Engg Survey1 Neww
Engg Survey1 Neww
FUNDAMENTALS OF
           SURVEYING
Korea.
                                   Table of Contents
No.                         Job name                              Page   Hours
      1-1 Revision of Secondary level mathematics and
 1    Science. Apply simple Algebraic formulae. Acquire            4       20
      skill in Graphical plotting. Define Number System.
                           Total                                  15       30
                                                                                 Hours
Job Name 1.a Perform Road survey
                                                                              2. Hold staff
Machine             paper         -3 or 5m staff          Tripod-1            temporary adjustment.
-Tripod           - Pencil        -Peg: rigid suitable,   Theodolite -1
-Theodolite       - Eraser         pointed and rigid      Staff-2             perfectly vertical.
-Staff            - Ink pen        type                   Pegs-2              3.Prevent instruments
-Pegs                             -Tape:20m or 30m        Tape-1              from rainfall or high
-Tape                              tape                   Hammer-1            heat.
-Hammer                                                                       4. Avoid working
                                                                              on extreme
                                                                              weather
                                                                              conditions.
     2. Reconnaissance
Reconnaissance survey is conducted to collect the
topographical information between two terminals
for the best route. It is a preliminary examination of
the entire area to select the best route and estimate
the cost of project. Some works in Reconnaissance
survey are as follows:
a. Data of rivers, culverts, subways etc. are
     collected.
b. Maximum discharge of river, HFL, breadth of
     river etc. are collected.
c. Earthwork, volume and cost of proposed route
     should be estimated.
d. For rough estimation of elevation, distance                Figure 1.a- 6 Reconnaissance /site visit of area
     instruments like altimeter, passometer etc. are
     used.
    3. Prepare Necessary Equipment
Different instruments are prepared. Tape is
used for distance measurement. Theodolite is
used for measurement of deflection angles.
Compass is used for measuring bearing of a IP
line. Pegs are used for marking the control
stations. Level machine is used for RL transfer
from benchmark nearby, L-section and Cross
section and staffs are used for taking readings
through level machine. Ranging Rods are used
to fix tangent points (PC & PT) from IP.              Figure 1.a- 7 Equipment used in Road alignment
                                                                           Survey
    4. Alignment     fixing           and       IP
       establishment
      Line/Leg                                   Chainage
                        IP to IP                                      Deflection Angle = ± Δ
                                       Station
   From       To                                   of IP
                        Distance
    IP        IP                                  station       ±           d          m           s
  Radius
              Tangent      Length      IP
                                        Apex         Chainage       Chainage    Chainage
    of
              Length      of Curve,    Distance,      of BC          of MC       of EC        Remarks
  Curve,
              TL (m)        L (m)       E (m)          (km)           (km)        (km)
  R (m)
 Station    BS     FS     HI    RL     Remarks
                                       PBM
                                                         Figure 1.a- 15 Fly levelling from BM to
                                       TBM                              alignment
                                       PBM
     Table 1.a- 1Field book of Fly levelling
    10. Perform L-section and Cross- Section
        simultaneously
The operation of leveling carried out to
determine the elevations of the points at
known distances apart and also other salient
features along a given straight line is called
profile leveling. It is also called longitudinal
leveling.
Cross sections are run at perpendicular to the               Figure 1.a- 16Profile of a plan
profile leveling and on either side of it for the
purpose of lateral outline of the ground nature.
For x-section there are two different approaches
can be applied
    (1) equal interval approach
    (2) Change in slope approach.
In equal interval approach the section is taken
perpendicular to the route at a particular interval
                                                               Figure 1.a- 17 Cross-section
(chainage) of the center line of the route in a
fixed interval. Where as in change in slope
approach the interval of the distance in the
section is not kept fixed but observations are
taken at the points along the x-section lines,
wherever the slope changes significantly.
Computation of survey data for RLs of all points are done as in the figure below.
