ADC & CKA-RYD Project: Projects' 2-Weeks Lookahead

This document provides a 2-week lookahead schedule for projects including the ADC & CKA-RYD Project. It outlines 22 activities with details on original start and finish dates, duration, and progress for the period between January 25th to February 8th 2017. The activities are grouped under blocks including Masonry, Civil Works, Earth Works, Electrical Works, and Service Building.

Uploaded by

smshaidr
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
127 views1 page

ADC & CKA-RYD Project: Projects' 2-Weeks Lookahead

This document provides a 2-week lookahead schedule for projects including the ADC & CKA-RYD Project. It outlines 22 activities with details on original start and finish dates, duration, and progress for the period between January 25th to February 8th 2017. The activities are grouped under blocks including Masonry, Civil Works, Earth Works, Electrical Works, and Service Building.

Uploaded by

smshaidr
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

ADC & CKA-RYD Project Projects' 2-Weeks lookahead

Rev. 0
17-Jan-17 09:46

Activity ID Activity Name Project Name Original Start Finish e January 2017 2017
Duration
25 01 08 15 22 29
%
Block M
Masonry 20 11-Jan-17 02-Feb-17 %

11-Jan-17
11-Jan- 20 11-Jan-17 02-Feb-17 %
GRND060 Lay Bricks for Ground Floor CKA Project-RY 20 11-Jan-17 02-Feb-17 %

Civil Works
Wo 26 08-Jan-17 06-Feb-17 %

08-Jan-17
08-Jan- 15 08-Jan-17 24-Jan-17 % 24-Jan-17,...
FiF460 Perform Curing for poured First Floor Columns CKA Project-RY 15 08-Jan-17 24-Jan-17 % Perform Cu...
FiF470 Perform Steel Works for First Floor Beams & Roof CKA Project-RY 10 08-Jan-17 18-Jan-17 % Perform St...

16-Jan-17
16-Jan- 2 16-Jan-17 17-Jan-17 % 17-Jan-17,...
GRND070 Perform formwork for Ground Floor Staircase CKA Project-RY 2 16-Jan-17 17-Jan-17 % Perform fo...

18-Jan-17
18-Jan- 2 18-Jan-17 19-Jan-17 % 19-Jan-17,...
GRND080 Pour Concrete for Ground floor Staircase CKA Project-RY 2 18-Jan-17 19-Jan-17 % Pour Concr...

19-Jan-17
19-Jan- 7 19-Jan-17 26-Jan-17 % 26-Jan-17,...
FiF030 Perform Formwork for First Floor Beams & Roof CKA Project-RY 7 19-Jan-17 26-Jan-17 % Perform Fo...

21-Jan-17
21-Jan- 15 21-Jan-17 06-Feb-17 %
GRND450 Perform Curing for poured Ground Floor Staircase CKA Project-RY 15 21-Jan-17 06-Feb-17 %

29-Jan-17
29-Jan- 2 29-Jan-17 30-Jan-17 % 30-Jan-1

FiF040 Pour Concrete for First Floor Beams & Roof CKA Project-RY 2 29-Jan-17 30-Jan-17 % Pour Con

Earth Works
W 65 12-Dec-16 25-Feb-17 %

12-Dec-16
12-Dec- 35 12-Dec-16 21-Jan-17 % 21-Jan-17,...
EW1000 Excavation work for Main Building ADC Project-RY 35 12-Dec-16 21-Jan-17 % Excavation...

16-Jan-17
16-Jan- 20 16-Jan-17 07-Feb-17 %
EW1060 Excavation work for Tunnel ADC Project-RY 20 16-Jan-17 07-Feb-17 %

22-Jan-17
22-Jan- 30 22-Jan-17 25-Feb-17 %
EW1010 Compact & Level the Surface for Main Building ADC Project-RY 5 22-Jan-17 26-Jan-17 % Compact & ...
EW1070 Excavation work for Service Building ADC Project-RY 30 22-Jan-17 25-Feb-17 %

28-Jan-17
28-Jan- 5 28-Jan-17 01-Feb-17 %
EW1020 Apply termite Control to the leveled surface of M.Building ADC Project-RY 5 28-Jan-17 01-Feb-17 %

Electric Works
Electrical 1 28-Jan-17 28-Jan-17 % 28-Jan-17,...

28-Jan-17
28-Jan- 1 28-Jan-17 28-Jan-17 % 28-Jan-17,...
FiF190 Install conduits for electrical wiring in roof for First Floor CKA Project-RY 1 28-Jan-17 28-Jan-17 % Install co...

Service Building 0 22-Jan-17 22-Jan-17 % 22-Jan-17,...

22-Jan-17
22-Jan- 0 22-Jan-17 22-Jan-17 % 22-Jan-17,...
MS1090 Service Building Works Initiation ADC Project-RY 0 22-Jan-17 % Service Bu...

Actual Work Critical Remaining Work summary Page 1 of 1


Remaining Work Milestone