FF Al Construct in
FF Al Construct in
equested. Holidays for UAE-2016, 2017, 2018 and 2019 shall be applicable.
Work Breakdown Structure (WBS) : The High level WBS structure is as attached below,
detailed WBS shall be submitted during the Construction programme Phase
Programme – Overview
New Mashreq Bank Head Office Tow er, Dubai Overview MEP Programme
Dur
May 17
May 18
Nov 16
Mar 17
Nov 17
Mar 18
Nov 18
Mar 19
Description Start Finish
Aug 17
Aug 18
Oct 16
Feb 17
Oct 17
Feb 18
Oct 18
Feb 19
Sep 16
Dec 16
Apr 17
Sep 17
Dec 17
Apr 18
Sep 18
Dec 18
Apr 19
Jan 17
Jan 18
Jan 19
Jun 17
Jun 18
Jul 17
Jul 18
Days
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
CONSTRUCTION
6 Under Ground works till including Raft MEP U/G 106 15-Dec-16 30-Mar-17
10 MEP Works H/L (1st and 2nd Fix) 458 19-Jul-17 20-Oct-18
18 Handover 18-Apr-19
Page 1 of 10
METHODS OF CONSTRUCTION
EE
Page 2 of 10
METHODS OF CONSTRUCTION
EE
Page 3 of 10
METHODS OF CONSTRUCTION
EE
System Description
Electrical System:
RMU Room is Located in Ground floor, comprising of 6 Transformers (Supplied
by DEWA) and 4 ACB’s located in ground floor which feed MDB’s (4 nos.) in
Level-1. Incoming cable to transformer by DEWA.
For uninterrupted backup of critical services modular UPS, 3 modular each with
200kva (total 600kva UPS) and 500kva UPS 1 no. back-up time 15 minutes, lead
acid battery. UPS to support the IT system located in the building MDF, the
technology room / IDF and for the telephony agent / operator to have UPS for
their PC’s.
Essential loads are feeding through 2 nos. of 1500kva prime power rated
generator and 14 nos. of ATS panels. Generator units shall be synchronized and
paralleled parallelism switchgear and sync controls.
From Transformer the power is fed to 4 ACB’s which is feeding 4 LV panels
located in Level-1 LV Room through Bus bars. From the LV panels the power is
distributed to the entire building through various SMDB, MCC`s & DB`s located at
various Places. Total 10 nos. of Bus bar risers in which 4 nos. are feeder bus
bars (between ACB to MDB – Panel – Level GF to Level -01) and other 6 nos.
are riser bus bars feeding from MDB to higher floor levels. Rating of bus bars are
2500A, 2000A, 1600A, 1250A. Non-essential bus bars are 400V TPN & E copper
sandwich construction and essential bus bars are fire rated 400V TPN & E
copper cast resin type. Also, at level-1 a separate MDB is fed from generator for
emergency power. The cable also fed from LV room in the first floor distributed
through the riser to basement and to upper floors.
Lighting Control System
(a) European Installation Bus Technology (KNX) System.
(b) The LCPs shall be surface mounted in IP65 polycarbonate enclosures
together with built-in DIN-rails for. Dedicated Lighting Control Panel (LCP) for
every DB
Fire Alarm System
(a) Analogue Addressable System with Voice Evacuation
(b) PAVA Head end scope not clear. Needs Clarification.
Page 4 of 10
METHODS OF CONSTRUCTION
EE
Sealed Earth Pit, Solid Copper rod. Pile Earthing for Lightning Protection
System. Structural Re-bar to be used as Down conductor
CCTV System
Access Control System including Gate Barrier
Intercom System
Light Fittings
(a) Supply, installation of Internal and External Light Fittings.
(b) Façade and Landscaping part of Specialist Lighting Package.
HVAC System :
• The cooling for Mashreq Bank Headquarters Building is provided by
chilled water supplies from the district cooling provider (Emaar District
Cooling L.L.C).
• Tap off connections for 1,700 TR are taken from District cooling system
and further supplied connected to HEX installed at basement 1, The
Chilled water pumps are located at the Basement-1 which are serving the
chilled water to entire building.
• Two separate chilled water loops are serving to the tower building, (a)
chilled water low riser system (PN 16 pressure rated), (b) chilled water
high riser system (PN 25 pressure rated).
• In the event of power failure cooling to areas such as the elevator M/C
room, Central IT room, UPS room, satellite service equipment rom and the
telecommunication service entrance room is maintained through Air
cooled package chiller located at 4 level with dedicated piping network.
• From Level -9 to level-31, open offices, provided with Temporary Fan coil
unit without Ductwork and its accessories & Capped off Provision given for
Tenant FCU Connection.
• AHU’s are located in ground, first, level 4 & basement 3 parking. FAHU’s
are located in the 8th floor and lower roof serving the fresh air requirement
for the tower.
Page 5 of 10
METHODS OF CONSTRUCTION
EE
• Stair & Lift well are serving with pressurization system fans.
• Kitchen extract systems serving Level 6 & 7 kitchen are with Ecology
System.
BMS System
The BMS system shall be used to control and monitor the functions of the building
MEP systems, plant and equipment.
Plumbing Scope
Water Supply
• Potable water services will be provided by a DEWA incoming cold water supply.
The supply shall enter the Building at Basement Level B1 high level and serve 2
nos. of potable water storage tanks. To maintain water quality, a copper silver
ionization unit shall be provided. The cold water shall pass through a variable
speed cold water booster set and distribute to serve all the appliances within the
building.
• Supply to tenant at ground floor will be metered by DEWA. The tenants plumbing
system shall terminate with an isolating valve and pressure reducing valve and
shall be capped for continuation by tenants.
• All water supply pipework shall be in stainless steel and pipework concealed in the
wall shall be PEX.
• Hot water shall be supplied using instantaneous point-of-use electric water
heaters for the 27, 28, 29, 30 & 31 floors & direct LPG fired water heaters located
in level-8 feeding kitchens.
Page 6 of 10
METHODS OF CONSTRUCTION
EE
Irrigation System –
• Irrigation (TSE) water to be supplied directly from the Main External Network to
the irrigation tank located at the basement level. Internal planter areas to be
irrigated with Irrigation water supply by Irrigation specialist.
Gas System
• Connection to local LPG Network
• LPG distribution system -Tap off from network & supply in tenant area.
• LPG is using for the gas fired water heater.
Page 7 of 10
METHODS OF CONSTRUCTION
EE
Our centralised Procurement Team based at our Dubai head office will liaise closely
with the project team to provide efficient procurement support.
• Prepare material procurement schedule in accordance with the Construction
Programme.
• Follow up with Vendors and manufacturers for On-Time deliveries &
manufacturing updates.
• Float enquiries to specified Vendors with capability and track record to deliver
projects of this size & nature
• Secure delivery commitment as per project requirements.
• Co-ordinate with Logistic department for follow-up, receipt, clearance and site
delivery
Logistics
Logistics will be a key factor in the successful delivery of this project, requiring detailed co-
ordination between procurement, planning & construction departments.
Upon Contract Award Trans Gulf will develop a detailed logistics can comprising the
following:-
Co ordination
One of the Key elements for this project is proactive approach to resolve the perceived
intricacies and conflicts between internal disciplines as well as other package contractors
Page 8 of 10
METHODS OF CONSTRUCTION
EE
Commissioning
• Overall Testing & Commissioning Management plan will be prepared for the
project.
Page 9 of 10
METHODS OF CONSTRUCTION
EE
Page 10 of 10
METHODS OF CONSTRUCTION