INPUTS FOR CALCULATION OF PROJECT FINANCIALS
Yellow cells require data entry       Blue cells require only 'selection' from available                  All other cells are locked and no changes
                by user                                    drop-down list                                        can be made in the contents therein
                                                                       Contact Information
Customer's Name                           Temple Advertising                                   Sales Office
Address                                                                                        Sales Manager
City                                      Bangalore                                            Sales Contact Number
Pin Code
State
Customer Contact Person                                                                        Proposal Number
Customer Contact Number                                                                        Date of Proposal                                            3-Oct-09
                                                                             Project Details
WTG Model (Rating in MW)                                  1.25 MW                              Depreciation Benefit                    With Dep. Benefit
No. of WTGs                                                    1                               Commissioning Period                    October to March
Price per WTG                                              675 Rs Lacs
Total Project Size                                        1.25 MW
                                                                                               Est. rate for carbon trading (Rs. Per
Total Project Cost                                         675 Rs. Lacs                        unit of power)
                                                                                                                                                                      0.5
Est. Annual Generation per WTG                                 25 KWh (units Lacs)
                                                                                               Number of years CDM Available                                          10
O & M Price for 2nd year                                       12 Rs. Lacs
Annual Escalation in O&M Price from 3rd
year onwards
                                                           5%                                  Project Location (State)                Karnataka
                                                                                               Project Type                            Sale EB
                                                                                               Generation Based Incentive (GBI)        No
                                                                        Investment Details
Equity (%)                                                 30%                                 Loan Tennure (Years)                                              7
Borrowings (%)                                             70%                                 Moratorium Period                                                 1
Rate of Interest p.a. (%)                                13.0%
                                                 Summary of Project Financials for Wind Power Project Comprising of
                                                                 1 no(s) of 1.25 WTG in Karnataka
                                                                                                          Contact Information
Customer's Name                                                  Temple Advertising                                             Sales office                                                                  -
Address                                                                                                           -             Sales Manager                                                                 -
                                                                                                                  -                                                                                           -
City                                                             Bangalore                                                      Sales Contact Number                       0
Pin Code                                                        0
State                                                                                                             -
Customer Contact Person                                         0                                                               Proposal Number                            0
Customer Contact Number                                         0                                                               Date of Proposal                                                  03-Oct-09
                          IRR & Payback Calculations                                                                                                                    Basis for Calculations
     1       Equity (Promotor's Contribution)                                     202.5 Lacs               30%                  Project Life Cycle Period                                                                             20 Years
     2       Borrowings (Bank Loan)                                               472.5 Lacs               70%                  WTG Model (Rating in MW)                                                                           1.25 MW
     3       Project Investment (1+2)                                             675.0 Lacs                                    Total Project Size                                                                                   1.3 MW
             Life cycle expenses (O&M,
     4                                                                            421.8 Lacs                                    No. of WTGs                                                                                            1
             Insurance)
     5       Interest on Loan                                                     230.1 Lacs                                                                                                                                            (kWh
                                                                                                                                Estimated annual power generation per WTG in Units                                               25.00 units)
             Expenses over Project Life                                                                                                                                                                                                (Lacs)
     6                                                                            651.8 Lacs
             Cycle (4+5)
             Estimated revenue from sale of                                                                                                                                                                                                Rs Per
     7                                                                         1,700.0 Lacs                                     Est. rate for carbon trading (Rs. Per unit of power)                                               0.50
             power                                                                                                                                                                                                                         Unit
