B-B
1.00 7.850 7.850 0.600 4.710
Along Grid C-C 1.00 7.850 7.850 0.600 4.710
Along Grid D-D 1.00 7.850 7.850 0.600 4.710
Along Grid E-E 1.00 7.850 7.850 0.600 4.710
Along Grid F-F 1.00 7.850 7.850 0.600 4.710
Along Grid 1-1
1.00 29.250 29.250 0.600 17.550
Along Grid 2-2 1.00 29.000 29.000 0.600 17.400
Along Grid 3-3
1.00 29.000 29.000 0.600 17.400
80.610 Sq.m
For Top Tie Beam
Along Grid A-A
1.00 7.850 7.850 0.600 4.710
Along Grid B-B
1.00 7.850 7.850 0.600 4.710
Along Grid C-C 1.00 7.850 7.850 0.600 4.710
Secondary Beam
Betweeen Grid A-A & B-B 1.00 7.900 7.900 0.580 4.582
Betweeen Grid B-B & C-C 1.00 7.900 7.900 0.580 4.582
Betweeen Grid D-D & E-E 1.00 7.900 7.900 0.580 4.582
Betweeen Grid E-E & F-F 1.00 7.900 7.900 0.580 4.582
Betweeen Grid 2-2 & 3-3 1.00 26.330 26.330 0.580 15.271
Staircase beam 1.00 4.400 4.400 0.460 2.024
151.138 Sq.m
First Floor
Main Beam
Along Grid A-A
1.00 7.850 7.850 1.150 9.027
Along Grid B-B
1.00 7.850 7.850 1.150 9.027
Along Grid C-C 1.00 7.850 7.850 1.150 9.027
Along Grid D-D 1.00 7.850 7.850 1.150 9.027
Along Grid E-E 1.00 7.850 7.850 1.150 9.027
Along Grid F-F 1.00 7.850 7.850 1.150 9.027
Along Grid 1-1
1.00 27.250 27.250 1.150 31.337
Along Grid 2-2 1.00 27.000 27.000 1.150 31.050
Along Grid 3-3
1.00 27.000 27.000 1.150 31.050
147.599 Sq.m
Total formwork for beam 456.657 Sq.m
For slab,staircase,lintel,sill etc
Sides For Column footing
F1 2.00 12.600 25.200 0.150 3.780
F2 2.00 11.400 22.800 0.150 3.420
F3 2.00 11.100 22.200 0.150 3.330
F4 4.00 9.900 39.600 0.150 5.940
F5 2.00 8.700 17.400 0.150 2.610
F6 4.00 6.600 26.400 0.150 3.960
F7 2.00 6.000 12.000 0.150 1.800
Total formwork for footing 24.840 Sq.m
Sides for PCC work below
foundation beam
Along Grid A-A
1.00 7.850 7.850 0.150 1.177
Along Grid B-B
1.00 7.850 7.850 0.150 1.177
Along Grid C-C 1.00 7.850 7.850 0.150 1.177
Along Grid D-D 1.00 7.850 7.850 0.150 1.177
Along Grid E-E 1.00 7.850 7.850 0.150 1.177
Along Grid F-F 1.00 7.850 7.850 0.150 1.177
Along Grid 1-1
1.00 29.250 29.250 0.150 4.387
Along Grid 2-2 1.00 29.000 29.000 0.150 4.350
Along Grid 3-3
1.00 29.000 29.000 0.150 4.350
Total formwork for PCC 20.149 Sq.m
Slab
Staircase
Ground Floor
First Flight
First landing slab 1.00 2.100 2.100 1.200 2.520
Sides 2.00 1.200 2.400 0.175 0.420
Waist slab 1.00 3.360 3.360 2.100 7.056
Sides 2.00 3.360 6.720 0.325 2.184
Second Landing slab 1.00 1.660 1.660 2.100 3.486
Sides 1.00 3.760 3.760 0.175 0.658
Riser 10.00 2.100 21.000 0.150 3.150
Second Flight
Landing slab 1.00 2.040 2.040 2.100 4.284
Sides 1.00 4.340 4.340 0.175 0.759
Waist slab 1.00 3.360 3.360 2.100 7.056
Sides 2.00 3.360 6.720 0.325 2.184
Riser 10.00 2.100 21.000 0.150 3.150
36.907 Sq.m
Total formwork for staircase 36.907 Sq.m
Siil band
Ground Floor
Along Grid A-A
2.00 5.650 11.300 0.100 1.130
Along Grid B-B
2.00 5.650 11.300 0.100 1.130
Along Grid C-C 2.00 5.650 11.300 0.100 1.130
Along Grid D-D 2.00 5.650 11.300 0.100 1.130
Along Grid E-E 2.00 5.650 11.300 0.100 1.130
Along Grid F-F 2.00 5.650 11.300 0.100 1.130
Along Grid 1-1
2.00 4.900 9.800 0.100 0.980
Along Grid 2-2 2.00 24.250 48.500 0.100 4.850
Along Grid 3-3
2.00 29.000 58.000 0.100 5.800
Between Grid 2-2 and 3-3 2.00 5.430 10.860 0.100 1.086
Between Grid D-D and E-E 2.00 5.890 11.780 0.100 1.178
Between Grid E-E and F-F 2.00 5.890 11.780 0.100 1.178
Deduction for openings
D1(1100*2100) -16.00 1.100 -17.600 0.100 -1.760
D3(1100*2100) -4.00 1.100 -4.400 0.100 -0.440
19.652 Sq.m
First Floor
Along Grid A-A
2.00 5.650 11.300 0.100 1.130
Along Grid C-C 2.00 5.650 11.300 0.100 1.130
Along Grid D-D 2.00 5.650 11.300 0.100 1.130
Along Grid E-E 2.00 5.650 11.300 0.100 1.130
Along Grid F-F 2.00 5.650 11.300 0.100 1.130
Along Grid 1-1
2.00 31.550 63.100 0.100 6.310
Along Grid 2-2 2.00 22.250 44.500 0.100 4.450
Along Grid 3-3
2.00 27.000 54.000 0.100 5.400
Deduction for openings
D1(1100*2100) -12.00 1.100 -13.200 0.100 -1.320
20.490 Sq.m
Total formwork for sill band 40.142 Sq.m
Ground Floor
Along Grid A-A
2.00 5.650 11.300 0.150 1.695
Along Grid B-B
2.00 5.650 11.300 0.150 1.695
Along Grid C-C 2.00 5.650 11.300 0.150 1.695
Along Grid D-D 2.00 5.650 11.300 0.150 1.695
Along Grid E-E 2.00 5.650 11.300 0.150 1.695
Along Grid F-F 2.00 5.650 11.300 0.150 1.695
Along Grid 2-2 2.00 22.600 45.200 0.150 6.780
10 REINFORCEMENT
Column (3%) 1.00 15.675 3691.463
Beam (2.5%) 1.00 48.250 9469.063
Slab,staircase,bands,footing (1%) 1.00 76.503 6005.486
Total reinforcement work ### Kg
13.3 Window/ventilation
13.3.1 Metal Window Sq.m
Ground Floor
V1(1100*1200) 2.00 1.100 2.200 1.200 2.640
W1(1800*1200) 10.00 1.800 18.000 1.200 21.600
W2(1200*1200) 2.00 1.200 2.400 1.200 2.880
First Floor
W1(1800*1200) 11.00 1.800 19.800 1.200 23.760
W2(1200*1200) 1.00 1.200 1.200 1.200 1.440
W4(1800*1000) 1.00 1.800 1.800 1.000 1.800
Total metal Works 54.120 Sq.m
15 Railing work
Supply , weilding & fabricating MS
Kg
Circular pipe railing with redoxide paint
Ramp Railing
Ramp Railing on GF Length TL Wt/m
50mm dia blackpipe post 2.00 0.450 0.900 4.110 3.699
50mm dia blackpipe railing 2.00 8.070 16.140 4.110 66.335
Total MS railing for ramp 70.034 Kg
16 FALSE CEILLING
Supplying and Installation of 6mm thick
16.1 Gypsum board False Ceiling with GI Sq.m
framing and all accessories complete
First Floor
Corridor 1.00 29.000 29.000 2.475 71.775
71.775 Sq.m
Inner rooms
Library 1.00 11.833 11.830 5.890 69.678
Lab 1 1.00 5.890 5.890 5.760 33.926
Lab 2 1.00 5.890 5.890 5.760 33.926
Staircase portion 1.00 5.890 5.890 4.400 25.916
163.446 Sq.m
Total Gypsum board false ceiling 235.221 Sq.m
17 ROOFING WORK
Colour Coated CGI Sheet Works: 24
17.1 guage 0.5mm CGI sheet (red coloured) Sq.m
roofing.
First Floor
Roof cover 1.000 31.800 31.800 10.805 343.599
Total CGI sheet 343.599 Sq.m
18 ROOF TRUSS
First Floor (Roof cover) Length TL Wt/m
80 NB dia rafter (4.5mm thick) 10.00 11.312 113.120 8.360 945.683
80 NB dia lower tie (4.5mm thick) 10.00 8.800 88.000 8.360 735.680
80 NB dia vertical strut (4.05mm thick) 10.00 7.260 72.600 8.360 606.936
80 NB dia inclined strut (4.05mm thick) 10.00 7.330 73.300 8.360 612.788
65 NB dia purlin (3.65mm thick) 16.00 31.800 508.800 6.420 3266.496
19 CEMENT BOARD
First Floor
Sides of truss 1.000 8.850 8.850 1.450 12.832 2 sides
Total cement board work 12.832 Sq.m
20 Eaves Board
First Floor
Roof cover 2.000 43.260 86.520 0.250 0.0012 203.754
Total eaves board work 203.754 Kg
S.N. Description
Unit Quantity
1 Earthwork
1.1 Excavation Cum 182.63
1.2 Backfilling @ 30% of excavation Cum 54.79
2 Stone Soling
Foundation And Floor Sqm 17.59
17.59
3 P.C.C. works in foundation
Foundation And Floor Sqm 117.24
117.24
4 Concreting for R.C.C. works
Foundation Cum 107.20
Ground Floor Cum 51.42
First Floor Cum 48.35
206.97
5 Steel Reinforcement Works for Total concrete works
Foundation Kg 16,830.75
Ground Floor Kg 8,073.49
First Floor Kg 7,591.33
32,495.57
6 Brickworks
Chimney made
Below Plinth Cum 26.16
Ground Floor Cum 68.13
First Floor Cum 66.90
Cum 135.03
7 Plaster works
7.1 Plaster outer surface
Ground Floor Sqm 128.31
First Floor Sqm 133.76
262.07
7.2 Plaster inner surface
Ground Floor Sqm 456.33
First Floor Sqm 458.00
914.33
7.3 Plaster Ceiling
Ground Floor Sqm 200.00
200.00
7.4 Providing Pani patti on outer periphery of slab
Ground Floor Rm 57.92
57.92
8 Painting works
8.1 Painting works outer surface
Ground Floor Sqm 134.39
First Floor Sqm 139.83
274.22
8.2 Painting inner surface
Ground Floor Sqm 456.33
First Floor Sqm 458.00
914.33
8.3 Painting Ceiling
Ground Floor Sqm 200.00
200.00
8.4 Enamel Painting
Ground Floor Sqm 59.40
First Floor Sqm 57.74
117.14
9 Flooring Works
9.1 Screeding
Ground Floor Sqm 200.00
First Floor Sqm 200.00
400.00
A Foundation.
