DAILY REPORT
STUDENT: Asetre, Dwight Christian F.
COMPANY: Asia Brewery Incorporated
DEPARTMENT: Carbonated Soft Drinks (CSD)
DAY
DATE
DAILY TASK
NO. OF
WORKING
HOURS
Monday
18-Apr-16
Tuesday
19-Apr-16
Wednesday
20-Apr-16
Thursday
21-Apr-16
Friday
22-Apr-16
Introduction: about ASIA Brewery
Inc. (history,departments), mission
and vision, safety, rules and
regulations, department assigned:
CSD(Carbonated Soft Drinks)
Meet with the Department Head
(Engr. Nane Remulta), Supervisors
(Engr. Dexter Fernandez & Jan
Ryan Ching) and other employees,
CSD Tour (Cobra Production
Equipments); Lecture on Cobra
Production (Line 3); Fabrication
Works Familiarization
Bottled Water Department Tour
(Line 4); Project Management
Planning (Pipe/Equipment
installation plan) by Engr. Nane
Remulta; Plastic bottle production
using: Resin/Pre-formed bottles, and
Lecture on Bottled Water production
Stick/SMAW welding (proper
welding positions); Project Request
(PR) forms familiarization &
Material Acquisition; Grinder
Repair (by Sir Jan Ryan Ching)
Operation/ Project Approval:
Department Head Signatures;
Basic AutoCAD 2011 tutorial;
Familiarization of ABI future
projects, and Acetylene Cutting
Observation
DAY
DATE
DAILY TASK
NO. OF
WORKING
HOURS
Monday
25-Apr-16
Tuesday
26-Apr-16
Wednesday
27-Apr-16
Thursday
28-Apr-16
Friday
29-Apr-16
DAY
DATE
Project Visit (Utilities 2), and
Material Acquisition (flexible
grinding disc)
Familiarizing Pipe Standards;
Utilities 2 Project Visit and
Observation;
Plant Refrigeration Lectures
( Ammonia, Glycol, CO2 Storage);
Discussion on types of valves
(Check, ball, butterfly)
Research of standard: flanges and
symbols; Work Approval
Processing; Material Acquisition
Platform construction (Utilities 2
CO2 Storage); AutoCAD drawing
(Platform); Material Acquisition
Measuring actual dimensions of
platform (Utilities 2); Continuation
AutoCAD drawing (platform)
DAILY TASK
NO. OF
WORKING
HOURS
Monday
02-May-16
Tuesday
03-May-16
Wednesday
04-May-16
Thursday
05-May-16
Watching Air vent installation @
Soft H2O discharge; Continuation
of AutoCAD design of the platform
Lectures on Pipe & Flanges
Specifications; Lay outing
(Reducer)
AutoCAD
Tutorial (How to get pipe suction
and & discharge diameter); Lecture
about the steam pipes (slope, steam
trap, drip leg, thermal expansion on
pipes, rollers); Research pump
8
8
Friday
06-May-16
DAY
DATE
formula
Control room U2 (Utilities 2) visit;
Processing of work permit for
leaking piping (CSD)
DAILY TASK
NO. OF
WORKING
Monday
09-May-16
Tuesday
10-May-16
Wednesday
11-May-16
Thursday
12-May-16
Friday
13-May-16
DAY
DATE
HOLIDAY
Lay out ( Square to Round);
Processing Work permit for
installation of Reverse Osmosis
(R.O)
Material Acquisition for R.O (Dn
50 stainless pipes, Pneumatic
Valve)
Processing Work Permit for
installation of water level gauge &
spray ball (Bottled Water
Department Product Storage Tank)
Lay outing; Processing work permit
for installation of exhaust fan
(Bottled Water Department)
DAILY TASK
HOURS
8
8
NO. OF
WORKING
HOURS
Monday
16-May-16
Tuesday
17-May-16
Wednesday
18-May-16
Thursday
19-May-16
Installation of level gauge & spray
ball (Bottled Water Department
Product Storage Tank)
Continuation of the installation of
level gauge & spray ball (Bottled
Water Department Product Storage
Tank)
Continuation of the installation of
level gauge & spray ball (Bottled
Water Department Product Storage
Tank)
Installation of exhaust fan
Friday
20-May-16
Fabrication Works Aide
DAY
DATE
DAILY TASK
NO. OF
WORKING
HOURS
Monday
23-May-16
Tuesday
24-May-16
Wednesday
25-May-16
Thursday
26-May-16
Friday
27-May-16
Monday
30-May-16
Processing Work Permit (Installation
of Pipe for Recovery line, Filler
No.5 & 6 Bottled Water
Department); Observing (Welding
CO2 filter leaking); CO2 Filter
repair, Material Acquisition (10
pieces Dn 50 Stainless Steel Pipe)
AutoCAD; Installation of Pipe for
Recovery line, Filler No.5 & 6 Aide;
Material Acquisition (17 pieces Dn
50 Stainless Steel Pipe)
Installation of Pipe for Recovery
line, Filler No.5 & 6 continuation
Installation of Pipe for Recovery
line, Filler No.5 & 6 continuation;
Cutting Pipes Dn 50 (5 in.) for pipe
recovery line
Utilities 2 visit; Inserting drain valve
for CO2 Storage
Welding of scrap box: Storage tank
calculations/computations;
Discussion on thermal expansion on
steam pipelines; Roller and saddle
application on steam pipeline; Metal
standards
8
8
TOTAL NO. OF HOURS: 240
Certified by:
__________________
Department Head