Ep 19 00 00 02 SP
Ep 19 00 00 02 SP
1.          Introduction
            The majority of high voltage feeders on the RailCorp electrical network have a pilot wire
            protection scheme installed.
            Where there is a pilot wire scheme installed, then in addition to the schematic diagrams produced
            for the individual equipment at either end of the scheme, an overall "Pilot Wire Schematic"
            drawing is required to be produced.
            If an existing pilot wire scheme is being modified and there is not an existing pilot wire schematic
            drawing, then the project is responsible for producing a pilot wire schematic drawing.
            Where an additional substation is installed between two existing substations and hence the
            existing pilot wire scheme becomes two schemes there shall be a pilot wire schematic for each
            individual scheme. The project is responsible for producing the pilot wire schematics.
                 	   Current transformers (including CT's used for other protection schemes) with secondary
                      circuitry connection to the pilot wire relay. CT's to be shown in correct position and
                      polarity identified.
Voltage transformers
                 	   Pilot wire relays and associated test blocks, with all connections to the PW relay detailed
                      and referenced to the equipment schematic drawings.
            The following drawings provide examples of the typical content and layout to be included on the
            diagram:
Line Description
Authorisation:
Signature
Engineering Standard
EP 19 00 00 02 SP
PROTECTION SYSTEM
VOLTAGE NETWORK
Version 4.1
Disclaimer
This document was prepared for use on the RailCorp Network only.
RailCorp makes no warranties, express or implied, that compliance with the contents of this document shall be
sufficient to ensure safe systems or work or operation. It is the document users sole responsibility to ensure that the
copy of the document it is viewing is the current version of the document as in use by RailCorp.
RailCorp accepts no liability whatsoever in relation to the use of this document by any party, and RailCorp excludes
any liability which arises in any manner by the use of this document.
Copyright
The information in this document is protected by Copyright and no part of this document may be reproduced, altered,
stored or transmitted by any person without the prior consent of RailCorp.
Document control
Version                  Date                    Summary of change
                         June 2007               Last Technical Review
         4.0             May 2010                Application of TMA 400 format
         4.1             June 2012
                                                             Update list of Australian and RailCorp standards
                                                             Incorporate P543 & P124 standard test block
                                                              diagrams, input and output relay configuration
                                                             Incorporate a section on Rectifier transformer frame
                                                              leakage
                                                             Update Approved Protection Relay and incorporate
                                                              standard test block diagrams.
                                                             Update headings & numbering of section 6.2
                                                             Voltage transducer model changed to ISTAT 400
                                                              series.
                                                             Update Voltage transformer burdens
                                                             Incorporate a section for Voltage transformer for
                                                              11kV side of system transformers.
                                                             Update the metering requirements for 66, 33 &
                                                              11kV feeders
                                                             Added new appendix detailing metering
                                                              requirements for bulk supply locations.
                                                             Added new appendix detailing wire codes for CTs,
                                                              VTs and related equipment.
                                                             Incorporate 11kV overcurrent protection on system
                                                              transformers in ACCB Trip Coil table .
                                                             Incorporate a section for the Requirement for
                                                              capacity of batteries added.
                                                             Incorporate standard test block diagram for neutral
                                                              leakage protection.
                                                             Update Approved protection relays for new
                                                              switchboards.
 RailCorp                                                                                              Page 2 of 71
Issued June 2012                          UNCONTROLLED WHEN PRINTED                                      Version 4.1
RailCorp Engineering Standard  Electrical
Protection System Requirements for the High Voltage Network                                                                    EP 19 00 00 02 SP
Contents
1 Introduction .............................................................................................................................6
RailCorp Page 3 of 71
Documentation .........................................................................................24
RailCorp Page 4 of 71
Connection .............................................................................................................28
Appendix H Standard Test Block Wiring & Input/Output Relay Configuration ....................34
RailCorp Page 5 of 71
1              Introduction
               This document covers the Protection System requirements for the RailCorp High Voltage
               AC Network for 11kV, 33kV, 66kV and 132kV system voltages.
This document does not include protection requirements for the 1500V DC system.
