GS03 - Project Execution Schedule
(to be submitted both as signed stamped pdf and editable .xlsx
formats)
SNo. Activity
1 Issuance of Letter of Award
2 Site handover/ NTP
3 Site Studies & Site Mobilization, Opening of Site Office & Preparatory
works
4 Basic Engineering Design- Layout, PVSyst, SLD
5 Long lead items (MMS, IDT, Switchgear) Procurement
6 Detailed Design & Engg. (Electrical, Civil & Structural)
7 Other Plant Equip/ Material Procurement
8 Electrical AC/ DC Erection
9 Civil Erection
10 Testing & Commissioning (including punch list)
Duration