1 Site Clearance works 1 Job 1.00 Lumpsum
2 Earthwork in excavation
Foundation Trenches
Isolated footing (F1) Cum 14.00 2.10 2.10 2.00 123.48
Isolated footing (F2) Cum 4.00 2.50 2.50 2.00 50.00
Lower Tie Beam
Along grid 1,2,3 Cum 3.00 15.63 0.30 0.30 4.22
Along grid A,B,C,D,E,F Cum 6.00 9.13 0.30 0.30 4.93
Total Earthworks: 182.63 Cum
4 Stone Soling
Foundation Trenches
Isolated footing (F1) Cum 14.00 2.10 2.10 0.15 9.26
Isolated footing (F2) Cum 4.00 2.50 2.50 0.15 3.75
Lower Tie Beam
Along grid 1,2,3 Cum 3.00 15.63 0.30 0.15 2.11
Along grid A,B,C,D,E,F Cum 6.00 9.13 0.30 0.15 2.47
Total Brick Soling works: 17.59 Cum
5 Sand Filling
Foundation Trenches
Isolated footing (F1) Cum 14.00 2.10 2.10 0.05 3.09
Isolated footing (F2) Cum 4.00 2.50 2.50 0.05 1.25
Lower Tie Beam
Along grid 1,2,3 Cum 3.00 15.63 0.30 0.05 0.70
Along grid A,B,C,D,E,F Cum 6.00 9.13 0.30 0.05 0.82
Total Sand Filling works: 5.86 Cum
Columns
Cum 18.0 0.35 0.35 2.88 6.35
Beam
Main Beam
Along grid 1-3 Cum 3.00 15.63 0.30 0.35 4.92
Along grid A-F Cum 6.00 10.18 0.30 0.35 6.41
Lintel/ Sill Band
230mm walls
Along grid A Cum 2.00 10.18 0.23 0.10 0.47
Along grid B Cum 2.00 8.83 0.23 0.10 0.41
Along grid C Cum 2.00 8.83 0.23 0.10 0.41
Along grid D Cum 2.00 8.83 0.23 0.10 0.41
Along grid E Cum 2.00 8.83 0.23 0.10 0.41
Along grid F Cum 2.00 10.18 0.23 0.10 0.47
Along grid 1 Cum 2.00 15.63 0.23 0.10 0.72
Between 1-2 Cum 2.00 13.87 0.23 0.10 0.64
Along grid 2 Cum 2.00 15.63 0.23 0.10 0.72
Along grid 3 Cum 2.00 15.63 0.23 0.10 0.72
115mm walls
Between B-C Cum 4.00 2.33 0.12 0.10 0.11
Along grid 1-2 Cum 4.00 2.48 0.12 0.10 0.12
Slab Cum 1.0 Area 200.00 0.125 25.00
landing Beam
Between C-D Cum 1.00 3.48 0.30 0.35 0.37
Staircase
Main Staircase
Waist slab Cum 1.0 6.71 1.15 0.15 1.16
landings Cum 2.0 1.20 1.43 0.15 0.51
Steps Cum 20.0 1.15 0.30 0.15 0.52
Deduction
Stair viod Cum -1.0 4.12 4.83 0.125 -2.48
Total concrete works for First Floor 48.37 Cum
2.0 Formworks
Columns
Sqm 18.0 1.40 2.88 72.58
Beam
Main Beam
Along grid 1-3 Sqm 6.0 15.63 0.35 32.82
Along grid A-F Sqm 12.0 10.18 0.35 42.76
Lintel/ Sill Band
230mm walls
Along grid A Sqm 4.0 10.18 0.10 4.07
Along grid B Sqm 4.0 8.83 0.10 3.53
Along grid C Sqm 4.0 8.83 0.10 3.53
Along grid D Sqm 4.0 8.83 0.10 3.53
Along grid E Sqm 4.0 8.83 0.10 3.53
Along grid F Sqm 4.0 10.18 0.10 4.07
Along grid 1 Sqm 4.0 15.63 0.10 6.25
Between 1-2 Sqm 4.0 13.87 0.10 5.55
Along grid 2 Sqm 4.0 15.63 0.10 6.25
Along grid 3 Sqm 4.0 15.63 0.10 6.25
115mm walls
Between B-C Sqm 8.0 2.33 0.10 1.86
Along grid 1-2 Sqm 8.0 2.48 0.10 1.98
Slab Sqm 1.0 Area 200.00 200.00
Side Of Slab Sqm 1.0 68.15 0.13 8.86
landing Beam
Between C-D Sqm 2.0 3.48 0.35 2.44
Staircase
Main Staircase
3 Earthback Filling
Filling Upto Ground Level
For Footing of column
F1 2.00 1.800 3.600 1.800 1.775 11.502
CF1 3.00 3.685 11.055 1.800 1.775 35.320
For Foundation Beam
Along Grid A-A 1.00 1.085 1.085 0.450 1.470 0.717
Along Grid B-B
1.00 1.085 1.085 0.450 1.470 0.717
Along Grid 1-1
1.00 4.608 4.608 0.450 1.470 3.048
Along Grid 2-2 1.00 4.608 4.608 0.450 1.470 3.048
Along Grid 3-3 1.00 3.070 3.070 0.450 1.470 2.030
Filling in floor
Room1 1.00 4.640 4.640 2.655 0.075 0.923
Room2 1.00 4.640 4.640 2.405 0.075 0.836
Room3 1.00 3.110 3.110 2.405 0.075 0.560
Lobby 1.00 4.665 4.660 1.200 0.075 0.419
Ramp floor 1.00 3.600 3.600 1.300 0.150 0.702
4 Boulder Soling
For Footing of column
F1 2.00 1.800 3.600 1.800 0.150 0.972
CF1 3.00 3.685 11.055 1.800 0.150 2.984
For Foundation Beam
Along Grid A-A 1.00 1.585 1.585 0.350 0.150 0.083
Along Grid B-B
1.00 1.585 1.585 0.350 0.150 0.083
Along Grid 1-1
1.00 4.608 4.608 0.350 0.150 0.241
Along Grid 2-2 1.00 4.608 4.608 0.350 0.150 0.241
Along Grid 3-3 1.00 3.070 3.070 0.350 0.150 0.161
Floors
Room1 1.00 4.640 4.640 2.655 0.150 1.847
Room2 1.00 4.640 4.640 2.405 1.150 12.833
5 Sand Filling
Floors
Room1 1.00 4.640 4.640 2.655 0.050 0.615
Room2 1.00 4.640 4.640 2.405 0.050 0.557
Room3 1.00 3.110 3.110 2.405 0.050 0.373
Lobby 1.00 4.665 4.660 1.200 0.050 0.279
Ramp floor 1.00 3.600 3.600 1.300 0.050 0.234
Total Sand Filling Work 2.058 Cu.m
8.2 M15
Floors
Room1 1.00 4.640 4.640 2.655 0.075 0.923
Room2 1.00 4.640 4.640 2.405 0.075 0.836
Room3 1.00 3.110 3.110 2.405 0.075 0.560
Lobby 1.00 4.665 4.660 1.200 0.075 0.419
Ramp floor 1.00 3.600 3.600 1.300 0.075 0.351
Total M15 (1:2:4) PCC 3.089 Cu.m
8.3 M20
For Column footing
Rectangular Section
F1 2.00 1.800 3.600 1.800 0.40 2.592
CF1 3.00 3.685 11.055 1.800 0.53 10.546
Trapazoidal Section
V= h/6(A1+A2+4*mean Area)
F1 2.00 1.800 3.600 0.800 0.200 0.776
Total RCC for footing 13.914 Cu.m
Column
For Column upto Top Tie Beam
Column C1 8.00 0.300 2.400 0.300 1.475 1.062
1.062 Cu.m
Ground Floor
Column C1 8.00 0.300 2.400 0.300 2.500 1.800
1.800 Cu.m
Total RCC for column 2.862 Cu.m
Beam
For Foundation Beam
Along Grid A-A 1.00 2.585 2.585 0.230 0.230 0.136
Along Grid B-B
1.00 2.585 2.585 0.230 0.230 0.136
Along Grid 1-1
1.00 7.570 7.570 0.230 0.230 0.400
Along Grid 2-2 1.00 7.570 7.570 0.230 0.230 0.400
Along Grid 3-3 1.00 4.570 4.570 0.230 0.230 0.241
1.313 Cu.m
For Top Tie Beam
Along Grid A-A 1.00 4.920 4.920 0.230 0.230 0.260
Along Grid B-B
1.00 4.920 4.920 0.230 0.230 0.260
Along Grid C-C
1.00 4.920 4.920 0.230 0.230 0.260
Along Grid 1-1
1.00 7.570 7.570 0.230 0.230 0.400
Along Grid 2-2 1.00 7.570 7.570 0.230 0.230 0.400
Along Grid 3-3 1.00 4.570 4.570 0.230 0.230 0.241
1.821 Cu.m
Ground Floor
Main Beam
Along Grid A-A 1.00 4.920 4.920 0.230 0.200 0.226
Along Grid B-B
1.00 4.920 4.920 0.230 0.200 0.226
9 FORMWORKS
Column
For Column upto Top Tie Beam
Column C1 8.00 1.200 9.600 1.475 14.160
Ground Floor
Column C1 8.00 1.200 9.600 2.500 24.000
Total formwork for column 38.160 Sq.m
Beam
For Foundation Beam
Along Grid A-A 1.00 2.585 2.585 0.460 1.189
Along Grid B-B
1.00 2.585 2.585 0.460 1.189
Along Grid 1-1
1.00 7.570 7.570 0.460 3.482
Along Grid 2-2 1.00 7.570 7.570 0.460 3.482
Along Grid 3-3 1.00 4.570 4.570 0.460 2.102
11.444 Sq.m
For Top Tie Beam
Along Grid A-A 1.00 4.920 4.920 0.460 2.263
Along Grid B-B
1.00 4.920 4.920 0.460 2.263
Along Grid C-C
1.00 2.335 2.335 0.460 1.074
Along Grid 1-1
1.00 7.570 7.570 0.460 3.482
Along Grid 2-2 1.00 7.570 7.570 0.460 3.482
Along Grid 3-3 1.00 4.570 4.570 0.460 2.102
14.666 Sq.m
Ground Floor
Main Beam
Along Grid A-A 1.00 4.920 4.920 0.630 3.099
Along Grid B-B
1.00 4.920 4.920 0.630 3.099
Along Grid C-C
1.00 4.920 4.920 0.630 3.099
Along Grid 1-1
1.00 7.570 7.570 0.630 4.769
Along Grid 2-2 1.00 7.570 7.570 0.630 4.769
Along Grid 3-3 1.00 4.570 4.570 0.630 2.879
Secondary Beam
Between Grid A-A and B-B 1.00 5.080 5.080 0.490 2.489
Between Grid B-B and C-C 1.00 2.425 2.425 0.490 1.188
25.391 Sq.m
Total formwork for beam 51.501 Sq.m
For slab,lintel,slab etc
Sides For Column footing
F1 2.00 7.200 14.400 0.40 5.760
CF1 3.00 10.970 32.910 0.53 17.442
Total formwork for footing 23.202 Sq.m
10 REINFORCEMENT
Reinforcement(2%) 1.00 29.405 4616.585
Total reinforcement work 4616.585 Kg
11.4.2 On Floor
Girls Toilet 1.00 6.270 6.270 2.425 15.204
Boys Toilet 1.00 4.660 4.660 2.655 12.372
Disabled Toilet 1.00 2.425 2.420 1.500 3.630
Total tile on floor 31.206 Sq.m
12 PLASTERING WORKS
12.5mm thick cement plaster in (1:3) in
12.1 Sq.m
ceiling ,beams etc
Ground Floor
Ceiling
Girls Toilet 1.00 6.270 6.270 2.425 15.204
Boys Toilet 1.00 4.660 4.660 2.655 12.372
Disabled Toilet 1.00 2.425 2.420 1.500 3.630
Projected ceiling 1.00 12.38 12.380
Sides 1.00 31.00 31.000 0.100 3.100
Main Beam along Grid C-C 2.00 1.53 3.060 0.200 0.612
Sec Beam between Grid A-A and B-B 2.00 5.08 10.160 0.130 1.320
Sec Beam along Grid B-B and C-C 2.00 2.43 4.860 0.130 0.631
Total 1:3 plaster on ceiling 49.249 Sq.m
Roof Top
Parapet wall 1.00 28.460 28.460 0.865 24.617
24.617 Sq.m
Total 1:4 external plaster 94.829 Sq.m
Ground Floor
Stair outside girls toilet
Riser 2.00 1.360 2.720 0.15 0.408
Tread 2.00 1.360 2.720 0.300 0.816
Stair outside boys toilet
Riser 2.00 4.665 9.330 0.15 1.399
Tread 1.00 4.665 4.660 0.300 1.398
Ramp Floor 1.00 3.600 3.600 1.300 4.680
Total 1:4 floor plaster 8.701 Sq.m
13 Woodwork/Aluminium work
13.1 Door Frame
Salwood frame of size 75*100mm Cu.m
Ground Floor
D1(750*2100) 6.00 4.950 29.700 0.075 0.100 0.222
D2(900*2100) 2.00 5.100 10.200 0.075 0.100 0.076
D3(1000*2100) 1.00 5.200 5.200 0.075 0.100 0.039
Total salwood frame 0.337 Cu.m
Ground Floor
D1(750*2100) 6.00 0.750 4.500 2.100 9.450
D2(900*2100) 2.00 0.900 1.800 2.100 3.780
D3(1000*2100) 1.00 1.000 1.000 2.100 2.100
Total solid core flush door shutter 15.330 Sq.m
Ground Floor
D1(750*2100) 6.00 0.750 4.500 2.000 2.100 18.900
D2(900*2100) 2.00 0.900 1.800 2.000 2.100 7.560
D3(1000*2100) 1.00 1.000 1.000 2.000 2.100 4.200
Total chapra polish work 30.660 Sq.m
Door Frame
Ground Floor
D1(750*2100) 6.00 4.950 29.700 0.250 7.425
D2(900*2100) 2.00 5.100 10.200 0.250 2.550
D3(1000*2100) 1.00 5.200 5.200 0.250 1.300
Total enamel paint work 11.275 Sq.m
Ground Floor
6" lintel
Grid A,C,E,F,H,J 6 5.32 0.23 0.15 1.10
Grid 1 1 28.55 0.23 0.15 0.98
Grid 2 1 24.32 0.23 0.15 0.84
Deduction
Opening -1 2.40 0.23 0.15 -0.08
3" Sill
Grid A,C,E,F,H,J 6 5.32 0.23 0.08 0.59
Grid 1 1 28.55 0.23 0.08 0.53
Grid 2 1 24.32 0.23 0.08 0.45
Deduction
Opening -8 1.20 0.23 0.08 -0.18
3" Sill
Grid A,C,E,F,H,J 6 5.32 0.23 0.075 0.55
Grid 1 1 28.55 0.23 0.075 0.49
Grid 2 1 24.32 0.23 0.075 0.42
Deduction
Opening -8 1.20 0.23 0.075 -0.17
Parapet 1
High wall 8 1.37 0.23 0.075 0.19
iclined downward 8 0.75 0.23 0.075 0.10
Low wall 8 1.66 0.23 0.075 0.23
Second Floor
6" lintel
Grid A,C,E,F,H,J 6 5.32 0.23 0.15 1.10
Grid 1 1 28.55 0.23 0.15 0.98
Grid 2 1 24.32 0.23 0.15 0.84
Deduction
Opening -1 2.40 0.23 0.15 -0.08
3" Sill
Grid A,C,E,F,H,J 6 5.32 0.23 0.075 0.55
Grid 1 1 28.55 0.23 0.075 0.49
Grid 2 1 24.32 0.23 0.075 0.42
Deduction
Opening -8 1.20 0.23 0.075 -0.17
Parapet 1
High wall 8 1.37 0.23 0.075 0.19
iclined downward 8 0.75 0.23 0.075 0.10
Low wall 8 1.66 0.23 0.075 0.23
Staircase
beam at plinth 1 4.23 0.30 0.30 0.38
Flight 2 3.02 2.05 0.15 1.85
Landing 1 4.81 2.23 0.15 1.61
landing beam 1 4.23 0.23 0.20 0.19
Steps 20 2.05 0.30 0.15 0.92
Column upto Second floor
C1 4 0.35 0.35 3.000 1.47
C2 8 0.35 0.35 3.000 2.94
C3 8 0.35 0.35 3.000 2.94
C4 10 0.30 0.30 3.000 2.70
Main Beam at 2nd floor
Grid A,B,C,D,E,F,G,H,I,J 10 7.33 0.23 0.275 4.64
Grid 2,3 2 28.55 0.23 0.225 2.95
=3.39*8+4.58-0.35-8*0.35
Grid 1 1 29.00 0.23 0.225 1.50
=3.39*8+4.58-0.3-8*0.3
Staircase
beam at plinth 1 4.23 0.30 0.30 0.38
Flight 2 3.02 2.05 0.15 1.85