               These protection requirements cover general design principles for protection schemes, as
               well as requirements relating specifically to the protection equipment. They do not
               include equipment used for detection and measurement of non-electrical protection
               parameters (such as oil and gas sudden pressure change, fibre optic temperature
               measurement), other than to specify necessary interface details.
               The correct design, implementation and management of the overall protection system are
               critical to the safe and reliable operation of the RailCorp power system. As such, all
               design processes for the protection system must follow the RailCorp Engineering Design
               Management Procedures.
               All new installations, modified and refurbished existing installations must comply with the
               requirements in this document.
               High voltage protection systems existing at the date of release of this document are not
               affected by the requirements of this document.
2              Normative References
               The following documents are either referenced in this standard or can provide further
               information. The edition is current at the time of publication of this document.
 RailCorp                                                                                       Page 6 of 71
Issued June 2012                          UNCONTROLLED WHEN PRINTED                               Version 4.1
RailCorp Engineering Standard  Electrical
Protection System Requirements for the High Voltage Network                                EP 19 00 00 02 SP
DC Direct Current
               Dedicated Pilot Cable A communication cable that is used only for the control, indication
               and pilot wire functions between two substations. The cable is continuous between
               substations.
IT Inter-trip
               Low Voltage Compartment The compartment on the high voltage switchgear where the
               protection relays, control equipment and wiring is installed. The compartment is usually
               accessed by a hinged door and does not require any isolation or operation of the
               switchgear for safe access.
 RailCorp                                                                                       Page 7 of 71
Issued June 2012                          UNCONTROLLED WHEN PRINTED                               Version 4.1
RailCorp Engineering Standard  Electrical
Protection System Requirements for the High Voltage Network                               EP 19 00 00 02 SP
               MTA Protection relay used for the multi-tripping of ACCBs. This is a automatically reset
               relay with a hand reset flag.
               MTM Protection relay used for the multi-tripping of ACCBs. This is a manually reset relay
               with a hand reset flag.
               Substation The following are locations within the RailCorp electrical network which are
               classified as system substations for the purpose of this document.
               2kV locations, RMU locations that have an ACCB for the transformer, pole top and other
               distribution substations that use HV fuses for protection are not classed as system
               substations.
4.1            General
               In designing the protection schemes for RailCorps high voltage network, the following
               general principles shall be applied:
               		 All high voltage faults shall be detected and able to be cleared by two independent
                   sets of protection (primary and backup). Either may be circuit breakers or fuses.
               		 The primary and backup protection schemes shall be independent. All HV circuit
                   breakers shall be equipped with dual trip coils.
               		 Where primary and backup protection is installed in the same substation, that
                   substation shall have two battery systems. Some substations are exempt from this
                   requirement. This exemption is based on risk exposure considering safety, operational
                   impact, economic and environmental considerations.
               		 The rated continuous thermal current of the CTs shall not constrain the rating of
                   associated power system elements.
               		 Primary protection shall be implemented using unit schemes wherever practical.
               		 The protection schemes shall be designed to eliminate or manage blind spots.
 RailCorp                                                                                     Page 8 of 71
Issued June 2012                          UNCONTROLLED WHEN PRINTED                             Version 4.1
RailCorp Engineering Standard  Electrical
Protection System Requirements for the High Voltage Network                                    EP 19 00 00 02 SP
4.2            P
               	 rotection Settings
               		 The protection shall be set to operate at not more than 2/3 of the minimum phase to
                   phase fault and not more than 2/3 of the minimum earth fault.
               		 The overcurrent protection settings shall, as far as practicable, be at least 1.5 times
                   the maximum load current.
               		 Fault clearing times shall be minimised.
4.3            G
               	 rading
               		 The protection shall be graded to ensure that the fault is cleared by the protection
                   closest to the fault, and the area of interruption is minimised.
               		 A 0.3 second grading margin shall be provided as far as practicable for protection in
                   series except that breaker fail timers shall be 0.2 second.
               		 Relay settings shall be, as far as practicable, at least 1.5 times the highest
                   downstream setting.
                      		 The primary and backup schemes shall use separate trip coils, one trip coil for
                          the primary scheme the second trip coil for the backup scheme. Refer to
                          Appendix B for standard trip coil arrangements and Appendix N for typical HV
                          switchboard arrangements.
