COMPANY NAME
Date: Floor Area: Lot area:
Project: Location :
Owner
BILL OF MATERIALS
Item No. Item Description Quantity Unit Unit Price, Php Amount, Php
I. GENERAL REQUIREMENTS
• As-built plan (1 set tracing & 7 complete sets blue print) (all signed and sealed) lot -
• Building Permit lot -
• Provision of temporary board up, covers, safety signages lot -
• Temfacil lot -
• Mobilization/Demobilization/Site Clearing lot -
• Excavation m³ -
• Backfill Works m³ -
• Lot Relocation lot -
• Staking out/layout lot -
• Termites and Pesticides Treatment for structural preparation lot -
• Occupancy Permits lot -
• Construction Permits lot -
Sub Total = -
II. CIVIL /STRUCTURAL WORKS
II.i. CONCRETING/MASONRY WORKS/REINFORCEMENTS
RC Footings (3000 PSI) m³
• Cement 86,00 bgs 270,00 23 220,00
• Sand 5,00 m³ 800,00 4 000,00
• Gravel 3/4" 10,00 m³ 1 600,00 16 000,00
• 16 mmø def bar 88,00 pcs 470,00 41 360,00
• 10 mmø def bar (Grade 40) pcs 250,00 -
• GI Tie Wire # 16 kgs 85,00 -
RC Columns (3000 PSI) m³
• Cement 64,00 bgs 270,00 17 280,00
• Sand 3,60 m³ 800,00 2 880,00
• Gravel 3/4" 7,00 m³ 1 600,00 11 200,00
• 16 mmø def bar (Grade 60) 29,00 pcs 470,00 13 630,00
• 10 mmø def bar (Grade 40) 158,00 pcs 250,00 39 500,00
• GI Tie Wire # 16 kgs 85,00 -
Tie beams (3000 PSI) m³
• Cement 39,00 bgs 270,00 10 530,00
• Sand 2,50 m³ 800,00 2 000,00
• Gravel 3/4" 4,30 m³ 1 600,00
• 12 mmø def bar (Grade 60) 90 pcs 350,00 1 505,00
• 10 mmø def bar (Grade 40) 65,00 pcs 250,00 16 250,00
• GI Tie Wire # 16 kgs 85,00 -
Slab on Grade (3000 PSI) m³
• Cement 169,00 bgs 270,00 45 630,00
• Sand 9,35 m³ 800,00 7 476,00
• Gravel 3/4" 18,69 m³ 1 600,00 29 904,00
• 10 mmø def bar (Grade 40) 136,00 pcs 250,00 34 000,00
• GI Tie Wire # 16 kgs 85,00 -
Suspended Beams (3000 PSI) m³
• Cement 38,34 bgs 270,00 10 351,80
• Sand 2,13 m³ 800,00 1 704,00
• Gravel 3/4" 4,26 m³ 1 600,00 6 816,00
• 16 mmø def bar (Grade 60) 29,00 pcs 470,00 13 630,00
• 10 mmø def bar (Grade 40) 158,00 pcs 250,00 39 500,00
• GI Tie Wire # 16 kgs 85,00 -
Roof Beams (3000 PSI) m³
• Cement 38,34 bgs 270,00 10 351,80
• Sand 2,13 m³ 800,00 1 704,00
COMPANY NAME
Date: Floor Area: Lot area:
Project: Location :
Owner
BILL OF MATERIALS
Item No. Item Description Quantity Unit Unit Price, Php Amount, Php
• Gravel 3/4" 4,26 m³ 1 600,00 6 816,00
• 12 mmø def bar (Grade 40) 29,00 pcs 350,00 10 150,00
• 10 mmø def bar (Grade 40) 158,00 pcs 250,00 39 500,00
• GI Tie Wire # 16 kgs 85,00 -
COMPANY NAME
Date: Floor Area: Lot area:
Project: Location :
Owner
BILL OF MATERIALS
Item No. Item Description Quantity Unit Unit Price, Php Amount, Php
Suspended Slab (3000 PSI) m³
• Cement 169,00 bgs 270,00 45 630,00
• Sand 9,35 m³ 800,00 7 480,00
• Gravel 3/4" 18,69 m³ 1 600,00 29 904,00
• 12 mmø def bar (Grade 40) 136,00 pcs 350,00 47 600,00
• GI Tie Wire # 16 kgs 85,00 -
Masonry Works
• Concrete hollow block - 6" 2 746,00 pcs 15,00 41 190,00
• Cement 418,00 bgs 270,00 112 860,00
• Sand 260,00 m³ 800,00 208 000,00
• 12mmø def bar pcs 350,00 -
• 10 mmø def bar pcs 250,00 -
• GI Tie Wire # 16 kgs 85,00 -
Stiffiner Columns and lintel beams
• Cement bgs 270,00 -
• Sand m³ 800,00 -
• Gravel 3/4" m³ 1 600,00 -
• 12 mmø def bar (Grade 40) pcs -
• 10 mmø def bar (Grade 40) pcs -
• GI Tie Wire # 16 kgs -
Exterior & Interior Plastering
• Cement bgs 270,00 -
• Sand m³ 800,00 -
Stairs (3000 PSI) m³
• Cement bgs -
• Sand m³ -
• Gravel 3/4" m³ -
• 16 mmø def bar (Grade 40) pcs -
• 10 mmø def bar (Grade 40) pcs -
• GI Tie Wire # 16 kgs -
• Consumables lot
Sub Total = 949 552,60
II.ii. FORMWORKS
• Phenolic Board pcs 1 250,00 -
• Consumables (Assorted Nails etc) lot 25 000,00 -
• Lumber for formworks ( 2"x 3" and 2"x 2") bdft 65,00 -
• Scaffoldings or Rental lot -
• (OTHERS SPECIFY) lot -
Sub Total = 1 500 000,00