Saes P 119
Saes P 119
Contents
1 Scope ................................................................ 2
2 Conflicts and Deviations ................................... 2
3 References........................................................ 2
4 Acronyms and Definitions ................................. 5
5 General ............................................................. 5
6 Substation Buildings ......................................... 8
7 Substation Yard .............................................. 12
8 Substation Bus Configurations ........................ 19
Revision Summary................................................. 21
1 Scope
This standard presents the mandatory requirements for the design and installation of
onshore and when specifically specified in this standard, offshore power substations.
This document may not be attached to nor made a part of purchase orders.
2.1 If there are any conflicts between this standard and associated project or
engineering documents, this standard shall take precedence. The exception is if
an approved Waiver Request has been included with the purchasing documents.
2.2 Any conflicts between this document and other applicable Mandatory Saudi
Aramco Engineering Requirements (MSAERs*) shall be addressed to the
EK&RD Coordinator.
* Examples of MSAERs are Saudi Aramco Materials System Specifications (SAMSSs),
Engineering Standards (SAESs) and Standard Drawings (SASDs).
2.3 Any deviation from the requirements herein shall follow internal company
procedure SAEP-302.
3 References
The selection of material and equipment, and the design, construction, maintenance, and
repair of equipment and facilities covered by this standard shall comply with the latest
edition of the references listed below unless otherwise noted.
5 General
5.4 Location of substation and substation equipment shall comply with SAES-B-055.
Substations shall be located in non-classified areas as defined by SAES-B-068.
5.5.3 The following status conditions shall be displayed, but not limited to:
a) Loss of circuit breaker tripping supply (Minimum one alarm per bus)
b) Loss of switchgear protection supply (Minimum one alarm per bus)
c) Loss of circuit breaker SF6 gas pressure
d) Low circuit breaker operating air pressure
e) Power transformer combustible gas present
f) Power transformer pressure relief valve operated
g) Power transformer Buchholz relay alarm
h) Power transformer Buchholz relay trip
i) On load tap changer oil flow relay trip
j) Power transformer high winding temperature
k) Power transformer loss of reference potential on Automatic Voltage
Regulator (AVR)
l) Power transformer loss of cooling fan supply voltage
Saudi Aramco: Company General Use
Page 6 of 21
Document Responsibility: Electrical Substations Equipment Standards Committee SAES-P-119
Issue Date: 1 January 2018
Next Planned Update: 30 July 2020 Substations
Alarms are equipment specific. Some substations will not have all of
these alarms, or may require more as deemed necessary.
5.6 Tap changer, automatic voltage regulator, protection and circuit breaker control
panels shall be located inside the substation building when associated equipment
is located in an outdoor transformer yard or switchyard (for example,
transformer with an automatic tap changer or outdoor circuit breaker).
Exception to 5.6:
Built-in control panels within the SF6 dead tank circuit breakers shall be installed
with the breakers outside.
6 Substation Buildings
6.2 Passageways shall have an unobstructed width of 1.12 meter and shall provide a
minimum 2.3 meter headroom.
The exterior cable buses should have the minimum bend angles as most
of bends angles should be accommodated inside the substation.
6.3.2 Cable buses shall not be routed through the space, shown as Space (y)
in Figure 1 and Figure 2, which is directly in front of the adjacent large
transformer containing more than 7,570 liter of insulated oil.
6.3.4 The elevation of the bottom of the lowest interior cable tray shall be a
minimum of 2.67 meter above the main substation floor.
6.4 Substation service-entrance and branch circuit feeders conductors other than
grounding conductors shall enter or exit through the building walls, and enter
the equipment from the top.
Exceptions to 6.4:
- GIS requires cable basement/cable entry room. AIS or controlgear, housed in the
same GIS building in the vicinity of 33 or 34.5 kV GIS, or in the adjacent building to
GIS housing auxiliary controlgear(s) and/or switchgear(s), are allowed for bottom
entry/exit.
6.5 Maximum substation building length and width shall be limited to 75 and 15
meters respectively.
Exception to 6.5:
6.6 Structural design calculations to verify the buildings blast design capacity shall
be conducted in accordance with SAES-B-014.
Commentary Note:
6.7 Substation interior and exterior lighting shall be provided as per SAES-P-123.
6.8 All interior substation lighting shall be fed from different buses of Secondary-
Selective low voltage switchgear.
Commentary Note:
6.13 Substation roof drainage shall not be to the transformer yard side of the
substation building.
6.14.2 The ground below the building shall be at or above finished grade.
6.14.4 Shall not drain to the transformer yard side of the substation building.
6.14.5 The side of the building adjacent to the transformer yard shall have a
solid wall (fire-rating the same as the building wall) that separates the
space from the transformer yard.
