The report certifies the examination of a Rotary Drilling Rig owned by A.N. Construction at the Agra Metro Project site, confirming no defects were found during the inspection conducted on March 5th and 6th, 2025. The next inspection is due on September 4th, 2025. The report includes a disclaimer stating that it reflects the machine's condition as of the examination date and disclaims any liability for accidents related to the equipment.

Uploaded by

rp200795
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
12 views1 page

Ceigall Rig 6 3 25

The report certifies the examination of a Rotary Drilling Rig owned by A.N. Construction at the Agra Metro Project site, confirming no defects were found during the inspection conducted on March 5th and 6th, 2025. The next inspection is due on September 4th, 2025. The report includes a disclaimer stating that it reflects the machine's condition as of the examination date and disclaims any liability for accidents related to the equipment.

Uploaded by

rp200795
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Certificate No.

-IEC/CIL/AG-25-31

REPORT OF EXAMINATION OF LIFTING MACHINE/TACKLE

1. Name of Owner A.N. Construction c/o M/s Ceigall India Ltd.

2. Address of Site SITE: Agra Metro Project, AGCC-05, Sikandra Station, Agra.

ROTARY DRILLING RIG - Make: XCMG, Model XR210J - Max. Torque output
3.Distinguishing number or mark if 210KN - Max. push force 180 KN. Max. pull force 190 kn- max. drilling depth 60
any and description sufficient to metres - max. drilling dia. 1800 mm. PIN No. XUG0210RKLHJ00314 - Mfd.
identify the lifting machine, chain , Year 2021 (as per ID Plate)
rope or tackle

4. Date when the lifting Machine,


chain rope or tackle was first As per owner's record.
taken into use at site

5. Details of certificate relating to As per Manufacturers T.C.


tests and examinations by
manufacturer

6. Date of last periodical thorough October 2024, by us


examination made and by whom
carried out
7. Date of annealing or other Heat Not Applicable
treatment)

No defects found on physical test.


8. Particulars of any defects
affecting the safe working load
found at current examination and
the steps to remedy the defects

It is certified that on 5th & 6th March 2025 this Lifting Machine/Tackle was thoroughly examined and the
above is a correct report of the result

Next Inspection Due : 4th Sptember 2025

Subject to DISCLAIMER below.

VARUN BHILOTRA
B.Tech. (Mech.)
“COMPETENT PERSON”
DISCLAIMER: This Report of examination reflects the condition of the machine/ equipment as on date. We accept no
liability / responsibility whatsoever in case of any accident / mishap on/with/ due to this machine / equipment