0% found this document useful (0 votes)
8 views3 pages

Estimate

The document is a detailed bill of materials for a construction project, outlining general requirements and civil/structural works. It includes item descriptions, quantities, units, unit prices, and total amounts for various materials needed, such as cement, sand, gravel, and reinforcement bars. The total estimated cost for the materials is broken down into subtotals for different categories of work.

Uploaded by

Sandra Dalisay
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
8 views3 pages

Estimate

The document is a detailed bill of materials for a construction project, outlining general requirements and civil/structural works. It includes item descriptions, quantities, units, unit prices, and total amounts for various materials needed, such as cement, sand, gravel, and reinforcement bars. The total estimated cost for the materials is broken down into subtotals for different categories of work.

Uploaded by

Sandra Dalisay
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

COMPANY NAME

Date: Floor Area: Lot area:


Project: Location :
Owner
BILL OF MATERIALS
Item No. Item Description Quantity Unit Unit Price, Php Amount, Php
I. GENERAL REQUIREMENTS
• As-built plan (1 set tracing & 7 complete sets blue print) (all signed and sealed) lot -
• Building Permit lot -
• Provision of temporary board up, covers, safety signages lot -
• Temfacil lot -
• Mobilization/Demobilization/Site Clearing lot -
• Excavation m³ -
• Backfill Works m³ -
• Lot Relocation lot -
• Staking out/layout lot -
• Termites and Pesticides Treatment for structural preparation lot -
• Occupancy Permits lot -
• Construction Permits lot -
Sub Total = -
II. CIVIL /STRUCTURAL WORKS
II.i. CONCRETING/MASONRY WORKS/REINFORCEMENTS
RC Footings (3000 PSI) m³
• Cement 86,00 bgs 270,00 23 220,00
• Sand 5,00 m³ 800,00 4 000,00
• Gravel 3/4" 10,00 m³ 1 600,00 16 000,00
• 16 mmø def bar 88,00 pcs 470,00 41 360,00
• 10 mmø def bar (Grade 40) pcs 250,00 -
• GI Tie Wire # 16 kgs 85,00 -

RC Columns (3000 PSI) m³


• Cement 64,00 bgs 270,00 17 280,00
• Sand 3,60 m³ 800,00 2 880,00
• Gravel 3/4" 7,00 m³ 1 600,00 11 200,00
• 16 mmø def bar (Grade 60) 29,00 pcs 470,00 13 630,00
• 10 mmø def bar (Grade 40) 158,00 pcs 250,00 39 500,00
• GI Tie Wire # 16 kgs 85,00 -

Tie beams (3000 PSI) m³


• Cement 39,00 bgs 270,00 10 530,00
• Sand 2,50 m³ 800,00 2 000,00
• Gravel 3/4" 4,30 m³ 1 600,00
• 12 mmø def bar (Grade 60) 90 pcs 350,00 1 505,00
• 10 mmø def bar (Grade 40) 65,00 pcs 250,00 16 250,00
• GI Tie Wire # 16 kgs 85,00 -

Slab on Grade (3000 PSI) m³


• Cement 169,00 bgs 270,00 45 630,00
• Sand 9,35 m³ 800,00 7 476,00
• Gravel 3/4" 18,69 m³ 1 600,00 29 904,00
• 10 mmø def bar (Grade 40) 136,00 pcs 250,00 34 000,00
• GI Tie Wire # 16 kgs 85,00 -

Suspended Beams (3000 PSI) m³


• Cement 38,34 bgs 270,00 10 351,80
• Sand 2,13 m³ 800,00 1 704,00
• Gravel 3/4" 4,26 m³ 1 600,00 6 816,00
• 16 mmø def bar (Grade 60) 29,00 pcs 470,00 13 630,00
• 10 mmø def bar (Grade 40) 158,00 pcs 250,00 39 500,00
• GI Tie Wire # 16 kgs 85,00 -

Roof Beams (3000 PSI) m³


• Cement 38,34 bgs 270,00 10 351,80
• Sand 2,13 m³ 800,00 1 704,00
COMPANY NAME
Date: Floor Area: Lot area:
Project: Location :
Owner
BILL OF MATERIALS
Item No. Item Description Quantity Unit Unit Price, Php Amount, Php
• Gravel 3/4" 4,26 m³ 1 600,00 6 816,00
• 12 mmø def bar (Grade 40) 29,00 pcs 350,00 10 150,00
• 10 mmø def bar (Grade 40) 158,00 pcs 250,00 39 500,00
• GI Tie Wire # 16 kgs 85,00 -
COMPANY NAME
Date: Floor Area: Lot area:
Project: Location :
Owner
BILL OF MATERIALS
Item No. Item Description Quantity Unit Unit Price, Php Amount, Php
Suspended Slab (3000 PSI) m³
• Cement 169,00 bgs 270,00 45 630,00
• Sand 9,35 m³ 800,00 7 480,00
• Gravel 3/4" 18,69 m³ 1 600,00 29 904,00
• 12 mmø def bar (Grade 40) 136,00 pcs 350,00 47 600,00
• GI Tie Wire # 16 kgs 85,00 -

Masonry Works
• Concrete hollow block - 6" 2 746,00 pcs 15,00 41 190,00
• Cement 418,00 bgs 270,00 112 860,00
• Sand 260,00 m³ 800,00 208 000,00
• 12mmø def bar pcs 350,00 -
• 10 mmø def bar pcs 250,00 -
• GI Tie Wire # 16 kgs 85,00 -

Stiffiner Columns and lintel beams


• Cement bgs 270,00 -
• Sand m³ 800,00 -
• Gravel 3/4" m³ 1 600,00 -
• 12 mmø def bar (Grade 40) pcs -
• 10 mmø def bar (Grade 40) pcs -
• GI Tie Wire # 16 kgs -

Exterior & Interior Plastering


• Cement bgs 270,00 -
• Sand m³ 800,00 -

Stairs (3000 PSI) m³


• Cement bgs -
• Sand m³ -
• Gravel 3/4" m³ -
• 16 mmø def bar (Grade 40) pcs -
• 10 mmø def bar (Grade 40) pcs -
• GI Tie Wire # 16 kgs -
• Consumables lot
Sub Total = 949 552,60
II.ii. FORMWORKS
• Phenolic Board pcs 1 250,00 -
• Consumables (Assorted Nails etc) lot 25 000,00 -
• Lumber for formworks ( 2"x 3" and 2"x 2") bdft 65,00 -
• Scaffoldings or Rental lot -
• (OTHERS SPECIFY) lot -
Sub Total = 1 500 000,00