QCS 2010
Section 19
Part 1
General
Page 1
1.
GENERAL ...................................................................................................... 2
1.1
INTRODUCTION ........................................................................................... 2
1.1.1
1.1.2
Scope
References
1.2
REGULATIONS AND STANDARDS.............................................................. 2
1.2.1
1.2.2
Qatar General Electricity & Water Corporation
Compliance with Standards
1.3
CONTRACTORS RESPONSIBILITY ............................................................ 2
1.3.1
1.3.2
1.3.3
1.3.4
1.3.5
1.3.6
General
Approval to Carry Out Plumbing Works
Registration of Plumbers and Plumbing Contractors
Notice of Intent
Existing Services
Maintenance Period Requirements
1.4
CRAFTSMEN................................................................................................. 3
1.4.1
1.4.2
Workmanship
Qualifications
1.5
MATERIALS................................................................................................... 3
1.5.1
General
1.6
DRAWINGS ................................................................................................... 3
1.6.1
1.6.2
1.6.3
1.6.4
Explanation of Project Drawings
Shop Drawings
Co-ordination Drawings
Record Drawings
1.7
SITE WORKS ................................................................................................ 4
1.7.1
1.7.2
1.7.3
1.7.4
1.7.5
Openings
Painting
Co-operation with other Trades.
Protection of Finish
Clean-Up
1.8
OPERATION AND MAINTENANCE MANUALS ............................................ 5
1.8.1
General Requirements
QCS 2010
2
2
2
2
2
2
2
3
3
3
3
3
3
3
4
4
4
4
5
5
5
5
5
QCS 2010
Section 19
Part 1
General
Page 2
1.
GENERAL
1.1
INTRODUCTION
1.1.1
Scope
This Section specifies the requirements for the construction and installation of all works
associated with the supply, storage and distribution of potable water, with the exception of
those works normally undertaken by the Qatar General Electricity & Water Corporation
(QGEWC).
1.1.2
References
Related Sections are as follows:Section 1
Section 9
General
Mechanical and Electrical
1.2
REGULATIONS AND STANDARDS
1.2.1
Qatar General Electricity & Water Corporation
The Contractor shall conform to all the requirements of the Rules and Regulations for
Plumbing Works as prepared by QGEWC.
1.2.2
Compliance with Standards
It is required that certain products, components and materials covered in this Section comply
with the provisions of particular standards (e.g. British Standards). Where there is a conflict
between a particular referenced standard and the requirements of QGEWC, the latter shall
prevail.
The Contractor shall conform to any requirements QGEWC may have with respect to
ensuring that products, components and materials comply with any referenced standard.
Such requirements may include, but not be limited to, samples, test results and supporting
documentation.
1.3
CONTRACTORS RESPONSIBILITY
1.3.1
General
The Contractor is responsible for obtaining all necessary approvals and permits required to
complete the Works.
1.3.2
Approval to Carry Out Plumbing Works
Approval to carry out plumbing works must be obtained from QGEWC for new installations
and extensions or alternations to existing installations.
All approval procedures shall be as required by QGEWC.
1.3.3
Registration of Plumbers and Plumbing Contractors
All plumbers and plumbing contractors shall be approved by QGEWC.
All QGEWC water supply works shall be carried out by a contractor or sub-contractor prequalified and approved by the QGEWC. Proof of such approval shall be required in writing
QCS 2010
QCS 2010
Section 19
Part 1
General
Page 3
prior to the Works commencing on Site and the name of any sub-contractor to be used shall
be entered in the appropriate forms when the tender is submitted.
1.3.4
Notice of Intent
The Contractor shall notify QGEWC in writing at least 14 days prior to the commencement of
any plumbing works.
During the course of the Works, QGEWC or its nominated representative shall have full
access to the Works.
1.3.5
Existing Services
The Contractor is responsible for locating and identifying all existing services in the area of
the work or likely to be affected by the Work.
1.3.6
Maintenance Period Requirements
The Contractor is responsible for all the maintenance period requirements for all parts and
components of the Works covered in this Section. Such requirements shall include, but not
be limited to, the requirements of the Project Documentation and the manufacturers
recommendations.
1.4
CRAFTSMEN
1.4.1
Workmanship
Construction of each part of the Works covered in this Section shall be undertaken by
experienced craftsmen capable of performing the tasks allocated to them in a professional
and competent manner.
If required by the Engineer, the Contractor shall instruct craftsmen to demonstrate their ability
to perform tasks allocated to him.
1.4.2
Qualifications
Where the Project Documentation specifies that specialist craftsmen are required to
undertake a specific work task, the Contractor shall furnish the Engineer with copies of
qualifications pertinent to performing such work tasks for those craftsmen who will be
undertaking the work.
1.5
MATERIALS
1.5.1
General
All materials, components and products shall comply with the relevant provisions of Section
1, General, subject to the provisions of Clause 1.2.2 of this Part.
All materials, components and products shall be supplied by experienced and approved
manufacturers as designated in the Project Documentation and to the written approval of the
Engineer.