                      		 The backup scheme (protection relay, trip coil control and supply) shall have its
                          auxiliary supply from a dedicated circuit originating at the distribution board.
               		 Where two DC auxiliary supplies are required (see Section 5.5) the primary protection
                   scheme is to be supplied by battery A and the backup protection scheme supplied by
                   battery B.
                      		 SCADA monitored trip circuit supply supervision with local indication shall be
                          provided for all tripping circuits. The TCS scheme shall monitor with the ACCB
                          in the open or closed position.
                      		 The auxiliary supply for each bus-zone protection scheme (protection and multi-
                          trip relays) shall have its auxiliary supply from a dedicated circuit originating at
                          the distribution board. Fuse protection and monitoring shall be provided with the
                          monitoring relay connected to the SCADA system.
                      		 Individual protection schemes to be connected to dedicated current
                          transformers.
 RailCorp                                                                                          Page 9 of 71
Issued June 2012                          UNCONTROLLED WHEN PRINTED                                  Version 4.1
RailCorp Engineering Standard  Electrical
Protection System Requirements for the High Voltage Network                                   EP 19 00 00 02 SP
               		 It is not economically feasible to install additional CTs (eg. Circuit breaker would have
                   to be replaced; additional post type CTs would be required.)
               		 The protection schemes are not the primary and backup protection for the same
                   equipment.
               		 A failure of the CTs will not result in a piece of equipment having no protection due to
                   an existing compromise in the protection system.
               		 The output of the current transformers shall be sufficient for the burden of all the
                   connected protection schemes and associated equipment to ensure each scheme
                   operates as required up to the available fault level.
5.2.4          Inter-trip
               If the breaker fail function is associated with a feeder that does not have a dedicated
               ACCB, then it is acceptable to implement an inter-trip by destabilising the pilot wire
               schemes of feeders that are a possible source of fault current. When destabilising the
               pilot wire schemes this must be implemented at the pilot wire relay.
               The CT shall be easily replaceable and shall be installed with polarity markings assuming
               supply from the bus in all cases. All secondary leads shall be terminated in individual
               links in the appropriate compartment where the CT is installed and the earth point formed
               by using a proprietary cross connection for the links being used. The CTs shall be
               earthed at one point. This single point earth is to be within the applicable LV
               compartment.
               CTs shall be rigidly clamped to prevent movement under short circuit conditions. They
               shall be provided with rating plates and terminal markings as specified in AS 60044.1.
               The rating plates shall be mounted in such a manner that they are visible, and the
               secondary terminals shall be readily accessible. Duplicate rating plates shall be mounted
               in the instrument compartment with connection diagram.
 RailCorp                                                                                        Page 10 of 71
Issued June 2012                          UNCONTROLLED WHEN PRINTED                                 Version 4.1
RailCorp Engineering Standard  Electrical
Protection System Requirements for the High Voltage Network                              EP 19 00 00 02 SP
               The majority of existing CTs installed in the RailCorps system has a rated secondary
               current of 5A. With the installation of GIS switchgear, the reduced space available for
               CTs has resulted in the necessity to install CTs with a rated secondary current of 1A.
               CTs shall safely withstand the mechanical and thermal stresses set up by a short circuit
               equal to the full short circuit rating of the switchgear. CTs shall have a minimum rated
               continuous thermal current of at least 150% of rated primary current unless modified by
               the RFT for the specific location.
See Section 6.1.5 for CT location requirements for 33 & 66kV Feeders.
See Section 6.3.4 for CT location requirements for HV Busbars and Bus-Ties.
               The CT terminals shall be clearly marked to enable correct changing of the ratio. The
               associated rating plate shall also be marked with the information to enable correct
               changing of the ratio.
                Differential schemes  5P
                Overcurrent & earth fault  10P
               The rated short time current shall have a minimum rating equal to the short time
               withstand current of the associated switchboard or circuit breaker.
               Appendix B has a table listing the typical ratio and designation of current transformers,
               which are preferred for use in the RailCorp electrical network.
               As a general guide the following are typical class of accuracy used in the RailCorp
               network:
                0.5 class for general tariff metering such as supplies to shops, workshops etc.
                2.0 class for general measurement such as transducers and ammeters.