Landing 1 4.81 2.23 0.15 1.61
landing beam 1 4.23 0.23 0.20 0.19
Steps 20 2.05 0.30 0.15 0.92
Column upto roof
C1 4 0.35 0.35 3.32 1.63
C2 8 0.35 0.35 3.32 3.25
C3 8 0.35 0.35 3.32 3.25
C4 10 0.30 0.30 3.32 2.99
3" Sill
Grid A,C,E,F,H,J 12 5.32 0.08 5.11
Grid 3 2 28.55 0.08 4.57
Grid 2 2 24.32 0.08 3.89
Deduction
Opening -16 1.20 0.08 -1.54
First Floor
6" lintel
Grid A,C,E,F,H,J 12 5.32 0.15 9.58
Grid 3 2 28.55 0.15 8.57
Grid 2 2 24.32 0.15 7.30
Deduction
Opening -2 2.40 0.15 -0.72
3" Sill
Grid A,C,E,F,H,J 12 5.32 0.08 5.11
Grid 3 2 28.55 0.08 4.57
Grid 2 2 24.32 0.08 3.89
Deduction
Opening -16 1.20 0.08 -1.44
3" Sill
Grid A,C,E,F,H,J 12 5.32 0.08 5.11
Grid 3 2 28.55 0.08 4.57
Grid 2 2 24.32 0.08 3.89
Deduction
Opening -16 1.20 0.08 -1.44
Total of Formworks 1,630.20 sq.m
4 BRICK / STONE WORKS
4.2 Brick Masonry Works in 1:6 C/S
Upto plinth
Footing wall
Grid A,B,C,D,E,F,G,H,I,J 10 7.33 0.23 0.95 16.02
=1.5+0.45-0.4-2*0.3
Grid 2,3 2 28.55 0.23 0.95 12.48
Grid 1 1 29.00 0.23 0.95 6.34
Deduction
Parapet 1
High wall 8 1.72 0.23 1.20 3.80
inclined downward 8 0.75 0.23 0.95 1.31
Low wall 8 2.04 0.23 0.70 2.63
First Floor
Grid 3 1 28.55 0.23 2.65 17.40
(3-0.35)
Grid A,J 2 5.32 0.23 2.65 6.49
Grid 2 1 24.32 0.23 2.65 14.82
Grid C,E,F,H 4 5.32 0.23 2.65 12.97
Deduction
Doors -8 1.20 0.23 2.10 -4.64
windows -8 2.00 0.23 1.50 -5.52
-1 1.50 0.23 1.00 -0.35
Parapet 1
High wall 8 1.72 0.23 1.20 3.80
inclined downward 8 0.75 0.23 0.95 1.31
Low wall 8 2.04 0.23 0.70 2.63
Parapet 1 5.67 0.23 1.20 1.56
Second Floor
Grid 3 1 28.55 0.23 2.97 19.50
=(3.952+2.692)/2-0.35
Grid A,J 2 5.32 0.23 2.97 7.27
Grid 2 1 24.32 0.23 2.97 16.61
Grid C,E,F,H 4 5.32 0.23 2.97 14.54
Deduction
Doors -8 1.20 0.23 2.10 -4.64
windows -8 1.50 0.23 2.00 -5.52
-1 1.50 0.23 1.00 -0.35
Parapet 1
High wall 8 1.72 0.23 1.20 3.80
inclined downward 8 0.75 0.23 0.95 1.31
Low wall 8 2.04 0.23 0.70 2.63
Total For CGI Sheet Roofing Total of CGI Sheet Roofing 395.85 sq.m
8 PLASTER/PAINTING WORKS
8.1 Internal Plaster
8.1.1 Internal Plaster on Wall
Ground Floor
Teachers room 2 6.55 2.88 37.73
2 5.50 2.88 31.68
Nepali Medium class 1 2 6.55 2.88 37.73
2 5.50 2.88 31.68
Staircase 2 5.74 2.88 33.06
1 4.35 2.88 12.53
ECD1 2 6.55 2.88 37.73
2 5.50 2.88 31.68
ECD2 2 6.55 2.88 37.73
2 5.50 2.88 31.68
Deduction For
Doors -8 1.2 2.10 -10.08 50%
-1 0.75 2.10 -0.79
Windows -8 2 1.50 -12.00
-1 2.4 1.40 -1.68
First Floor
English Medium Class 2 2 6.55 2.88 37.73
2 5.50 2.88 31.68
English Medium Class 1 2 6.55 2.88 37.73
2 5.50 2.88 31.68
Staircase 2 5.74 2.88 33.06
On Ceiling
Main Beam at 1st floor
Grid A,B,C,D,E,F,G,H,I,J 20 7.33 0.275 40.32
Grid 2,3 4 28.55 0.225 25.70
Grid 1 2 29.00 0.225 13.05
Second Floor
Grid A,J 2 5.320 2.58 27.45
Grid 2,3 2 28.55 2.58 147.32
Parapet 16 4.48 1.13 80.64
1 4.230 1.40 5.92
Deduction For
Windows -8 2.000 1.50 -24.00
-1 1.000 1.50 -1.50
Doors -8 1.200 2.10 -20.16
Second Floor
Grid A,J 2 5.320 2.58 27.45
Grid 2,3 2 28.55 2.58 147.32
Parapet 16 4.48 1.13 80.64
1 4.230 1.40 5.92
Deduction For
Windows -8 2.000 1.50 -24.00
-1 1.000 1.50 -1.50
Doors -8 1.200 2.10 -20.16
3 Earthback Filling
Filling Upto Ground Level
For Footing of column
F1 2.00 1.900 3.800 1.900 1.200 8.664
F2 2.00 2.000 4.000 2.000 1.200 9.600
F3 1.00 2.100 2.100 2.100 1.200 5.292
F4 2.00 2.700 5.400 2.700 1.200 17.496
F5 2.00 2.900 5.800 2.900 1.200 20.184
F6 2.00 3.000 6.000 3.000 1.200 21.600
F7 1.00 3.300 3.300 3.300 1.200 13.068
F8 1.00 3.400 3.400 3.400 1.200 13.872
F9 1.00 3.600 3.600 3.600 1.200 15.552
F10 1.00 3.700 3.700 3.700 1.200 16.428
For Foundation Beam
Along Grid A-A 1.00 3.700 3.700 0.600 0.900 1.998
4 Boulder Soling
For Footing of column
F1 2.00 1.900 3.800 1.900 0.200 1.444
F2 2.00 2.000 4.000 2.000 0.200 1.600
F3 1.00 2.100 2.100 2.100 0.200 0.882
F4 2.00 2.700 5.400 2.700 0.200 2.916
F5 2.00 2.900 5.800 2.900 0.200 3.364
F6 2.00 3.000 6.000 3.000 0.200 3.600
F7 1.00 3.300 3.300 3.300 0.200 2.178
F8 1.00 3.400 3.400 3.400 0.200 2.312
F9 1.00 3.600 3.600 3.600 0.200 2.592
F10 1.00 3.700 3.700 3.700 0.200 2.738
For Foundation Beam
Along Grid A-A 1.00 5.550 5.550 0.350 0.100 0.194
Along Grid B-B
1.00 5.550 5.550 0.350 0.100 0.194
Along Grid C-C 1.00 5.550 5.550 0.350 0.100 0.194
Along Grid D-D 1.00 5.550 5.550 0.350 0.100 0.194
Along Grid E-E 1.00 5.550 5.550 0.350 0.100 0.194
Along Grid 1-1
1.00 19.100 19.100 0.350 0.100 0.668
Along Grid 2-2 1.00 19.100 19.100 0.350 0.100 0.668
Along Grid 3-3 1.00 19.100 19.100 0.350 0.100 0.668
Floors
Room between Grid A-A and B-B 1.00 7.900 7.900 5.700 0.150 6.754
Room between Grid B-B and C-C 1.00 7.900 7.900 5.700 0.150 6.754
Room between Grid C-C and D-D 1.00 7.900 7.900 5.700 0.150 6.754
5 Sand Filling
Floors
Classroom 1 1.00 5.750 5.750 5.750 0.050 1.653
Classroom 2 1.00 5.750 5.750 5.750 0.050 1.653
Classroom 3 1.00 5.750 5.750 5.750 0.050 1.653
Staircase portion 1.00 6.500 6.500 4.200 0.050 1.365
Corridor 1.00 22.950 22.950 2.500 0.050 2.868
Ramp 1.00 6.500 6.500 1.325 0.050 0.430
Total Sand Filling Work 9.622 Cu.m
7 Brickwork
Brick Masonry Works in 1:6 C/S
7.1 Cu.m
mortar
Upto Plinth Level
Toe wall between lower and upper tie
beam
Along Grid A-A 1.00 7.600 7.600 0.230 0.375 0.655
Along Grid B-B
1.00 7.600 7.600 0.230 0.375 0.655
Along Grid C-C 1.00 7.600 7.600 0.230 0.375 0.655
Along Grid D-D 1.00 7.600 7.600 0.230 0.375 0.655
Along Grid E-E 1.00 7.600 7.600 0.230 0.375 0.655
Along Grid 1-1
1.00 20.700 20.700 0.230 0.375 1.785
Along Grid 2-2 1.00 20.700 20.700 0.230 0.375 1.785
Along Grid 3-3 1.00 20.700 20.700 0.230 0.375 1.785
Entry porch staircase(East-South direction)
Step I 1.00 19.550 19.550 0.60 0.250 2.932
Step II 1.00 18.950 18.950 0.30 0.150 0.852
Entry porch staircase (West direction)
Step I 1.00 2.500 2.500 0.600 0.250 0.375
Step II 1.00 2.500 2.500 2.600 0.150 0.975
Trapazoidal
Section V=
h/6(A1+A2+4*mean Area)
F1 2.00 1.700 3.400 0.850 0.250 0.902
F2 2.00 1.800 3.600 0.850 0.250 0.990
F3 1.00 1.900 1.900 0.850 0.250 0.541
F4 2.00 2.500 5.000 0.850 0.250 1.742
F5 2.00 2.700 5.400 0.850 0.250 2.002 V=h/
6(A1+A2+4
F6 2.00 2.800 5.600 0.850 0.250 2.140 *mean Area)
F7 1.00 3.100 3.100 0.850 0.250 1.291
F8 1.00 3.200 3.200 0.850 0.250 1.370
F9 1.00 3.400 3.400 0.850 0.250 1.535
F10 1.00 3.500 3.500 0.850 0.250 1.621
Total RCC for footing 34.516 Cu.m
Column
For Column upto Top Tie Beam
Column (450*450) 15.00 0.450 6.750 0.450 0.750 2.278
2.278 Cu.m
Ground Floor
Column (450*450) 15.00 0.450 6.750 0.450 3.000 9.112
9.112 Cu.m
First Floor
Column (450*450) 15.00 0.450 6.750 0.450 3.000 9.112
9.112 Cu.m
Second Floor
Column (450*450) 15.00 0.450 6.750 0.450 3.000 9.112
9.112 Cu.m
Total RCC for column 29.614 Cu.m
Beam
For Foundation Beam
Along Grid A-A 1.00 7.600 7.600 0.250 0.300 0.570
Along Grid B-B
1.00 7.600 7.600 0.250 0.300 0.570
Secondary Beam
Betweeen Grid A-A & B-B 1.00 7.900 7.900 0.250 0.300 0.592
Betweeen Grid B-B & C-C 1.00 7.900 7.900 0.250 0.300 0.592
Betweeen Grid D-D & E-E 1.00 7.900 7.900 0.250 0.300 0.592
Betweeen Grid 2-2 & 3-3 1.00 16.350 16.350 0.250 0.300 1.226
15.014 Cu.m
First Floor
Main Beam
Along Grid A-A 1.00 7.600 7.600 0.300 0.400 0.912
Along Grid B-B
1.00 7.600 7.600 0.300 0.400 0.912
Along Grid C-C 1.00 7.600 7.600 0.300 0.400 0.912
Along Grid D-D 1.00 7.600 7.600 0.300 0.400 0.912
Along Grid E-E 1.00 7.600 7.600 0.300 0.400 0.912
Along Grid 1-1
1.00 20.700 20.700 0.300 0.400 2.484
Along Grid 2-2 1.00 20.700 20.700 0.300 0.400 2.484
Along Grid 3-3 1.00 20.700 20.700 0.300 0.400 2.484
Secondary Beam
Betweeen Grid A-A & B-B 1.00 7.900 7.900 0.250 0.300 0.592
First Floor
Entire blocks lab 1.00 22.950 22.950 8.950 0.125 25.675
Deduction for staircase portion -1.00 5.750 -5.750 4.500 0.125 -3.234
22.441 Cu.m
Total RCC for slab 44.882 Cu.m
Staircase
Ground Floor
First Flight
First landing slab 1.00 2.000 2.000 1.050 0.150 0.315
Waist slab 1.00 3.354 3.354 2.000 0.150 1.006
Second Landing slab 1.00 2.000 2.000 0.925 0.150 0.277
Riser 10.00 2.100 21.000 0.300 0.150 0.945
Second Flight
Landing slab 1.00 2.270 2.270 2.000 0.150 0.681
Waist slab 1.00 3.354 3.354 2.000 0.150 1.006
Riser 10.00 2.000 20.000 0.300 0.150 0.900
5.130 Cu.m
First Floor
First Flight
First landing slab 1.00 2.000 2.000 1.050 0.150 0.315
Waist slab 1.00 3.354 3.354 2.000 0.150 1.006
Second Landing slab 1.00 2.000 2.000 0.925 0.150 0.277
Riser 10.00 2.100 21.000 0.300 0.150 0.945
Second Flight
Landing slab 1.00 2.270 2.270 2.000 0.150 0.681
Second Floor
Along Grid A-A 1.00 5.550 5.550 0.230 0.075 0.095
Along Grid B-B
1.00 5.550 5.550 0.230 0.075 0.095
Along Grid C-C 1.00 5.550 5.550 0.230 0.075 0.095
Along Grid D-D 1.00 5.550 5.550 0.230 0.075 0.095
Along Grid E-E 1.00 5.550 5.550 0.230 0.075 0.095
Along Grid 1-1 1.00 20.700 20.700 0.230 0.075 0.357
Along Grid 2-2 1.00 16.200 16.200 0.230 0.075 0.279
Wall on side of door 3.00 0.485 1.455 0.230 0.075 0.025
Deduction for openings
D1(1100*2200) -6.00 1.100 -6.600 0.230 0.075 -0.113
1.023 Cu.m
Total RCC for sill band 3.091 Cu.m
Lintel band
Ground Floor
9 FORMWORKS
For column
For Column upto Top Tie Beam
Column (450*450) 15.00 1.800 27.000 0.750 20.250
20.250 Sq.m
Ground Floor
Column (450*450) 15.00 1.800 27.000 3.000 81.000
81.000 Sq.m
First Floor
Column (450*450) 15.00 1.800 27.000 3.000 81.000
81.000 Sq.m
Second Floor
Column (450*450) 15.00 1.800 27.000 3.000 81.000
81.000 Sq.m
Total formwork for column 263.250 Sq.m
For Beam
For Foundation Beam
Secondary Beam
Betweeen Grid A-A & B-B 1.00 7.900 7.900 0.850 6.715
Betweeen Grid B-B & C-C 1.00 7.900 7.900 0.850 6.715
Betweeen Grid D-D & E-E 1.00 7.900 7.900 0.850 6.715
Betweeen Grid 2-2 & 3-3 1.00 16.350 16.350 0.850 13.897
149.102 Sq.m
First Floor
Main Beam
Along Grid A-A 1.00 7.600 7.600 1.100 8.360
Along Grid B-B
1.00 7.600 7.600 1.100 8.360
Along Grid C-C 1.00 7.600 7.600 1.100 8.360
Along Grid D-D 1.00 7.600 7.600 1.100 8.360
Along Grid E-E 1.00 7.600 7.600 1.100 8.360
Along Grid 1-1
1.00 22.200 22.200 1.100 24.420
Along Grid 2-2 1.00 22.200 22.200 1.100 24.420
Along Grid 3-3 1.00 22.200 22.200 1.100 24.420
Secondary Beam
Betweeen Grid A-A & B-B 1.00 7.900 7.900 0.850 6.715
Betweeen Grid B-B & C-C 1.00 7.900 7.900 0.850 6.715
Betweeen Grid D-D & E-E 1.00 7.900 7.900 0.850 6.715
Betweeen Grid 2-2 & 3-3 1.00 16.350 16.350 0.850 13.897
149.102 Sq.m
Second Floor (Truss Level)
Main Beam
Along Grid A-A 1.00 7.600 7.600 1.100 8.360
Along Grid B-B
1.00 7.600 7.600 1.100 8.360
Along Grid C-C 1.00 7.600 7.600 1.100 8.360
Along Grid D-D 1.00 7.600 7.600 1.100 8.360
Along Grid E-E 1.00 7.600 7.600 1.100 8.360
Along Grid 1-1
