Making FLEXIBLE PAVEMENT from Trisulia- Banki Road (at Baanra Village) towards Chandaka reserved
forest in connection with the work “Construction of 130 MLD Water treatment plant and its Ancillary
structures for Improvement of water supply to Bhubaneswar City" on Engineering Procurement &
Construction (EPC contact including Operation & Maintenence for a period of five Years.
I. SITE CLEARANCE
1 Clearing and grubbing road land including uprooting trees rank vegetation,
grass, bushes, shrubs, saplings and girth up to 300 mm, removal of stumps of
trees cut earlier and disposal of unserviceable materials and stacking of
serviceable material to be used or auctioned, up to a lead of 1000 metres etc
7 Providing and applying tack coat with bitumen using Pressure distributor @
0.20kg/sqm on the prepared surface cleaned with mechanical brooms as per
clause 503 of MOSRT & H Specifications for Road & Bridge works
(5th.Revision)
1x 975.000 X 6.300 = 6142.500 Sqm
6142.50 Sqm 13.08 80343.90
1
2
9 Providing and laying semi dense bituminous concrete with100-120 TPH batch
type HPM producing an average output of 75 tonnes per hour using crushed
aggregates of specified grading, premixed with bituminous binder @4.5 to 5
percent of mix and filler.
Total Rs 16786828.31
3
Making FLEXIBLE PAVEMENT from Trisulia- Banki Road (at Baanra Village) towards Chandaka reserved forest in connection with the work “Construction of 130 MLD
Water treatment plant and its Ancillary structures for Improvement of water supply to Bhubaneswar City" on Engineering Procurement & Construction (EPC contact
including Operation & Maintenence for a period of five Years.
LEAD STATEMENT FROM QUARRY TO WORK SITE
1 2 3 4 5 6 7 8 9 10 11 12 13 14
Baidehipur
1 IRC Gr-II Metal. 27.00 562.45 130.00 13.00 6.50 9.00 158.50 720.95 867.30 1,588.25 Cum
Stone Quarry
Baidehipur
2 IRC Gr-III Metal. 27.00 562.45 130.00 13.00 6.50 9.00 158.50 720.95 923.46 1,644.41 Cum
Stone Quarry
Baidehipur
2 63 mm Size H.G (H.B) Metal 27.00 562.45 130.00 13.00 6.50 9.00 158.50 720.95 648.36 1,369.31 Cum
Stone Quarry
Baidehipur
3 45 mm Size H.G (C.B) Metal 27.00 562.45 130.00 13.00 6.50 9.00 158.50 720.95 839.86 1,560.81 Cum
Stone Quarry
4 40mm size H.G (C.B) Metal. Do 27.00 562.45 130.00 13.00 6.50 9.00 158.50 720.95 995.25 1,716.20 Cum
5 25mm size H.G (C.B) Metal. Do 27.00 562.45 130.00 13.00 6.50 9.00 158.50 720.95 1,135.74 1,856.69 Cum
6 26.5mm size HG(CB) Metal Do 27.00 562.45 130.00 13.00 6.50 9.00 158.50 720.95 1,097.74 1,818.69 Cum
7 22.4mm size HG(CB) Metal Do 27.00 562.45 130.00 13.00 6.50 9.00 158.50 720.95 1,123.78 1,844.73 Cum
8 20mm size H.G (C.B) Metal. Do 27.00 562.45 130.00 13.00 6.50 9.00 158.50 720.95 1,382.29 2,103.24 Cum
9 13.2mm size H.G (C.B) Chips. Do 27.00 562.45 130.00 13.00 6.50 9.00 158.50 720.95 1,342.76 2,063.71 Cum
10 12mm Size H.G (C.B) Chips. Do 27.00 562.45 130.00 13.00 6.50 9.00 158.50 720.95 1,372.71 2,093.66 Cum
11 11.2mm Size H.G (C.B) Chips. Do 27.00 562.45 130.00 13.00 6.50 9.00 158.50 720.95 1,375.20 2,096.15 Cum
12 10mm Size H.G (C.B) Chips. Do 27.00 562.45 130.00 13.00 6.50 9.00 158.50 720.95 1,397.67 2,118.62 Cum
13 6.7mm size H.G (C.B) Chips. Do 27.00 562.45 130.00 13.00 6.50 9.00 158.50 720.95 923.46 1,644.41 Cum
14 4.7mm size H.G (C.B) Chips. Do 27.00 562.45 130.00 13.00 6.50 9.00 158.50 720.95 836.11 1,557.06 Cum
Granite broken stone of size