  Station      Distance(m)                    Reading                     HI          RL         Remarks
           L      C       R      BS             IS      FS
 BM                                    1.155                           501.155       500      0+000 Chainage
                      0                          1.234                              499.921
 R1                           2                  2.325                               498.83
 R2                           4                  2.222                              498.933
 R3                           6                  1.575                               499.58
 L1            2                                 2.321                              498.834
 L2            4                                 2.325                               498.83
 L3            6                              3.215                            497.94
 C                    0               1.325               2.255     500.225     498.9        CP
 R1                            2              2.125                             498.1   0+015Chainage
 R2                            4              2.222                           498.003
 R3                            6              1.565                            498.66
 L1            2                              2.321                           497.904
 L2            4                              2.225                               498
 L3            6                                         2.215                 498.01
   Total                           ƩBS=2.48           ƩFS=4.47
 Arithmetic Check:
 ƩBS-ƩFS = Last RL-First RL
 or,2.48-4.47=498.01-500
   or,-1.99 =-1.99 Checked//
Figure 1.a- 28 Drawing of IPs stations                            Figure 1.a- 29 Marking tangent points
Figure 1.a- 30 Plan Manually                               Figure 1.a- Plan through CAD
b. Preparation of profiles (L-section) & X-section
Steps:
i.      Define the scale. Generally, the scale is defined as shown below;
                Type              Horizontal                  Vertical          Remarks
                                  (H)                         (V)
                L-section         1cm=10m i.e. 1:1000 1cm=1m                i.e. H= V/10
                                                              1:100
  Scale
                X-section         1cm=1m i.e. 1:100           1cm=1m            H=V
                                                              i,e.1:100
ii.    Horizontal distances are plotted along the horizontal axis to scale defined.
iii.   The elevations are plotted along the vertical scale defined.
iv.    Each ground point is thus plotted by the two coordinates (chainages and elevations).
           Horizontal distance; x- coordinate
           Vertical distance; y- coordinate
           Origin is assumed as per convenience i.e. below to lowest RL
.
Figure 1.a- 32 Designing X- &Y- axes
Figure 1.a- 33Plotting of profile in graph        Figure 1. a- 34Plotting of profile CAD
Figure 1.a- 36 Cross sections at graphs Figure 1.a- Cross section at O+OOO Chainage
                                                                       2. Hold staff
Machine         paper        -3 or 5m staff          Tripod-1          temporary adjustment.
-Tripod       - Pencil       -Peg: rigid suitable,   Theodolite -1
-Theodolite   - Eraser        pointed and rigid      Staff-2           perfectly vertical.
-Staff        - Ink pen       type                   Pegs-2            3.Prevent instruments
-Pegs                        -Tape:20m or 30m        Tape-1            from rainfall or high
-Tape                         tape                   Hammer-1          heat.
-Hammer                                                                4. Avoid working
                                                                       on extreme
                                                                       weather
                                                                       conditions.
                                                                                  Hours
Job Name                 2.Bridge Survey
                                                                               2. Hold staff
Machine                paper        -3 or 5m staff          Tripod-1           temporary adjustment.
-Tripod              - Pencil       -Peg: rigid suitable,   Theodolite -1
-Theodolite          - Eraser        pointed and rigid      Staff-2            perfectly vertical.
-Staff               - Ink pen       type                   Pegs-2             3.Prevent instruments
-Pegs                               -Tape:20m or 30m        Tape-1             from rainfall or high
-Tape                                tape                   Hammer-1           heat.
-Hammer                                                                        4. Avoid working
                                                                               on extreme
                                                                               weather
9. Perform Triangulation
A. Measure the length of baseline
The baseline AC and BD are measured either by
tape or EDM as per the project requirement,
budget and accuracy required. It is measured by
both forward and backward distance following
the specification. Generally, precision is 1:2000
for tape and 1:5000 for EDM measurement.
                                                    Figure 2- 20 showing baseline and bridge axis
This length of baseline is used further to
calculate the axis length after determining all
angles using sine rule
B. Measure all angles
a. Set up the instrument at station ‘A ‘and temporary adjustment of instrument is followed.
b. Bisect the station ‘C’ and set zero to the reading and record the reading as FL (face left) of C as
    O°0’0”
c. Turn telescope clockwise towards B and bisect exactly with the help of tangent screw, note the
    reading and record the reading as FL of B
d. Again bisect exactly station D and record the readings as FL of ‘D’
e. Now, transit the instrument and turn clockwise to bisect the target at ‘D’ and record the reading
    as FR (face right) of D.
f. Then turn anticlockwise continuously and bisect the station B & C exactly and record the
    readings as FR of ‘B’ and FR of ‘C’ respectively.
                                 FL+ FR
g. Calculate the mean angle as
                                     2
h. Repeat the same process by setting 90° instead of 0 degree and the readings and record all data
    in the field book as shown in the Figure 2- 21
i. Repeat whole process again by setting up instrument at station ‘C’,’B’ and ‘D’ and measures the
    angles in same manner and then ∡ CAB , ∡ CAD , ∡ BADas ∡ BAD=∡CAD−∡ CAB and other
    angles also in similar manner.
             sin ∡ ADB
∴ AB=BD×
             sin ∡ DAB
                AC        AB
                     =                                 Figure 2- 25Traverse adjustment for closing
            sin ∡ ABC sin ∡ ACB
                                                                         error
            sin ∡ ACB
∴ AB=AC×
            sin ∡ ABC
These obtained length of AB is compared with
required precision. In this way length of AB is
determined.
