HKIS (QSD) CPD
Topic : Contractors Pricing for Preliminaries
Speaker
: Mr. Paul K. L. Wong
(Director of Chinney Construction Co. Ltd.)
Date : 20th January 2011
Time : 7:00pm  8:30pm
Venue: Surveyors Learning Centre
Contractors Pricing for Preliminaries - Overview
1.
There is no hard and fast rules to price preliminaries.
2.
The purpose of this seminar is to cover the basic principles of
building up cost and eventually pricing for preliminaries.
3.
The speaker will share his experience in pricing preliminaries for
submitting tenders of building projects.
4.
A Sample Case will be discussed for compiling the preliminaries
cost (not exhaustive) of a sample building project.
Method of Pricing Preliminaries
1.
To allow % mark-up (based on similar previous projects) on the
estimated cost of the project.
2.
Build up the cost of preliminaries items (with significant cost
implication not covered in BQ/SOR) in detail.
Factors to be Considered When Pricing Preliminaries
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
Standard preliminaries items (See Sample Case)
Contract requirements
Statutory requirements
Payment method for preliminaries items
Maximum % of preliminaries stated in the tender documents
Type of Contract (Lump sum with or w/o quantities)
Contract period (and actual construction period)
Amount of LD (and EOT clause)
Reputation of the Employer and Consultants
Mode of Sub-contracting
Location of the Site
Ground condition
Market condition
Contractors resources, financial capability and workload
Contractors pricing strategy
Prices to be Included in Preliminaries or BQ/SOR
Prices for some items that may be included or absorbed in BQ/SOR.
Examples: 1. Items Included in BQ/SOR
Hoarding
ELS works
Some testing items
(e.g. water test for waterproofing and windows & performance test for curtain
walls, etc.)
Safety management
Attendance on NSC works
2. Contractors Pricing Practice
Mobile crane (included in the rates of structural steel works)
Scaffolding (included in the rates of ceiling works)
Wet cleaning (included in the rates of tiling works)
Payment Method for Preliminaries Items
1.
2.
3.
4.
5.
Initial cost (e.g. premium for insurances, set up cost for site offices, tower
crane, scaffolding, electricity and water, etc.)
Work related cost (e.g. setting out & levies, etc.)
Time related cost (e.g. watchmen & site management staff, etc.)
Removal cost (e.g. removal cost for site offices, tower crane, scaffolding,
electricity and water, etc.)
Stipulated payment terms for preliminaries items
Examples :Payment for the excess amount priced in those preliminaries items (e.g.
insurances) will be effected over the period of the Contract.
Payment for time and work related items will be effected as per the
proportion of the total value of the Main Contract Work.
No payment will be included in interim payment for those preliminaries
items with no amounts being inserted.
Preliminaries Items
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
Bond
Site Management
Setting out
Insurances
Levies
Site Cleaning
Plant
Safety Management
Environmental Management
Watchmen
Site Accommodation for Contractor
Site Offices for Employers Representatives
Transportation
* Entertainment and Other Expenses
Hoarding
Scaffolding
Water
Electricity
Testing and Sample
Other Items
* No such relevant preliminaries items in BQ/SOR
Preliminaries Items
1.
Bond
1. Performance bond or demand bond
2. Bond for Defects Liability Period (for the release of the Bond during the
Contract period)
3. Required in the Contract? (Yes / No)
4. 1% / 5% /10% / x% / fixed amount of Contract Sum
5. Up to the issuance of Certificate of Practical Completion / Substantial
Completion or Making Good Defects
6. Premium
7. Collateral
8. Tender Bond
Preliminaries Items
2.
Site Management
1. Full time site management staff required in the Contract (e.g. Project
Manager, Construction Manager, Site Agent, Project Co-ordinator,
Labour Officer, Graduate Engineer & Apprentice, etc.)
2. Other site management and clerical staff
3. Direct site labour
4. Site management staff during defects liability period
5. Quantity surveying staff during contract period and final account period
Preliminaries Items
3.