             Gain from Tax Saving due to
     8                                                                            224.3 Lacs                                    Project Type                                                                                 Sale EB
             depreciation
             Estimated additional revenue from                                                                                                                                                                                             Rs Per
     9                                                                            112.5 Lacs                                    Prevaling Power Purchase Tariff (for sale to EB)                                                   3.40
             Carbon Trading                                                                                                                                                                                                                Unit
             Estimated revenue over Project                                                                                                                                                                                                Rs Per
    10                                                                         2,036.8 Lacs                                     Prevaling Cost of Power (for captive project)                                                        NA
             Life Cycle (7 + 8 + 9)                                                                                                                                                                                                        Unit
             Net Gain over Project Life Cycle                                                                                   Cost of power generation from wind power project (Avg.                                                     Rs Per
    11                                                                            710.0 Lacs                                                                                                                                       2.59
             (10-(3+6))                                                                                                         over project life cycle)                                                                                   Unit
    12       Equity IRR                                                        12.05%                                           Estimated savings in power expenditure per unit (%)                                                  NA
    13       Project IRR                                                       12.53%                                           Rate of Interest p.a. (%)                                                                          13%
    14       Project Payback                                                         5.5                                        Loan Tennure including moratorium (Years)                                                              7 years
             Weighted average DSCR for the
    15                                                                             1.16 : 1                                     Moratorium Period                                                                                      1 years
             period of loan repayment
                                                                                                                                O & M Price for 2nd year (1st year O&M is free. Annual
                                                                                                                                                                                                                                 12.00 Rs Lacs
                                                                                                                                Escalation in O&M price of 5 % from 3rd year onwards)
                                                                                                                                                                                                                          October to
                                                                                                                                Commissioning Period
                                                                                                                                                                                                                              March
Disclaimer
The above data is only indicative of the returns on investment in a typical wind power project. The actual financial could vary depending upon changes in project parameters. This statement does not warrant accuracy / completeness of the data or
calculations. There is no explicit / implicit warranty associated.
                                                                                                                                                                                                                        (Feasibility Report)
                                          Rs Lacs/WTG Rs Lacs
              COST BREAK UP                                                                   Size of Project                     1.25                       Number of WTGs                            1                    State of Installation                                            Karnataka
Cost of Land                                     15.00           15.00                     Loan                        70%         472.50        472.50                O & M (Rs. Lacs)                   12               Tarrif (i) (Rs.)              3.40
                                                                                                                                                                                                                                                                            Depreciation Rate                 80%
Cost of WTG                                     507.50          507.50                     Equity                      30%         202.50        202.50                Escalation                      5.0%                Escalation                    0.00
Erection & Commissioning Charge                 113.00          113.00                     Interest                    13%                                             Free O&M (Yrs)                      1               Tarrif (ii) (Rs.)             3.40
                                                                                                                                                                                                                                                                                Corp. Tax                    33.99%
Infrastructure Charges                           39.50           39.50                     Loan term                     7                                             Generation (kWh)                   25               Insurance                     0.50
Processing Fees                                   0.00            0.00                     Moratorium                    1                                             Losses                            0%                Serive Tax Rate            12.36%