 Transit rule
The transit rule may be employed where
angular measurements are more precise
than the linear measurements.
According to this rule, total error in latitude
and departure is distributed in proportion to         Figure 2- 28 Using Compass to read bearing of
                                                                          a line
the latitude and departures of the sides.
f. Calculate Independent Coordinates by
    filling in Gale’s table as shown in the
    Figure 2-29
                  Figure 2- 29 Filling Gale’s table for independent Coordinates
A. Calculation of velocity(V)
a. Water section is divided into section like
   C/S-1 and C/S-2 like in figure
b. The float is released slightly ahead C/S-1,
   when the float just crosses the section, the
   stop watch is started and when it just
   crosses the section C/S-2, the time is
   noted.                                             Figure 2- 30 Calculation of velocity
c. This process is repeated several times and
   mean time is calculated. Distance of
   section is measured. Thus obtained mean
   time and distance gives the velocity.
suitable method,
Then Discharge Q = A∗V
12. Perform Detailing of a bridge Site
The total station was used for detailing the entire
bridge site. The reading was taken from the
different station set up. The detailing was done
concerning the skeleton formed by triangulation.
                                                      Figure 2- 36 Centre line & cross-section line Fixing
The vertices of triangles serve as a control point.
The details were booked, up to (specified)m
upstream and (specified)m downstream with
sections dividing at 10m & left, and the right of
the cross-section at 15m. Tree, structures, spot
height etc. data are taken. Rough skech showing
all details are also prepared so that plotting work
will be very easier and accurate.
13. Cover upstream and downstream
Centre line is fixed and cross-section are also        Figure 2- 37 River Section showing details
established where HFL (high flood level)., LFL
(low flood level) WL (water level) data are
collected. Upstream and downstream distances are
specified according to project requirement
Objectives
                                                                    2. Hold staff
Machine         paper     -3 or 5m staff          Tripod-1          temporary adjustment.
-Tripod       - Pencil    -Peg: rigid suitable,   Theodolite -1
-Theodolite   - Eraser     pointed and rigid      Staff-2           perfectly vertical.
-Staff        - Ink pen    type                   Pegs-2            3.Prevent instruments
-Pegs                     -Tape:20m or 30m        Tape-1            from rainfall or high
-Tape                      tape                   Hammer-1          heat.
-Hammer                                                             4. Avoid working
                                                                    on extreme
                                                                    weather
                                                                    conditions.
<Related Knowledge>
    1.Setout Simple Hou
Job                rs
       Circular
       curve          8
            1. Understand Elements of
               simple circular curve
            2. Calculate Chainage of curve
Obj         3. Calculate data for setting
ecti           out
ves         4. Understand          different
               methods of setting out
               Simple curve
Inst
rum                    Safety
     Ma
ents      Specifi Quan  and
     ter
and       cation tity Cautio
     ials
Too                      n
                                    1.Set
ls
-       - S    -Auto     Level                  Figure 4- 1 Curve in highway
Leve      h      Leve    machi      up
l         e      l       ne-1       followin
Mac       e    -3 or     Tripod     g
hine      t      5m      -1         tempora
-         p      staff   Theod      ry
Tripo     a    -Peg:     olite -1   adjustm
                                    2.
d         p      rigid   Staff-2    ent.
-         e      suita   Pegs-2                Figure 4- 2 Simple circular curve
Theo      r      ble,    Tape-1     Hol
dolit   - P      point   Hamm       d
e         e      ed      er-1       staf
-         n      and                f
Staff     c      rigid              perf
-Pegs     il     type               ectl
-       - E    -                    y
Tape      r      Tape               vert         Figure 4- 3Compound Curve
-         a      :20m               ical.
Ham       s      or                 3.Preven
mer       e      30m                t
          r      tape               instrume
        - I                         nts from
          n                         rainfall
          k                         or high
          p                         heat.
          e                         4.
          n                         Avo          Figure 4- 4 Transition Curve
                                    id
                                    wor
                                    king
                                    on
                                    extr
                                    eme
                                    wea
                                    ther
                                    con
                                    ditio
                                    ns.
<Related Knowledge>                                        Figure 4- 5 Reverse Curve
Curve
Curves are the geometric arcs which are
introduced in order to avoid the abrupt
(sudden) change in direction in both the
horizontal as well as in vertical planes.
Curve is arc of finite radius Introduced when
two straight lines (with different direction)
need to be joined/connected.
Necessity of curve                                        Figure 4- 6 Broken-back Curve
 Make vehicle to move comfortably and
     safely, avoiding the sudden change in the
     route.
 Whenever the direction of a road or
     railway line is to be changed, curves are
     provided between the intersecting
     straights
Types of curve
a. Simple Circular curve
It connects two intersection straight lines. It  Figure 4- 7 Types of curve
Consists of a single arc of a circle i.e. the
curve has constant radius. The curve is
tangential to the connected straight lines at
the joining points
b. Compound Curve
It is combination of two or more simple
circular curves in the same direction with
different radii.
c. Transition Curve
It is introduced between simple circular
curve and straight line or between two simple            Figure 4- 8 Simple circular curve
circular curves with varying radius. It
provides a gradual change from straight line
to the circular curve and vice versa It is also
known as easement curve
d. Reverse Curve
It is the combination of two or more simple
circular curves in the opposite direction with
same or different radii. It is also known as
serpentine curve. It is not suitable for
                                                 Figure 4- 9 Elements of simple circular curve
highways but suitable for hill roads.
e. Combined Curve
Combination of simple circular curves and
transition curve
f. Broken back curve
It is two circular curves, having centers in the
same side, connected with a tangent.
                                                    Figure 4- 10 Deflection angle measurement
Elements of simple circular Curve
Tangent length(T): It is the distance
between the point of curvature to the point of
intersection; also the distance between the
point of intersection to the point of tangency.
In figure, T1 I or IT2 is tangent distance.
In ∆ T ! IO,
    ∆ T1I              ∆ T                  ∆
tan =           or, tan =       ∴ T=R tan
     2 O T1            2 R                  2
Long Chord(L): Chord of the circular curve
joining the point of curvature(T1) and point of      Figure 4- 11 Chainaging of curve(PC,PT)
tangency(T2) In Figure, T1DT2 is long Chord.
In ∆ T ! DO
      ∆ T1 D                                  ∆
sin    =               or,       T1D=OT1sin
      2 OT1                                   2
                ∆
∴ T 1 D=R sin
                2
                             ∆
L= T1DT2=2 T1D= 2 R sin
                             2
Mid Ordinate(M): The distance between the           Figure 4- 12 Methods of setting out simple
apex of the curve (C) and mid-point (D) of the                    circular curve
long chord, also known as versine of the curve.
In fig. CD is the Mid ordinate
In ∆ T ! DO
    ∆ OD                          ∆
cos    =        or, OD= OT1cos
    2 O T1                         2
               ∆
∴OD = R cos         or, CD = OC-OD
               2
                ∆                     ∆           Figure 4- 13 perpendicular offsets from tangent
CD= R- R cos          ∴ CD=R ¿ cos       )                           method
                2                     2
External Distance(E): Distance between the
point of Intersection (I) and apex of the curve
(C), also known as apex distance. In figure
IC is the apex distance.
In ∆ O T ! I
                           OT 1        R
    ∆ O T1
cos =           or, OI =      ∆ =        ∆
    2     OI              cos        cos
                              2          2
                  R
                      −R             ∆
IC= OI-OC =         ∆       = R( sec -1)
               cos                   2
                    2
Length of the Curve(l): Total Arc length
between point of curvature and point of
tangency. In figure, T1T2 is length of curve.
By Geometry,
          ARC          l
Angle=          or, ∆=   or,l=R∆ (in radian)      Figure 4- 14 Calculating Perpendicular offsets
         Radius        R
     πR ∆                                                        from tangents
l=        (in degree)
     180°
Chainage of curve
<Operation Procedures>
a. Before setting out the curve P.I., P.C. and
    the P.T. are located on the ground
b. After locating the P.I., theodolite is
    placed at that point
c. The angle of deflection is measured.
    (Telescope is pointed towards one
    straight, transited by 180° and swung
                                                 Figure 4- 15 Radial Offsets from tangent method
    towards other straight)
d. Using this deflection angle, Tangent
    length can be computed by:
        T = R Tan (Δ/2)
e. This tangent length is measured along IP 0
    → IP 1and IP1→ IP 2 to fix PC and PT.
    Then chainage is calculated as:
Chainage of PC= Chainage of IP –Tangent
length
Chainage of PT = Chainage of P.C+ curve
length
Setting out curve
A. Linear method: Only tape/chain is used
    for setting out curve.
B. Angular method: Theodolite & tape or
                                                  Figure 4- 16 Offsets from long chord method
    only theodolite is used to set out curve.
<operation procedures>
A. Linear method
1. Offsets from tangents
i.Perpendicular offsets
Let Ox be the perpendicular offsets to
tangents at D, ‘X’ distance from T1. EE1 is
perpendicular to line T1O.
From derivation, Ox = R−√ (R2− X 2¿ )¿
which gives the value of perpendicular
offsets At different distances from the
tangents.