               The measurement current transformers shall have the same ratio and rated continuous
               thermal current as the associated protection CTs on the circuit.
 RailCorp                                                                                   Page 11 of 71
Issued June 2012                          UNCONTROLLED WHEN PRINTED                            Version 4.1
RailCorp Engineering Standard  Electrical
Protection System Requirements for the High Voltage Network                                 EP 19 00 00 02 SP
               The wiring shall be connected to the associated protection relay (or meter) via a test
               block that allows isolation of the relay / metering and short-circuiting of the current
               transformer secondary. If the relay test blocks are not integral with the relay enclosure,
               test blocks of the type Schneider MMLG01 shall be provided.
The test blocks shall be located adjacent to the respective protection relay.
                  A : red
                  B : white
                  C : blue
                  Neutral : black
                                                            2
               The wiring shall be a minimum size of 2.5mm and have an insulation rating of 0.6/1 kV.
                              2
               Where 2.5mm wiring is used it shall have a stranding of 50/0.25mm. All wiring
               connections to CTs and to protection relays shall be made using double grip ring type
               pre-insulated crimp lugs.
    PERFORMANCE
                               RATED VOLTAGE                  ACCURACY CLASS       RATED BURDEN
      CATEGORY
        Protection                   110/3 V                       3P                    50VA
         Metering                    110/3 V                      0.5                    50VA
               The neutral point of the star connected primary shall be earthed. The neutral point of the
               star connected secondary winding shall be brought out and connected to suitably
               insulated terminals located in the LV compartment and earthed.
               The voltage transformers shall be protected by suitably rated circuit breakers connected
               in the low voltage circuit as close as possible to the transformer terminals.
 RailCorp                                                                                       Page 12 of 71
Issued June 2012                          UNCONTROLLED WHEN PRINTED                                Version 4.1
RailCorp Engineering Standard  Electrical
Protection System Requirements for the High Voltage Network                               EP 19 00 00 02 SP
               High voltage fuse protection of VTs is not mandatory and is only required where
               necessitated by equipment design.
               The requirement for a residual winding is dependent on the type of protection relays to be
               used.
               For maintenance, and for the commissioning of protection relays, it shall be possible to
               simulate the voltage conditions that would occur during earth faults and the supplier shall
               explain how this is achieved. A typical way to achieve this is to remove the high-voltage
               fuse in any one phase and earth that phase of the voltage transformer.
               Terminal blocks for VT secondary wiring shall provide 4mm sockets for the connection of
               test equipment.
               All ACCBs shall be individually supplied from the 125V DC or 48V DC distribution
               board(s). The majority of RailCorp locations have an auxiliary supply of 125V DC, other
               locations have a supply of 48V DC.
               In each ACCB, distinct control circuits and equipment shall be individually fused. The
               fuses shall be sized to ensure there is discrimination.
               The following is a list of typical ACCB circuits and equipment that would be individually
               protected by fuses.
 RailCorp                                                                                    Page 13 of 71
Issued June 2012                          UNCONTROLLED WHEN PRINTED                             Version 4.1
RailCorp Engineering Standard  Electrical
Protection System Requirements for the High Voltage Network                                  EP 19 00 00 02 SP
               		 Connectivity of the substation (4 or more high voltage feeders) within the RailCorp
                   electrical network.
               		 Maximum high voltage fault level and the margin to the rated short-time withstand
                   current capacity of the switchgear installed at the substation.
               		 Criticality of the substation within the rail system. (eg. Main supply substation for city
                   circle, rail tunnel, rail junction, last traction substation on a radial rail line).
               		 Where primary and backup protection is installed in the same substation, that
                   substation shall have two battery systems. Some substations are exempt from this
                   requirement. This exemption is based on risk exposure considering safety, operational
                   impact, economic and environmental considerations.
               		 Complexity of the protection schemes and any resulting compromises in the protection
                   coordination.
               The associated main distribution boards of the battery systems are to be capable of being
               paralleled.
               The two battery systems shall be of equal capacity and individually be rated for the full
               load and duty cycle of the substation. Refer to EP 06 00 00 01 SP  System Substation
               Battery for further details.
