PROJECT PROFILE
Bill No. 01 Foundation Structural Work
SL Remar
Details Descriptions Unit QTY Rate Amount TK
No. ks
1. Cement BAG 84 550 46200
2. Sand CFT 198 80 15840
3. Base Stone CFT 396 220 87120
4. 16mm KG 1740 90 156600
5. 10mm KG 186 90 16740
7. Total Cost 322500
8 Cement BAG 16 550 8800
9 Sand CFT 37 80 2960
10 Stone CFT 74 220 16280
Short Column 16mm KG 437 90 39330
11 8mm KG 58 90 5220
12
13 Total Cost 72590
21. Cement BAG 50 550 27500
22. Sand CFT 118 80 9440
23. Stone CFT 235 220 51700
Grade Beam1
24. 16mm KG 995 90 89550
25. 8mm KG 354 90 31860
26. Total Cost 210050
27. Cement BAG 50 550 27500
28. Sand CFT 118 80 9440
29. Stone CFT 235 220 51700
Grade Beam2
30. 16mm KG 995 90 89550
31. 8mm KG 354 90 31860
32. Total Cost 210050
27. Cement BAG 18 550 9900
28. Sand CFT 43 80 3440
29. Stone CFT 86 220 18920
Septic Tank
30. Brick NOS 1860 15 27900
31. 10mm KG 360 90 32400
32. Total Cost 92560
Bill No. 02 Ground Floor Structural Work
33. Cement BAG 40 550 22000
34. Sand CFT 97 80 7760
35. Stone CFT 186 220 40920
36. Long Column 16mm KG 1048 90 94320
37. 8mm KG 50 90 4500
38.
39. Total Cost 169500
40. Cement BAG 67 550 36850
41. Sand CFT 167 80 13360
42. Stone CFT 313 220 68860
Drop Beam 16mm KG 995 90 26550
43. 8mm KG 354 90 31860
44.
45. Total Cost 177480
46. Cement BAG 66 550 36300
47. Sand CFT 323 80 25840
5” Wall
48. Brick NOS 18280 15 274200
49. Total Cost 336340
50. Cement BAG 132 550 72600
51. Plaster Sand CFT 646 80 51680
52. Total Cost 124280
53. Cement BAG 148 550 81400
54. Sand CFT 362 80 28960
55. 5” Slab Stone CFT 726 220 159720
56. 10mm KG 1812 90 163080
58. Total Cost 433160
59. Cement BAG 11 550 6050
60. Sand CFT 21 80 1680
61. Stone CFT 42 220 9240
Stair
62. 12mm KG 120 90 10800
63. 10mm KG 120 90 10800
64. Total Cost 38570
Bill No. 03 First Floor Structural Work
65. Cement BAG 40 550 22000
66. Sand CFT 97 80 7760
67. Stone CFT 186 220 40920
68. Long Column 16mm KG 1048 90 94320
69. 8mm KG 50 90 4500
70. 0
71. Total Cost 169500
72. Cement BAG 67 550 36850
73. Sand CFT 167 80 13360
74. Stone CFT 313 220 68860
Drop Beam 16mm KG 995 90 26550
75. 8mm KG 354 90 31860
76.
77. Total Cost 177480
78. Cement BAG 66 550 36300
79. Sand CFT 323 80 25840
5” Wall
80. Brick NOS 18280 15 274200
81. Total Cost 336340
82. Cement BAG 132 550 72600
83. Plaster Sand CFT 646 80 51680
84. Total Cost 124280
85. Cement BAG 148 550 81400
86. Sand CFT 362 80 28960
87. 5” Slab Stone CFT 726 220 159720
88. 10mm KG 1812 90 163080
90. Total Cost 433160
91. Cement BAG 11 550 6050
92. Sand CFT 21 80 1680
93. Stone CFT 42 220 9240
Stair
94. 12mm KG 120 90 10800
95. 10mm KG 120 90 10800
96. Total Cost 38570
Bill No. 04 2nd Floor Structural Work
65. Cement BAG 40 550 22000
66. Sand CFT 97 80 7760
67. Stone CFT 186 220 40920
68. Long Column 16mm KG 1048 90 94320
69. 8mm KG 50 90 4500
70. 0
71. Total Cost 169500
72. Cement BAG 67 550 36850
73. Sand CFT 167 80 13360
74. Stone CFT 313 220 68860
Drop Beam 16mm KG 995 90 26550
75. 8mm KG 354 90 31860
76.
77. Total Cost 177480
78. Cement BAG 66 550 36300
79. Sand CFT 323 80 25840
5” Wall
80. Brick NOS 18280 15 274200
81. Total Cost 336340
82. Cement BAG 132 550 72600
83. Plaster Sand CFT 646 80 51680
84. Total Cost 124280
85. Cement BAG 148 550 81400
86. Sand CFT 362 80 28960
87. 5” Slab Stone CFT 726 220 159720
88. 10mm KG 1812 90 163080
90. Total Cost 433160
91. Cement BAG 11 550 6050
92. Sand CFT 21 80 1680
93. Stone CFT 42 220 9240
Stair
94. 12mm KG 120 90 10800
95. 10mm KG 120 90 10800
96. Total Cost 38570
SL
Details Descriptions Unit QTY Rate Amount TK
No.
97. Ad mixer Chemical Litter 80 150 12000
Electrical
98. RFT 6060 120 727200
Work
99. Labor Shied QTY 1 20000 20000
100. Labor Bill SFT 6060 450 2727000
101. Total Cost 3486200
NO DESCRIPTION Cost
1. Foundation Structural Work 907750
2. Ground Floor Structural Work 1279330
3. First Floor Structural Work 1279330
4. 2nd Floor Structural Work 1279330
5 Additional work 3486200
6. GRAND TOTAL 8231940
LS 5% 8643537
Description Amount
102. Unit QTY Rate Remarks
s TK
103. Cement BAG 1610 550 885500
104. Sand CFT 5362 80 428960
104. Stone CFT 4827 220 1061940
105. Brick NOS 56700 15 850500
105. 16mm KG 10368 90 933120
106. 12mm KG 360 90 32400
107. 10mm KG 6342 90 570780
108. 8mm KG 1978 90 178020
109.
110. Total Cost 4941220