Steps:
a) Measure equal distances, say, 20 or 30m
    along the tangent T1 V from T1.         Figure 4- 17 Calculating offsets from long -Chord
                                                                 method
b) Set out the offsets calculated from
    formula perpendicular to T1B at each
    distance,
    Ox = R−√ (R2− X 2¿ )¿
ii.Radial offsets
Let Ox =the Radial offsets for point E at any
point along the tangents =DE
T1D= x (Distance of radial offsets from T1
By Derivation,
                                                   Figure 4- 18 Rankine's method of tangential
Radial offsets(OX)= √(R 2+ X 2 ¿)−R ¿                                angles
Steps:
a. Erect the ranging rods at T1, V, T2 and O.
b. Measure the distance X along T1V and
    fix point D.
c. From point D, a distance equal to the
    calculated offsets length OX, along the
    line joining the point D and the center of
    curve.
d. Similarly locate other points on the first
    half of curve.
2. Offsets from long –chord                        Figure 4- 19 Specimen of data to be set out by
This method is suitable for a curve having                       Rankine's method
small radius
Let, x be the distance from mid-point of long
chord from which offsets(Ox) are drawn to
find the point on curve. The offsets(Ox) are
calculated as:
    √
Ox = (R 2−X 2 ¿ )−√ R2−¿ ¿ ¿
‘x’ is the distance from mid-point of long
chord to either P.C. or PT i.e. if long chord is
40 m then (L/2) =20 m and x can be taken as
0,5,10,15,20 or any other regular interval and       Figure 4- 20 using Total deflection angle to be directed
O0, O5, O10, O15, O20 can be calculated.
Steps:
a. Fix the ranging rods at T1, D and T2
b. Divide the long chord T1T2 in equal parts
    of suitable length.
c. Calculate the lengths of the offsets
    corresponding to the distance (x) from
    the origin at D by using the formula
    shown above
      as:
         √
   Ox = (R 2−X 2 ¿ )−√ R2−¿ ¿ ¿
B. Angular method
i. Rankine’s method of tangential angles
In this method, a tape is used for making
linear measurement and a theodolite is used
for      making       angular     measurements
simultaneously.
Here, normal Peg interval =C
First sub-chord =C1 Last sub-chord =Cn
     1718.9C 1            1718.9 C          1718.9 C
δ 1=             min , δ=          min δ n=
           R                  R                 R
, ( All angles are in min. unit)
.
                                                                                      Hours
Job Name 2.Perform Construction survey
                                                                                               8
                       5.   Understand Elements of simple circular curve
                       6.   Calculate Chainage of curve
Objectives             7.   Calculate data for setting out
                       8.   Understand different methods of setting out Simple curve
Instruments                                                                              Safety and
            Materials                Specification              Quantity
                                                                                   1. Set up following
and Tools                                                                                 Caution
-Level             - Sheet         -Auto Level             Level machine-1
                                                                                   2. Hold staff
Machine              paper         -3 or 5m staff          Tripod-1                temporary adjustment.
-Tripod            - Pencil        -Peg: rigid suitable,   Theodolite -1
-Theodolite        - Eraser         pointed and rigid      Staff-2                 perfectly vertical.
-Staff             - Ink pen        type                   Pegs-2                  3. Prevent instruments
-Pegs                              -Tape:20m or 30m        Tape-1                  from rainfall or high
-Tape                               tape                   Hammer-1                heat.
-Hammer                                                                            4. Avoid working
                                                                                   on extreme
                                                                                   weather
                                                                                   conditions.
<Related Knowledge>
Construction Survey
Site Survey
It is an inspection of an area where work is proposed ,to gather information for a design or an estimate to
complete the initial tasks required for an outdoor activity.
It can determine a precise location, access, best orientation for the site and location of obstacles
1. Total Stations: A total station is a versatile electronic instrument that combines the functions of a
   theodolite and an electronic distance measurement (EDM) device. It allows surveyors to measure
   angles and distances with high precision, providing accurate information on the position, elevation,
   and alignment of various points on the construction site.
2. GPS/GNSS Receivers: Global Positioning System (GPS) or Global Navigation Satellite System
   (GNSS) receivers use satellite signals to determine the precise location and elevation of points on the
   earth’s surface. These devices enable surveyors to collect real-time, accurate geospatial data, even in
   remote or inaccessible areas, without the need for line-of-sight measurements.
3. Levels: Levels are essential optical instruments used by surveyors to determine the height differences
   between points and establish a horizontal plane. There are various types of levels, such as automatic
   levels, digital levels, and laser levels, each offering different levels of accuracy and ease of use.
4. 3D Laser Scanners: 3D laser scanners emit laser beams to capture the shape, size, and position of
   objects and surfaces within their range. They generate millions of data points, known as point clouds,
   which can be processed to create highly detailed and accurate 3D models of the construction site or
   structure.
