Chemical and Preparation Room
Direct Cost
                                                                                                                                        Total Direct
Items                                  Description      Quantity     Unit           Materials                        Labor
                                                                                                                                           Cost
                                                                             Unit Cost     Total Cost      Unit Cost      Total Cost
  1.00 Concreting Works
          Concreting of Footings 4000 psi                     7.20   cu.m      5,800.00      41,760.00        2,200.00      15,840.00     57,600.00
          Concreting of Columns 4000 psi                      4.50   cu.m      5,800.00      26,100.00        2,200.00       9,900.00     36,000.00
          Concreting of Beams 4000 psi                        8.26   cu.m      5,800.00      47,908.00        2,200.00      18,172.00     66,080.00
          Concreting of Slab on Fill 4000 psi                 9.00   cu.m      5,800.00      52,200.00        2,200.00      19,800.00     72,000.00
  2.00 Reinforcing Steel Bars
          10mm Dia Rsb Grade 40                             480.00    pcs        175.00      84,000.00          110.00      52,800.00    136,800.00
          12mm Dia Rsb Grade 40                             180.00    pcs        218.00      39,240.00          160.00      28,800.00     68,040.00
          16mm Dia Rsb Grade 60                             140.00    pcs        355.00      49,700.00          160.00      22,400.00     72,100.00
          G.I Tie Wire #16                                    8.00   rolls     2,000.00      16,000.00        1,500.00      12,000.00     28,000.00
  3.00 Masonry Works
          Chb Layering                                      181.00   sq.m        450.00      81,450.00         350.00      63,350.00     144,800.00
          Plastering Works - 16mm thick                     362.00   sq.m        130.00      47,060.00         350.00     126,700.00     173,760.00
  4.00 Formworks and Scaffolding
          Phenolic Board 4' x 8' x 3/4"                      25.00   pcs         850.00      21,250.00         750.00       18,750.00     40,000.00
          Gi pipe 1 1/2 sched 20                            112.00   pcs         400.00      44,800.00         150.00       16,800.00     61,600.00
          Fixed Clamp                                       300.00   pcs          39.00      11,700.00          25.00        7,500.00     19,200.00
          Swivel Clamp                                      150.00   pcs          39.00       5,850.00          25.00        3,750.00      9,600.00
          Base jack                                          48.00   pcs         190.00       9,120.00         100.00        4,800.00     13,920.00
          U-head                                             48.00   pcs         190.00       9,120.00         100.00        4,800.00     13,920.00
          Flange nut                                        256.00   pcs          59.00      15,104.00          30.00        7,680.00     22,784.00
          Tie rod 12mm x 1m                                 128.00   pcs          60.00       7,680.00          30.00        3,840.00     11,520.00
          Shoring jack                                       36.00   pcs         750.00      27,000.00         100.00        3,600.00     30,600.00
          Blackscrew for metal 1 1/2                          2.00   box         300.00         600.00         300.00          600.00      1,200.00
          Scaffolding complete sets                           6.00   sets      1,800.00      10,800.00         200.00        1,200.00     12,000.00
  5.00 Floor Finishes
          Chemical resistant epoxy flooring 2mm thick        45.60   sq.m        950.00      43,320.00         450.00       20,520.00     63,840.00
  6.00 Wall Finishes
          Chemical resistant epoxy coating finish           120.00   sq.m        250.00      30,000.00         100.00       12,000.00     42,000.00
  7.00 Ceiling Works
       CF-04
           Steel framing                                   45.60   sq.m      600.00    27,360.00          350.00        15,960.00     43,320.00
           PVC ceiling panel                               45.60   sq.m      550.00    25,080.00          350.00        15,960.00     41,040.00
       CF-05
           Steel framing                                   52.20   sq.m      600.00    31,320.00          350.00        18,270.00     49,590.00
           Linear metal ceiling panel                      52.20   sq.m      600.00    31,320.00          250.00        13,050.00     44,370.00
  8.00 Painting Works
           Boysen Flat latex paint                          4.00    pail    2,800.00   11,200.00        2,500.00        10,000.00     21,200.00
           Davies Elastomeric Paint                         5.00    pail    4,000.00   20,000.00        2,500.00        12,500.00     32,500.00
           Skimcoat 25kgs                                  12.00   bags       450.00    5,400.00          450.00         5,400.00     10,800.00
           Concrete neutralizer                            13.00    gal       285.00    3,705.00          200.00         2,600.00      6,305.00
           Sand paper #120                                  3.00   meter      110.00      330.00          100.00           300.00        630.00
           Sand paper #100                                  3.00   meter      150.00      450.00          100.00           300.00        750.00
           Paint brush                                      6.00    pcs       160.00      960.00          160.00           960.00      1,920.00
           Paint roller 6"                                  6.00    pcs       165.00      990.00          165.00           990.00      1,980.00
           Baby roller                                      6.00    pcs        15.00       90.00           15.00            90.00        180.00
           Paint tray                                       4.00    pcs        50.00      200.00           50.00           200.00        400.00
           Masking tape 1"                                  4.00   rolls       15.00       60.00           15.00            60.00        120.00
  9.00 Roofing Works
           W8x 13 x 6lm                                     9.00    pcs    11,000.00   99,000.00        5,000.00        45,000.00    144,000.00
           LC 150mm x 65mm x 20 x 2.0                      28.00    pcs     1,400.00   39,200.00          400.00        11,200.00     50,400.00
           Sag rods 10mm diameter                           4.00    pcs       145.00      580.00          120.00           480.00      1,060.00
           Steel Plate - size and thickness?                        pcs                      -                                -             -
           Anchor bolts - size and quanatity per plate?             pcs                      -                                -             -
           Pre-painted metal roof 0.6mm                   120.00    lm        450.00   54,000.00          100.00        12,000.00     66,000.00
           Pre-painted metal flashing 0.9mm                12.00    pcs       850.00   10,200.00          250.00         3,000.00     13,200.00
           Pre-painted metal gutter 0.9mm                   8.00    pcs       850.00    6,800.00          250.00         2,000.00      8,800.00
           Pe foam insulation one-sided 10mm thick          3.00   rolls    3,200.00    9,600.00          400.00         1,200.00     10,800.00
 10.00 Stainless Steel Works
           Stainless steel pipe 50mm diameter               8.00    pcs     3,700.00   29,600.00          600.00         4,800.00     34,400.00
Exclusion                                                                                          Materials Cost   ₱               1,129,207.00
   1.00 Doors and Windows                                                                             Labor Cost    ₱                 651,922.00
   2.00 Excavation and compaction                                           2%                               Ocm    ₱                  35,622.58
   3.00 Carpentry works                                                     6%                             Profit   ₱                 106,867.74
   4.00 Electrical works
   5.00 Plumbing works                                                                               Grand Total    ₱               1,923,619.32