Commentary Note:
Note that paragraph 6.4 does not allow cable or electrical raceways to
enter/exit through the floor, except GIS installations as per exception to
6.4.
6.15 The concrete floor in front of switchgear shall be flush with the roller level of
lower breaker carriage rack and have a smooth surface to facilitate removal and
rolling of breaker. This floor area shall be surface hardened for rolling stock.
6.16 Underneath switchgear and controlgear, one of the following shall be provided
to ensure the equipment is maintained on an even plane:
6.16.2 The floor shall be horizontal in both planes with a maximum surface
height variation less than 5 mm per 3 meters.
6.17 Substation buildings shall have a minimum 2 hour fire rating and be constructed
in accordance with SAES-M-100, and where required by SAES-O-Series as
vital equipment.
6.18 A battery room and battery handling facilities shall be provided for stationary
batteries in accordance with SAES-P-103.
6.19 Circuit breaker testing facilities and operating tools shall be provided and
Since providing for future double-ending will require additional floor space,
this should be addressed in the design basis or project proposal documents.
6.21 Substation buildings shall have a telephone and data communications. This shall
include connection to the plant local area network. SAES-P-126 mandates a
dedicated (stand lone) Ethernet network for the power system automation.
6.22 Substation buildings shall have provisions for mounting and protecting as-built
key one-line diagrams for ready reference of operating personnel.
6.23 Substation buildings shall have smoke detection systems per SAES-B-014.
6.24 Substation buildings shall have Distributed Control System (DCS) Input/Output
(I/O) ports available. This shall be implemented either by remote I/O racks(s)
and/or DCS controllers within the substation. Design, installation, and
interconnection to plant DCS system shall be per the applicable SAES-J-Series.
6.25 Substation buildings housing 69 kV and above GIS and its adjacent building
housing auxiliary controlgear(s) and/or switchgear(s) should be constructed with
same elevation level as main building to avoid re-entrance corners or recessed
areas as per SAES-M-009.
6.26 The GIS building shall be constructed with an underground cable basement/cable
entry room as specified in TES-P-119.19 and TES-P-119.21. The building
basement floor shall be at least 1.0 meter above the ground water table level.
Exception to 6.26:
In areas with high underground water level, an elevated GIS building, without
basement/cable entry room, is allowed.
6.27 Substation buildings shall be provided with exit doors every 15 meters in the
long side wall, which is opposite to transformers side.
absorber before its release outside the substation building. The duct shall be
oriented in horizontal plane, and the exhaust shall be extended at least 2 meters
beyond the periphery of the switchgear. The duct outlet shall exhaust into a
restricted access area that shall extend a minimum of 3 meters directly in front
of the exhaust outlet and 1.5 meters to each side of the exhaust outlet.
7 Substation Yard
7.1.3 The intent of the above requirements is met by gate(s) which can be
opened to provide the required clearance.
7.2.1 For transformers containing 7,570 liters and less of insulated oil:
Clearance shall be per 7.1 above.
7.2.2 For transformers containing more than 7,570 liter of insulated oil:
a) Separation from buildings:
If the building has a fire rating; 6.1 meters or greater (Figure 1).
b) Separation from any other substation yard equipment, for
example, transformers, reactors, capacitor banks:
If no fire barrier or barrier fire rating is less than 1 hour: greater
than a minimum of 9.1 meters of clear space (Figure 2).
X
2 hours Firewall
Building
Building
Substation
2 hours Firewall
X
<X <X
Generic
Space (y)
2m
600 mm
1 hour Firewall
Building 2 hours
Substation
Firewall
300 mm
600 mm
2m
6.1m
6.1m
6.1m
9.1 m
Space (y)
6.1m
Figure 2
7.3.1 For power transformers up to 2.5 MVA no drainage is required and oil
containment shall be in the form of toe walls of sufficient height and
area to contain twice the oil volume of the transformer.
Exception to 7.3.1:
7.3.2 For power transformers 2.5 MVA and above, the following oil
containment/drainage system shall be provided:
a) Oil containment and drainage systems shall meet the general
requirements of IEEE Std 980 and the specific requirements of
SAES-S-020.
b) Oil containment systems shall be designed to withstand a
minimum 3 hours fire occurring within the bounds of the
containment system.
c) Oil containment shall be in the form of a concrete pit constructed
around the transformer foundation to contain 110% of
transformer oil. The perimeter of the spill containment shall be
located beyond the portion of the electrical equipment containing
oil, based on the height of bushing and conservator. The pit shall
be equipped with a steel grating covered with crushed rock to a
7.4 Transformer Neutral Ground Resister (NGR) shall be located in the substation
yard. NGR shall be constructed as per 14-SAMSS-531 and shall not be
mounted on a transformer.
7.5 Fire water system design shall be in compliance with SAES-B-017 and
SAES-B-019 for transformer, substation, and substation yard protection.