Setting out
1. To be subletted or done by Contractors in-house staff?
2. Land surveying (Initial setting out)
3. Setting out works (Levellers)
4. Surveying tools and equipment
Preliminaries Items
4.
Insurances
1. Contractor All Risk (CAR) Insurance and Employee Compensation (EC)
Insurance
2. To be effected by the Employer or the Contractor?
3. EC Insurance for NSC Works (to be effected by MC or NSC?)
4. Premium
5. Excess
6. CAR & EC Insurances during extended Contract period (Reimbursable?)
7. EC Insurance after Defects Liability Period
8. Professional Indemnity Insurance
Preliminaries Items
5.
Levies
1. Construction Industry Levy (0.43% (including 0.03% of Construction
Workers Registration Authority Levy) of Contract sum)
2. Pneumoconiosis and Mesothelioma Levy (0.25% of Contract sum)
3. HKCA levy (*0.03% (Contract sum  $120M  $1,000M) or *0.06%
(Contract sum $1,000M) of Contract sum of relevant Employer 
HKSAR, HKHA, HKHS, AA, MTRC, Ocean Park and Science Park)
* The indicated rates of levy are for building works contract.
Preliminaries Items
6. Site Cleaning
1. General site cleaning during progress of the Works
2. Wet cleaning
3. Final cleaning upon completion of the Works
4. Temporary refuse chute
5. Dumpling trucks
6. Trip ticket system
Preliminaries Items
7. Plant
1. Tower cranes (setting up, running and removal cost)
2. Material hoists (setting up, running and removal cost)
3. Passenger hoists (setting up, running and removal cost)
4. Concrete pump trucks
5. Trucks
6. Mobile cranes
7. Gondolas
8. Fuel
9. Small tools
10. Maintenance
Preliminaries Items
8. Safety Management
1. Safety audit at 6 months interval (* where the total no. of persons employed on Site 
100 or Contract sum  $100M) or safety review at 6 months interval (* where the
total no. of persons employed on Site = 50-59)
2. Safety Officer (*1 No. full Safety Officer where the total no. of persons employed on
Site  100)
3. Safety Supervisor (*1 No. full Safety Supervisor where the total no. of persons
employed on Site  20)
4. General labour for safety duty
5. Safety tools (e.g. safety gloves & safety labels, etc.)
6. Safety materials (e.g. temporary barriers & temporary lift shaft doors etc.)
7. Safety precaution (e.g. fire extinguishers & fire pumps (* 1 fire pump / 30m high) with
pipes for high rise buildings, etc.)
* Statutory requirements
Preliminaries Items
9. Environmental Management
1. Environmental Officer
2. Environmental Supervisor
3. Dust control
4. Noise control
5. Temporary site drainage system
6. Vehicle washing bay
7. Wastewater treatment system
Preliminaries Items
10.
Watchmen
1. Watchmen
2. Guard house
3. Handkey access control system
4. CCTV system
Preliminaries Items
11. Site Accommodation for Contractor
12. Site Offices for Employers Representatives
1. Site offices and facilities for Employers representatives (minimum
requirements in the Contract)
2. Site offices and facilities for Contractor (& Sub-contractors)
3. Site storage area
4. Office furniture and equipment
5. Temporary latrines
6. Re-location of site offices and site storage area
7. Off site bending yard and storage area
Preliminaries Items
13.
Transportation
1. Contract car or Contractors car
2. Shuttle bus (for remote site)
3. Car insurance and licence fee
4. Driver
5. Mobile phone (for driver)
6. Fuel
7. Maintenance cost of car
Preliminaries Items
14. Entertainment and Other Expenses
1. Work commencement ceremony, topping out ceremony & Lo Pan,
etc.