5. Drones/UAVs: Unmanned Aerial Vehicles (UAVs) or drones equipped with high-resolution
   cameras or LiDAR sensors have become popular tools for construction surveying. They allow
   surveyors to quickly capture aerial images and topographic data, even in challenging terrain or large-
   scale projects, reducing the time and effort required for data collection.
6. Data Collectors: Data collectors are handheld devices or tablets that enable surveyors to record, store,
   and manage the data obtained from various survey instruments. They often come with built-in
   software for data processing, analysis, and visualization, allowing surveyors to generate maps,
   reports, and other deliverables on-site.
7. Measuring Tapes and Wheels: While more technologically advanced tools have become prevalent,
   measuring tapes and wheels still play a crucial role in construction surveying. They are used for quick
   measurements of linear distances, particularly when high precision is not required or when electronic
   instruments are not available.
8. Safety Equipment: Construction surveyors work in diverse environments and often encounter
   hazards such as heavy machinery, uneven terrain, and adverse weather conditions. Therefore, they
.
°and120°.
vvvvglesareformedcarefullytoensureanglesbetween30
°and12
Bridgeaxislengthandcontrolpointfixingdonebytriangula
tion.Trianglesareformedcarefullytoensureanglesbetwe
en30°and120°.
0°.
                                                                                Hours
Job Name Calculate Area
                                                                                        8
                 1. Understand methods of area finding of field
                 2. Measure area of regular and irregular figures
Objectives       3. Understand the methods of determining the area from map/plan
                                                                             2. Hold staff
Machine             paper       -3 or 5m staff            Tripod-1           temporary adjustment.
-Tripod           - Pencil      -Peg: rigid suitable,     Theodolite -1
-Theodolite       - Eraser       pointed and rigid        Staff-2            perfectly vertical.
-Staff            - Ink pen      type                     Pegs-2             3. Prevent instruments
-Pegs                           -Tape:20m or 30m          Tape-1             from rainfall or high
-Tape                            tape                     Hammer-1           heat.
-Hammer                                                                      4. Avoid working
                                                                             on extreme
                                                                             weather
                                                                             conditions.
<Related knowledge>
Distance measurement
For instance, lengths, heights, and widths
of geometric figures are distances, as are
the radius, diameter and circumference of a
circle.
Distance is measured in linear units, such
as inches, feet, yards, miles, meters,
centimeters, millimeters and kilometers.
There are many other units of linear
measure, but those listed above are
commonly used.
Basic units of distance measurement in the
English system (inches, feet, yards, miles),
and among the basic units of linear measure
in the metric system (meters, centimeters,         Figure 6 - 3 Distance unit conversion table
millimeters, kilometers).
Area Measurement
Generally, area refers to the total regions
being occupied. The term ‘area ‘in the
context of surveying refers to the area of a
tract of a land projected upon the horizontal
plane, and not to the actual area of land
surface. Generally field area may be
expressed in the following units.                       Figure 6 - 4 Ropani and Bigaha system
i.Square meters
ii.Hectares
iii.Square feet
iv.Acres (1 Acre =4840 sq.= 43560 sq.)
Beside this, in Nepal, the area is expressed
in
Ropoani-aana-Paisa-Dam (in velley)
Bigaha-Katha-Dhur-Kanuwa ( in Terai
region)
One should know conversion mentioned in
Figure 6- 1 during area measurement and
calculation.
Equipment used in distance                              Figure 6 - 5 Area unit Conversion
measurement:
 Chain/tape is used for linear measurement.
Ranging rod is used for distance
measurement by ranging by when distance
is too far. Arrow is used to fix point of
starting or ending point, Dimension of
arrow is shown in figure. If two points are
in slope relative to each other, then distance
measurement by stepping is shown in the
                                                    Figure 6 - 6 Correctly horizontal distance
figure Figure 6- 2                                         measurement and slopping
   2. Trapezoid
   Steps:
   a. Establish pegs at stations covering area
      representing trapezoid.
   b. Measure distance horizontally denoting
      as a.b,h as shown in the Figure 6 - 2       Figure 6 - 13 Area calculation for different shape
                                                                       of land
                                  a+b
   c. Apply formula for area A=        ×h
                                   2
   d. Convert area into required unit
   e. Sum the area for total area if the region
   is divided     into   the     number   of
   trapezoids.
