I Project Plan

The project aims to modernize a telecom company's customer portal and internal network management system to enhance customer experience and operational efficiency. Key objectives include improving self-service capabilities, reducing incident resolution time, and ensuring compliance with industry standards. The project will be executed over six months with a budget of approximately $192,500, utilizing Agile Scrum methodology and focusing on quality management and risk mitigation.

Uploaded by

arc5285
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
6 views3 pages

I Project Plan

The project aims to modernize a telecom company's customer portal and internal network management system to enhance customer experience and operational efficiency. Key objectives include improving self-service capabilities, reducing incident resolution time, and ensuring compliance with industry standards. The project will be executed over six months with a budget of approximately $192,500, utilizing Agile Scrum methodology and focusing on quality management and risk mitigation.

Uploaded by

arc5285
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 3

1.

Executive Summary

This project aims to modernize the telecom company's customer portal and upgrade its internal network management
system to improve customer experience, operational efficiency, and scalability. The plan outlines scope, objectives,
timelines, budget, resources, risk management, quality approach, and communication strategy.

2. Project Objectives

 Enhance customer self-service capabilities.

 Improve real-time monitoring and fault management of telecom networks.

 Reduce average incident resolution time by 30%.

 Ensure compliance with telecom industry standards (e.g., TRAI, ISO 27001).

 Seamlessly integrate new modules with existing CRM and billing systems.

3. Project Scope

✅ In Scope:

 Redesign and deployment of the customer web portal.

 Implementation of real-time network performance dashboards.

 Integration with OSS/BSS systems.

 Data migration and user acceptance testing.

 Staff training and knowledge transfer.

❌ Out of Scope:

 Hardware procurement outside the approved budget.

 Upgrades to legacy billing systems (except required interfaces).

4. Deliverables

# Deliverable Description Due Date

1 Project Charter Approved project authorization Week 1

2 Customer Portal (MVP) Functional portal with core self-service features Month 3

3 Network Monitoring Dashboard Live dashboard for operations Month 4

4 UAT Sign-off Verified by business users Month 5

5 Deployment & Go-Live Full rollout and support Month 6

5. Project Schedule (High-Level)

Phase Duration Timeline

Initiation & Planning 2 weeks Month 1

Design & Development 10 weeks Month 2–4


Phase Duration Timeline

Testing 4 weeks Month 4–5

Deployment & Training 4 weeks Month 5–6

Closure 2 weeks Month 6

6. Project Budget (Estimated)

Item Cost (USD)

Software development 120,000

Testing & QA 25,000

Integration & Data Migration 20,000

Training & Change Management 10,000

Contingency (10%) 17,500

Total Estimated Budget 192,500

7. Project Team & Roles

Role Name Responsibilities

Project Sponsor [Executive Name] Overall governance & funding

Project Manager [Your Name] Planning, execution, monitoring

Technical Lead [Name] System architecture & development

QA Lead [Name] Quality assurance & testing

Business Analyst [Name] Requirements gathering, user stories

DevOps Engineer [Name] CI/CD pipeline & deployments

Training Lead [Name] User training & documentation

8. Risk Management

Risk Likelihood Impact Mitigation

Scope creep Medium High Change control process

Integration issues Low High Early integration testing

Resource attrition Medium Medium Cross-training and backup resources

Data migration failures Low High Dry runs & backup plans

9. Quality Management

 Adhere to SDLC best practices and CMMI/ISO guidelines.

 Use automated testing (unit, integration).


 Conduct code reviews and peer inspections.

 Customer acceptance based on documented criteria.

10. Communication Plan

Audience Frequency Medium Purpose

Project Team Weekly Stand-up / Teams Progress updates & blockers

Steering Committee Monthly Presentation Review milestones & risks

End Users Before Go-Live Email, demo Training & awareness

Sponsors As needed Email / Meetings Escalations & approvals

11. Change Management

 All change requests logged and evaluated.

 Change Advisory Board (CAB) to review high-impact changes.

 Prioritized based on business value and impact.

12. Tools & Methodologies

 Agile Scrum for development.

 Jira for backlog and sprint tracking.

 Confluence for documentation.

 CI/CD pipeline using Jenkins.

 GitHub for version control.

13. Success Criteria

 Reduction in average issue resolution time by 30%.

 Increase in customer portal usage by 40% within 3 months.

 Project delivered within ±10% of planned budget.

 User satisfaction score ≥ 8/10.

✅ 14. Sign-Off

Name Role Signature Date

[Name] Project Sponsor

[Name] Project Manager