15 not less than 0.0025cum Do 27.00 562.45 130.00 13.00 6.50 9.00 158.50 720.95 291.96 1,012.91 Cum
stacked
16 Stone other than granite Do 27.00 562.45 130.00 13.00 6.50 9.00 158.50 720.95 291.96 1,012.91 Cum
17 Granite Broken Stone Do 27.00 562.45 130.00 13.00 6.50 9.00 158.50 720.95 238.36 959.31 Cum
18 Crusher Dust Do 27.00 562.45 35.00 3.50 1.75 9.00 49.25 611.70 136.33 748.03 Cum
19 Moorum Local 5.00 276.01 35.00 3.50 1.75 0.00 40.25 316.26 61.25 377.51 Cum
Kathajodi R/S
20 Sand for Road work 16.00 419.23 35.00 3.50 1.75 150.00 190.25 609.48 56.19 665.67 Cum
Mundamuhana
Kathajodi R/S
21 Sand for Mortar 16.00 419.23 35.00 3.50 1.75 150.00 190.25 609.48 62.58 672.06 Cum
Mundamuhana
22 Bitumen VG-30 Bulk Paradeep 104.00 1328.32 0.00 0.00 0.00 0.00 0.00 1328.32 48,432.00 49,760.32 M.T
23 Bitumen Emulsion (SS) Haldia 375.00 4065.42 0.00 0.00 0.00 0.00 0.00 4065.42 46,007.00 50,072.42 M.T
24 Bitumen Emulsion (RS) Haldia 375.00 4065.42 0.00 0.00 0.00 0.00 0.00 4065.42 45,396.00 49,461.42 M.T
25 Cement Cuttack 20.00 426.22 0.00 0.00 0.00 0.00 0.00 426.22 538.88 581.50 Qntl
Cetified that the quaries mentioned above are the nearest approved quaries and the leads provided above are shortest and correct to the best of my knowledge and
belief.
Certified that the quarries above have been nearest approved quarry and leads provided in this estimate are correct and
minimum to the best of my knowledge.
1 P.R.R. 8-10 Ton for soil compaction @ 70 cum / hr Per Day 2558 Hour 524.70
P.R.R. 8-10 Ton for BM compaction @ 25 cum / hr Hour
2 Vibratory Roller (8-10 tonne) for earth /soil @ 100 cum /hr Per Day Hour 1538.54
Vibratory Roller (8-10 tonne) for GSB @ 60 cum /hr Hour
Vibratory Roller (8-10 tonne) for WMM @ 60 cum /hr Hour
3 Tendem Roller Per Day Hour 1142.30
4 Sheep foot roller Per Day Hour 500.00
5 H.R.R. Per Day
6 Plate compactor Per Day Hour 153.23
7 H.M.P. (8-10) Ton Per Day Hour 1586.51
8 H.M.P. (40-60) Ton Per Day Hour 11066.95
9 H.M.P Batch mix type. (100-120) Ton @ 75.0 ton per hour Per Day Hour 17284.56
actual out put
10 Wet Mix Plant 75 ton per hour Per Day Hour 1700.00
11 Paver Finisher (Mechanical) Per Day Hour 1143.90
12 Paver Finisher (With sensor) @75 cum per hour Per Day Hour 1724.97
13 Paver Finisher Mechanical (paving of DLC ) @ 75cum/hr Per Day Hour 1816.61
14 Motor Grader 3.35 mtr blade clearing @ 200 cum / hour Per Day Hour 2391.39
for spreading 200 cum / hour Hour
for GSB @ 50 cum / hour Hour
for WMM @ 50 cum / hour Hour
15 Tractor with ordinary grader Hour 447.31
16 Tractor mounted Rotovator Per Day Hour 373.55
17 Water tanker 6.0KL capacity Per Day Hour 900.84
17 Tractor With reeper @60.0cum per hour Per Day Hour 378.55
18 Tractor With trolly/tractor for mastic work Per Day Hour 357.55
19 Tipper 10 ton or 5.5 cum capacity/flat body truck capacity Hour 5.50 per Km . 37.15
cum
Per Ton km. 3.86
Hour 900.84
20 Front End Loader 1 cum bucket capacity for soil loading @ Per Day Hour 804.86
60 cum /hour
for Aggregate loading @ 25 cum / hour Hour
21 Hydraulic self propelled Chipse Spreader @1500sqmt per Per Day Hour 1480.62
hour
22 Bitumen Pressure Distributer @1750 sqm per hour Per Day Hour 1071.10
23 Bitumen Emulsion Pressure Distributer @1750 sqm per Per Day Hour 798.68
hour
24 Tar Boiler Per Day Hour 114.54
25 Bitumen boiler 1500 liter capacity Per Day Hour 198.11
Sl Name of Machine UNIT RATE UNIT RATE
No.
