Close Traverse
Close Traverse
INTRODUCTION
In the past, transits and theodolites were the most commonly used surveying
instruments for making angle observations. These two devices were
fundamentally equivalent and could accomplish basically the same task. Today,
the total station instrument has replaced transits and theodolite. Total station
instrument can accomplish all of the tasks that could be done with transits and
theodolite and do them much more efficiently. In addition, they also can observe
the distance accurately and quickly. Furthermore, they can make computation
with the angle and distance observations and displays results in real time. These
and many other significant advantages had made total stations the predominant
instrument used in surveying practice today. They are used for all types of
surveys including topographic, hydrographic, cadastral and construction surveys.
OBJECTIVES
The objectives for conducting the fieldwork of boundary survey (‘booking’) are:
1. To set out and conduct survey for the boundary of specified buildings
around Tandarason Resort & Country Club(TRCC) by open and closed
traverse.
2. Calculate the bearing and length of every side of traverse after finding
coordinates.
3. Calculate area of any traverse boundary after knowing length and bearing.
Step i: Generally,
Step ii:
Step iii:
Instrument then changes position from tripod B to tripod C: Press PWR to OFF
and move.
Step i:
Step ii:
f) The total station has been changed from TBM to tripod at point CP1.
g) At CP1 the total station is set to face left and angle (ANG) is pressed as the
previous reading of face right and ENT to confirm.
i) The distance is recorded.
j) The total station then sighted to the point at each corner of the building.
k) The value of X, Y, and Z is recorded for each point from the building.
Step iii:
l) Before changing point, the total station is sighted back to the prism at
TBM.
m) The face right is recorded from horizontal angle (HA).
n) The total station is sighted to the CP2.
o) The face left and face right are recorded from the horizontal angle from
CP1.
p) The distance is recorded.
q) Total station is moved to the CP2.
Step iv:
FRO TO DISTANC
STATIO
BEARING/ANGLE M LINE ST E COMMENTS
N
STN N (m)
FINAL
FACE FACE
MEAN BEARIN
LEFT RIGHT
G
A 271°13'
91°13' 58'' 12.0433
58''
B
C 238°40'22'' 58°40'22''
B 238°40'
58°40'22'' 13.5136
C 22''
198°26'
D 18°26' 27''
27''
C 198°
18° 26' 27'' 12.8631
D 26'27''
201°17'
E 21°17' 12''
12''
D 201°17'
E 21° 17' 12'' 18.6442
12''
E
17° 44' 7'' 197° 44' 7'' 31.5539
F
G 184° 4° 28' 17''
28'17''
F 184°28'
4° 28' 17'' 34.9146
G 17''
H 130° 54' 0'' 314° 54' 0''
G
310° 54' 0'' 130° 54' 0'' 37.2854
H
I 118° 39' 9'' 298° 39' 9''
H
298° 39' 9'' 118° 39' 9'' 29.4481
I
131°58' 311°58'
J
27'' 27''
J
276° 0'41'' 96° 0' 41'' 36.9226
K
L 46° 8' 9'' 226° 8' 9''
K
226° 8' 9'' 46° 8' 9'' 32.1604
L
166°41'
M 346° 41' 1''
41''
L 166°41' 346°41'
42.7968
M 41'' 41''
355°28' 175°28'
N
54'' 54''
M 175°28' 355°28'
30.4053
N 54'' 54''
O 328° 32' 1'' 148° 32' 1''
274°16'
P 94° 16' 42'' 12.0433
A 42''
B 271°11'
91° 11' 35''
35''
Tabulation of Data for the Clockwise Horizontal Angle Reading (after correction)
TO DISTAN
STATI FROM COMME
BEARING/ANGLE LINE ST CE
ON STN NTS
N (m)
FACE FACE FINAL
MEAN
LEFT RIGHT BEARING
I 118° 298° - (-
Total Correction:
= 91° 11' 35'' - 91° 13' 58''
= (-) 0° 2' 23''
= (-) 0° 0' 8.94'' per station
Autocad drawing of close traverse
DISCUSSION
According to (Kavanagh B. F., 2003) a total station is able to measure and record
horizontal and vertical angles together with its slope distances. Total station is
also capable to do the averaging multiple angle measurements; averaging
multiple distance measurements; determining horizontal and vertical distances;
X(easting), Y(northing) and Z coordinates; and determining remote object
elevations and distances between remote points. “Horizontal angles are usually
measured with a theodolite or total station whose precision can range from 1’ to
20’’ of arc. Angles can be measured between lines forming closed traverse,
between lines forming an open traverse, or between a line and a point to aid in
the location of that point” (Kavanagh B. F., 2003) .