1.00 22.200 22.200 1.100 24.420
Along Grid 2-2 1.00 22.200 22.200 1.100 24.420
Along Grid 3-3 1.00 22.200 22.200 1.100 24.420
115.060 Sq.m
Total formwork for beam 585.854 Sq.m
For Footing
Sides For Column footing
F1 2.00 6.800 13.600 0.200 2.720
F2 2.00 7.200 14.400 0.200 2.880
F3 1.00 7.200 7.200 0.200 1.440
F4 2.00 10.000 20.000 0.200 4.000
F5 2.00 10.800 21.600 0.200 4.320
F6 2.00 11.200 22.400 0.200 4.480
F7 1.00 12.400 12.400 0.200 2.480
F8 1.00 12.800 12.800 0.200 2.560
F9 1.00 13.600 13.600 0.200 2.720
F10 1.00 14.000 14.000 0.200 2.800
Total formwork for footing 30.400 Sq.m
For PCC
Sides for PCC work below foundation
beam
Along Grid A-A 1.00 6.800 6.800 0.100 0.680
Along Grid B-B
1.00 6.800 6.800 0.100 0.680
Along Grid C-C 1.00 6.800 6.800 0.100 0.680
Along Grid D-D 1.00 6.800 6.800 0.100 0.680
Along Grid E-E 1.00 6.800 6.800 0.100 0.680
Along Grid 1-1
1.00 20.600 20.600 0.100 2.060
Along Grid 2-2 1.00 20.600 20.600 0.100 2.060
Along Grid 3-3 1.00 20.600 20.600 0.100 2.060
Total formwork for PCC 9.580 Sq.m
For Slab
Ground Floor
Entire blocks slab 1.00 22.650 22.650 8.950 202.717
Sides 1.00 83.700 83.700 0.125 10.462
10 REINFORCEMENT Kg
Reinforcement(2%) 1.00 194.402 30521.114
Total reinforcement work ### Kg
Ground Floor
Inner staircase
Riser 20.00 2.000 40.000 0.150 6.000
Tread 18.00 2.000 36.000 0.300 10.800
Landing 1.00 4.400 4.400 2.000 8.800
Outer entrance steps (E-S direction)
Step i
Ground Floor
D1(1100*2200) 6.00 0.974 5.844 2.137 12.488
D2(1000*1550) 1.00 0.874 0.874 1.487 1.299
First Floor
D1(1100*2200) 6.00 0.974 5.844 2.137 12.488
Second Floor
D1(1100*2200) 6.00 0.974 5.844 2.137 12.488
Total solid core flush door shutter 38.763 Sq.m
14.3 Window/ventilation
Metal Window Sq.m
Ground Floor
W1(1100*1450) 12.00 1.100 13.200 1.450 19.140
W3(1100*370) 2.00 1.100 2.200 0.370 0.814
First Floor
W1(1100*1450) 12.00 1.100 13.200 1.450 19.140
W2(1100*1000) 2.00 1.100 2.200 1.000 2.200
Second Floor
W1(1100*1450) 12.00 1.100 13.200 1.450 19.140
W2(1100*1000) 2.00 1.100 2.200 1.000 2.200
Total metal window 62.634 Sq.m
Door Frame
Ground Floor
D1(1100*2200) 6.00 5.500 33.000 0.250 8.250
D2(1000*1550) 1.00 4.100 4.100 0.250 1.025
First Floor
D1(1100*2200) 6.00 5.500 33.000 0.250 8.250
Second Floor
D1(1100*2200) 6.00 5.500 33.000 0.250 8.250
Total enamel on sal frame 25.775 Sq.m
On railing
Staircase Railing
Ground Floor Length TL pi*d
40mm dia handrail(3.2 mm thick) 1.00 7.045 7.040 0.126 0.887
4 layers of 25mm square horizontal
4.00 6.940 27.760 0.100 2.776
railing(3.2 mm thick)
38 mm square vertical post 8.00 0.900 7.200 0.152 1.094
4.757 Sq.m
16 Railing work
Staircase Railing
Ground Floor Length TL Wt/m
40mm dia handrail(3.2 mm thick) 1.00 7.045 7.040 3.560 25.062
4 layers of 25mm square horizontal
4.00 6.940 27.760 1.980 54.964
railing(3.2 mm thick)
38 mm dia vertical post 8.00 0.900 7.200 3.250 23.400
103.426 Kg
First Floor
40mm dia handrail(3.2 mm thick) 1.00 7.190 7.190 3.560 25.596
4 layers of 25mm square horizontal
4.00 6.940 27.760 1.980 54.964
railing(3.2 mm thick)
38 mm dia vertical post 8.00 0.900 7.200 3.250 23.400
103.960 Kg
Second Floor
40mm dia handrail(3.2 mm thick) 1.00 2.250 2.250 3.560 8.010
4 layers of 25mm square horizontal
4.00 2.250 9.000 1.980 17.820
railing(3.2 mm thick)
38 mm dia vertical post 2.00 0.900 1.800 3.250 5.850
31.680 Kg
Total MS railing for staircase 239.066 Kg
Varandah Railing
First Floor Length TL Wt/m
Ramp Railing
Ramp Railing on GF Length TL Wt/m
40mm dia handrail(3.2 mm thick) 1.00 8.170 8.170 3.560 29.085
4 layers of 25mm square horizontal
4.00 8.170 32.680 1.980 64.706
railing(3.2 mm thick)
38 mm dia vertical post 5.00 0.900 4.500 3.250 14.625
Total MS railing for ramp 108.416 Kg
17 FALSE CEILLING
Supplying and Installation of 6mm thick
Gypsum board False Ceiling with GI Sq.m
framing and all accessories.
Second Floor
Corridor 1.00 22.950 22.950 2.500 57.375 Outer
57.375 Sq.m
Inner rooms
Above class room 7 1.00 5.750 5.750 5.750 33.062
Above class room 8 1.00 5.775 5.770 5.750 33.177
Above class room 9 1.00 5.775 5.770 5.750 33.177
Staircase portion 1.00 5.550 5.550 4.400 24.420
123.836 Sq.m
Total gypsum board false ceiling work 181.211 Sq.m
18 ROOFING WORK
19 ROOF TRUSS
Second Floor (Roof cover) Length TL Wt/m
No of Truss 8
Top Chord NB50M 2 5.64 11.28 5.03 453.907 (3.6 mm th)
Bottom Chord NB40M 1 8.83 8.83 3.56 251.478 (3.2 mm th)
Vertical Strut NB40M 2 0.42 0.84 3.56 23.923
2 0.83 1.66 3.56 47.276
2 1.09 2.18 3.56 62.086
Inclined Struts NB32M 2 1.27 2.54 3.10 62.992 (3.2 mm th)
2 1.12 2.24 3.10 55.552
2 1.28 2.56 3.10 63.488
King Post NB40M 2 1.35 2.70 3.56 76.896
Purlin NB 40M 12 24.75 297.00 3.56 1057.320
Runner NB40M 2 24.75 49.50 3.56 176.220
BracingNB40M 16 2.92 46.72 3.56 166.323
25% For wastage, Nut,Bolts and Plate 2497.46 624.365
Total MS pipe for roof truss 3121.826 Kg
20 CEMENT BOARD
Second Floor
Sides of truss 1.000 8.446 8.440 1.374 11.596 2 sides
Total cement board work 11.596 Sq.m
21 Eaves Board
Second Floor
Roof cover 2.000 36.050 72.100 0.250 0.0012 169.7950
Total eaves board work 169.795 Kg
23 GRILL WORK
Ground Floor
2 Earthwork in Excavation
2.1 Earth work in excavation manually Cu.m
For chain link fence 92.00 0.3000 27.6000 0.3000 0.6000 4.968
Total excavation work manually 4.968 Cu.m
4 Stone soling
Dry stone / boulder soling work in
Cu.m
foundation of retaining wall.
For chain link fence 92.00 0.300 27.600 0.300 0.150 1.242
Staircase-1 1.00 7.799 7.799 2.000 0.150 2.339
Ramp 1.00 37.220 37.220 2.000 0.150 11.166
Total stone soling 14.747 Cu.m
9 GRAVEL COMPACTION
Around the school block 1.00 Area= 128.310 0.250 32.077
Ramp 1.00 37.220 37.220 2.000 0.200 14.888
Total gravel compaction 46.965 Cu.m
Item Rate
Rate with
FURNITURE DESCRIPTIONS.
(NRs.) Transportatio Total Cost
Unit
Ex-Factory n and (NRs.)
S.N. Description Basic Specification Quantity Installation
Cost
cost
Classroom
1.0 Furniture
Top Board: 19mm thick Plywood with 1mm Laminate top and
10mm pine wood edge lipping all around enamel painted;
Student Desk Foot Rest: 25x40x1.5mm MS Square Pipe; Frame:
1.1 No 8.00 7,600.00 8,360.00 66,880.00
(2 seater) 25x25x1.5mm MS Square Pipe with book rack made of 16
gauge metal sheet;powder coated paint finish with rubber
shoe, all complete.
Top Board: 19mm thick Plywood with 1mm Laminate top and
10mm pine wood edge lipping all around, enamel painted;
Student Desk Foot Rest: 25x40x1.5mm MS Square Pipe; Frame:
1.2 No 8.00 8,300.00 9,130.00 73,040.00
(3 seater) 25x25x1.5mm MS Square Pipe with book rack made of 16
gauge metal sheet; powder coated finish with rubber shoe, all
complete.
Top Board: 19mm thick Plywood with 1mm Laminate top and
10mm polished pine wood edge lipping all around, enamel
Student Bench
1.30 painted; Foot Rest: 25x40x1.5mm MS Square Pipe; Frame: No 40.00 6,500.00 7,150.00 286,000.00
(2 seater)
25x25x1.5mm MS Square Pipe; powder coated finish with
rubber shoe, all complete.
Top Board: 19mm thick Plywood with 1mm Laminate top and
10mm polished pine wood edge lipping all around, enamel
Student Bench
1.40 painted; Foot Rest: 25x40x1.5mm MS Square Pipe; Frame: No 36.00 7,400.00 8,140.00 293,040.00
(3 seater)
25x25x1.5mm MS Square Pipe; powder coated finish with
rubber shoe, all complete.
Top Board: 19mm thick Plywood with 1mm Laminate top and
10mm pine wood edge lipping all around, enamel
ECD Student
1.5 painted;Support: 25mm thick Plywood with25x3mm strap No 0.00 6,800.00 7,480.00 -
Desk (6 seater)
support at the three corners; enamel paint with laminate
finish with nylone shoe, all complete.
Top Board: 19mm thick Plywood with 1mm Laminate top and
10mm pine wood edge lipping all around enamel painted;
1.60 Teacher's Table Foot Rest: 25x40x1.5mm MS Square Pipe; Frame: No 12.00 7,810.00 8,591.00 103,092.00
25x25x1.5mm MS Square Pipe; powder coated finish with
rubber shoe, all complete.
Seat with back rest; Metal frame, without arm rest, rubber
1.70 Teacher's Chair No 12.00 2,200.00 2,420.00 29,040.00
shoe cap, powder coated finish, all complete
Front board: 12 mm soft board over 12mm plywood with
fabric cover and enamel painted pine wood edging, including
1.8 Soft Board No 4,500.00 4,950.00 -
2 hanging eye-hooks and stay; Support frame : 25x25x1mm
MS Square Pipe powder coat finish, all complete.
19 mm Plywood with pine wood edge lipping and base
1.9 Book Shelf No 15,000.00 16,500.00 -
skirting; enamel painted finsh, all complete
Front board: 19 mm ply board with with 1mm white laminate
gloss finish top cover and wood edging, including 3 eye
1.10 White Board No 12.00 5,000.00 5,500.00 66,000.00
hooks, stay and marker pad; Support frame : 25x25x1mm MS
Square Pipe, enamel painted all complete
2.00 Library No -
Top Board: 19mm Plywood with 1mm Laminate top, wood
2.10 Library Table edge lipping, enamel painted; Frame: 25x25 Steel square No 0.00 11,000.00 12,100.00 -
pipe, nylone shoe, powder coated finish, all complete.
19 mm Plywood, wood edge lipping and base skirting; wood
2.20 Library Shelf No 0.00 23,000.00 25,300.00 -
underframe, enamel painted finsh all complete
3.00 Computer No 0.00 - - -
Top Board: 19mm thick Plywood with 1mm Laminate top and
10mm pine wood edge lipping all around enamel painted;
3.10 Computer Table Foot Rest: 25x40x1.5mm MS Square Pipe; Frame: No 0.00 9,200.00 10,120.00 -
25x25x1.5mm MS Square Pipe ; powder coated finish with
rubber shoe, all complete.
Swivel type Paded seat with low back rest; Metal frame,
3.20 Computer Chair without arm rest, rubber shoe cap, powder coated finish; No 0.00 4,000.00 4,400.00 -
height manually adjustable type, all complete
4.00 Office No 0.00 - - -
8 Providing and laying first class local made brick in foundation in cement mortar ( 1 : 6 ) ,including m3
material and transportation up to 30m 17784.70
Good quality local chimney made Brickwork in 1:4 C/S mortar above ground floor in perfect line level
9 finished including wetting the bricks,racking the joints and curing the work for at least 7 days all m3
complete. 17954.46
10 110 mm ( Half Brick ) Thick chimney Fired brick works in cement mortar( 1 : 4 ). (per 10 sq.m.) m 2
2084.22
Providing and Laying Rubble masonry works including supply of hard stone blocks, preparing cement
11 m3 18871.25
mortar (1:6) and construction of wall upto 5 m high (Haulage distance up to 10 m)
P.C.C. in 1:3:6 (M10)work for levelling in ground with approved quality of cement and sand and
12 crushed stone aggregate including mixing,laying,curing etc all as per instruction and specification all m3 21844.43
complete.