3. Trapezoidal rule
While applying the trapezoidal rule, boundaries
between the ends of ordinates are assumed to be
straight.                                                Figure 6 - 20 Average ordinate rule
a. Divide the region into number of trapezoids.
b. Measure the ordinate O1, O2...... perpendicular
    to chain line at regular interval ‘d
c. Apply formula to calculate area of entire
    region,
5. Coordinate Method
a. Set up total station covering area of interest
b. Set prism to all corner A, B, C & D.
c. Measure coordinate and note down as
   A(x1,y1), B(x2,y2), C(x3,y3) and D(x4,y4)
d. Apply the formula coordinate method of
   calculating area shown below Repeat the first
                                                         Figure 6 – 19 Coordinate measurement by
   coordinate in last too.                                              Total station
                                                                           2. Hold staff
Machine            paper       -3 or 5m staff         Tripod-1             temporary adjustment.
-Tripod          - Pencil      -Peg: rigid            Theodolite -1
-Theodolite      - Eraser       suitable, pointed     Staff-2              perfectly vertical.
-Staff           - Ink pen      and rigid type        Pegs-2               3. Prevent instruments
-Pegs                          -Tape:20m or 30m       Tape-1               from rainfall or high
-Tape                           tape                  Hammer-1             heat.
-Hammer                                                                    4. Avoid working
                                                                           on extreme
                                                                           weather
                                                                           conditions.
<Related Knowledge>
Volume
The volume of an object is the amount of space occupied by the object or shape, which is in
three-dimensional space. It is usually measured in terms of cubic units. In other words, the
volume of any object or container is the capacity of the container to hold the amount of fluid (gas
or liquid).
Volume for different Solid shapes
1. Cube
The volume of a cube can be easily found out by just knowing the
length of the edge of the cube. If the length of the cube is s, then the
formula to calculate the volume of a cube is:
Volume of the cube V =S 3 where 's is the length of the side of the
                                                                             Figure 7- 1 Cube
cube.
2. Cuboid:
The volume of a cuboid is the space occupied by a cuboid. The volume of
the cuboid is equal to the product of the base area (area of the rectangular
face) and height. Volume = (Length × width) × Height                             Figure 7- 2 Cuboid
3. Sphere
The volume here depends on the diameter or radius of
the sphere since if we take the cross-section of the sphere, it is
a circle. The surface area of sphere is the area or region of its outer
surface. To calculate the sphere volume, whose radius is ‘r’ we
have the below formula: Volume of a sphere(V) = 4/3 πr3                    Figure 7- 3 Sphere
4. Cone
The volume of a cone is the space occupied by the cone. The formula to find
the volume of a cone, whose radius is 'r' and height is 'h' is given as, Volume =
(1/3) πr2h cubic units.
                                                                                 Figure 7- 4 Cone
1. Cylinder
The volume of a cylinder is the amount of space there is inside a cylinder. In
order to find the volume of a cylinder we first need to find the circular area of
the base. The formula for calculating the area of a circle is: Area=πr2 We then
multiply the area of the circular base by the height (or length) of the
cylinder.
The formula for the volume of a cylinder is:
                              d
Volume(V)=πr2h where r =
                              2
Conversion of Volume into quantity
1 m3=1000 liter
If a rectangular tank has dimensions 9’×9’×2’. Then amount/quantity
of water that can be inside tank is calculated as:
                                                           162
Volume(V) = 9×9×2 =162 cube feet =
                                                   3.2808∗3.2808∗3.2808
m3=4.5875litre
But, as per the course of study, we only practice cases of Level section. In this case width of
embankment is denoted by ‘b’, height is denoted by ‘h’ and Side
slope is denoted as S:1, Then
                             b+ b+2 sh
Cross Sectional Area ( A ) =           ∗h=( b+ sh ) h
                                 2
Earthwork estimation
Earthwork estimation refers determination of the quantity(volume) of earth material (soil, rock, etc.)
that needs to be excavated or added at a construction site. This estimation is very essential for
planning and budgeting purposes in construction projects.
<Procedures>
a. after the centerline has been staked, ground profiles
    called cross sections are taken (at right angles to the
    centerline), usually at intervals of full or half stations if
    the English system of units is being used, or at perhaps
    10, 20, 30, or 40 m if the metric system is being
    employed.
b. Cross-sectioning consists of observing ground
    elevations and their corresponding distances left and
    right perpendicular to the centerline.
c. Readings must be taken at the centerline, at high and
   low points, and at locations where slope changes occur to determine the ground profile
   accurately.
d. This can be done in the field using a level, level rod, and tape
 Different methods can be used in earthwork estimation.We
can apply following methods for calculation.