Total Cost                                      675.00
Cost Per MW.                                     540.0
                                          Mar'10            Mar'11          Mar'12         Mar'13      Mar'14      Mar'15      Mar'16          Mar'17      Mar'18      Mar'19      Mar'20          Mar'21      Mar'22      Mar'23      Mar'24       Mar'25      Mar'26      Mar'27      Mar'28      Mar'29      Mar'30
                      Yr                       0                1              2              3           4           5             6             7           8           9            10             11          12          13           14          15          16          17          18          19             20
Receipts (Rs Lacs)
Power Tariff (Rs. / kWh)                                          3.40           3.40           3.40        3.40        3.40            3.40        3.40        3.40        3.40            3.40        3.40        3.40        3.40         3.40        3.40        3.40        3.40        3.40        3.40           3.40
Power Tariff (Rs. / kWh)                                          0.00           0.00           0.00        0.00        0.00            0.00        0.00        0.00        0.00            0.00        0.00        0.00        0.00         0.00        0.00        0.00        0.00        0.00        0.00           0.00
Receipt (Sale of Power)                                            0.0            0.0            0.0         0.0         0.0             0.0         0.0         0.0         0.0             0.0         0.0         0.0         0.0          0.0         0.0         0.0         0.0         0.0         0.0            0.0
Receipt (Sale of Power)                                           85.0           85.0           85.0        85.0        85.0            85.0        85.0        85.0        85.0            85.0        85.0        85.0        85.0         85.0        85.0        85.0        85.0        85.0        85.0           85.0
IT Benefit                                          89.7         107.7           21.5            4.3         0.9         0.2             0.0         0.0         0.0         0.0             0.0         0.0         0.0         0.0          0.0         0.0         0.0         0.0         0.0         0.0            0.0
Generation Based Incentive                                         0.0            0.0            0.0         0.0         0.0             0.0         0.0         0.0         0.0             0.0         0.0         0.0         0.0          0.0         0.0         0.0         0.0         0.0         0.0            0.0
CDM Benefit                                                        0.0           12.5           12.5        12.5        12.5            12.5        12.5        12.5        12.5            12.5         0.0         0.0         0.0          0.0         0.0         0.0         0.0         0.0         0.0            0.0
Total Receipts                                      89.7         192.7         119.0          101.8         98.4        97.7            97.5        97.5        97.5        97.5            97.5        85.0        85.0        85.0         85.0        85.0        85.0        85.0        85.0        85.0           85.0
Expenses (Rs. Lacs)
O&M                                                  0.0              0.0        12.0           12.6        13.2        13.9            14.6        15.3        16.1        16.9            17.7        18.6        19.5        20.5         21.6        22.6        23.8        24.9        26.2        27.5           28.9
Service Tax on O&M                                   0.0              0.0         1.5            1.6         1.6         1.7             1.8         1.9         2.0         2.1             2.2         2.3         2.4         2.5          2.7         2.8         2.9         3.1         3.2         3.4            3.6
Intrest on Loan                                      0.0             59.0        50.5           41.7        32.9        24.1            15.4         6.6         0.0         0.0             0.0         0.0         0.0         0.0          0.0         0.0         0.0         0.0         0.0         0.0            0.0
Insurance                                            0.0              0.5         0.5            0.5         0.5         0.5             0.5         0.5         0.5         0.5             0.5         0.5         0.5         0.5          0.5         0.5         0.5         0.5         0.5         0.5            0.5
Scheduling charges                                   0.0              0.0         0.0            0.0         0.0         0.0             0.0         0.0         0.0         0.0             0.0         0.0         0.0         0.0          0.0         0.0         0.0         0.0         0.0         0.0            0.0
Total Expenses                                       0.0             59.5        64.4           56.3        48.3        40.2            32.2        24.3        18.6        19.5            20.4        21.4        22.5        23.6         24.7        25.9        27.2        28.5        29.9        31.4           32.9
Yearly Cash Accrual                                 89.7         133.2          54.6           45.5        50.1        57.4          65.3          73.2        78.9        78.0          77.1          63.6        62.5         61.4        60.3        59.1        57.8        56.5        55.1         53.6           52.1
Cumulative Cash accrual                             89.7         223.0         277.6          323.0       373.1       430.5         495.8         569.1       648.0       726.0         803.1         866.7       929.2        990.7      1050.9      1110.0      1167.8      1224.3      1279.4       1332.9         1385.0
Loan Repay                                                        67.5          67.5           67.5        67.5        67.5          67.5          67.5        33.8         0.0           0.0           0.0         0.0          0.0         0.0         0.0         0.0         0.0         0.0          0.0            0.0
Profit Before Tax                                   -17.4         -9.3          -1.8            6.3        14.4         22.4            30.4        38.4       44.1        43.2          42.2          28.7        27.7         26.6        25.4        24.2        23.0        21.6        20.2         38.3           52.1
Depreciation (As per A/c Stnd.)                      17.4         34.8          34.8           34.8        34.8         34.8            34.8        34.8       34.8        34.8          34.8          34.8        34.8         34.8        34.8        34.8        34.8        34.8        34.8         15.3            0.0
Cumulative cash Inflow                               89.7        155.5         142.6          120.5       103.1         93.0            90.8        96.6      141.7       219.8         296.8         360.4       423.0        484.4       544.7       603.8       661.6       718.0       773.1        826.7          878.8
                           ESTIMATED RESULTS
Equity Payback (Year)                                                                8.8
Project Payback (Year)                                                               5.5
                                      `
Cumulative cash Inflow (20 Years) (Rs. Lacs/ WTG)                             878.75
Internal Rate of Return (20 Yr.)                                              12.53%
D S C R (Debt Service Coverage Ratio)                                            1.16