P.C.C. in 1:2:4 (M15)work for levelling in ground with approved quality of cement and sand and
13 crushed stone aggregate including mixing,laying,curing etc all as per instruction and specification all m3 24524.56
complete.
P.C.C. in 1:1.5:3 (M20) work for levelling in ground with approved quality of cement and sand and
14 crushed stone aggregate including mixing,laying,curing etc all as per instruction and specification all m3 28064.85
complete.
15 19mm ply formwork for beam,column,slab,staircase,lintel,sill etc. m2 1270.11
Cutting, bending & placing of reinforcement bars in position as shown in the drawings and binding by
16 Kg 123.92
GI wire for RCC works with 30 m lead all complete
17 38 mm PCC(1:2:4) with punning m2 1094.33
18 50 mm PCC(1:2:4) with punning m2 1385.91
19 3mm thick 1:1 CS punning m 2
324.62
20 Glazed tile in 1:4 C/S mortar m2 3141.01
21 Unglazed tile in 1:4 C/s mortar m2 2801.86
22 12.5 mm thick plastering for levelling surface,1:3 cement sand mortar on ceiling m 2
539.78
23 12.5 mm thick plastering for levelling surface,1:4 cement sand mortar other than ceiling m2 481.82
24 20 mm thick plastering for levelling surface,1:4 cement sand mortar on outer side m 2
665.68
25 3/4" thick Panipatti in 1:3 C/S mortar rm 285.14
26 Neat cement skirting rm 109.43
27 Salwood frame m3 285801.47
Supplying and fitting Ready made Teak wood Doors, special (Seasoned and Poisoned treated ,one
28 m2 9301.96
side teak) with all neccessary hardware all complete.
Supplying and fitting Ready made Teak wood Doors,ordinary (Seasoned and Poisoned treated ,one
29 m2 9403.42
side teak and other side water proof ply fitting) with all neccessary hardware all complete.
30 Metal window m2 9074.28
31 Two coat distemper paint with one coat primer m2 143.27
2 coats of weather coat of approved colour with one coat primer to give uniform coloring after
32 m2 244.69
rendering the surface on wall,column etc over properly cleaned surface all complete.
33 3 coats of chapra polish m2 140.44
2 coats of ready made enamel paint of approved colour over 1 coats of primer Painting over properly
34 m2 264.25
sanded wooden surface all complete.
Supply , weilding & fabricating MS pipe railing with redoxide paint all complete as per specification
35 Kg 136.95
and instruction.
49 Demolition of roof of CGI sheet with wooden truss and removing the material at a distance of 10m m 2
44.49
50 Demolition of TLC and removing the material at a distance of 10m m2 113.71
Earthwork excavation (Manual excavation) in Gravel mixed soil in foundation including stacking
2 the soil 1 m from the edge of the foundation and 30m hauling distance and 3m lift all Unit: 1 m3
complete as per instruction by site engineer. Amount
S. N. Description Unit Quantity Rate (NRs.) Remarks
(NRs.)
A Labour
Unskilled MD 0.80 480.00 384.00
B Material
Nil
C Equipment
@ 3% of (A) LS 1.00 11.52
D Subtotal (A+B+C) 395.52
E Contractor's Overhead@ 15% 0f(D) 59.33
Total(D+E) 454.85
Rate per 1 m3 454.85
Earthwork excavation in all type of soil using hydraulic excavation (capacity 0.8 m3) all
3 complete as per instruction by site engineer. Unit: 1 m3
Amount
S. N. Description Unit Quantity Rate (NRs.) Remarks
(NRs.)
A Labour
Unskilled MD 480.00
B Material
Diesel Lt 0.15 77.50 11.63
C Equipment
Hydraulic Excavator m3 0.0125 4180.00 52.25
D Subtotal (A+B+C) 63.88
E Contractor's Overhead@ 15% 0f(D) 9.58
Total(D+E) 73.46
Rate per 1 m3 73.46
4 Earthwork in filling by laying 15-15 cm layer soil with spraying water and compacted by labour Unit: 1 m3
Amount
S. N. Description Unit Quantity Rate (NRs.) Remarks
(NRs.)
A Labour
Unskilled MD 0.50 480.00 240.00
B Material
water ltr 5.00 0.30 1.50
C Equipment
D Subtotal (A+B+C) 241.50
E Contractor's Overhead@ 15% 0f(D) 36.23
Total(D+E) 277.73
Rate per 1 m3 277.73
Dry stone soling with sand foundation/floor including sand filling in joint levelling ramming to
5 Unit: 1 m3
level including sand filling joints.
Amount
S. N. Description Unit Quantity Rate (NRs.) Remarks
(NRs.)
A Labour
Skilled MD 680.00
Unskilled MD 1.50 480.00 720.00
B Material
Stone m3 1.00 8437.70 8437.70
River Sand m3 0.20 7529.60 1505.92
C Equipment
Nil
6 Filling with sand, water spraying and compaction including transportation from 10m distance. Unit: 1 m3
Amount
S. N. Description Unit Quantity Rate (NRs.) Remarks
(NRs.)
A. Labour:
Unskilled md 0.70 480.00 336.00
B. Material:
Sand m3 1.10 7529.60 8282.56
water lit. 5.00 0.30 1.50
C. Subtotal (A+B) 8620.06
D. Contractor's Overhead @ 15% of (C) 1293.01
Total (C+D) 9913.07
\ Rate per m3 9913.07
Supplying and laying 500micron tear proof good quality polythene above the compacted
7 Unit: 10 m2
boulder stone.
S. N. Description Unit Quantity Rate (NRs.) Amount (NRs.) Remarks
A Labour
Skilled MD 0.60 680.00 408.00
Unskilled MD 0.60 480.00 288.00
B Material
500 Micron Polythene Sheet m2 11.00 31.71 348.81
D Subtotal (A+B+C) 1044.81
E Contractor's Overhead@ 15% 0f(D) 156.72
= Total(D+E) 1201.53
Rate per m2 120.15
First class local chimney made Brickwork in 1:6 C/S mortar on ground floor in perfect line level
8 finished including wetting the bricks,racking the joints and curing the work for at least 7 days Unit:1m3
all complete.
Amount
S. N. Description Unit Quantity Rate (NRs.) Remarks
(NRs.)
A Labour
Skilled MD 1.50 680.00 1020.00
Unskilled MD 2.20 480.00 1056.00
Unskilled MD 0.20 480.00 96.00
B Material
Cement MT 0.07 1399.98 98.00
Sand m3 0.30 7529.60 2258.88
Brick Nos 560.00 19.47 10903.20
water ltr 100.00 0.30 30.00
C Equipment
3% of A LS 1.00 2.88
D Subtotal (A+B+C) 15464.96
E Contractor's Overhead @15% of (D) 2319.74
Total(D+E) 17784.70
Rate per 1 m3 17784.70
First class local chimney made Brickwork in 1:4 C/S mortar above ground floor in perfect line
9 level finished including wetting the bricks,racking the joints and curing the work for at least 7 Unit:1m3
days all complete.
Amount
S. N. Description Unit Quantity Rate (NRs.) Remarks
(NRs.)
A Labour
Skilled MD 1.50 680.00 1020.00
Unskilled MD 2.20 480.00 1056.00
Unskilled MD 0.70 480.00 336.00
B Material
Cement MT 0.10 1399.98 140.00
Sand m3 0.28 7529.60 2108.29
Brick Nos 560.00 19.47 10903.20
water ltr 130.00 0.30 39.00
C Equipment
3% of A LS 1.00 10.08
D Subtotal (A+B+C) 15612.57
E Contractor's Overhead @15% of (D) 2341.89
Total(D+E) 17954.46
10 110 mm ( Half Brick ) Thick chimney Fired brick works in cement mortar( 1 : 4 ). (per 10 sq.m.) Unit:10 m2
Amount
S. N. Description Unit Quantity Rate (NRs.) Remarks
(NRs.)
A Labour
Skilled MD 1.90 680.00 1292.00
Unskilled MD 2.60 480.00 1248.00
B Material
Cement MT 0.11 1399.98 154.00
Sand m3 0.30 7529.60 2258.88
Brick Nos 673.00 19.47 13103.31
Water ltr 100.00 0.30 30.00
C Equipment
3% of A LS 1.00 37.44
D Subtotal (A+B+C) 18123.63
E Contractor's Overhead @15% of (D) 2718.54
Total(D+E) 20842.17
Rate per 1 m2 2084.22
11 Providing and Laying Rubble masonry works including supply of hard stone blocks, preparing Unit:1m3
cement mortar (1:6) and construction of wall upto 5 m high (Haulage distance up to 10 m)
Amount
S. N. Description Unit Quantity Rate (NRs.) Remarks
(NRs.)
A Labour
Skilled MD 1.50 680.00 1020.00
Unskilled MD 5.00 480.00 2400.00
B Material
Cement MT 0.106 1399.98 148.40
Sand m3 0.47 7529.60 3538.91
Block stone m3 1.00 8437.70 8437.70
Bond stone m3 0.10 8437.70 843.77
water ltr 70.00 0.30 21.00
C Equipment
P.C.C. in 1:3:6 (M10)work for levelling in ground with approved quality of cement and sand and
12 crushed stone aggregate including mixing,laying,curing etc all as per instruction and Unit: 1 m3
specification all complete.
Amount
S. N. Description Unit Quantity Rate (NRs.) Remarks
(NRs.)
A Labour
Skilled MD 1.00 680.00 680.00
Unskilled MD 4.00 480.00 1920.00
B Material
Cement MT 0.22 27999.60 6159.91
River Sand m3 0.47 7529.60 3538.91
Crushed agg.40mm down m3 0.65 7429.60 4829.24
Crushed agg.20mm down m 3
0.24 7629.60 1831.10
water ltr 120.00 0.30 36.00
C Equipment
Nil
D Subtotal (A+B+C) 18995.16
E Contractor's Overhead@ 15% 0f(D) 2849.27
Total(D+E+F) 21844.43
P.C.C. in 1:2:4 (M15)work for levelling in ground with approved quality of cement and sand and
13 crushed stone aggregate including mixing,laying,curing etc all as per instruction and Unit: 1 m3
specification all complete.
Amount
S. N. Description Unit Quantity Rate (NRs.) Remarks
(NRs.)
A Labour
Skilled MD 1.00 680.00 680.00
Unskilled MD 4.00 480.00 1920.00
P.C.C. in 1:1.5:3 (M20) work for levelling in ground with approved quality of cement and sand
14 and crushed stone aggregate including mixing,laying,curing etc all as per instruction and Unit: 1 m3
specification all complete.
Amount
S. N. Description Unit Quantity Rate (NRs.) Remarks
(NRs.)
A Labour
Skilled MD 0.50 680.00 340.00
Unskilled MD 3.50 480.00 1680.00
B Material
Cement MT 0.40 27999.60 11199.84
River Sand m3 0.425 7529.60 3200.08
Crushed agg.20mm down m3 0.57 7629.60 4348.87
Crushed agg.10mm down m3 0.29 7529.60 2183.58
Water ltr 200.00 0.30 60.00
Diesel ltr 3.00 77.50 232.50
Petrol ltr 0.10 101.50 10.15
C Equipment
Vibrator Hrs 0.25 96.80 24.20
Mixer Hrs 0.60 1875.00 1125.00
D Subtotal (A+B+C) 24404.22
E Contractor's Overhead@ 15% 0f(D) 3660.63
Total(D+E) 28064.85
Unit: 100
15 Plywood formworks with steel adjustable pipe props for floor and slab
Amount m2
S. N. Description Unit Quantity Rate (NRs.) Remarks
(NRs.)
A. Labour:
Skilled md 17.20 680.00 11696.00
Unskilled md 25.70 480.00 12336.00
B. Material:
19mm board m2 16.50 1596.00 26334.00 use for 6
Local wood m3 0.232 80096.28 18582.34 times
Iron pipes (NMB50-M) No. 4.40 84.09 370.00
Iron nails Kg 25.00 94.80 2370.00
C. Equipment:
@ 3% of (A) LS 720.96
D. Subtotal (A+B+C) 72409.30
E. Contractor's Overhead @ 15% of (D) 10861.40
Total (D+E) 83270.70
\ Rate per 1 sq m 832.71
19mm plywood formworks for beam including materials and removing with transpotation upto
16 Unit: 10 m2
30m.
Amount
S. N. Description Unit Quantity Rate (NRs.) Remarks
(NRs.)
A. Labour:
Skilled md 2.67 680.00 1815.60
Unskilled md 4.00 480.00 1920.00
B. Material:
ply board m2 1.65 1596.00 2633.40
local wood cum 0.039 80096.28 3123.75
steel prop no. 0.40 2429.10 971.64
nails Kg 2.50 94.80 237.00
C. Subtotal (A+B) 10701.39
D. Contractor's Overhead @ 15% of (C) 1605.21
Total (C+D) 12306.60
19mm plywood formworks for column including materials,erection,nailing, removing with Unit: 4.20
17
transpotation upto 30m.(formwork on 2m dia column) m2
Amount
S. N. Description Unit Quantity Rate (NRs.) Remarks
(NRs.)
A. Labour:
Skilled md 1.574 680.00 1070.32
Unskilled md 2.361 480.00 1133.28
B. Material:
ply board m2 0.6930 1596.00 1106.03
local wood cum 0.019 80096.28 1521.83
steel prop no. 0.54 2429.10 1311.71
nails Kg 2.50 94.80 237.00
C. Subtotal (A+B) 6380.17
D. Contractor's Overhead @ 15% of (C) 957.03
Total (C+D) 7337.20
\ Rate per 1 sq m 1746.95
Cutting, bending & placing of reinforcement bars in position as shown in the drawings and
19 Unit: 1 Kg
binding by GI wire for RCC works with 30 m lead all complete
Amount
S. N. Description Unit Quantity Rate (NRs.) Remarks
(NRs.)
A. Labour:
Skilled md 0.012 680.00 8.16
Unskilled md 0.012 480.00 5.76
B. Material:
Reinforcement bar (Fe 500) Kg 1.05 88.04 92.44
Binding wire Kg 0.01 97.80 0.98
C. Equipment:
@ 3% of (A) LS 0.42
D. Subtotal (A+B+C) 107.76
E. Contractor's Overhead @ 15% of (D) 16.16
Total (D+E) 123.92
\ Rate per 1 Kg 123.92
20 Providing and Laying 38mm PCC (1:2:4) with 1:1 C/S punning on all rooms Unit:10 m2
Amount
S. N. Description Unit Quantity Rate (NRs.) Remarks
(NRs.)
A Labour
Skilled MD 1.25 680.00 850.00
Unskilled MD 2.00 480.00 960.00
B Material
Cement MT 0.13 27999.60 3639.95
Sand m3 0.18 7529.60 1355.33
Aggregate m 3
0.36 7529.60 2710.66
C Equipment
Nil
D Subtotal (A+B+C) 9515.94
E Contractor's Overhead @15% of (D) 1427.39
Total(D+E) 10943.33
21 Providing and Laying 50mm PCC (1:2:4) with 1:1 C/S punning on terrace. Unit:10 m2
Amount
S. N. Description Unit Quantity Rate (NRs.) Remarks
(NRs.)