               Refer to Section 5.1 and Appendix C for specific requirements relating to protection
               schemes when there are two auxiliary supplies at a substation.
               Appendix A has a table listing the protection relays which are currently approved for use
               in the RailCorp electrical network.
               When specifying the type of protection relay to be used consideration must be given to
               ensure adequate integrated system support including availability of system spares.
 RailCorp                                                                                       Page 14 of 71
Issued June 2012                          UNCONTROLLED WHEN PRINTED                                Version 4.1
RailCorp Engineering Standard  Electrical
Protection System Requirements for the High Voltage Network                                  EP 19 00 00 02 SP
               System transformers and 11kV/415V transformers shall have a close inhibit contact in
               both the primary and secondary ACCB closing circuits where fitted.
               If a protection relay has more than one function (eg A and C overcurrent elements),
               then where practical each function shall have a separate alarm output.
               Refer to Appendix A for protection relays currently preferred for use in the RailCorp
               Electrical Network for type of inter-trip relay.
               If there are no spare pilots in the existing pilot cable, the inter-trip may be achieved by
               manipulating the feeder pilot wire scheme.
               A minimum of 15kV isolation shall be provided to avoid transfer of voltages across the
               pilots. This may be achieved by using an inter-trip relay that provides isolation at both
               ends of the scheme.
 RailCorp                                                                                        Page 15 of 71
Issued June 2012                          UNCONTROLLED WHEN PRINTED                                 Version 4.1
RailCorp Engineering Standard  Electrical
Protection System Requirements for the High Voltage Network                                 EP 19 00 00 02 SP
               All pilot wire schemes shall include pilot circuit supervision. This may be implemented
               either as a function of the pilot wire relay or using dedicated pilot circuit supervision
               equipment.
 RailCorp                                                                                       Page 16 of 71
Issued June 2012                          UNCONTROLLED WHEN PRINTED                                Version 4.1
RailCorp Engineering Standard  Electrical
Protection System Requirements for the High Voltage Network                                    EP 19 00 00 02 SP
               It is preferred that the feeder pilot wire relay provides this function. Where the pilot wire
               relay does not have this function an overcurrent and earth fault relay (with directional
               capabilities) shall be provided to implement the breaker fail scheme. A contact from the
               pilot wire relay shall be connected to the overcurrent and earth fault relay, which will
               initiate an internal timer (nominally set to 0.2s). If the fault has not been cleared within this
               time all possible sources of supply shall have their ACCBs tripped. All ACCBs on the
               same busbar section as the failed ACCB shall be tripped via a multi-trip relay.
               The buszone multi-trip relay shall be used for this purpose where fitted, otherwise the
               multi-trip relay shall be an MTM relay for an indoor switchboard and an MTA relay for an
               outdoor busbar.
               However where this is not practicable, the current transformers for feeder protection may
               be located on the line side of the feeder circuit breaker. In this arrangement an inter-trip
               shall be provided to trip the feeder circuit breaker at the far end of the feeder whenever
               the local feeder circuit breaker is tripped. The far end circuit breaker is only required to
               trip if fault current is flowing through that circuit breaker.
               Refer to Appendix Q for specific current and voltage transformer requirements applicable
               to bulk supply points.
               Details of the ammeter, metering and their connection are specified in the appropriate
               switchgear standard.
 RailCorp                                                                                         Page 17 of 71
Issued June 2012                          UNCONTROLLED WHEN PRINTED                                  Version 4.1
RailCorp Engineering Standard  Electrical
Protection System Requirements for the High Voltage Network                                      EP 19 00 00 02 SP
               The criticality of the installation, accessibility of the 11kV feeder and the fault level
               determines the type of protection to be provided.
               All pilot wire schemes shall include pilot circuit supervision. This can be implemented
               either as a function of the pilot wire relay or using dedicated pilot circuit supervision
               equipment.
               Where the primary protection scheme is not required to be a pilot wire scheme, the
               feeder shall be protected with an over-current and earth fault scheme.
               Where the primary protection is a pilot wire scheme, the backup over-current and earth
               fault scheme can be located on the same circuit breaker panel, however the scheme
               must operate via a separate protection relay and ACCB trip coil.
