ROYAL INSTITUTION OF SURVEYORS MALAYSIA
BUILDING COST INFORMATION CENTRE
ELEMENTAL COST ANALYSIS - Form 1
JOB TITLE:
CLIENT:
LOCATION:
TENDER DATE:
INFORMATION TOTAL PROJECT
Project and Contract Information
Contract:
Project Details and Site Condition:
Market Conditions:
Contract Particulars:
Type of Contract:
Cost Fluctuation:
Yes
No
Basis of Tender
Open/Selected
Bills of Quantities
Competition
Government
Bills of Appr. Quant.
Negotiated
Private
Sched. Of Rates/
Spec. & Drawings
Provisional Sum
RM
Prime Cost Sum
RM
Preliminaries
RM
Contingencies
RM
Contract Sum
RM
Serials
Contract Period Stip. By Client:
Contract Period Offered by Builders:
Number of Tenders Issued:
Number of Tenders Received:
ANALYSIS OF SINGLE BUILDING
Design/Shape Information
Accommodation and Design Features:
Areas:
Functional Unit:
Lower Ground Floor
m2
Ground Floor
m2
External Wall Area
Upper Floor
m2
Gross Floor Area
GROSS FLOOR AREA
m2
Usable Area
m2
Circulation Area
m2
Ancillary Area
m2
=
Storey Heights:
Internal Division
m2
GROSS FLOOR AREA
m2
Av. Below Grd. Floor
Floor Space NOT Enclosed
m2
At Ground Floor
Roof Area
m2
Above Ground Floor
(Structural & Plant Rooms)
Brief Cost Information
Contract Sums
RM
Functional Unit Costs
Provisional Sums
RM
excluding external works:
Prime Cost Sums
RM
Preliminaries
RM
being
of remainder
Contingencies
RM
being
Contract Sum
Contract Sums less Contingencies
RM
Competitive Tender List
RM
Int (jv)/L
Design/Shapes
Percentage of Gross Floor Area
(a)
Below Grd. Flr.
(b)
Single Storey
Construction
(c)
Two-Storey
Construction
(d)
(e)
3-Storey
Construction
- Storey
Construction
INSTITUTION OF SURVEYORS MALAYSIA
BUILDING COST INFORMATION CENTRE
ELEMENTAL COST ANALYSIS - Form 2
ELEMENT COST ANALYSIS - Form 2
SUMMARY OF ELEMENT COSTS
GROSS FLOOR AREA:
Total Cost
of Element
RM
1
Substructure
1A Piling
1B Work Below Lowest
Floor Finish
Group Element Total
2
Superstructure
2A Frame
2B Upper Floors
2C Roof
2D Stairs
2E External Walls
2F Windows & External Doors
2G Internal Walls & Partitions
2H Internal Doors
Group Element Total
3
3A
3B
3C
3D
Finishes
Internal Wall Finishes
Internal Floor Finishes
Internal Ceiling Finishes
External Finishes
Group Element Total
4
Fittings and Furnishings
5
5A
5B
5C
5D
Services
Sanitary Appliances
Plumbing Installation
Refuse Disposal
Air-conditioning & Ventilation
System
Electrical Installation
Fire Protection Installation
Lift & Conveyor Installation
Communication Installation
Special Installation
Builder's Profit & Attendance
5E
5F
5G
5H
5J
5K
Cost per m2
GFA
RM
Element
Unit
Quantity
Preliminaries Shown Separately
Element Unit
Rate
RM
5L
on Services
Builder's Work in Connection
with Services
Group Element Total
Sub-total exc. External Works,
Preliminaries and Contingencies
6
6A
6B
6C
6D
6E
External Works
Site Work
Drainage
External Services
Ancillary Buildings
Recreational Facilities
Group Element Total
Preliminaries
TOTAL (less Contingencies)
ARY OF ELEMENT COSTS
TENDER DATE:
Preliminaries Shown Separately
INSTITUTION OF SURVEYORS MALAYSIA
BUILDING COST INFORMATION CENTRE
ELEMENTAL COST ANALYSIS - Form 3
BRIEF SPECIFICATION
GROSS FLOOR AREA:
ELEMENT
1
Substructure
1A
Piling
1B
Work Below Lowest Floor Finish
Superstructure
2A
Frame
2B
Upper Floors
2C
Roof
2D
Stairs
2E
External Walls
2F
Windows & External Doors
2G
Internal Walls & Partitions
2H
Internal Doors
Finishes
3A
Internal Wall Finishes
3B
Internal Floor Finishes
3C
Internal Ceiling Finishes
3D
External Finishes
Fittings and Furnishings
Services
5A
Sanitary Appliances
5B
Plumbing Installation
5C
Refuse Disposal
5D
Air-conditioning & Ventilation System
5E
Electrical Installation
5F
Fire Protection Installation
5G
Lift & Conveyor Installation
5H
Communication Installation
5I
Special Installation
5J
Builder's Profit & Attendance on Services
5K
Builder's Work in Connection
with Services
TENDER DATE:
SPECIFICATION
External Works
6A
Site Work
6B
Drainage
6C
External Services
6D
Ancillary Buildings
6E
Recreational Facilities
BRIEF SPECIFICATION
SPECIFICATION