Providing and laying 6mm porcelain glazed tiles on walls and floor of approved colored laid
Unit: 10 sq
23 with cement sand mortar(1:4) finished with white cement including polishing all complete as
m
per specification and instruction of site engineer
Amount
S. N. Description Unit Quantity Rate (NRs.) Remarks
(NRs.)
A. Labour:
Skilled md 13.00 680.00 8840.00
Unskilled md 4.50 480.00 2160.00
B. Material:
Cement mt. 0.056 27999.60 1567.98
Sand cu.m. 0.152 7529.60 1144.50
White Cement kg 3.228 52.25 168.66
Porcelain glazed tile sq.m. 11.00 1221.09 13431.99
Providing and laying 6mm porcelain non glazed tiles on walls and floor of approved colored laid
Unit: 10 sq
24 with cement sand mortar(1:4) finished with white cement including polishing all complete as
m
per specification and instruction of site engineer
Amount
S. N. Description Unit Quantity Rate (NRs.) Remarks
(NRs.)
A. Labour:
Skilled md 13.00 680.00 8840.00
Unskilled md 4.50 480.00 2160.00
B. Material:
Cement mt. 0.056 27999.60 1567.98
Sand cu.m. 0.152 7529.60 1144.50
White Cement mt 3.228 52.25 168.66
Porcelain non glazed tile sq.m. 11.00 952.99 10482.89
26 12.5 mm thick plastering for levelling surface,1:4 cement sand mortar other than ceiling Unit:100 m2
Amount
S. N. Description Unit Quantity Rate (NRs.) Remarks
(NRs.)
A Labour
Skilled MD 12.00 680.00 8160.00
Unskilled MD 16.00 480.00 7680.00
B Material
Cement MT 0.538 27999.60 15063.78
Sand m3 1.46 7529.60 10993.22
C Equipment
Nil
D Subtotal (A+B+C) 41897.00
E Contractor's Overhead @15% of (D) 6284.55
Total(D+E) 48181.55
Rate per 1 m2 481.82
Supplying and fitting ready made Teak wood doors,special (Seasoned and Poisoned treated one
31 Unit:sqm
side teak) with all necessary hardware all complete.
Amount
S. N. Unit Quantity Rate (NRs.) Remarks
(NRs.)
A Labour
Skilled MD 1.61 680.00 1094.80
Unskilled MD 0.161 480.00 77.28
B Material
Readymade teak wood m2 1.10 2668.48 2935.33
Wooden listy r.m. 7.434 404.22 3004.97
Gum L.S. 20.00
100mm Hinge Nos 3.00 30.56 91.68
150mm tower bolt Nos 2.00 56.28 112.56
Mortis lock(Ordinary) Nos 1.00 732.04 732.04
Screw nail L.S. 20.00
D Subtotal (A+B+C) 8088.66
E Contractor's Overhead @15% of (D) 1213.30
Total(D+E) 9301.96
Rate per 1 m2 9301.96
Supplying and fitting ready made Teak wood doors,special (Seasoned and Poisoned treated one
32 Unit:sq.m
side teak,and other side water proof ply fittings) with all necessary hardware all complete.
Amount
S. N. Unit Quantity Rate (NRs.) Remarks
(NRs.)
A Labour
Skilled MD 1.61 680.00 1094.80
Unskilled MD 0.161 480.00 77.28
B Material
Readymade teak wood sq.m 1.00 3023.56 3023.56
Wooden listy rm 7.434 404.22 3004.97
Gum L.S. 20.00
100mm Hinge Nos 3.00 30.56 91.68
150mm tower bolt Nos 2.00 56.28 112.56
Mortis lock Nos 1.00 732.04 732.04
Screw nail L.S. 20.00
D Subtotal (A+B+C) 8176.89
E Contractor's Overhead @15% of (D) 1226.53
Total(D+E) 9403.42
Rate per 1 m2 9403.42
2 coats of apex paint (weather coat) of approved colour with one coat primer to give uniform
35 coloring after rendering the surface on wall,column etc over properly cleaned surface all Unit:100 m2
complete.
Amount
S. N. Description Unit Quantity Rate (NRs.) Remarks
(NRs.)
A Labour
Skilled MD 5.80 680.00 3944.00
Unskilled MD 5.80 480.00 2784.00
B Material
Apex paint LT 16.00 768.31 12292.96
Primer LT 8.00 282.09 2256.72
C Equipment
Nil
D Subtotal (A+B+C) 21277.68
E Contractor's Overhead @15% of (D) 3191.65
Total(D+E) 24469.33
Rate per 100 m2 24469.33
Rate per 1 m2 244.69
2 coats of ready made enamel paint of approved colour over 1 coats of primer Painting over
37 Unit:100 m2
properly sanded wooden surface all complete.
Amount
S. N. Description Unit Quantity Rate (NRs.) Remarks
(NRs.)
A Labour
Skilled MD 12.00 680.00 8160.00
Unskilled MD 8.00 480.00 3840.00
B Material
Primer LT 8.10 282.09 2284.93
Enamel paint LT 16.00 543.31 8692.96
C Equipment
Nil
D Subtotal (A+B+C) 22977.89
E Contractor's Overhead @15% of (D) 3446.68
Total(D+E) 26424.57
38 Providing & fixing of MS grill with sanded and one coat red oxide Unit: 1 kg
Amount
S. N. Description Unit Quantity Rate (NRs.) Remarks
(NRs.)
A. Labour:
Skilled md
Unskilled md
B. Material:
all types of black pipes making and fixing kg 1.00 119.09 119.09
primer paint LS
C. Equipment:
@ 3% of (A) LS
D. Subtotal (A+B+C) 119.09
E. Contractor's Overhead @ 15% of (D) 17.86
Total (D+E) 136.95
\ Rate per 1 kg 136.95
Supply,fitting and fixing of MS grill made in 4.5mm X 20mm size MS patti frame with 12mm X
Unit: 10
39 12mm solid core square rod grill with sandpapering and prime coat all complete as per
sqm
instruction of site incharge
Amount
S. N. Description Unit Quantity Rate (NRs.) Remarks
(NRs.)
A. Labour:
Skilled md 0.70 680.00 476.00
Unskilled md 0.60 480.00 288.00
A. Material:
4.5mm X 20mm size MS patti frame kg 28.24 144.09 4069.10
Making and fixing 12mm X 12mm solid core 21734.35
kg 215.00 101.09
square rod grill
C. Subtotal 26567.45
D. Contractor's Overhead @ 15% of (C) 3985.12
Total (C+D) 30552.57
\ Rate per sq. m. 3055.26
Supplying and Installation of Gypsum board False Ceiling with GI framing and all accessories
40 Unit: 1 m2
complete as per drawing, specification and instruction of the consultant/ Engineer all complete
Amount
S. N. Description Unit Quantity Rate (NRs.) Remarks
(NRs.)
12.5mm thick Gypsum Board False ceiling
A. Sq.m 1.00 1228.00 1228.00
including all necessary material
B. Subtotal 1228.00
C, Contractor's Overhead @ 15% of (D) 184.20
Total (B+D) 1412.20
\ Rate per m2 1412.20
42 Providing materials and constructing 2ft wide ridge from 0.5mm plain GI sheet and also fixing Unit:10 rm
Unit: 18.94
43 Providing & fixing of MS truss with one coat red oxide
Amount kg
S. N. Description Unit Quantity Rate (NRs.) Remarks
(NRs.)
A. Labour:
Skilled md 0.687 680.00 467.16
Unskilled md 0.781 480.00 374.88
B. Material:
all types of black pipes making and fixing kg 18.94 84.09 1592.66
primer paint LS 110.00
C. Equipment:
@ 3% of (A) LS 25.26
D. Subtotal (A+B+C) 2569.96
E. Contractor's Overhead @ 15% of (D) 385.49
Total (D+E) 2955.45
\ Rate per 1 kg 156.04
B. Material:
Cement Board Sq.m 27.00 460.29 12427.83
Fixture R.m 15.40 450.00 6930.00
Joint Filling R.m 36.00 125.00 4500.00
C. Equipment:
@ 3% of (A) LS 264.60
D. Subtotal (A+B+C) 32942.43
E. Contractor's Overhead @ 15% of (D) 4941.36
Total (D+E) 37883.79
\ Rate per m2 3156.98
Providing and fixing mild steel angle (bracing), 50*50*5mm ,16 gauge MS sheets and mild steel
Unit: 10
48 sqaure pipes treated with one coats of primer and two coats of enamel paint, all complete as
sq.m
detailed in drawing, specification and instructions of the Engineer.
Amount
S. N. Description Unit Quantity Rate (NRs.) Remarks
(NRs.)
A. Labour:
Skilled md
Unskilled md
B. Material:
Metal Gate sq.m 10.00 3205.40 32054.00
C. Subtotal 32054.00
D. Contractor's Overhead @ 15% of (C) 4808.10
Total (C+D) 36862.10
\ Rate per sq. m. 3686.21
Providing 1.5 meter high chain link fence having mesh size 50mm x 50mm woven with SWG 10
heavy GI coated wire with 50x50x5 mm ISA line post spaced at 2.5 meter center to center,
50x50x5 mm corner and end post , 50x50x5 mm ISA bracing post at every 15 meter straight run
=
and at every change in direction more than 15 degree and at end and corner post, 40x40x4 mm
49 Unit: 10 m2
ISA top and bottom rail including installation of all post by excavating hole (300x300x600) and
filling with concrete 1:2:4 (1 cement : 2 sand : 4 stone aggregate 20 mm and down grade),
rails, stretching chain link fabric, fixing chain link fabric securely in all post, top and bottom
rail, etc., all complete as per drawings, specification and instruction of the Engineer.
52 Demolition of roof of sheet with wooden truss removing the material at a distance of 10m Unit: 1 m2
Amount
S. N. Description Unit Quantity Rate (NRs.) Remarks
(NRs.)
A Labour
Skilled MD 0.027 680.00 18.36
Unskilled MD 0.04 480.00 19.20
B Equipment
@ 3% of (A) LS 1.13
C Subtotal (A+B+C) 38.69
D Contractor's Overhead@ 15% 0f(D) 5.80
Total(D+E) 44.49
Rate per 1 m2 44.49
B Equipment
@ 3% of (A) LS 2.88
Total(D+E) 113.71
1
I.P W C. COMODE with low level cistern complete set.
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 3 nos 680.00 2,040.00
un skilled 3 nos 480.00 1,440.00 3,480.00
a. Porcelain clay white glaze Indian Pattern
Comode (Hindware Parryware, bolan or
equivalent ) regular 1 nos 1,825.05 1,825.05
c.10.0 ltr.porcelain clay low level flushing
cistern complete accessories( Internal PVC
materials fittings) 1 nos 4,092.85 4,092.85
c .Bakelite toilet seat cover 1 nos 317.40 317.40
c. 3.2x60 Cm (1 1/4"x24") flushing CP pipe 1 nos 586.50 586.50
d. 1.5x45 CM (½" x18") PVC pipe connector 1 nos 164.45 164.45
e. screw, etc. Ls 40.00 7,026.25
Totall rate 10,506.25
Extra 10% 702.63
Actual Rate 11,208.88
15% contractor overhead 1,681.33
Rate per set Rs. 12890.21 Total (Rs.) 12,890.21
2
580 mm Porcelain clay white glaze Orissa Pan complete set
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 1 nos 680.00 680.00
un skilled 1 nos 480.00 480.00 1,160.00
a. 580 mm Porcelain clay white glaze Orissa
materials Pan 1 nos 1.15 1.15
1.15
Total rate 1,161.15
Extra 10% 0.12
Actual rate 1,161.27
15% contractor overhead 174.19
Rate per set Rs. 1,335.46 Total (Rs.) 1,335.46
3
50x40cm OVAL WASH BASIN with mixer COMPLETE SET
4
Kitchen Sink 37" long stainless steel
sources Level Qty Unit Rate/unit cost Total cost
labour skilled 2 nos 680.00 1,360.00
un skilled 1 nos 480.00 480.00 1,840.00
a. Stainless steel, 19"x16" size Bowl with
materials
drain board. Ordinary type 1 sets 2,661.10 2,661.10
b. Pvc bottle trap with 32mm Dia CP waste
coupling with CP chain and rubber. 1 nos 547.40 547.40
c. ½" dia CP sink cock. 1 nos 1,505.35 1,505.35 4,878.30
1.5x45CM (1/2"x18")Pipe Connector 1 nos 164.45 164.45
e,Zinc Oxide Screw ls
Total Rate 6,718.30
Extra 10% 487.83
Actual rate 7,206.13
15% contractor overhead 1,080.92
Rate per set Rs. 8287.05 Total (Rs.) 8,287.05
5
45*35 cm white glazed squatting plate urinal set
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 2 nos 680.00 1,360.00
un skilled 1 nos 480.00 480.00 1,840.00
materials 45*35 cm white glazed squatting plate urinal s 1 nos 12,121.15 12,121.15
12,121.15
Total rate 13,961.15
Extra 10% 1,212.12
Actual rate 15,173.27
15% contractor overhead 2,275.99
17449.26 Total (Rs.) 17,449.26
6
15mm CP Bib Cock
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.11 nos 680.00 74.80 74.80
materials 15mm CP bib cock 1 nos 13,611.13 13,611.13 13,611.13
Total rate 13,685.93
Extra 10% 1,361.11
Actual rate 15,047.04
15% contractor overhead 2,257.06
Rate per nos Rs. 17304.10 Total (Rs.) 17,304.10
7
15mm Stainless Steel Bib Cock
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.11 nos 680.00 74.80 74.80
materials a. 15mm Stainless Steel bib cock 1 nos 5,088.75 4,425.00 4,425.00
Total rate 4,499.80
8
15mm Auto closing Bib Cock with aerator
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.11 nos 680.00 74.80 74.80
materials a. 15mm Auto closing bib cock with aerator 1 nos 26,121.15 26,121.15 26,121.15
Total rate 26,195.95
Extra 10% 2,612.12
Actual rate 28,808.07
15% contractor overhead 4,321.21
Rate per nos Rs. 33129.28 Total (Rs.) 33,129.28
9
15mm Urinal Auto closing Valve with built in control cock
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.11 nos 680.00 74.80 74.80
materials a. 15mm Urinal Auto closing valve with 1 nos 3,098.10 3,098.10 3,098.10
built - in control cock
Total rate 3,172.90
Extra 10% 309.81
Actual rate 3,482.71
15% contractor overhead 522.41
Rate per nos Rs. 4005.12 Total (Rs.) 4,005.12
10
C.P. 15mm Angle valve
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.11 nos 680.00 74.80 74.80
materials a. 15mm fancy type angle valve 1 nos 12,441.15 12,441.15 12,441.15
Total rate 12,515.95
Extra 10% 1,244.12
Actual rate 13,760.07
15% contractor overhead 2,064.01
Rate per nos Rs. 15824.08 Total (Rs.) 15,824.08
11
15mm two way angle valve
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.11 nos 680.00 74.80 74.80
materials a. 15mm two way angle valve 1 nos 11,571.15 11,571.15 11,571.15
Total rate 11,645.95
Extra 10% 1,157.12
Actual rate 12,803.07
15% contractor overhead 1,920.46
Rate per nos Rs. 14723.53 Total (Rs.) 14,723.53
12
13
CHROME PLATE TOILET PAPER HOLDER
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.11 nos 680.00 74.80 74.80
materials a.Chrome plate toilet paper holder 1 nos 1,068.35 1,068.35
b.Zink oxide screw etc. Ls 40.00 1,108.35
Total rate 1,183.15
Extra 10% 110.84
Actual rate 1,293.99
15% contractor overhead 194.10
Rate per nos Rs. 1488.09 Total (Rs.) 1,488.09
14
PVC FLOOR TRAP 11x7.5cm (4" X 2½")
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.11 nos 680.00 74.80
un skilled 0.10 nos 480.00 48.00 122.80
materials Floor Trap 11x7.5cm (4" X 2½") 1 nos 322.00 322.00 322.00
Total rate 444.80
Extra 10% 32.20
Actual rate 477.00
15% contractor overhead 71.55
Rate per nos Rs. 548.55 Total (Rs.) 548.55
15
CP Grab bar European Pattern 300mm long bend type Grohe,Essel or Equivalent
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled(1/9) 0.22 nos 680.00 149.60 149.60
CP Grab bar European Pattern 300mm long
materials bend type Grohe,Essel or Equivalent 1 nos 47,861.15 47,861.15
b. Zink oxide screw etc. Ls 40.00 47,901.15
Total rate 48,050.75
Extra 10% 4,790.12
Actual rate 52,840.87
15% contractor overhead 7,926.13
Rate per nos Rs. 60767.00 Total (Rs.) 60,767.00
16
CHROME PLATE SOAP DISH.