7.6 The substation yard shall be completely paved as a plant area in accordance with
the requirements of SAES-Q-006. The thickness of the combined asphalt layers
shall not be less than 10 cm.
Commentary Note:
The high surface resistivity of an asphalt-aggregate mixture under both wet and
dry conditions reduces the number of ground grid conductors required to obtain
safe step and touch potentials during ground faults.
7.8 Equipment located in the substation yard shall not be accessible from the roof of
the substation building.
Saudi Aramco: Company General Use
Page 15 of 21
Document Responsibility: Electrical Substations Equipment Standards Committee SAES-P-119
Issue Date: 1 January 2018
Next Planned Update: 30 July 2020 Substations
7.9.2 Outdoor units shall be equipped with self-closing covers which are
weatherproof when the covers are closed.
7.9.3 Outdoor receptacles shall be fed from a Ground Fault Circuit Breaker
with 5 mA trip or from Equipment Protection Device (EPDs) with
nominal 30 mA trip. Receptacles with integral ground fault protection
are not acceptable).
7.10 The Outdoor Substation switchyard (69 kV and above) shall be in accordance
with the following:
Commentary Note:
The Outdoor Substation construction is prohibited for new installations and only
allowed for expanding existing substations.
7.11 Exposed equipment insulators, except for surge arresters, shall have a minimum
leakage distance of 40 mm per kV line-to-line of the nominal system voltage.
7.12 Surge arresters shall be installed on systems with nominal operating voltages of
13.8 kV and above at the following locations:
7.12.1 At interface points between overhead lines, open bus, and underground
lines. This include open bus transition used to connect underground
cables to air type transformer bushings.
7.13.2 Surge arrester shall be of the composite insulation type with silicone
rubber compound external insulation over a hermetically sealed
fiberglass core.
8.2 The bus configuration of 33 or 34.5 kV GIS shall be single-bus with normally
open bus-section circuit breaker.
8.3 The mandatory requirements for selecting and configuring GIS bus designs for
substations operating at 69 kV or above are defined in Table 3.
Saudi Aramco: Company General Use
Page 19 of 21
Document Responsibility: Electrical Substations Equipment Standards Committee SAES-P-119
Issue Date: 1 January 2018
Next Planned Update: 30 July 2020 Substations
Commentary Note:
380 Breaker-and-a-Half S1
Breaker-and-a-Half S1
2-2-8 2-2-8 or 2-1-6
S2
Double-Bus-Single-Breaker Double-Bus-Single-Breaker
230
- Ring-Bus S3
- Radial-Bus S5
2-2-8 2-1-6
S2
Double-Bus-Single-Breaker Double-Bus-Single-Breaker
Ring-Bus Ring-Bus S3
69 to 132
- Inverted-PI S4
- Radial-Bus S5
Specific Note(s):
S1 Breaker-and-a-Half Configuration:
Spare bay breakers shall not be installed.
Layout shall accommodate future addition of necessary breakers to complete bay
configuration.
S2 Double-Bus-Single-Breaker Configuration:
(2-2-8) arrangement consists of two (2) sectionalizers, two (2) couplers,
and eight (8) disconnectors, or
(2-1-6) arrangement consists of two (2) sectionalizers, one (1) coupler,
and six (6) disconnectors configured in Z shape.
Bus sectionalizer and bus coupler shall be operated normally closed.
Redundant feeders or redundant power sources shall not be connected to the same
bus segment or connected to the bus segments connected by the bus coupler.
S3 Ring-Bus Configuration:
Redundant generation sources and redundant utility sources shall not be connected
to adjacent positions.
All breakers shall be operated normally closed.
The number of positions for onshore and offshore applications shall be limited to
four (4), and six (6), respectively.
Saudi Aramco: Company General Use
Page 20 of 21
Document Responsibility: Electrical Substations Equipment Standards Committee SAES-P-119
Issue Date: 1 January 2018
Next Planned Update: 30 July 2020 Substations
S4 Inverted-PI Configuration:
Limited to two (2) primary and two (2) secondary feeders.
No breakers shall be installed in the secondary feeders.
The bus coupler shall be operated normally closed.
S5 Radial-Bus Configuration:
Acceptable for substations dedicated to feed gas or oil production wellsites.
The configuration shall include spare incoming breaker for future alternate supply.
Revision Summary
5 November 2012 Major revision.
27 April 2014 Editorial revision to synchronize substation receptacle requirement with SAES-P-100
requirement.
17 February 2015 Minor revision by adding 600 mm dike between transformer fire wall and substation building
and detailing the grading and oil containment pits for power transformers.
30 July 2017 Major revision by revising substations bus configurations and mandate GIS modular design
for 33 kV and above, increase substation length, and other improvements.
1 January 2018 Editorial revision to modify paragraphs 6.6.