2. Petty cash (for staff messing)
3. Progress photos
4. Combined services drawings & as-built drawings, etc.
5. Others
Preliminaries Items
15. Hoarding
1. New hoarding or take over existing hoarding
2. Covered walkway, hoarding, gantry, signboard and lighting, etc.
3. Maintenance
4. Alter hoarding to suit site operation
5. Alter gantry to suit site entrance
6. Temporary hoarding for fencing off site works (mainly for A&A works)
7. Removal of hoarding
8. Reinstate existing paving
Preliminaries Items
16. Scaffolding
1. External and internal scaffolding
2. Safety nylon mesh
3. Timber or steel board for working platform
4. Safety catch fence
5. Safety canopy at hoists and passenger lifts
6. Scaffolding in lift shafts
7. Ceiling scaffolding
8. Temporary working platform
9. Special temporary propping (e.g. for transfer plate)
Preliminaries Items
17. Water
1. Temporary water meter
2. Temporary pipe works, water tank & pump, etc.
3. Maintenance
4. Water fee
5. Removal cost for temporary water supply
Preliminaries Items
18.
Electricity
1. Generator
2. Fuel
3. Temporary transformer room (  400A)
4. Temporary main switch board
5. Temporary lighting
6. Electricians
7. Maintenance
8. Electricity fee
9. Removal cost for temporary electricity supply
Preliminaries Items
19. Testing and Sample
1. Testing fee (e.g. concrete & reinforcement, etc.)
2. Testing equipment (e.g. concrete cube mould, slump cone &
curing tank, etc.)
3. Samples submission
Preliminaries Items
20. Other Items
Some other items that may be required in the Contract or
to suit the site conditions.
Examples :1. Condition survey
2. Temporary steel working platform
3. Show flats
4. Diversion of existing services
5. Temporary works for obtaining Occupation Permit
2. Contractor's Superintendents
Grand Total : HK$
6,504,000.00
A vera ge per month :
HK$
PM
HK$
HK$
HK$
HK$
HK$
HK$
HK$
HK$
880,000.00
448,000.00
352,000.00
912,000.00
720,000.00
688,000.00
416,000.00
406,500.00/m th
Rate
a . C o nstruction Perio d
Project Mana ger/ A PM
- Site Agent
- Genera l Forema n
- Fo rema n
- A. Foreman
- Building Services C o -o rdina to r (BSC o)/ ABSC o
- Senio r Q.S.
( Including for fina l account )
- Q.S.
( Including for fina l account )
$
$
$
$
$
$
$
$
55,000
28,000
22,000
19,000
15,000
43,000
35,000
26,000
16 mths
16 mths
16 mths
16 mths
16 mths
16 mths
16 mths
16 mths
1.0 nos.
1.0 nos.
1.0 nos.
3.0 nos.
3.0 nos.
1.0 nos.
0.0 nos.
1.0 nos.
15,000
16 mths
1.0 nos. A.Q.S.
HK$
240,000.00
- Project C o-o rdina tor
22,000
16 mths
1.0 nos. PC
HK$
352,000.00
- Site Engineer
22,000
8 mths
1.0 nos. SE
HK$
176,000.00
- Graduate Engineer
14,000
16 mths
0.0 nos.
HK$
- Ex-C ITA
3,500
16 mths
0.0 nos.
HK$
- Site C lerk
8,500
16 mths
1.0 nos. Clerk
HK$
- Store Keeper
8,000
16 mths
0.0 nos.
HK$
- Ama h
7,500
16 mths
0.0 nos. Amah
HK$
- La bo ur
12,500
16 mths
2.0 nos.
HK$
400,000.00
- Site Agent
28,000
12 mths 1.00 no s.
HK$
336,000.00
- Fo rema n
19,000
12 mths 1.00 no s.
HK$
228,000.00
HK$
220,000.00
- A.Q.S.
( Including for fina l account )
SA
GF
F
AF
Bs Co
QS
136,000.00
b. Ma intena nce Perio d
Allo wa nce fo r M PF, Do uble Pa y ets.
3. Setting Out
Grand Total : HK$
A verage per month : HK$
3,110,000.00
194,375.00/m th
Rate
a. Podium, External Works & C ar Park
- Inital Setting Out
- Senior Surveyor
- Leveller
- Survey Equipment
HK$
$
$
b. Super-structure ( Tow er Blocks )
- Initial Setting Out
- Senior Surveyor
10 mths
10 mths
- Survey Equipment
50,000.00
800,000.00
640,000.00
Included
4.0 nos.