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.11 nos 680.00 74.80 74.80
17
Stainless Steel towel rod 1.5x45cm (½"x18")
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.22 nos 680.00 149.60 149.60
materials a . Stainless Steel Towel rod 1 nos 1,426.00 1,426.00
b. Screws etc. Ls 40.00 1,466.00
Total rate 1,615.60
Extra 10% 146.60
Actual rate 1,762.20
15% contractor overhead 264.33
Rate per nos Rs. 2026.53 Total (Rs.) 2,026.53
18
Looking Mirror Modi guard 450x600mm (18"x 24")
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.33 nos 680.00 224.40 224.40
materials a.Bevelled edge looking mirror 50x40 cm 1 nos 1,677.85 1,677.85
b . Screws Ls 40.00 1,717.85
Total rate 1,942.25
Extra 10% 171.79
Actual rate 2,114.04
15% contractor overhead 317.11
Rate per nos Rs. 2431.15 Total (Rs.) 2,431.15
19
CPVC Pipe SDR 11, 15mm (1/2") CTS
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.01 nos 680.00 6.80
un skilled 0.01 nos 480.00 4.80 11.60
a. 15 mm CPVC Pipe SDR 11 CTS, 28.1
materials kg/cm2 1 Rm 1,331.15 1,331.15
b. Cpvc fittings Ls 100.00
c. Jointing materials (flow guard adesive
soln) Ls 30.00 1,461.15
Total rate 1,472.75
Extra 10% 146.12
Actual rate 1,618.87
15% contractor overhead 242.83
Rate per Rm Rs. 1861.70 Total (Rs.) 1,861.70
20
CPVC Pipe SDR 11, 20mm (3/4") CTS
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.01 nos 680.00 6.80
21
CPVC Pipe SDR 11, 25mm (1") CTS
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.01 nos 680.00 6.80
un skilled 0.01 nos 480.00 4.80 11.60
a. 25 mm CPVC Pipe SDR 11 CTS, 28.1
materials kg/cm2 1 Rm 285.20 285.20
b. Cpvc fittings Ls 120.00
c. Jointing materials (flow guard adesive soln) Ls 30.00 435.20
Total rate 446.80
Extra 10% 43.52
Actual rate 490.32
15% contractor overhead 73.55
Rate per Rm Rs. 563.87 Total (Rs.) 563.87
22
CPVC Pipe SDR 11 , 32mm (1 1/4") CTS
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.011 nos 680.00 7.48
un skilled 0.019 nos 480.00 9.12 16.60
a. 32 mm CPVC Pipe SDR 11 CTS, 28.1
materials kg/cm2 1 Rm 345.00 345.00
b. Cpvc fittings Ls 120.00
c. Jointing materials (flow guard adesive soln) Ls 30.00 495.00
Total rate 511.60
Extra 10% 49.50
Actual rate 561.10
15% contractor overhead 84.17
Rate per Rm Rs. 645.27 Total (Rs.) 645.27
23
CPVC Pipe SDR 11, 40mm (1 1/2") CTS
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.011 nos 680.00 7.48
un skilled 0.019 nos 480.00 9.12 16.60
a. 40 mm CPVC Pipe SDR 11 CTS, 28.1
materials kg/cm2 1 Rm 62.70 62.70
b. Cpvc fittings Ls 150.00
c. Jointing materials (flow guard adesive soln) Ls 50.00 262.70
Total rate 279.30
Extra 10% 26.27
Actual rate 305.57
15% contractor overhead 45.84
Rate per Rm Rs. 351.41 Total (Rs.) 351.41
25
CPVC CTS.15 mm ball Valve( 1/2")
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.11 nos 680.00 74.80
materials a. 15 mm CPVC ball valve, CTS sockets, 1 set 419.75 419.75 494.55
Total rate 494.55
Extra 10% 41.98
Actual rate 536.53
15% contractor overhead 80.48
Rate per Rm Rs. 617.01 Total (Rs.) 617.01
26
CPVC CTS. 20 mm ball Valve( 3/4")
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.11 nos 680.00 74.80
materials a. 20 mm CPVC ball valve, CTS sockets, 1 set 558.90 558.90 633.70
Total rate 633.70
Extra 10% 55.89
Actual rate 689.59
15% contractor overhead 103.44
Rate per Rm Rs. 793.03 Total (Rs.) 793.03
27
CPVC CTS. 25 mm ball Valve (1")
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.11 nos 680.00 74.80
materials a. 25 mm CPVC ball valve, CTS sockets, 1 set 5,881.15 5,881.15 5,955.95
Total rate 5,955.95
Extra 10% 588.12
Actual rate 6,544.07
15% contractor overhead 981.61
Rate per Rm Rs. 7525.68 Total (Rs.) 7,525.68
28
CPVC CTS. 32 mm ball Valve (1 1/4")
29
CPVC CTS. 40 mm ball Valve (1 1/2")
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.11 nos 680.00 74.80
materials a. 40 mm CPVC ball valve, CTS sockets, 1 set 1,889.45 1,889.45 1,964.25
Total rate 1,964.25
Extra 10% 188.95
Actual rate 2,153.20
15% contractor overhead 322.98
Rate per Rm Rs. 2476.18 Total (Rs.) 2,476.18
30
CPVC CTS. 50 mm ball Valve (2")
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.11 nos 680.00 74.80
materials a. 50 mm CPVC ball valve, CTS sockets, 1 set 21,171.15 21,171.15 21,245.95
Total rate 21,245.95
Extra 10% 2,117.12
Actual rate 23,363.07
15% contractor overhead 3,504.46
Rate per Rm Rs. 26867.53 Total (Rs.) 26,867.53
31
G.M 50mm float valve
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.44 nos 680.00 299.20 299.20
materials a.50 mm float valve 1 nos 5,288.85 5,288.85 5,288.85
Total rate 5,588.05
Extra 10% 528.89
Actual rate 6,116.94
15% contractor overhead 917.54
Total (Rs.) 7,034.48
32
1000 litre stainless steel WATER TANK
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 3 nos 680.00 2,040.00
un skilled 4 nos 480.00 1,920.00 3,960.00
a. 1000 liter stainless steel water tank 304
grade steel with Inlet, outlet, over flow,
cleanout hole etc. all compete
materials 1 nos 20,353.85 20,353.85
20,353.85
Total rate 24,313.85
Extra 10% 2,035.39
33
2000 litre stainless steel WATER TANK
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 3 nos 680.00 2,040.00
un skilled 6 nos 480.00 2,880.00 4,920.00
a. 2000 liter stainless steel water tank 304
grade steel with Inlet, outlet, over flow,
cleanout hole etc. all compete
materials 1 nos 37,654.45 37,654.45
b.Tanki nipples etc. Ls 185.00 37,839.45
Total rate 42,759.45
Extra 10% 3,783.95
Actual rate 46,543.40
15% contractor overhead 6,981.51
Rate per nos Rs. 53524.91 Total (Rs.) 53,524.91
34
2 H.P. Electrical motor water pump Multi stage, coupled pump (Crompton)
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 4 nos 680.00 2,720.00
un skilled 3 nos 480.00 1,440.00 4,160.00
a.2 H P Electricmotor pump with base plate
materials nuts, bolts etc.set crompton 1 nos 25,975.05 25,975.05
b.Zink oxide screws etc. Ls 40.00 26,015.05
Total rate 30,175.05
Extra 10% 2,601.51
Actual rate 32,776.56
15% contractor overhead 4,916.48
Rate per nos Rs. 37693.04 Total (Rs.) 37,693.04
35
50 mm dia PVC PIPE 6 KG/CM. SQ.
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled(1/18) 0.06 nos 680.00 40.80
un skilled(1/10) 0.10 nos 480.00 48.00 88.80
materials a.50 mm dia. Pvc pipe 1 RM 113.85 113.85
b. Jointing materialsetc. Ls 113.85
Total rate 202.65
Extra 10% 11.39
Actual rate 214.04
15% contractor overhead 32.11
Rate per Rm Rs. 246.15 Total (Rs.) 246.15
36
75 mm dia PVC PIPE 6 KG/CM. SQ
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.11 nos 680.00 74.80
37
110 mm dia PVC PIPE 6 KG/CM. SQ
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.17 nos 680.00 115.60
un skilled 0.20 nos 480.00 96.00 211.60
materials a.110 m m dia. Pvc pipe 1 Rm 531.30 531.30
b. Jointing material setc. Ls 25.00 556.30
Total rate 767.90
Extra 10% 55.63
Actual rate 823.53
15% contractor overhead 123.53
Rate per nos Rs. 947.06 Total (Rs.) 947.06
38
Motor Starter Switch
sources Level Qty Unit Rate/unit cost Total cost
labour skilled 0.25 nos 680.00 170.00
un skilled 0.17 nos 480.00 81.60 251.60
materials a. Motor Starter Switch (Cromption) 1 nos 3,907.70 3,907.70 3,907.70
Actual rate 4,159.30
15% contractor overhead 623.90
Rate per set Rs. 4783.20 Total (Rs.) 4,783.20
39
G.M. 25mm float valve
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.22 nos 680.00 149.60 149.60
materials G.M. 25mm float valve 1 nos 1,491.55 1,491.55 1,491.55
Actual rate 1,641.15
Extra 10% 149.16
Actual rate 1,790.31
15% contractor overhead 268.55
Rate per nos Rs. 2058.86 Total (Rs.) 2,058.86
40
150 mm RCC hump pipe NP2
For 32 m
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 3 nos 680.00 2,040.00
un skilled 15 nos 480.00 7,200.00 9,240.00
materials a.150 mm RCC hump pipe np2 32 Rm 595.70 19,062.40
41
200 mm RCC hump pipe NP2
For 32m
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 4 nos 680.00 2,720.00
un skilled 20 nos 480.00 9,600.00 12,320.00
materials a.200 mm RCC hump pipe np2 32 Rm 773.95 24,766.40
b.200mm RCC collar 13 nos 195.50 2,541.50
c. cement 0.052 mt 27,999.60 1,455.98
d. sand 0.08 cum 7,529.60 602.37
e. Jute 2.4 kg 50.00 120.00 29,486.25
Total rate 41,806.25
Extra 10% 2,948.63
Actual rate 44,754.88
15% contractor overhead 6,713.23
Rate per Rm Rs. 1608.38 Total (Rs.) 51,468.11
42
Foldable hinge
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 2 nos 680.00 1,360.00
un skilled 1 nos 480.00 480.00 1,840.00
materials Foldable hinge 1 nos 1,393.80 1,393.80
1,393.80
Total rate 3,233.80
Extra 10% 139.38
Actual rate 3,373.18
15% contractor overhead 505.97
3879.15 Total (Rs.) 3,879.15
43
Euro Guard (Filter)
sources Level Qty Unit Rate/unit cost Total cost
labour skilled 3 nos 680.00 2,040.00
semi skilled 2 nos 480.00 960.00 3,000.00
a. Euro Guard Water purification set (one litre
materials
per minute) 1 sets 18,702.45 18,702.45
b.Jointing material etc Ls 25.00 18,727.45
Total rate 21,727.45
Extra 10% 1,872.75
Actual rate 23,600.20
15% conctractor overhead 3,540.03
27140.23 Total (Rs.) 27,140.23
45
C I Tank Cover 24"x24" (50Kg) Square (Locking Type)
sources Level Qty Unit Rate/unit cost Total cost
labour skilled 0.33 nos 680.00 224.40 224.40
C I Tank Cover 24"x24" (50Kg) Square
materials 1 nos 11,543.70 11,543.70 11,543.70
(Locking Type)
Total rate 11,768.10
Extra 10% 1,154.37
Actual rate 12,922.47
15% contractor overhead 1,938.37
14860.84 Total (Rs.) 14,860.84
46
5 kg fire extingusher ABC type Minimax, all complete set eversafe or equivalent .
sources Level Qty Unit Rate/unit cost Total cost
labour skilled 1.00 nos 680.00 680.00 680.00
5 kg fire extingusher ABC type Minimax, all
materials complete set eversafe or equivalent . 1 nos 8,199.50 8,199.50 8,199.50
Total rate 8,879.50
Extra 10% 819.95
Actual rate 9,699.45
15% contractor overhead 1,454.91
11154.36 Total (Rs.) 11,154.36
12 60 Amp MCCB
sources Level Qty Unit Rate/unit cost Total Cost
3012 labour skilled 0 nos 680.00 0.00
Semi skilled 0 nos 590.00 0.00
un skilled 0 nos 480.00 0.00 0.00
a. MCCB
materials 1 nos 6514.75 6514.75
b. CM, Screws, Grips etc.
