Annexure 3-Scope of Work

This document outlines the scope of work for the Engineering, Procurement, and Construction of the 1.0 MMBD Sustain Phase 1 Surface Facilities Project under Agreement No: 4700022962. It details the order of precedence for applicable laws, regulations, and project specifications that the contractor must follow. The annexure includes references to various sub-annexures that provide further details on project requirements and management plans.

Uploaded by

viroli
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
140 views3 pages

Annexure 3-Scope of Work

This document outlines the scope of work for the Engineering, Procurement, and Construction of the 1.0 MMBD Sustain Phase 1 Surface Facilities Project under Agreement No: 4700022962. It details the order of precedence for applicable laws, regulations, and project specifications that the contractor must follow. The annexure includes references to various sub-annexures that provide further details on project requirements and management plans.

Uploaded by

viroli
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

ADNOC Classification: Need-To-Know

ENGINEERING, PROCUREMENT & CONSTRUCTION FOR


1.0 MMBD SUSTAIN PHASE 1SURFACE FACILITIES PROJECT
PROJECT NO: E1150/10324 ANNEXURE 3

SCOPE OF WORK Page: 1 of 3

ANNEXURE -3

SCOPE OF WORK

Agreement No: 4700022962 Rev.: Issued for Contract


Annexure 3: Scope of work Date: 18 Mar 2024
ADNOC Classification: Need-To-Know

ENGINEERING, PROCUREMENT & CONSTRUCTION FOR


1.0 MMBD SUSTAIN PHASE 1SURFACE FACILITIES PROJECT
PROJECT NO: E1150/10324 ANNEXURE 3

SCOPE OF WORK Page: 2 of 3

1 INTRODUCTION

This ANNEXURE 3 is an AGREEMENT DOCUMENT forming part of the


AGREEMENT and shall be read with and into the AGREEMENT.

The PARTIES agree and acknowledge that, notwithstanding anything to the contrary
set out in this ANNEXURE or any other, this ANNEXURE shall be read and applied in
accordance with the order of precedence set out at Clause 1.6 of the FORM OF
AGREEMENT.

For the avoidance of doubt, the governing law and dispute resolution provisions of
Article [44] of ANNEXURE 2 (GENERAL TERMS AND CONDITIONS) apply to this
ANNEXURE 3.

In this ANNEXURE 3, unless otherwise defined, capitalised words and expressions


shall have the same meanings as are respectively assigned to them in the GENERAL
TERMS AND CONDITIONS.

2 SCOPE OF WORK – CONTENTS

The Engineering, Procurement, Construction, Pre-COMMISSIONING,


COMMISSIONING, START-UP and PERFORMANCE TEST SCOPE OF WORK is
specified in the Annexure and Sub-annexure as listed in the below table for ease of
reference only.

Annexure Title

ANNEXURE 3A

3A Project Description

ANNEXURE 3B

3B Detailed Requirements

3B-1 Interface Management Plan

3B-2 Insurance Spare List

ANNEXURE 3C – Novated / Free Issue Items – Not Applicable

ANNEXURE 3D

3D-1 Survey Data

3D-2 Site Survey Procedure

Agreement No: 4700022962 Rev.: Issued for Contract


Annexure 3: Scope of work Date: 18 Mar 2024
ADNOC Classification: Need-To-Know

ENGINEERING, PROCUREMENT & CONSTRUCTION FOR


1.0 MMBD SUSTAIN PHASE 1SURFACE FACILITIES PROJECT
PROJECT NO: E1150/10324 ANNEXURE 3

SCOPE OF WORK Page: 3 of 3

ANNEXURE 3E

3E-1 Rely Upon Information

3 ORDER OF PRIORITY

The documents within ANNEXURE 3 shall be read and applied in the following order
of priority.

The latest versions and amendments of all applicable UAE legislation and
environmental regulations, applicable international laws and regulations, ADNOC
Guidelines, Project specifications, COMPANY specifications and standards,
regulations, GOOD INDUSTRY PRACTICE, Guidance and Practice Documents and
all relevant codes and standards on the EFFECTIVE DATE of the AGREEMENT shall
be used by CONTRACTOR. In any event, CONTRACTOR shall comply with Article
1.3 ANNEXURE 2.

Accordingly, FEED documents shall be upgraded by CONTRACTOR during the


detailed engineering stage as necessary as per the below order of precedence:

• ANNEXURE 3E-1 – Rely Upon Information


• UAE Federal Laws and National Local Regulations
• ADNOC HSE Standards and ADNOC OFFSHORE Procedures
• PROJECT Philosophies
• Design basis
• P&ID's
• Plot Plans
• PROJECT Specifications
• Datasheets
• COMPANY Specifications
• all remaining PROJECT Deliverables
• COMPANY Standard specifications and Procedures
• Applicable International Design Codes, Standards and Regulations

If there is any conflict among the documents included in the AGREEMENT, the most
stringent requirement among them will prevail. CONTRACTOR shall promptly bring
to the notice of COMPANY any such conflicts, and COMPANY shall determine the
prevailing requirement and advise CONTRACTOR accordingly.