PLUMBING QUOTATION
FOR 7 STOREY BUILDING
From: Stephen Ndung'u
To: Joshua Murungi Date: 26th July 2025
# Item Unit Item Unit Price Total
1 Ground floor setting out 1 16,000.00 16,000.00
2 Ground floor manhole grease trap stormwater 1 34,000.00 34,000.00
3 Setting our point per floor 7 24,500.00 171,500.00
4 Marking & chasing 99 1,600.00 158,400.00
5 Piping work cold water 99 2,850.00 282,150.00
6 Internal drainage foul soil H20 99 1,650.00 163,350.00
8 Testing 99 1,800.00 178,200.00
9 Rasing main borehole 1 9,000.00 9,000.00
10 Droping main from tank 1 15,000.00 15,000.00
11 Main for hose reel line 1 9,000.00 9,000.00
12 Top roof drainage & piping work 1 5,500.00 5,500.00
13 Tank connection work 1 37,000.00 37,000.00
14 Storm water drainage from top roof 1 24,000.00 24,000.00
15 First floor drainage from above to septic 1 55,000.00 55,000.00
Subtotal 1,158,100.00
Fitting work
1 Water clocet (WC) 101 2,100.00 212,100.00
2 Wash Hand Basin (WHB) 101 1,800.00 181,800.00
3 Stop cork 101 310.00 31,310.00
4 Angle valve 210 110.00 23,100.00
5 Taps 300 130.00 39,000.00
6 Shower 98 600.00 58,800.00
7 Kitchen 98 1,100.00 107,800.00
8 Meter 98 400.00 39,200.00
9 Hose reel installation 6 3,000.00 18,000.00
Subtotal 711,110.00
Grand total 1,869,210.00
…..........................
Stephen Ndung'u
+254714263846