SMART HOME CONSTRUCTIONS
Building contractor:
Mohideen Meeran Yousuf
110A, 6th Street,
Eruvadi.
OwnerName:
Mr. Hameed Sha
Eruvadi.
Date:14/09/2023
AREA AND STRUCTURAL DESIGN
AREA:
House : A
Ground Floor = 945.00SQFT
First Floor = 467.00 SQFT
STRUCTURAL DATA FOR GROUND FLOOR:
Pillar:
Number of pillars based on the structural design - 14
Pillar Earth Excavation:
Length 4’0”
Breadth 4’0”
Depth 6’0”
40mm PCC concrete (1:4:8)
Length 4’0”
Breadth 4’0”
Depth 0’6”
Pillar bed 20mm RCC concrete (1:2:4)
Length 4’0”
Breadth 4’0”
Depth 1’3” (Steel bar 10mm) 6”c/c
Pillar rising 20mm RCC concrete (from PCC level to road level):
Length - 1’00”
Breadth -9”
Pillar Specification (Ø):
16mm – 4 numbers & 12mm – 2 numbers
8mm stir ups between 8” c/c
Earth preparation for Plinth Beam: (1:2:4)
Beam bed preparation width1’3” depth 1’0”.
40mm PCC Concrete width1’3” depth 0’6”.
Plinth structural beam size-9”X1’0” for complete structural area
Steelbarspecification(Ø)
12mm – 5 numbers
Necessary additional steel will be used for load balancing
Basement level:
Height 3feet from road level to basement level
9” Brick wall from plinth beam to damp proof course (DPC)
DPC concrete (1:2:4) with water proofing mechanism
Basement level refilling by gravel or crusher waste.
Earth embankment
40mm PCC concrete 1:4:8
Basement level to roof level:
Pillar shoe marking.
Pillar rising from plinth beam to roof level.
Brick wall construction till lintel level
Specification
Width-9”,
Height- 7’0”
Lintel level concrete
Specification
Width-9”
Height-6”
Steel bar specification (Ø) - 10mm/8mm
Brick wall construction from lintel level to roof beam (1:7)
Specification
Width-9"
Height- 1’6”
4½” brick wall in required places.
Roof and beam:
Beam specification
Width-9”
Height – 1’0”
16mm/12mm
8mm stirrups between8” c/c
Necessary additional steel–16mm(Ø) Roof
RCC Concrete (1:2:4):
Depth4½” 10mm/8mm 6”c/c.
Concealed beam12mm or16mm(Ø), stirrups-8mm 8”c/c.
Staircase concrete -12mm(or)10mmØ
Brick wall:
Parapet wall width 4½”, height3.0”
Plastering work:
Innerwall(1:5)
Ceiling(1:3)
Outerwall
Staircase bottom and side
Parapet wall
Other necessary places
Cement plastering thickness12mm/ 18mm.
Flooring work:-
Ground floor and First floor inner flooring area tile
specification Type - Marbonite
Size-2x2 (OR) 4x2
Price Range - Rs.45 to 50
Restroom wall tile
Height - 7 feet
Size-10”/15” (OR) 12”/ 18”
Price range– Rs.35 to Rs.40
Rest room flooring grip
tiles Size - 1/1.
Stair case steps grip tile
Shelf and lintel slab:
RCC lintel slab (Loft) with inner shelves width 1’6”x3”.
Lintel slabs will be constructed based on client requirements.
Wood and Grill:
Main door 1 numbers 7’0”x3’6”
Inner door 4 numbers 7’0”x3’0”
PVC door 2 numbers 7’0”x2’6”
Window wood door UPVC 6 numbers 4’6”x3’3”
Kitchen(W)wood door UPVC 1 numbers 3’0”x3’3”
Ventilation 2 numbers 1’6”x2’0”
Head Room Steel Door 1 numbers 7’0”x3’0”
Kitchen:
Kitchen slab – Granite stone
Kitchen shelves- RCC slab or Kadapa stone
Stainless steel (ss) sink 24”x18”
Storage shelf –RCC Slab or Kadapa stone
Plumbing and Sanitary ware Details:
Kitchen
Tap–1
Water purifier–1
Restroom
Tap–2
Health faucet–1
Shower – 1
Western or Indian closet –1
Dining
Washbasin–1
Overhead tank
PVC tank – 1
Capacity–1000liter
Material Specifications:
Cement (ISI Standard) - Sanka rbrand
Steel - (ISI Standard)
Vitrified & Bathroom Tile ISI Standard
Electrical Switches - (ISI Standard)
M.Sand First Quality
Lime First Quality
Aggregate 40Mm First Quality
Aggregate 20Mm First Quality
Wood–
Notes:-
Measurement roof outer/outer will be taken after project
is completed
Now the material amount is increased than the
previous estimation so you will have pay extra
amount
Quotation and price validity only 6 month only.
AMOUNT FOR TOTAL BUILDING
FLOOR SQFT RATE AMOUNT
GROUNDFLOOR 945 2000 18,90,000/-
FIRST FLOOT 467 1700 7,93,900/-
COMPOUND 20 1300 26,000/-
WALL(RUNNING
FEET)
COMMON BATH 81 1800 1,45,800
AND TOILET
OLD BUILDING
DEMOLISIHAND DISPOSE ----
SUMP (per liter – 25/-) ----
TOTAL 28,55,700/-
BuildingOwner: BuildingContractor
TERMS AND CONDITIONS:
Dear customers, our company will get the amount
based on the below conditions with part by part. If any changes in your
completed quotations (change in plan and accessories) you have the full
th
responsibilityfor the extra amount. This price for 6 month only
(15/07/2022to14/01/2023).
PARTS AREA PERCENTAGE AMOUNT SIGNATURE
OFAMOUNT
Part1 Basement level 30% 8,56,710/-
Part2 Basement level to roof 20% 5,71,140/-
level Brick wall
Part3 Roof Concrete to first 25% 7,13,925/-
floor brick wall and
parapetbrickwall
Part4 Inner, outer plastering 20% 5,71,140/-
, Inner flooring and
electrical,plumping
Part5 (Painting work) 5% 1,42,785/-
BuildingOwner: BuildingContractor: