THAVAM CONSTRUCTION
Risiny lhove
                                                                                 641402.
                           No.7, CNK Complex First Floor, Kalangal Road, Sulur -
                                  E-mail: thavamconstructions@gmail.com
                                                                                       Mob: 99443 71888
     Er.A. SATHEESH KUMAR, DCE.,LBS
 Licensed Building Surveyor                                           Registration no. 1115/2023-24
 Construction & Promoters
                                                                                           Date:15.10.2024
     DETAILED CUM ABSTRACT ESTIMATE FOR PROPOSAL CONSTRUCTION (GROUND
     FLOOR) OF RESIDENTIAL BUILDING IN SF NO: 132/2B, SITE NO : 29 AT ANANDHAM
     NAGAR, APPANAICKENPATTI VILLAGE & PANCHAYAT.SULTANPET PANCHAYAT
                           UNION, SULUR TALUK,COIMBATORE DISTRICT.
 Client name:- Ms. PAVITHRA SELVARAJ
Mrs. RASATHISELVARAJ
Ground floor area= 814 SQ.FT/2600
TOTAL ESTIMATE AMOUNT:- 21,16,400/
SLN        DESCRIPTION
                                    NOS             B       D       QTY        UNIT   RATE        AMOUNT
 1 |EarthWork Excavation
      |inall soils except soft
       rock or hard rock Upto
       70" depth
                                      1   12    3       3       5     540)CFT               80        43200
 2     M Sand Filling in
       Foundation and
       Basement and
      Consolidation with
      water
                                          12    3       3   0.5           54|CFT            80         4320
 3     P.C.C1:4:8 for
      Foundation and Flooring
      using 40mm size HBG
      stone
                                          12    3       3   0.5           54\CFT           110         5940
4 R.C.C 1:1.5:3 Base
  |Concrete in Foundation
     using 20mm size HBG
     stone including
     |centering, shuttering and
     steel fabrication
     |materials                           12    3       3   1.5        162|CFT              160       25920
            Column(C'onerete in C.C
           |:5:3upto Basenent
            Using 20mm size HIBG
            stone including
           centering, shuttering and
            stecl labrication
                                                                            106|CFT   300         31680
             materials                          12           0.8
     ()     |Reilling in Iarth Work
                                                                           I600CFT    120         192000|
            in found:ation
     7 |P.CC:3:6below plinth                                                           160|       7269.6|
                                                      |17    1.3     0.3     45CFT
   |beam
 8 |Pinth BcamConcrcte in
           C.C1:1.5:3 using 20mn1
           size HBG stone
           including centering.
          |shuttering and steel
           fabrication materials                     117     0.8    1.5     140)CFT   160         22464|
           Brick Work in CM 1:6
           For Upto Basement
   using Ist Class wired
                                                                            281|CFT    240|       67392
   cutting bricks                                    117     0.8      3
10 Basement Filling with
           Pit Sand                                                         600CFT    160         96000
           Basement M Sand
                                                                    0.5     408|CFT   220         89705
           Filling for P.C.C                    1| 23.3      35
12 P.C.C 1:3:6 for
           Basement Flooring using
           |20mm size HBG stone
           with shuttering             1        1|23.3       35     0.5     408|CFT   180         73395
           GROUND FLOOR
           SUPER STRUCTURE
 13 Colunn Concrete in C.C
    |1:1.5:3 upto Roof Level
           using 2Omm size HBG
          stone including
          centering, shuttering and
          stecl fabrication
           materials                       12        1.3    0.8     13      162|CFT   200         32448
          |9" Brick Work in CM
           l:6using First Class
          Brick upto Roof Lcvel
          (all around)
                                                     120    0.9     10     1080|CFT
          |Deduction
14
          IMain door MD                              3.5     0.9|           22
          Door D                           3                0.9            113
          Windowv W                    1   5          3     0.9      4      54                   ucton
          Window WI                         )
                                                            0.9             16                   Omater
      Ventilator V                         2           2    0.9              7                HDate:
                                                                                                 Sus
                                                                               213
                                                                                867|CFT          95386.5
   I5 4.5" Partition Wall Brick
      Wotk n CM 1:4 usinp
         Iirst Css Bicks upto
        |oot level (all around)
                                                 10.6                    10    106|SFT