4.0 nos.
1 Blk(s). HK$
1 Blk(s). HK$
900,000.00
720,000.00
HK$
- Leveller
A llowance for M PF, Double Pay ets.
20,000
16,000
20,000
9 mths
5.0 nos.
1 Blk(s). HK$
16,000
9 mths
5.0 nos.
1 Blk(s). HK$
Included
0%
N/ A
5. Levies
Grand Total : HK$
Average per month : HK$
210,781.25/m th
3,372,500.00
Rate
a. Allow
0.65%
(0.25%+0.40%) of Engineer's Budget for Pneumoconiosis and
Mesothelioma levy & C onstruction Industry Levy
(C WRA levy included in C below)
Engineer's Budget
$475,000,000.00
> Lift
> Electrical
> AC MV
> Fire Service
Sub-Total
475,000,000
Allow
0.65%
of Engineer's Budget
HK$
3,087,500.00
b. Allow
0.03%
of Engineer's Budget for HKC A
HK$
142,500.00
c. Allow
0.03%
of Engineer's Budget for C onstructio n Workers Registration Authority
HK$
142,500.00
Sub-Total : HK$
3,372,500.00
6. Site Cleaning
GCC 35 & 38
Grand Total : HK$
Average per month : HK$
4,662,940.00
291,433.75/m th
Rate
a. Site C leanliness
- Progress C leaning
> Tow er Blocks
> Podium & External Works + C ar Park Block
-
Hack Off of Floor Screeding
C leaning of Tiles
C leaning of Sanitary Fittings
Temp. Refuse C hute
$
$
15,000
15,000
16 mths
16 mths
15 lab.(s)
0 lab.(s)
1 Blk.(s) HK$
HK$
3,600,000.00
-
HK$
HK$
HK$
2.0 nos. HK$
91,540.00
225,000.00
995
46 m
- Tow er Blocks
15,000
1 mths
15 lab.(s)
1 Blk.(s) HK$
- > Podium, External Works & C ar Park
15,000
1 mths
0 lab.(s)
HK$
15,000
12 mths
0 lab.(s)
1 Blk.(s) HK$
1,555
24 floor
20.0 trucks
b. C learance of Site on C ompletion
c. General Labour (Defect Libilities Period)
- Tow er Blocks
d. Remove rubbish off site to dumping area (incl w aste disposal fee)
ditto for podium
e. Allow
0.50%
of C ontract Sum for Waste dumping
746,400.0
incl. In above
Grand Total : HK$
7. Plant
A verage per month :
B. Automatic Material Hoist
a.
4,352,400.00
HK$272,025.00/ mth
Rate
no(s). for each Tow er Block
 10
sto reys &
11 mths
 X 2 Tow er
- Set up a nd Dismantle (Rental)
> Initial set up & Erection
29,000
1.0 nos.
2 Blk.(s)
HK$
> Purchase new material hoist
70,000
0.0 nos.
2 Blk.(s)
HK$
58,000.00
-
> Test & C o mmissioning
2 Blk.(s)
Included
> C able
2 Blk.(s)
Included
> Disma ntle & Transportation
34,000
2 Blk.(s)
HK$
68,000.00
> Enclosed by tarpaulin
14,000
1.0 nos.
2 Blk.(s)
HK$
28,000.00
> Miscelleno us and Maintenance
15,000
1.0 nos.
2 Blk.(s) HK$
330,000.00
> Rental (Mast = 41m)
30,000
0.0 nos.
2 Blk.(s)
HK$
5,000
0.0 nos.
2 Blk.(s)
HK$
11,000
1,200
- Running C ost
> C limbing
( at each 3 flrs = 2 times / Blk )
> Test fo r Ditto
steel passagew ay
Footing
4 Blk.(s)
10 floor
1.0 nos.
