### Work Breakdown Structure (WBS) for Scheduling
*Project: Design and Build of Passenger Terminal and Support Facility
Buildings at Dembidolo Airport*
#### **Level 1: Project**
1. **Passenger Terminal Building**
---
#### **Level 2: Major Components**
1. **Substructure (A)**
2. **Superstructure (B)**
3. **Systems & Finishes**
4. **External Works**
---
#### **Level 3: Work Packages & Tasks**
*(Based on Contract Items)*
1. **Substructure (A)**
  1.1. **Excavation & Earth Work**
    - Site clearance, excavation, backfilling, compaction.
  1.2. **Masonry Work**
    - Foundation masonry, retaining walls.
  1.3. **Concrete Work**
    - Footings, slabs, columns (substructure).
2. **Superstructure (B)**
  2.1. **Concrete Work (Superstructure)**
    - Slabs, beams, columns (above ground).
  2.2. **Steel Structure Works**
    - Structural steel framing, connections.
  2.3. **Block Works**
    - Partition walls, internal masonry.
  2.4. **Roofing Work**
    - Roof structure, waterproofing, insulation.
  2.5. **Carpentry & Joinery Works**
    - Doors, windows, cabinetry installation.
  2.6. **Aluminum Work**
    - Curtain walls, cladding, glazing supports.
  2.7. **Finishing Works**
    - Flooring, tiling, ceiling, drywall.
  2.8. **Painting Works**
   - Interior/exterior painting, coatings.
  2.9. **Glazing Works**
   - Window installation, glass facades.
3. **Systems & Finishes**
  3.1. **Sanitary and Mechanical Works**
    - Plumbing, piping, drainage systems.
  3.2. **Electrotechnical Works (BHS)**
    - Baggage handling system (BHS) electricals.
  3.3. **Furniture Supply**
    - Procurement and installation of fixed furniture.
  3.4. **Signage Works**
    - Directional, informational signage installation.
  3.5. **Electrical Works**
    - Lighting, power distribution, switchgear.
  3.6. **ICT & SAS Works**
    - IT infrastructure, airport-specific systems (e.g., PA, displays).
  3.7. **Fire Fighting System**
    - Sprinklers, alarms, fire suppression systems.
  3.8. **HVAC System Works**
    - Ductwork, AHUs, ventilation controls.
4. **External Works**
  4.1. **Site Work & Roads**
    - Landscaping, internal roads, drainage.
  4.2. **Parking Works**
    - Staff/passenger parking paving, markings.
---
#### **Level 4: Supporting Phases**
5. **Design Phase**
  - Architectural/structural design, MEPF coordination, approvals.
6. **Commissioning & Handover**
  - Systems testing, snagging, client training, documentation.
7. **Project Management**
  - Planning, procurement, site supervision, cost/schedule control.
---
### **WBS Dictionary Key Details**
| **Task ID** | **Description**                           | **Predecessors**              | **Key De-
pendencies**                         |
|-------------|----------------------------------|------------------------|-----------------------------
-------------|
| 1.1          | Excavation & Earth Work          | Design Approval         | Site sur -
vey, permits.                     |
| 1.3           | Substructure Concrete           | 1.1              | Curing period,
inspection.                  |
| 2.2          | Steel Structure Works          | 1.3             | Fabrication lead
time.                   |
| 2.4           | Roofing Work               | 2.2               | Weather-sealing,
safety protocols.             |
| 2.7           | Finishing Works             | 2.1–2.6             | Dry-in comple -
tion.                     |
| 3.1            | Sanitary/Mechanical Works         | 2.3, 2.7           | Coordina-
tion with electrical/HVAC.            |
| 3.8          | HVAC System Works                | 3.1, 2.8          | Duct integra -
tion with structure.            |
| 4.1            | Site Work & Roads               | All above-ground works | Final
grading, utility tie-ins.           |
|5            | Design Phase               | None                | Must precede all
construction.               |
|6            | Commissioning                 | All tasks          | Sequential sys -
tem tests (MEPF, ICT, SAS).|
### **Notes for Scheduling**
1. **Critical Path:**
  - Substructure (1.1 → 1.3) → Superstructure (2.1 → 2.9) → Systems (3.1 →
3.8).
  - External works (4.1–4.2) parallel to finishes.
2. **High-Value Items:**
   - Sanitary/Mechanical (20%), Finishing (6%), and Electrical (4%) require
resource prioritization.
3. **Integration Points:**
  - **Steel-to-Roof (2.2 → 2.4):** Critical for weather protection.
   - **MEPF Coordination (3.1, 3.5, 3.8):** Clash detection in design phase
essential.
4. **Milestones:**
   - Substructure completion → Superstructure start → Envelope closure →
Systems installation.
---
This WBS enables granular scheduling using tools like MS Project or Pri-
mavera, with tasks mapped to cost weights (e.g., Sanitary/Mechanical =
20% of budget). Support Facility Buildings can be added as a parallel L2
component once scoped.