B 198 26 27 198 26
58 40 22 238 40 22 – 13.5136
C 44.8
(- 0 0
D 198 26 27 18 26 27 17.88)
After summing up all the correction in each point, value of 00 ᵒ02' 23'' obtain
again as shown in the example below:
For the open traverse, surveys were conducted on each corner of the structure
we found in range area given which is from Raflessia building, lake, field,
bamboo chalet and up to mountain view motel. A total of 15 corners were
identified and measured. The x, y and z coordinate are jot down in reference to
the temporary benchmark. On the hand, a total of 12 buildings
Throughout these survey sessions, there were several errors or problems
faced during the fieldworks, however these problems were successfully rectified
with some solutions. Main issue we facing during the fieldwork is about weather.
Weather for 5 days at TRCC keep changing. Sometimes it was extremely hot and
sometimes it was pouring. When the weather was extremely hot especially in the
afternoon, we stop doing our work and take rest. Other than that, each of our
group take extra protection facing the hot weather by wearing sun block, hat and
drink a lot of water. Bad weather, which is rainy day, early morning in the
morning had caused the group to start the fieldwork (closed traverse) later than
planned. Supposedly, the work starts at 0600 and finish by 0900, instead of at
0800 and done at 1200, as we did. So, as soon as the work started, there are no
delay. All members were alert with their roles as planned on the night before.
Another problem we faced was the distance and area of survey. The distance
between point is too short. Because of the distance too short, another group
interfere in between our total station and prism causing reading cannot be taken.
Since our group were already half way through our surveying, we decided to wait
for the other group to finish first and causing us delay for about 1 and half hour.
Both open and closed traverse are highly applicable to the engineering
survey field. Close traverse is commonly used for boundary survey. Example of
closed traverse includes surveying for the boundary of a lake, or boundaries
which was set upon to bound a construction within. It is important to carry out
boundary survey in order to ensure that the construction area is within an
appropriate area and not clashing into some other individual’s property. The
characteristic of closed traverse is that we need to return to our original position
by the end of the survey. On the other hand, open traverse need not return to
the original survey position, thus it is more suitable for engineering works such
as highway survey where it is desired to survey an area which extends outwards
some distance from the temporary benchmark or starting point.
TASK 3: CONTOUR
INTRODUCTION
Surveyors and engineers most often use contours to depict relief. The reason is
that they provide an accurate quantitative representation of the terrain. A
contour can be defined as a line connecting points of equal elevation. Since
water assumes a level surface, the shorelines of a lake is a visible contour, but in
general, contours cannot be seen in nature. On maps, contours represent the
planimetric locations of the traces of level surfaces for different elevations.
In this survey camps, we use direct method to plot given area of Tandarason
Resort & Country Club(TRCC). This method performed by using a total station.
After the instrument is set up, the HI established and the telescope oriented
horizontally. Then, for the existing HI, the rod reading (foresight) that must be
subtracted to give a specific contour elevation is determined. Distance and are
observed electronically with total station instrument.
OBJECTIVES
METHODOLOGY
The area of contouring divided into 4 main parts which is main building of TRCC
(Raflessia building), field of TRCC, bamboo chalet and mountain view motel.
(b)The X, Y, and Z coordinates of the change point (where the prism holder was
setup) are calculated by using the total station.
(d)The TBM is then transferred to the new point then the ‘X, Y, and Z’ of point is
recorded
(e) The contouring is performed by placing the spot height at random. Thus, the
change points were located arbitrarily rounded the building area.
(h) These readings are combined and were plotted on D-Plot making contours.
(i) A detailed report is made containing all the information about the Contour
Survey.
RESULTS
DISCUSSION