35 Crane with grab1.0 cum /0.75 cum capacity Per Day Hour 1051.30
36 Crane15 ton capacity Per Day Hour 1051.30
37 Mastic cooker 1.0 ton capacity Per Day Hour 2454.85
38 Cement concrete Batch mix plant @175 cum per hour Per Day Hour 8791.61
39 Cement concrete Batch mix plant @20.0 cum per hour Per Day Hour 2144.23
40 Cement concrete Batch mix plant @75 cum per hour Per Day Hour 3421.29
45 Transit agitator 4.0 cum capacity upto 1.0 KM Hour 600 Per Ton K.M.
46 Transit agitator 4.0 cum capacity beyond 1.0 KM Hour Per Ton K.M. 1276.95
A Category Unskilled
Male mulia
1 Per day 452.00
Female mulia
2 Per day 452.00
Survey Khalasi /Chain man
3 Per day 452.00
C Category Skilled
Sl No. Category of Labour Unit Rate
Blaster(Second class)
1 Per day 552.00
19 Rigger and Cobbler with Tools Driver (Heavy Vehicle) Per day 602.00
1.Labour rates for un-skilled, Semi-skilled,Skilled and Highly
skilled as are to be fixedform time to time by labour Department
Notes
under Minimum wages Act shall prevail in respect of category
what so ever.
68
2. The rates for above four categories of labour are inclusive of
weekly day of rest.
70
3.An adult Employee shall work for 8(Eight)hours per day
including half-an hour of rest.
Other Cateory (Note covered by the Notification of Labour &
E Employment Department).
Boring Mistry (Special)
1 Per day 602.00
2
Sl. Item of work Quantity Unit Rate (in Amount ( Remarks
No Rs) in Rs )
1 2 3 4 5 6 7
5 Providing laying and compacting graded stone
agregate to wet mix macadum specification
including premixing the material with water at
OMC in mechanical mix plant,carriage of mixed
material by tipper to site, laying in uniform layer
with paver in sub-base and base course on well
prepared surface and compacting with vibratory
roller to achive desired density etc complete as
per the direction of Engineer-in-charge . Vide A/R Page - 166 , Item No-42
Taking Output = 225 Cum(495 tonnes)
(a) Labour
Mate 0.48 Each 502.00 240.96
Mazdoor 10.0 Each 452.00 4520.00
Skilled Mazdoor 2.0 Each 552.00 1104.00
5864.96
(b ) Machinery
Wet mix plant 75 Tonne/hr. capacity 6.60 hour 1700.00 11220.00
Paver finisher Mechanical 100 TPH 6.00 hour 1143.90 6863.40
Electric generator 125 KVA 6.00 hour 1341.16 8046.96
F.E.Loader 1 cum capacity 6.00 hour 804.86 4829.16
Water tanker 6KL capacity 3.00 hour 900.84 2702.52
Vibrator Roller 8-10 tonne 3.90 hour 1538.54 6000.31
Tipper t/km 495.00x3.86x22 hour 3.86 42035.40
Add 10% carriage 4203.54
85901.29
(c) Materials
45 mm to 22.4mm @ 30% (26.50 mm) 89.10 Cum 1097.74 97808.63
22.40 mm to 2.36 mm@ 40 % (13.2+6.7 )/2 118.80 Cum 1133.11 134613.47
2.36 mm to 75 micron @ 30 %(dust) 89.10 Cum 136.33 12147.00
Cost of water 18.00 Litre 10.00 180.00
244749.11
Total (a + b + c) 336515.35
(d) Over head Charge @ 7.50 % on (a+b+c) 25238.65
Contractor's Profit @ 7.50 % 25238.65
386992.65
(e) Cost of carriage & royality of materials
C.B Chips 207.90 Cum 720.51 149794.03
2.36 mm to 75 micron 89.10 Cum 611.26 54463.27
204257.30
Total 591249.95 / 225 cum
Rate per Cum 2627.78 per cum
Add 1% Labour Cess 26.28
2654.06 per cum
3
Sl. Item of work Quantity Unit Rate (in Amount ( Remarks
No Rs) in Rs )
1 2 3 4 5 6 7
96674.70
(c) Machinery
Mechanical Broom@1250 Sqm per Hour 2.80 Hour 356.00 996.80
Air Compressor 250 Cum 2.80 Hour 585.00 1638.00
Emulsion Pressure Distributor@1750 sqm/Hr 2.00 Hour 798.68 1597.36
Water Tanker 6 KL @ 1TRIP/Hour 1.000 Hour 900.84 900.84
5133.00
102751.86
(d) Overhead charges @ 7.50 % 7706.39
Contractor's Profit @ 7.50 % 7706.39
Cost per 5889 sqm = (a+b+c) 118164.64