### Revised Work Breakdown Structure (WBS) with MEP Phasing
*Project: Design and Build of Passenger Terminal at Dembidolo Airport*
*MEP Systems broken into 1st Fix (Rough-in), 2nd Fix (Installations), 3rd Fix
(Commissioning)*
---
#### **Level 1: Project**
1. **Passenger Terminal Building**
---
#### **Level 2: Major Components**
1. **Substructure**
2. **Superstructure**
3. **MEP Systems**
4. **Finishes & Special Systems**
5. **External Works**
---
### **Level 3: MEP Systems (Detailed Phasing)**
#### **3.1 MEP 1st Fix (Rough-in Works)**
*Work before walls/ceilings closed. Focus: Pathways, supports, hidden
components.*
- **3.1.1 Sanitary Rough-in**
  - Underground drainage piping, sewer lines, stub-outs
- **3.1.2 Mechanical Rough-in**
  - Chilled water pipes, ductwork sleeves, equipment pads
- **3.1.3 Electrical Rough-in**
  - Conduits, cable trays, backboxes, grounding systems
- **3.1.4 HVAC Rough-in**
  - Ductwork mains, risers, chiller plant piping
- **3.1.5 Fire Fighting Rough-in**
  - Sprinkler mains, risers, valve assemblies
- **3.1.6 ICT/SAS Rough-in**
  - Fiber conduits, data trunking, equipment room prep
#### **3.2 MEP 2nd Fix (Installations)**
*Work after structural close-in. Focus: Equipment, fixtures, visible compo-
nents.*
- **3.2.1 Sanitary Installations**
  - Above-ground piping, fixtures (sinks/toilets), pumps
- **3.2.2 Mechanical Installations**
  - Boilers, AHUs, pumps, VRF units
- **3.2.3 Electrical Installations**
  - Switchgear, lighting fixtures, sockets, panels
- **3.2.4 HVAC Installations**
  - FCUs, diffusers, grilles, controls wiring
- **3.2.5 Fire Fighting Installations**
  - Sprinkler heads, alarms, detectors, hose reels
- **3.2.6 ICT/SAS Installations**
  - BHS controls, PA systems, cameras, access points
#### **3.3 MEP 3rd Fix (Commissioning & Finishing)**
*Final connections, testing, and handover.*
- **3.3.1 Systems Testing**
  - Pressure tests (pipes), megger tests (wiring), duct balancing
- **3.3.2 Commissioning**
  - BHS integration, HVAC balancing, fire drills
- **3.3.3 Client Training**
  - O&M manuals, system demonstrations
- **3.3.4 Snagging & Rectification**
  - Punch list closure, final adjustments
---
### **Integration with Other WBS Components**
#### **4. Finishes & Special Systems**
- 4.1 Furniture Supply (after MEP 2nd Fix)
- 4.2 Signage Works (after MEP 3rd Fix)
- 4.3 Painting/Glazing (coordinate with MEP rough-in)
#### **5. External Works**
- 5.1 Site Utilities (tie-ins to MEP mains)
---
### **WBS Dictionary: MEP Dependencies**
| **Task ID** | **Description**                        | **Predecessors**                     | **Criti-
cal Inputs**                           |
|-------------|------------------------------|--------------------------------|-------------------------
---------------------|
| 3.1.1         | Sanitary Rough-in                   | Substructure Concrete (1.3) | Un -
derground survey, pipe bedding                           |
| 3.1.3          | Electrical Rough-in                  | Block Works (2.3)                      | Wall
chase approvals                              |
| 3.2.2        | HVAC Installations                 | Roofing Complete (2.4)                  | Equip -
ment lifting plan                          |
| 3.2.4     | Fire Fighting Installations | Finishing Works (2.7)      | Ceiling
grid layout                   |
| 3.3.2      | Systems Commissioning           | All MEP 2nd Fix, Power On     |
Client witness tests                   |
| 4.1         | Furniture Supply            | MEP 2nd Fix, Flooring Complete |
Damage protection protocols                  |
---
### **MEP Phase Scheduling Logic**
1. **Sequencing:**
  ```mermaid
  graph LR
  A[Substructure] --> B[MEP 1st Fix]
  B --> C[Superstructure Close-in]
  C --> D[MEP 2nd Fix]
  D --> E[Finishing Works]
  E --> F[MEP 3rd Fix]
  F --> G[Handover]
  ```
2. **Key Overlaps:**
  - Electrical Rough-in (3.1.3) runs parallel to HVAC Rough-in (3.1.4)
  - Fire Fighting Installations (3.2.4) overlaps with Ceiling Works (2.7)
  - BHS Commissioning (3.3.2) requires ICT Systems (4.3) complete
3. **Critical Path Alerts:**
  - **HVAC Balancing (3.3.2):** Longest lead time (2-4 weeks)
  - **Fire Approval (3.3.2):** Regulatory dependency
  - **Sanitary Pressure Tests (3.3.1):** Must precede final flooring
---
### **Resource Allocation Tips**
- **1st Fix:** Civil teams (excavators, pipefitters)
- **2nd Fix:** Specialist technicians (BHS, HVAC controls)
- **3rd Fix:** Commissioning agents + client representatives
- **High-Cost Focus:**
  - Sanitary/Mechanical (20% budget): Prioritize pipework crew
  - Electrical (4%) + ICT (2%): Dedicated low-voltage teams
---
This phased MEP breakdown enables conflict-free scheduling, aligns with
ISO 21838 standards, and isolates commissioning risks. Support facility
MEP can be added as a parallel stream.