         DeducIoD
         Door D|                           2     2.5                            35
                                                                                71SFT      J80    12780
   l6 RC.Clntcl 5"Tk in c.c
       |:5:3 using 2Omm sizc
       ||BG stonc including
       centering, shuttering and
       steel fabrication
      |materials                                 117           0.8|    0.5      47|CFT     140     6552
  17 Pr0vision of Loft
       concrete in CM 1:2:4 in
       Bed RoOm, store &
      kitchen including
      shuttering & steel                         36        1.5                 54|SFT     120      6480
 18     R.C.Csunshade 3" Tk in
        C.C :1.5:3 using 20mm
      size HBGstone
      including centering,
      shuttering andstccl
      |fabrication on 9" brick
        work
                                       5             4                         40|SFT     240      9600
 19 R.C.C lintel 5"Tk in C.C
    1:1.5:3 using 20mm size
     HBG stone including
    centering. shuttering and
   stecl fabrication on 4.5"
   |brick work
                                               117       0.8          0.4      37|CFT     200      7488
20 R.C.Cin ground floor
  |Roof Slab 5"Tk in C.C
  |1:1.5:3 using 2Omm size
   HBG stonc including
   centering, shuttering and
   steel fabrication
                                   1   1| 23.3            35                  816|SFT     240    195720
21 R.C.C in ground floor, 1
   st floor Roof beam 12"
   Tk in C.C1:1.5:3 using
   20mm size HBG stone
  |including centcring,
   shuttering an
   labricatioct
                                               117       0.8          1.5|    140CFT      120    16848
                   Date:
           |Parapet Wall Brick work
           |in CM 1:6                                       0.8              281|CFT    I60      44928
     23        DunmyColun
            Conerete in C.C 1:3:6 in
            terrace floor including
            |centering. shuttering and
            steel fabrication
                                               13          0.8                31|CFT    180       5616
 24 Column Concrete in C.C
            1:1.5:3 upto Roof Level
           using 20mm size HBG
           stone including
           ccntering, shuttering and
            steel fabrication
            materials                        3.05    105| 6.63      0.3|     639lCFT    160   102312.55|
 25 9" Brick Work in CM
    |I:6using First Class
           Brick upto Roof Level
           (all around)                              120   6.89 0,04         365|CFT
           Deduction
           Maindoor MD                                     3.5                25
          Door D                                                3    7            4
          Window W                       1                           4
          |Window W2                                            3    3
                                                                              88|SFT
                                                                            243/SFT    110     26755.3
26 Inncr Wall Plastering in
          CM 1:5 wall alround
       ground floor
      |hall                                    1     52                     520
      |kitchen/dining                                40             10|     400
      |bed 1                                         52|            10      520
      |bed 2                                         40             10       400|
          1oilet                         1           30             10      600
                                                                           2440 SFT
          Deduetion
                                         1     3      3                      63
                                                    2.5                      35
                                                                             21
          MD                                        3.5                      25
                                              5       3                      60
          WI
                                                                             18
                                                                              8
                                                                            230
                                                                            500|SFT    240     120000|
27    Outer wall single coat
       wall plastering in CM
           :S, 20mnm Thick
                                                    117    13              1521
      |Parapct inner wal
                      STruCto
      plastering                               1| 117       3
                                                                            351|
                                Date
                                                       1K7215FI     210)   393120|
 2% |ProvISion of Cuboard
     |wil kadlppa slab in
      bed &kitchen                                             S            40000
 29 |ProVISon ol kitchcn
     Comte slab                                               |LS           30000
30 |ProISIon of wooden
       sal/anchi windows
      witlh DooS & prill
        cudunp specal
     |nps.l:abours.
      materials etc..