2 Blk.(s)
Included
HK$
24,000.00
HK$
100,000.00
Sub-Total :
HK$
608,000.00
1.0 nos.
0 Blk.(s)
HK$
HK$
HK$
Sum
b. Pa ssanger Hoist
a.
11 mths
Rate
no(s). for each Tow er Block
 10
- Erection and Disma ntle
sto reys &
$
0 mths
400,000
 X 1 Tow ers
- Renta l
50,000
12 mths
1.0 nos.
0 Blk.(s)
- Hoist Operator
8,000
12 mths
1.0 nos.
0 Blk.(s)
Allowance for M PF, Double Pay ets.
0%
N/ A
7. Plant
Grand Total : HK$
Average per month : HK$
D. Tower C rane
a.
4,352,400.00
272,025.00/m th
Rate
no(s). for each Tow er Block
 10
storeys &
10 mths 
- Set up and Dismantle (Rental)
> Initial set up
210,000
1.0 nos.
2 Blk(s). HK$
420,000.00
> Foundation Support
170,000
1.0 nos.
2 Blk(s). HK$
340,000.00
> Test
11,000
280,000
1.0 nos.
2 Blk(s). HK$
560,000.00
115,000
1.0 nos.
2 Blk(s). HK$
230,000.00
> Rent
55,000
10 mths
1.0 nos.
2 Blk(s). HK$
1,100,000.00
> Tow er C rane Operator
22,000
10 mths
1.0 nos.
2 Blk(s). HK$
440,000.00
> Miscellenous and Maintenance
5,000
10 mths
0.0 nos.
2 Blk(s). HK$
> C limbing ( 1st time)
128,000
1.0 times
2 Blk(s). HK$
256,000.00
> C limbing ( 2nd to end = 6 times / Blk )
35,000
1.0 times
2 Blk(s). HK$
70,000.00
> Dismantle
( Including Mobilization )
( Including Delivery off Site )
> I-beam support frame
<100%>
<0%>
Included
- Running C ost
> Test for Ditto
0.0 nos.
Included
Sub-Total : HK$
E. Gondola
3,416,000.00
Rate
- Rental
1,800
- Testing C ertificate
- Install/ Dismantle
0 mths
0.0 nos.
1 Blk(s). HK$
900
0.0 nos.
1 Blk(s). HK$
900
0.0 nos.
1 Blk(s). HK$
Sub-Total : HK$
8. Safety Management
PRE 8.210
a.
b.
c.
d.
Safety Audit / Safety Review
( 2 times / year )
Safety Officer (2nos. required in the C ontract)
Assistant Safety Officer
General Labour
- Tow er Blocks
e. Tools
f. Safety materials for balcony and lift shaft 1000/ lift shaft, etc.
f. Safety Precautions
- Extinguisher
> Tow er Block
Grand Total : HK$
Average per month : HK$
2,260,200.00
141,262.50/m th
Rate
$
7,000
$
28,000
$
18,000
16 mths
16 mths
3.0 times
2.0 nos.
1.0 nos.
HK$
HK$
HK$
21,000.00
896,000.00
288,000.00
$
$
$
15,000
1,500
1,000
16 mths
16 mths
24 floor
2.0 nos.
1.0 nos.
4.0 nos.
1 Blk(s). HK$
<100%> HK$
1 Blk(s). HK$
480,000.00
24,000.00
96,000.00
550
10.0 nos.
24.0 sty HK$
132,000.00
15,000
1.0 tow er
0.0 nos. HK$
5,000
2.0 nos.
24.0 nos. HK$
240,000.00
Safety Offic erAssistant Safety Offic er
5% HK$
83,200.00
- Fire Pump w ith Pipe
> Tow er Block
Str opgs & Main roof W/ P
Allowance for M PF, Double Pay ets.
