FLOOR LEVEL COMPLETION REQUIRED CEILING ALIGNMENT HANDOVER
FLOOR LEVEL ACTUAL DATE OF HANDOVER STATUS / REMARKS
SCHEDULE TO KECI PRIOR TO INSTALLATION OF FCU'S
July 11, 2025 (9F-11F) -24 Days for 9F-11F
9th Floor to 15th Floor June 30, 2025 June 17, 2025
July 30, 2025 (12F-15F) -43 days for 12F-15F
16F Handed over Date August 4, 2025
17F Handed over Date August 8, 2025
Supposed July 30, 2025 Ceiling alignment 18F Handed over Date August 19, 2025
16th Floor to 21st Floor Changed to July 30 2025
hndover 19F Handed over Date August 26, 2025
20F Handed over Date August 28, 2025
21F Handed over Date August 29, 2025
22nd to 25th Floor June 30, 205 No Ceiling Alignment Handover
Changed to August 30 2025
26th Floor No Final Mech Plan
27nd & 28th Floor No Final Mech Plan
Roof Deck No Final Mech Plan
8th Floor to 3rd Floor September 30, 2025
2nd Floor to Ground Floor October 31, 2025
Basement Areas (B1 to B3) October 31, 2025
Note: Testing and Commissioning Activty Schedule: September to December 2025