1.6
DRAWINGS
1.6.1
Explanation of Project Drawings
For purposes of clearness and legibility, the Project Drawings are essentially diagrammatic,
and although size and location of equipment are drawn to scale where possible, the
QCS 2010
QCS 2010
Section 19
Part 1
General
Page 4
Contractor shall make use of all data in all of the Contract Documents and shall verify this
information prior to and during construction.
2
Scale and figure dimensions are approximate and are for estimating purposes only. Before
proceeding with any part of the Work, the Contractor shall assume all responsibility for the
fitting of his materials and equipment to other parts of the Works.
All work not shown in complete detail shall be installed in conformance with accepted
standard practice and manufacturers recommendations.
All items shall be installed in a manner and in locations avoiding all obstructions, preserving
headroom and keeping openings and passageways clear. Changes shall be made to the
location of equipment and materials as may be necessary in order to accomplish this.
The drawings are essentially diagrammatic to the extent that many offsets, beds, traps,
special fittings and exact locations are not indicated. The Contractor shall carefully study the
drawings and premises in order to determine the best methods, exact locations, route,
building obstructions, etc., and shall install all apparatus and equipment in the available
locations.
Work indicated on drawings, but not mentioned in Specifications, or vice versa, shall be
performed as if specifically mentioned or indicated by both. Any supplementary labour or
materials required for a complete, approved, and properly operating installation shall be
furnished by the Contractor.
1.6.2
Shop Drawings
The Contractor shall prepare shop drawings for all parts of the Works to be installed or
constructed under this Section and submit them to the Engineer for approval. The shop
drawings shall include diagrams, illustrations, schedules, general arrangements of equipment
and appurtenances in relation to buildings and structures, method statements and details of
specialised installation and construction work.
1.6.3
Co-ordination Drawings
These shall be prepared by the Contractor to show how interdisciplinary work will be coordinated. The location, size and details of fixings, box-outs, ducts, holes, pipe chases and
plinths shall be shown on the detailed layout drawings which are co-ordinated with all other
work disciplines.
1.6.4
Record Drawings
The Contractor shall prepare Record Drawings of all works constructed or installed under this
Section. These shall be prepared as work proceeds. They shall provide a record of any
modification to materials and equipment, and to the layout, arrangement and installation of
the Works.
1.7
SITE WORKS
1.7.1
Openings
The Contractor shall co-operate with all trades in obtaining information as to openings
required in walls, slabs and footings for all piping and equipment. Sleeves shall be accurately
located and placed in forms before concrete is poured. Where several pipes pass through
floors in close proximity, the Contractor may provide a single framed opening in lieu of
individual sleeves. Framed openings shall be to the approval of the Engineer and shall be
provided with 100 mm high curbs, on all sides. The Contractor shall pay all extra costs for
cutting of holes as a result of incorrect, delayed or neglected locations of sleeves or frame
openings.
QCS 2010
QCS 2010
Section 19
Part 1
General
Page 5
1.7.2
Painting
All finished painting shall be done as specified in the Project Documents. All apparatus and
equipment, not specified otherwise, shall be provided with a shop prime coat. All exposed
ironwork, tanks pipes, and fittings without factory finish, including pipe hangers and rods shall
be primed and painted with one coat of black asphalt varnish suitable for hot surfaces.
Exposed pipe threads in bare or insulated piping shall be thoroughly cleaned and painted with
two coats of metallic paint or red lead.
1.7.3
Co-operation with other Trades.
The Contractor shall so organise work progress to harmonise with the work of all trades so
that work may proceed as expeditiously as possible. The Contractor shall be responsible for
the correct placing of the Works and the connection thereof to the work of all related trades.
1.7.4
Protection of Finish
The Contractor shall provide adequate means for, and shall fully protect, all finished parts of
materials and equipment against damage from whatever cause during the progress of the
work and until final completion. All materials and equipment in storage and during
construction shall be covered in such a manner that no finished surfaces will be damaged or
marred and all moving parts shall be kept perfectly clean and dry. All damaged or defective
work shall be replaced prior to applying for final acceptance.
1.7.5
Clean-Up
During the progress of work, premises shall be kept reasonably free of the debris, waste
materials and rubbish resulting from work carried out under this Section. Upon completion
and before final acceptance of the Works, all debris, temporary protective coverings, rubbish,
left-over materials, tools and equipment shall be removed from the Site. Exposed piping,
machinery and other apparatus shall be thoroughly cleaned of cement, plaster, paint and
other materials; grease and oil spots shall be removed with cleaning solvent. Surfaces shall
be carefully wiped and all cracks and corners scraped clean. Chromium or nickel plated
materials and equipment shall be thoroughly polished. The entire installation shall be left in a
neat, clean and usable condition.
1.8
OPERATION AND MAINTENANCE MANUALS
1.8.1
General Requirements
The Contractor shall prepare Operation and Maintenance Manuals for all mechanical,
electrical and electronic equipment installed under this Section.
Operation and Maintenance Manuals shall conform to the requirements of Clause 1.1.4 of
Section 9.
END OF PART
QCS 2010