(f) Cost,carriage & royality of materials
Bitumen Emulsion @ 0.60 Kg/sqm 2.1 MT 4,065.42 8537.38
126702.02 / 3500 Sqm
Rate Per sqm 36.20
Add @1% for Labour Cess 0.36
36.56 / Sqm
(b ) Machinery
Batch mix plant HMP 100-120 TPH 6.00 Hour 17284.56 103707.36
Paver finisher hydrostatic with senser control 6.00 Hour 1724.97 10349.82
Electric generator 250 KVA 6.00 Hour 1600.00 9600.00
F.E.Loader 1 cum capacity 6.00 Hour 804.86 4829.16
Tipper 10 ton capacity 450.00x3.86x22 3.86 38214.00
Add 10%for carriage 3821.40
PRR (8 - 10 ton ) 3.90 Hour 524.70 2046.33
Vibrator Roller 3.90 Hour 1538.54 6000.31
Tendam Roller 3.90 Hour 1142.30 4454.97
(c ) Materials 183023.35
Supply of bitumen (60/70) 14.85 MT 48432.00 719215.20
25mm to10mm@40% (20mm) 116.04 Cum 1382.29 160400.93
10mm to 5mm @ 40% (Ave. 10mm & 4.7mm) 116.04 Cum 1116.89 129603.92
5mm& below@20% (Ave. 4.7mm & dust) 58.02 Cum 486.22 28210.48
1037430.53
Total (a+b+c) 1229923.40
5
Sl. Item of work Quantity Unit Rate (in Amount ( Remarks
No Rs) in Rs )
1 2 3 4 5 6 7
(b ) Machinery
Batch mix plant HMP 100-120 TPH 6.00 Hour 17284.56 103707.36
Paver finisher hydrostatic with senser control 6.00 Hour 1724.97 10349.82
Electric generator 250 KVA 6.00 Hour 1600.00 9600.00
F.E.Loader 1 cum capacity 6.00 Hour 804.86 4829.16
Tipper 10 ton capacity 450.00x3.86x22 3.86 38214.00
Add 10%for carriage 3821.40
PRR 3.90 Hour 524.70 2046.33
Vibrator Roller 3.90 Hour 1538.54 6000.31
Tendam Roller 3.90 Hour 1142.30 4454.97
(c ) Materials (GR-II) 183023.3
Supply of bitumen (60/70) 22.5 MT 48432.00 1089720.00
10mm to 5mm@57% (10 & 4.7mm Ave.) 162.45 Cum 1116.89 181438.8
5mm& below@41% (4.7 & dust ave) 116.85 Cum 486.22 56814.81
Filler @ 2% of weight of aggregates 5.7 Cum 136.33 777.08
1328750.7
1157.95
(c) Contractor's Profit @ 7.50% 86.85
(d) Overhead Charge @ 7.50% 86.85
470.55
(e) Add carraige & royality of Moorum 1.28 Cum 377.51 483.21
953.76
953.76
Add 1% Labour Cess 9.54
For one cum 963.30 /cum
6
Sl. Item of work Quantity Unit Rate (in Amount ( Remarks
No Rs) in Rs )
1 2 3 4 5 6 7
11 Earth work in embankment with approved
materials obtained from borrow pits with all leads
and lifts transporting to site,spreading, grading to
required slope and compacting at OMC by
Vibratory Roller to meet the requirement of Table-
300.2 as per Clause 305 of MoRT&H Specifications
dfor Road & Bridge works(5th. Revision) complet
including cost,conveyance,Royalities,Taxes of all
materials,all labours,hire and running charges of
all machineries,T&P ,sundries etc. complete as per
spcification and direction of Engineer-in-Charge.
(Vide A/R , Page - 157 , Item No-35)
(a) Labour
Mate 0.04 Each 502.00 20.08
Woman Mulia 1.00 Each 452.00 452.00
472.08
(b) Machinery
Hydraulic Excavator 1 cum bucket capacity
@ 60 cum per hour 1.670 Hour 1300.16 2171.27
Tipper 10 tonne capacity 160x5(L) Tonne.k 3.86 3088.00
Add 10% of cost of carriage to cover cost of 308.80
loading & unloading
Dozer 80 HP for spreading @ 200 cum per hr. 0.50 Hour 2834.00 1417.00
Motor Grader for grading @ 100 cum per hour 1.00 Hour 1195.70 1195.70
Water Tanker 6 KL capacity 4.00 Hour 900.84 3603.36
Vibratory Roller 8-10 tonnes @ 100 cum/hr. 1.00 Hour 1538.54 1538.54
13322.66
(c) Material
Cost of water 24.00 KL 10.00 240.00
Compensartion for earth taken from 100.00 Cum 0 0.00
240.00
14034.74
(d) Over Head Charges @ 7.50% (a+b+c) 1052.61
Contractor's Profit @ 7.50 % 1052.61
(e) Royality of earth 100.00 Cum 40.25 4025.00
Total (a+b+c+d+e) = 20164.95 Per 100 Cum
Rate per Cum 201.65 per Cum
Add @1% for Labour Cess 2.02
203.67 / cum