A. Mean Sectional Area Method
B. Trapezoidal Rule
C. Prismoidal Rule
B. Trapezoidal rule
It is extended form of mean area method i.e. it is used when there are more than two sections,
Steps:
a. Consider different sections as A1, A2,
     A3……An which are separated by common
     distance ‘d’
b. Then compute the total volume of earth work
     along the given section from the relation.                     Figure 7- 12 Trapezoidal rule
         D
     V= *(A0+An+2(A1+A2+A3+……..+An-1)
         2
C. Prismoidal Rule
The volume V of a prismoid can be found using the prismoidal formula. The Prismoidal formula is
applicable when there are odd number of sections. If the number of sections are even, the end
section is treated separately and the area is calculated according to the trapezoidal rule. The volume
of the remaining section is calculated in the usual manner by the prismoidal formula. Then both the
result is added to obtain the total volume.
Steps:
a. Consider Ao and A1 as the areas of the faces in the two
     parallel planes,
b. Take Am as the area of the intersection of the prismoid
     with the plane parallel to the two planes and midway
     between them. If h denotes the distance between the planes
     with areas Ao and A1,
                            h
c. Calculates Volume V= ¿ 0+4Am+A1)
                            6
d. Convert into required unit.
e. If there are no of cross –sections separated by a common            Figure 7- 13 Prismoidal Rule
     distance D, then
     D
V= [first area + last area + 4 ∑ Even area + 2 ∑ odd areas].
     3
       D
∴V= [A1 +An + 4(A2+ A4+..+An-1)+2(A3+A5+…+An-2)].
       3
If there are 7 Croo-sections,then                               Figure 7- 14Applying Prismoidal Rule
      D
V= [A1 +A7 + 4(A2+ A4+A6)+2(A3+A5)]
      3
Prismoidal Correction:
a) The volume by the prismoidal formula is more accurate than any other method.
b) But the trapezoidal method is more often used for calculating the volume of earthwork in the field.
c) The difference between the volume computed by the trapezoidal formula and the prismoidal formula is
   known as a prismoidal correction.
d) since the trapezoidal formula always overestimates the volume, the prismoidal correction is always
   subtractive in nature is usually more than calculated by the prismoidal formula, therefore the prismoidal
   correction is generally subtractive.
e) Volume by prismoidal formula = volume by the trapezoidal formula - prismoidal correction
 It may be noted that in Fig. total volume calculations             Figure 7- 18 Using spot height for
depth of some corners appear once, some twice, some of                           volume
them 3 times and some 4 times. If
∑h1 = some of depths used once                              ∑h2 = sum of depths used twice
∑h3 = sum of depths used thrice                            ∑h4 = sum of depths used four times.
                                      A
i. Then calculate the volume as V=       (∑h1+2∑h2+3∑h3+4∑h4) for rectangular spot height grid.
                                      4
    For triangular spot height grid depth of some corners appear once, some twice, some of them 3
                                       A
    times and some 6 times so V= V= (∑h1+2∑h2+3∑h3+4∑h6)
                                       3
j. Alternative method of calculation earthwork is shown in figure below.
j.1 Triangular grid
j.2 Rectangular grid
        Figure 7- 20 Rectangular gular grid spot height using for earthwork calculation
3. From Contours
Contour is an imaginary line connection point of
equal elevation. The vertical distance between two
consecutive contour is called contour interval.
Contour interval is kept small for flat area whereas it                                   is
kept large for sloppy areas. Horizontal distance
between two consecutive contour is horizontal equivalent. It is not constant It varies according to
terrain or sloppiness of the ground
The measurement of volume can be made by contour map. But volume computed by this method is
approximate as the full ground irregularities are not predicted by contours and contour intervals are
not small, Volume computed from this method is likely to be approximate. To compute volume
from this method general recommendation of the contour interval is max.2m for regular ground and
0.5m for irregular topography.
<Procedures>
a) Identify Contour Lines: Start by identifying the contour lines on the topographic map. Each
    line represents a specific elevation level.
b) Determine Contour Interval: The contour interval is the vertical distance between two
    consecutive contour lines. It is recommended to use a maximum interval of 2 meters for regular
    ground surfaces and 0.5 meters for more detailed areas.
c) Divide the Area: Divide the area into sections or regular shapes (e.g., trapezoids or rectangles)
    based on the contour lines. This helps in simplifying the volume calculation.
d) Calculate Area of Each Section: For each section, calculate the area based on the contour lines.
    The area can be estimated using geometric formulas depending on the shape of the section.
e) Calculate Volume: The volume can be estimated by multiplying the average area of each
    section by the contour interval. The formula for volume V between two contour lines can be
    expressed as:
                                      V=Area ×Contour Interval
f. Sum the Volumes: Add the volumes of all sections to get the total volume of the area being
    analyzed.
If we have to calculate volume from starting of the data collection to contour formation then,
Steps:
Figure 7- 24 Dividing the area into grid
Exercise