For
9. Environmental Management
Grand Total : HK$
Average per month : HK$
13,750.00/mth
220,000.00
HK$
HK$
50,000.00
50,000.00
HK$
HK$
HK$
<100%> HK$
50,000.00
70,000.00
-
Rate
a. Dust C ontrol
b. Noise C ontrol
c. Site Drainage System
- Dewatering
- Temporary C hannels & Drainage
d. Vehicle Washing Bay
e. Wastewater Treatment System
$
$
70,000
200,000
1.0 nos.
0.0 nos.
10. Watchmen
a.
b.
c.
d.
Watchman (day and night)
Guard House (Deliver from Godown)
Handkey Access C ontrol System
C C TV System
Grand Total : HK$
Average per month : HK$
Rate
$
23,000 19 mths
$
-
1.5 nos.
1.0 nos.
HK$
HK$
HK$
665,500.00
41,593.75/mth
655,500.00
10,000.00
N/ A
11. Site Accommodation for Contractor
Grand Total : HK$
Average per month : HK$
702,400.00
43,900.00/m th
Rate
a. Initial Set Up
- Set up Site Office
- C ontainer Office (initial)
- Delivery & collection charge
- C ontainer Office (Toilet)
- Delivery & collection charge
- Toilet accommodation (10+7WC , 12+7U, 9+7basin.)
- Relocate site office
- Other Equipment & Facilities
$
$
$
$
$
1,200
1,200
1,200
1,200
1,200
> Air C onditioner
4,000
> Office Furniture and stationery
5,000
> C omputer System (C lerk-1, QS-1, SA-1, BS-1, PC -1)
5,000
> Photo C opy Machine
> Fax. Machine
> Tel. Handset
- off site yard incl. elect. & w ater
HK$
HK$
HK$
HK$
HK$
HK$
HK$
216,000.00
10,800.00
7,200.00
19,200.00
2,400.00
62,400.00
50,000.00
HK$
40,000.00
HK$
80,000.00
6.0 nos.
HK$
30,000.00
8,000
1.0 nos.
HK$
8,000.00
3,000
1.0 nos.
HK$
3,000.00
600
8.0 nos.
HK$
4,800.00
10,000
3 mths
2 trip
16 mths
2 trip
180.0 m2
3 nos.
3 nos.
1 nos.
1 nos.
<allow >
10.0 nos.
16 mths
0 mths
HK$
11. Site Accommodation for Contractor
Grand Total : HK$
Average per month : HK$
702,400.00
43,900.00/m th
Rate
b. Running C ost
- Telephone Line & Fax line
200
16 mths
6.0 nos.
HK$
19,200.00
- Mobile Phone Monthly C harge
200
0 mths
0.0 nos.
HK$
> Site Agent
120
0 mths
0.0 nos.
HK$
> General Foreman
120
0 mths
0.0 nos.
HK$
> Site Agent
500
16 mths
1.0 nos.
HK$
8,000.00
> General Foreman
500
16 mths
1.0 nos.
HK$
8,000.00
> Foreman
500
16 mths
2.0 nos.
HK$
16,000.00
> Assistant Foreman
500
16 mths
1.0 nos.
HK$
8,000.00
> Project C o-ordinator
500
16 mths
1.0 nos.
HK$
8,000.00
> Watchman
500
16 mths
1.0 nos.
HK$
8,000.00
500
10 mths
1.0 nos.
1 Blk(s). HK$
5,000.00
HK$
50,000.00
HK$
38,400.00
- Pager to Site Staff
- Radio C ommunication System
> Tow er C rane
( Tower Block )
c. Dismantle and Reinstatement (allow lump sum)
d. Portable Toilet
1,200
16 mths
2.0 nos.
12. Site Offices for Employer's Representatives
Grand Total : HK$
Average per month : HK$
535,940.00
33,496.25/mth
Rate
a. Initial Set Up
- Set Up Site Office
- C ontainer Office (initial)
- Delivery & collection charge
- C ontainer Office (Toilet)
- Delivery & collection charge
- Toilet accommodation (3+1WC , 2U, 3+1basin.)
- Relocate site office
$
$
$
$
$
1,200
1,200
1,200
1,200
1,200
2 mths
2 trip
2 mths
2 trip
140.0 m
2 nos.