LS 0.00
6514.75
Total rate 6514.75
Extra 10% 651.48
Actual Rate 7166.23
Rate per set Rs. 8241.16 15% conctractor overhead 1074.93
Total (Rs.) 8241.16
13 Voltmeter (0-500)
sources Level Qty Unit Rate/unit cost Total Cost
3013 labour skilled 0 nos 680.00 0.00
Semi skilled 0 nos 590.00 0.00
un skilled 0 nos 480.00 0.00 0.00
a. Voltmeter
materials 1 nos 1176.45 1176.45
c. CM, Screws, Grips etc.
LS 0.00
1176.45
Totaal rate 1176.45
Extra 10% 117.65
Actual Rate 1294.10
Rate per set Rs. 1488.22 15% conctractor overhead 194.12
13 Indicator
sources Level Qty Unit Rate/unit cost Total Cost
3013 labour skilled 0 nos 680.00 0.00
Semi skilled 0 nos 590.00 0.00
un skilled 0 nos 480.00 0.00 0.00
a. Indicator
materials 1 nos 272.55 272.55
c. CM, Screws, Grips etc.
LS 0.00
272.55
Totaal rate 272.55
Extra 10% 27.26
Actual Rate 299.81
Rate per set Rs. 344.78 15% conctractor overhead 44.97
Total (Rs.) 344.78
14 Amp. Meter (0-500)
sources Level Qty Unit Rate/unit cost Total Cost
3014 labour skilled 0 nos 680.00 0.00
Semi skilled 0 nos 590.00 0.00
un skilled 0 nos 480.00 0.00 0.00
a. Amp.Meter
materials 1 nos 1125.85 1125.85
b. CM, Screws, Grips etc.
LS 0.00
1125.85
Total rate 1125.85
Extra 10% 112.59
Actual Rate 1238.44
Rate per set Rs. 1424.21 15% conctractor overhead 185.77
Total (Rs.) 1424.21
15 Slector Switch
sources Level Qty Unit Rate/unit cost Total Cost
3015 labour skilled 0 nos 680.00 0.00
Semi skilled 0 nos 590.00 0.00
un skilled 0 nos 480.00 0.00 0.00
a. Selector Switch
materials 1 nos 817.65 817.65
b. CM, Screws, Grips etc.
LS 0.00
817.65
Total rate 817.65
Extra 10% 81.77
Actual rate 899.42
Rate per set Rs. 1034.33 15% conctractor overhead 134.91
Total (Rs.) 1034.33
16 C.T.Coil
sources Level Qty Unit Rate/unit cost Total Cost
3016 labour skilled 0 nos 680.00 0.00
Semi skilled 0 nos 590.00 0.00
21 Musical Bell
sources Level Qty Unit Rate/unit cost Total Cost
3021 labour skilled 0.5 nos 680.00 340.00
Semi skilled 0.5 nos 590.00 295.00
un skilled 0 nos 480.00 0.00 635.00
a.M.Bell
materials 10 nos 255.30 2553.00
b. CM, Screws,.
LS 90.00
2643.00
Total rate 3278.00
Extra 10% 264.30
Actual Rate 3542.30
Rate per set Rs. 407.36 15% conctractor overhead 531.35
Total (Rs.) 4073.65
Multistrand Flexible wire( 1 coil=90.00M)
Concelled Wiring
22 1.5mm2 PVC insulated copper wire
sources Level Qty Unit Rate/unit cost Total Cost
3022 labour skilled 0.75 nos 680.00 510.00
Semi skilled 1.3 nos 590.00 767.00
un skilled 1.2 nos 480.00 576.00 1853.00
a.Cu wire
materials 100 Rm 18.31 1831.00
b.HDP, hooks
100 LS 7.11 711.00
1.15 2543.15
Total rate 4396.15
15996.50
Total rate 15996.50
Extra 10% 1599.65
Actual Rate 17596.15
Rate per Nos. Rs. 2023.55 15% conctractor overhead 2639.42
Total (Rs.) 20235.57
1975.85
Total rate 2758.35
Extra 10% 197.59
Actual Rate 2955.94
Rate per Set. Rs. 3399.33 15% conctractor overhead 443.39
Total (Rs.) 3399.33
1673.40
1289.30
Total rate 2071.80
Extra 10% 128.93
Actual Rate 2200.73
Rate per Set. Rs. 2530.84 15% conctractor overhead 330.11
Total (Rs.) 2530.84
1180.00
Total rate 1962.50
Extra 10% 118.00
Actual Rate 2080.50
Rate per Set. Rs. 2392.58 15% conctractor overhead 312.08
Total (Rs.) 2392.58
35 6-32 Amp DP MCB
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0 nos 680.00 0.00
Semi skilled 0 nos 590.00 0.00
un skilled 0 nos 480.00 0.00 0.00
a.MCB
materials 10 Nos 710.70 7107.00
b.CM, Screws LS 0.00 0.00
7107.00
Total rate 7107.00
Extra 10% 710.70
Actual Rate 7817.70
Rate per Set. Rs. 899.03 15% conctractor overhead 1172.66
38 4cx16 mm2 Cu Cable + 10 mm2 Cu wire throuhgt 50 mm dia HDPE Conduit ( 4 kgf/cm2 )
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 1 nos 680.00 680.00
Semi skilled 2 nos 590.00 1180.00
un skilled 2 nos 480.00 960.00 2820.00
a.16 mm sq Cu Cable
materials 100 Rm 1191.57 119157.00
b.10mm sq Cu wire
100 Rm 212.84 21284.00
c.HDPE
100 Rm 93.15 9315.00
d.Saddle,Grips, Screws
100 LS 37.95 3795.00
153551.00
Total rate 156371.00
Extra 10% 15355.10
Actual Rate 171726.10
Rate per Rm. Rs. 1974.85 15% conctractor overhead 25758.92
Total (Rs.) 197485.02
161524.00
Total rate 164344.00
Extra 10% 16152.40
Actual Rate 180496.40
Rate per Rm. Rs. 2075.70 15% conctractor overhead 27074.46
Total (Rs.) 207570.86
4c x 35 Sqmm Cu arm cable & 1 no of 6 Sqmm Cu wire through 50 mmdia. HDPE Conduit
40 ( 4 kgf/cm2 )
340393.00
Total rate 343213.00
Extra 10% 34039.30
Actual Rate 377252.30
Rate per Rm. Rs. 4338.40 15% conctractor overhead 56587.85
Total (Rs.) 433840.15
41 4 mm2 2 core Armored cable wire through 40 mm dia HDPE conduit (4 kgf/cm2)
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.75 nos 680.00 510.00
Semi skilled 1.3 nos 590.00 767.00
un skilled 1.2 nos 480.00 576.00 1853.00
a.4mm sq Cu wire
materials 100 Rm 219.65 21965.00
b.HDPE
100 Rm 93.15 9315.00
c.Saddle,Grips, Screws
100 LS 25.30 2530.00
1.15
4mm2 2 core Armored cable wire through 40mm dia HDPE Conduit(4kgf/cm2)
42
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.75 nos 680.00 510.00
Semi skilled 1.3 nos 590.00 767.00
un skilled 1.2 nos 480.00 576.00 1853.00
a.4 mm sq Cu Cable
materials 100 Rm 219.65 21965.00
b.HDPE
100 Rm 93.15 9315.00
c.Saddle,Grips, Screws
100 LS 25.30 2530.00
33810.00
Total rate 35663.00
Extra 10% 3381.00
Actual Rate 39044.00
Rate per Rm. Rs. 449.00 15% conctractor overhead 5856.60
Total (Rs.) 44900.60
Shree Manedanda mavi Page 108 of 209 Basic rate (No print)
Distances (km) Transporation charge
Weight/ Unit Rate at
S.No Materials Unit Unit Rate Market / Source Earthen Type of Loading Tranportation Loading
unit (kg) Metalled Total Site
(Average) Charges /Unloading
17 ms pipe-50mm prop nos. 30.6 1998.00 Biratnagar 53.7 0.0 Inconvenient 425.59 5.51 431.10 2,429.10
18 Nail kg 1 82.00 Biratnagar 53.7 0.0 Convenient 12.62 0.18 12.80 94.80
19 Hinge 75 mm nos. 0.15 17.00 Biratnagar 53.7 0.0 Convenient 1.89 0.03 1.92 18.92
20 Tower bolt 100mm nos. 0.1 55.00 Biratnagar 53.7 0.0 Convenient 1.26 0.02 1.28 56.28
21 Handle nos. 0.005 60.00 Biratnagar 53.7 0.0 Convenient 0.06 0.00 0.06 60.06
22 Glass 5mm m2 51.6 838.50 Biratnagar 53.7 0.0 Inconvenient 717.67 9.29 726.96 1,565.46
23 Holdfast nos. 0.15 14.00 Biratnagar 53.7 0.0 Convenient 1.89 0.03 1.92 15.92
24 Mortis lock nos. 0.5 725.00 Biratnagar 53.7 0.0 Inconvenient 6.95 0.09 7.04 732.04
25 20mm wooden bit rm 0.3 400.00 Biratnagar 53.7 0.0 Inconvenient 4.17 0.05 4.22 404.22
26 Steel Screw Nail 35mm nos. 0.01 5.00 Biratnagar 53.7 0.0 Convenient 0.13 0.00 0.13 5.13
27 Hinge 100mm nos. 0.2 28.00 Biratnagar 53.7 0.0 Convenient 2.52 0.04 2.56 30.56
28 tower bolt 150mm nos. 0.06 67.00 Biratnagar 53.7 0.0 Convenient 0.76 0.01 0.77 67.77
29 Tower bolt 300mm nos. 0.1 107.00 Biratnagar 53.7 0.0 Convenient 1.26 0.02 1.28 108.28
30 Locking set 300mm nos. 1 1735.00 Biratnagar 53.7 0.0 Convenient 12.62 0.18 12.80 1,747.80
31 Sand m3 1600 1000.00 Local 1 16.6 0.0 Convenient 6241.60 288.00 6,529.60 7,529.60
32 Brick nos. 2.5 15.49 Local 3 6.0 0.0 Convenient 3.53 0.45 3.98 19.47
33 Agg 40mm m3 1600 900.00 Local 1 16.6 0.0 Convenient 6241.60 288.00 6,529.60 7,429.60
34 Agg 20mm m3 1600 1100.00 Local 1 16.6 0.0 Convenient 6241.60 288.00 6,529.60 7,629.60
35 Agg 10 mm m3 1600 1000.00 Local 1 16.6 0.0 Convenient 6241.60 288.00 6,529.60 7,529.60
36 Local Wood m3 550 77632.61 Local 2 16.6 0.0 Inconvenient 2364.67 99.00 2,463.67 80,096.28
37 Sal Wood(Agrath) m3 810 197610.29 Local 2 16.6 0.0 Inconvenient 3482.51 145.80 3,628.31 201,238.60
38 Stone m3 1700 1500.00 Local 2 16.6 0.0 Convenient 6631.70 306.00 6,937.70 8,437.70
39 CGI Sheet m2 4 705.72 Biratnagar 53.7 0.0 Inconvenient 55.63 0.72 56.35 762.07
40 Plain Sheet m 4 330.45 Biratnagar 53.7 0.0 Inconvenient 55.63 0.72 56.35 386.80
41 White lime kg 1 20.00 Biratnagar 53.7 0.0 Convenient 12.62 0.18 12.80 32.80
42 Gum kg 1 262.00 Biratnagar 53.7 0.0 Convenient 12.62 0.18 12.80 274.80
43 Washable Distemper kg 1 203.00 Biratnagar 53.7 0.0 Inconvenient 13.91 0.18 14.09 217.09
44 Primer ltr 1 268.00 Biratnagar 53.7 0.0 Inconvenient 13.91 0.18 14.09 282.09
45 Bracket nos. 1 81.54 Biratnagar 53.7 0.0 Inconvenient 13.91 0.18 14.09 95.63
46 Connection of Iron grill kg 1 105.00 Biratnagar 53.7 0.0 Inconvenient 13.91 0.18 14.09 119.09
47 Door windows metal frame rm 2.8 700.00 Biratnagar 53.7 0.0 Inconvenient 38.94 0.50 39.44 739.44
48 Door Shutter m2 3.5 12500.00 Biratnagar 53.7 0.0 Inconvenient 48.68 0.63 49.31 12,549.31
49 Windows Shutter m2 3.5 9500.00 Biratnagar 53.7 0.0 Inconvenient 48.68 0.63 49.31 9,549.31
50 GI FACIA (EAVES) kg 1 200.00 Biratnagar 53.7 0.0 Inconvenient 13.91 0.18 14.09 214.09
51 White Cement bag 50 1450.00 Biratnagar 53.7 0.0 Convenient 630.98 9.00 639.98 2,089.98
52 Marble chips 3 mm (marble = kg 1 18.00 Biratnagar 53.7 0.0 Convenient 12.62 0.18 12.80 30.80
2620 kg/m3)
53 Water repellent paints L 1 619.00 Biratnagar 53.7 0.0 Inconvenient 13.91 0.18 14.09 633.09
54 Non Glazed Tile m2 18 699.40 Biratnagar 53.7 0.0 Inconvenient 250.35 3.24 253.59 952.99
55 Glazed Tile m2 18 967.50 Biratnagar 53.7 0.0 Inconvenient 250.35 3.24 253.59 1,221.09
56 16 Gauge Iron Gate m2 21.5 2902.50 Biratnagar 53.7 0.0 Inconvenient 299.03 3.87 302.90 3,205.40
57 Sub-aggregate m3 1600 900.00 Local 1 2.0 0.0 Convenient 752.00 288.00 1,040.00 1,940.00
58 Aluminium Sliding Window Sq.m 9.997 5500.00 Biratnagar 53.7 0.0 Inconvenient 139.04 1.80 140.84 5,640.84
59 Aluminium Fixed Window Sq.m 9.997 5300.00 Biratnagar 53.7 0.0 Inconvenient 139.04 1.80 140.84 5,440.84
60 Polythene Sheet m2 0.05 31.00 Biratnagar 53.7 0.0 Inconvenient 0.70 0.01 0.71 31.71
61 False Ceiling Sq.m 10 1100.00 Biratnagar 53.7 0.0 convenient 126.20 1.80 128.00 1,228.00
62 Elastocrete Cemetitious Sq.m 1 559.52 Biratnagar 53.7 0.0 Inconvenient 13.91 0.18 14.09 573.61
63 4.5mm X 20mm size MS patti Kg 1 130.00 Biratnagar 53.7 0.0 Inconvenient 13.91 0.18 14.09 144.09
frame
Making and fixing 12mm X
64 12mm solid core square rod Kg 1 87.00 Biratnagar 53.7 0.0 Inconvenient 13.91 0.18 14.09 101.09
grill
Shree Manedanda mavi Page 109 of 209 Basic rate (No print)