INTERIM PAYMENT FORM NO                             DATED:
Contractor:
A.      DETAILS OF THE PROJECT
        Project:              Villa Ground+1                              Const.Started on:
        Owners Name:          Mr.                                           Completed on:
        Contract Sum Dhs.     0.00                                         Extention. up to:
B.      PAYMENT AMOUNT
     Gross Amount Certified        0.00%                                               Dhs 0.00
        DEDUCTIONS
     1. Amount recd. directly from owner                                               Dhs     0.00
     2. Retention till date                                                            Dhs     0.00
     3. Amount recd. from MRHE                                                         Dhs     0.00
        Total deductions                                                               Dhs     0.00
        Amount of this bill                                                            Dhs 0.00
        Less: Retention under this bill                                                Dhs 0.00
        Amount due for payment                                                         Dhs 0.00
C.      RETENTION MONEY
        Previous Amount of Retention Held                                              Dhs 0.00
        Retention on this payment                                                      Dhs 0.00
        Total Retention Held                                                           Dhs 0.00
D.      CONTRACTOR'S CERTIFICATION
        We certify that this claim is true and correct. Kindly release payment.
        Signed on behalf of the Contractor
E.      CONSULTANT'S CERTIFICATION
        We undertake that the actual percentage of this payment is checked & certified in accordance with
        the agreed schedule, specification and excuted work at site.
        We are responsible for any financial & legal implications on that.
        Signed on behalf of the Consultant                                           Date:
F.      OWNER'S SINGTURE                                                             Date:
                                 (FOR Engineering Department USE ONLY)
F.      MRHE File No.:
        MRHE Loan A/C No.:                                             MRHE Loan Amount:                Dhs.
G.      Engineering Department CERTIFICATION: We have checked the progress of work
                              and certify that amount of this claim is in order.
Signed on behalf of Engineering Department   Date:
                                                     MRHE/QP/156/QF/06
MRHE/QP/156/QF/06