2 nos.
2 nos.
2 nos.
<allow >
b. Dismantle and Reinstatement existing pavement(allow lump sum)
HK$
HK$
HK$
HK$
HK$
HK$
HK$
HK$
168,000.00
4,800.00
4,800.00
4,800.00
4,800.00
50,000.00
-
c. Furniture & Equipment
- Air C onditioners
- Office Furniture and Stationary
- Photo C opy Machine
- Fax. Machine
$
$
$
$
4,000
1,000
6,500
3,000
12.0 nos.
HK$
48,000.00
120.0 m
<100%> HK$
120,000.00
1.0 nos.
<100%> HK$
6,500.00
1.0 nos.
<100%> HK$
3,000.00
39,000.00
- C omputer System
13,000
3.0 nos.
<100%> HK$
- Radio Pager
500
0.0 nos.
HK$
- Mobile Phone
3,000
3.0 nos.
HK$
9,000.00
- C amera
1,500
6.0 nos.
HK$
9,000.00
- Tel. Handset
600
2.0 nos.
HK$
1,200.00
- Telephone Line & Fax Line & Modem
200
16 mths
2.0 nos.
HK$
6,400.00
- Radio Pager
120
16 mths
2.0 nos.
HK$
3,840.00
- Mobile Phone Monthly C harge
500
16 mths
3.0 nos.
HK$
24,000.00
- C amera
300
16 mths
6.0 nos.
HK$
28,800.00
d. Running C ost
13. Transportation
Grand Total : HK$
Average per month : HK$
Rate
a. Employer's Representatives' Transportation
- shuttle bus
- C ontract C ar
- Insurance and Liense Fee
- Mobile Phone
$
$
$
140,000
20,000
3,500
2.00 yrs.
0.0 nos.
0.0 nos.
0.0 nos.
HK$
HK$
HK$
b. Running C ost
- Driver
- Fuel C onsumption
$
$
10,000
8,500
14 mths
14 mths
0.0 nos.
0.0 nos.
HK$
HK$
- Tunnel Fee
800
14 mths
0.0 nos.
HK$
- Mobile Phone Monthly Service
200
14 mths
0.0 nos.
HK$
- Maintenance Fee
1,000
14 mths
0.0 nos.
HK$
HK$
Allowance for M PF, Double Pay ets.
13%
14. Entertainment & Other Expenses
a.
b.
c.
d.
e.
C ommencement x 1 ; Lunar New Year x 1 ; Lo Pan x 2 ; Finish x 1
Petty C ash
Progress Photo
C ombined Services Dw g.
As Built Draw ing
Grand Total : HK$
Average per month : HK$
Rate
$
10,000
$
6,000
$
500
3.0 times
16 mths
16 mths
HK$
HK$
HK$
HK$
HK$
384,000.00
24,000.00/m th
30,000.00
96,000.00
8,000.00
150,000.00
100,000.00
15. Hoarding
> C atchfan
( Type 2 )
> C atchfan
( Type 1 )
> Hoarding maintenance and removal
> Additional 1 no. of Site Gantry
> Notice Board and Advertising
- New Erect
banner
Typ4 covered w alkway under footbridge construction
> Site Entrance Gate
Grand Total : HK$
Average per month : HK$
65,000.00
4,062.50/mth
$
$
$
$
Rate
3,850
4,750
850
25,000
0.0 m
0.0 m
0.0 m
1.0 nos.
HK$
HK$
HK$
HK$
25,000.00
$
$
$
$
20,000
20,000
10,000
250,000
1.0 nos.
1.0 nos.