                                        5          4    60
      wl                                           3     18
                                        2                 8
                                                        86\SFT      400     34400
31 Provision for main doors
   with I st quality tcak
      wOod Irames & Shutters
      main door                             3.5|   7    25SET       300      7350
32 |Provision for other d0ors
      with Ist quality teak
       wOod Frames cith Flush
     |Doors
                                             3     7    21
     |DI                                    2.5          18
                                                         39 SFT     400     15400
33 Providing, fixing and
      |laying in position of
      1Omm thk avitrified
     tiles of size 600mm x
     600mm of Navccn.
     |Khajaria or Johnson
     make, colour, shade and
     pattern as approved.
     |illing joints with ncat
     matching coloured
     cement slurry, complete
     with all labour and
      material. Basic cost of
     |tile-(a 50/Sft
                                                       470|SFT       40     18800
34     Whitewashing one coat
     primer and two coat
      asian emulsion paint
     |including inner and outer
     walls ceiling ctc., as per
     plastering mcasuencnts
                           cttion                       814 SFT      20|    16280
                                opote
                        Dater
                        Suhs
35     Provision of
      |Tlectritication
       Arangements(Polyecap.
     |Ancor.Kundanwirs &
      ancOr swilches)
                                                     814|SFT                 20|     16280
36 |Provision for sanitary &
     plumbing arrangements
     (hindware & neyeer
     |Iitting)|Cpvc for
     consiled pipe line &
     |Upve for outer pipe
      jlinc)(finolex & supreme
     pipes)
                                                     814|SFT             20          16280
37 Under ground sump &
   |septic tank                                    4000|lit                          80000
 38|Provision of rain water
     harvcsting pit                                      LS                          40000
39 Over head water Sintex
     tank
                                                   z000|it               20          40000
                                                                                     26290
                                 GRAND TOTAL                                       2116400
RUPEES- TWENTY ONE LAKHS SIXTEEN THOUSAND FOUR HUNDRED ONLY
                                             A
                                        Er. A. SATHEESH KÚMAR DCE,LBS
                                       Thavam Construction & Prorhoters
                                        Noi7.CNK Complex,    First Floor,
                                       KaliRoad,  Sulur, Cotmbatore-641402
                                               Cell:- 9944371888
PLAN SHOWING THE PROPOSED CONSTRUCTIONOF RCC R00F RESIDENTIAL.
BUILDING (GE) IN SF. NO: 132/2B,SITE NO: 29 AT ANANDHAM NAGAR.
 APPANAICKENPATTI VILLAGE AND PANCHAYAT, SULTANPET PANCHAYAT
UNION, SULUR TALUK, COIMBATORE DISTRICT
APPLICANT : Ms. PAVITHRA SELVARAJ
           Mrs. RASATHISELVARAJ
                                                            35
                  9-3"                                           23'-3"                           2-6"
                                                                                                            2'-6"
                                                 KITCHEN                        BEDRMOM
                                                                                  111'
                                                  10'"10'
                                 wll                               D                              |W
                                                                                     D1
                                W                                      TOILET
                                                                       5'6"*5
                                                                                     OLET
                                                                        D1
                                                  HALL
                                                 10"16'
                                                                                  EDROM
                                                                   D                              W
                                           MD
                                                PORTICO
                                                11'9"69"
                                                            ROAD
 SITE N0: 29
  AREA DETAILS:
 LANDAREA =1405 sg.ft
 BUILDING AREA
 GROUND FLOOR = 814 sq.ft
                                                                       EEA SATHEESH  KUMAR DCE,LBs
                                                                       Thm   Construction &Promoters
           THAVAM CONSTRUCTION
                                                                          N.7.CNK Complex, Pirst Floor,
                                         Rising Above                                 Cotmbatore-641402
                                                                                  Road, Sulur,
                                                                          KalangalCell:- 9944371888
               Er. A. SATHEESH KUMAR, DCE.,. LBS
                   CONSTRUCTION & PROMoTERS
            NO7,CNK COMPLEX, FIRST FLOOR. KALANGAL ROAD
                          SULUR-641402
                                                                                  Registration no. 1115/2023-24
                                                                          ENGINEER SIGNATURE