The document outlines the scheduled and actual handover dates for various floors in a building project, indicating delays for several floors. The 9th to 15th floors are scheduled for completion by June 30, 2025, but have significant delays, while the 16th to 21st floors have adjusted completion dates. Additionally, there are no final mechanical plans for the 26th floor and above, with testing and commissioning activities scheduled from September to December 2025.

Uploaded by

Benjelou Breis
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
6 views1 page

2

The document outlines the scheduled and actual handover dates for various floors in a building project, indicating delays for several floors. The 9th to 15th floors are scheduled for completion by June 30, 2025, but have significant delays, while the 16th to 21st floors have adjusted completion dates. Additionally, there are no final mechanical plans for the 26th floor and above, with testing and commissioning activities scheduled from September to December 2025.

Uploaded by

Benjelou Breis
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

FLOOR LEVEL COMPLETION REQUIRED CEILING ALIGNMENT HANDOVER

FLOOR LEVEL ACTUAL DATE OF HANDOVER STATUS / REMARKS


SCHEDULE TO KECI PRIOR TO INSTALLATION OF FCU'S
July 11, 2025 (9F-11F) -24 Days for 9F-11F
9th Floor to 15th Floor June 30, 2025 June 17, 2025
July 30, 2025 (12F-15F) -43 days for 12F-15F
16F Handed over Date August 4, 2025
17F Handed over Date August 8, 2025
Supposed July 30, 2025 Ceiling alignment 18F Handed over Date August 19, 2025
16th Floor to 21st Floor Changed to July 30 2025
hndover 19F Handed over Date August 26, 2025
20F Handed over Date August 28, 2025
21F Handed over Date August 29, 2025
22nd to 25th Floor June 30, 205 No Ceiling Alignment Handover
Changed to August 30 2025
26th Floor No Final Mech Plan
27nd & 28th Floor No Final Mech Plan
Roof Deck No Final Mech Plan

8th Floor to 3rd Floor September 30, 2025

2nd Floor to Ground Floor October 31, 2025

Basement Areas (B1 to B3) October 31, 2025

Note: Testing and Commissioning Activty Schedule: September to December 2025