0.0 m
0.0 blk
HK$
HK$
HK$
HK$
20,000.00
20,000.00
-
16. Scaffolding
Grand Total : HK$
Average per month : HK$
6,608,843.00
413,052.69/m th
Rate
a. 1 no(s). Tow er Blocks
-
HK$
Superstructure External - Double layer without safety net
Nylon Mesh (Double Layer)
Safety C atch Fence
Safety C anopy at Hoist & Passenger Lift
Bamboo Scaffolding in lift shaft
C eiling
Timber board for working platform
- Superstructure External - single layer without safety net
(6m x 6m)
$
$
$
$
$
$
$
34
15
165
5,000
42
120
95
160,000 m
9,000 m
1,800 m
1.0 nos.
1,050 m
888 m
800 m
1 Blk(s).
1 Blk(s).
1 Blk(s).
1 Blk(s).
1.0 nos.
1.0 nos.
1.0 nos.
HK$
HK$
HK$
HK$
HK$
HK$
HK$
26
0 m
1 Blk(s).
HK$
- Temporary w orking platform
HK$
5,440,000.00
135,000.00
297,000.00
5,000.00
44,100.00
106,560.00
76,000.00
200,000.00
b. Extra propping for transfer plate
230,000
0 Blk(s).
HK$
c. Temporary gutter around perimeter of tower block
30,000
0 Blk(s).
HK$
Allow
5%
Wastage
HK$
305,183.00
17. Water
Grand Total : HK$
Average per month : HK$
401,280.00
25,080.00/m th
Rate
a. Initial C ost
- Initial set up & maintenance
- Water Meter - W.S.D.
- Water Tank & Pump
- Vertical Pipe with Gate Valve
b. Running C ost
HK$
( Tower Block )
$
$
15,000
120
2 no
10,000
16 mths
47.0 m
200,000.00
Included
1 Blk.(s) HK$
30,000.00
2 Blk.(s) HK$
11,280.00
HK$
160,000.00
18. Electricity
Grand Total : HK$
Average per month : HK$
3,321,000.00
207,562.50/mth
Rate
a. Initial C ost
- Allow for Generator-60KVA(3,000/ M);125KVA(3,800/ M);220KVA(4,800/ M)
- Fuel, Oil and gas for ditto
- Main Sw itch Board
- Vertical C able
(400A x 1 cables x 2 sets)
Incl.
- Temporary Lighting
- Sub-Main Sw itch Board
- Temporary Transformer room/ C LP cable
> Deposit for Lighting C o.
$
$
4,800
15,000
$
$
800
12,000
- Electrician
15,000
- Riser
3,400
- Electricity C harges
24,000
5 mths
5 mths
3.0 nos.
3.0 nos.
47.0 m
24.0 flrs.
HK$
HK$
HK$
2 Blk(s). HK$
1 Blk.(s) HK$
HK$
HK$
72,000.00
225,000.00
200,000.00
75,200.00
288,000.00
200,000.00
N/ A
1 Blk.(s) HK$
480,000.00
2 Blk.(s) HK$
6,800.00
HK$
150,000.00
HK$
1,600,000.00
5% HK$
24,000.00
b. Running C ost
- Electricity for Bldg A (for Adjoining site) (Special C ontract requirements)
Allowance for M PF, Double Pay ets.
16 mths
12 mths
2.0 nos.
20. Other Items
NIL
Grand Total : HK$
Average per month : HK$
Contractors Pricing for Preliminaries  Submitting Tender
1.
Cost adjudication.
2.
Confirming preliminaries items to be priced with amounts.
3.
Allocating the price to relevant preliminaries items.
4.
Finalize the price of preliminaries by adjusting the amounts in
relevant preliminaries items.
Are you Capable to Price Preliminaries?
The following questions may help you decide.
1.
Are you able to work out or at least to read method statement?
2.
Are you able to work out or at least to read programme?
3.
Do you have good sense to find out risk items in Preliminaries?
4.
Do you have basic knowledge of building technology?
5.
Do you have basic knowledge of statutory requirements?
6.
Do you have good relationship with your project team?
7.
Do you have good relationship with sub-contractors and suppliers /
plant hirers?
8.
Have you updated yourself from working experience and learning?
9.
Are you able and willing to work overtime or even overnight?
END
(QUESTIONS & ANSWERS)
Thank you for your attendance!