               Where the primary protection is not a pilot wire scheme, the backup over-current and
               earth fault scheme shall operate via a circuit breaker and current transformers that are
               not part of the primary scheme.
               Where the primary protection is an overcurrent and earth fault scheme and is located on
               a 11kV switchboard supplied directly from a transformer, a neutral leakage relay shall be
               used as backup protection for earth faults.
 RailCorp                                                                                            Page 18 of 71
Issued June 2012                           UNCONTROLLED WHEN PRINTED                                    Version 4.1
RailCorp Engineering Standard  Electrical
Protection System Requirements for the High Voltage Network                                 EP 19 00 00 02 SP
               If the feeders are protected by a pilot wire scheme then the appropriate upstream circuit
               breaker(s) shall be tripped. A time delay (0.2s) shall be provided to avoid nuisance
               tripping.
               However where this is not practicable, the current transformers for feeder protection can
               be located on the line side of the feeder circuit breaker. This is subject to RailCorp
               approval.
               Details of the ammeter, metering and their connection are specified in the appropriate
               switchgear standard.
               The requirement for 11kV indoor switchgear to have bus zone protection depends
               whether the location is a:
                strategic location
                location with high fault levels
                location where there is more than one busbar section
               The traditional high impedance bus-zone protection scheme using CTs is an approved
               RailCorp scheme. A fault detection scheme that has been type tested and is an integral
               system within the switchgear may be offered for consideration by RailCorp and if
               approved will be the preferred scheme.
               Strategically important outdoor 33kV and 66kV busbars shall also have high impedance
               bus zone protection as the primary protection. The criteria for this decision will be
               provided in a later version of this document.
 RailCorp                                                                                       Page 19 of 71
Issued June 2012                          UNCONTROLLED WHEN PRINTED                                Version 4.1
RailCorp Engineering Standard  Electrical
Protection System Requirements for the High Voltage Network                                  EP 19 00 00 02 SP
               Separate schemes shall be provided for each section of the busbar. All ACCBs on the
               associated bus-section shall be tripped. Close inhibit shall also be implemented, refer to
               Section 5.7
               The tripping of circuit breakers on an indoor switchboard shall be via a MTM relay. The
               tripping of circuit breakers on an outdoor busbar shall be via an MTA relay.
               The scheme shall be arranged to trip the circuit breakers at both ends of the tie cable via
               a manually reset multi-trip relay. Close inhibit shall also be implemented, refer to Section
               5.7.
               The backup protection for a bus-tie shall be upstream over-current and earth fault
               protection except where the switchboard directly interfaces with a Supply Authority.
               Where the switchboard interfaces with a Supply Authority the bus-tie cables shall have a
               duplicate high impedance protection scheme as the backup protection. Refer to Appendix
               A for the type of relay to be used.
               The current transformers for protection of the bus-tie cables shall be located on the
               busbar side of the tie circuit breaker.
               Where the current transformers for the feeder, bus-tie, or transformer circuits are not
               located on the busbar side of the circuit breaker and the bus zone scheme is used to
               cover the blind spots between the circuit breakers and the CTs, then the bus-zone
               scheme shall also initiate tripping of the circuit breakers at the far end of the feeder or tie
               cable, or on the other winding of the transformer.
               If the transformer is cable connected (terminals/bushings are not exposed), the circuit
               breaker shall be tripped via a MTM relay for earth faults.
               The overcurrent elements are required to operate when a fault on the +1500V DC busbar
               (constant voltage arc of 400V between positive busbar and negative used in calculation)
               is detected.
               A current transducer shall be provided in the B protection circuit. The transducer output
               shall be connected to the panel ammeter and analogue input to SCADA.
 RailCorp                                                                                        Page 20 of 71
Issued June 2012                          UNCONTROLLED WHEN PRINTED                                 Version 4.1
RailCorp Engineering Standard  Electrical
Protection System Requirements for the High Voltage Network                                    EP 19 00 00 02 SP
               If the transformer is cable connected, the circuit breaker shall be tripped via a MTM relay
               for earth faults.
               A dedicated instantaneous relay (and test block) shall be installed in the same location as
               the primary and backup protection relays for the rectifier transformer.
               The tripping of the circuit breakers shall be via a multi-trip relay. If the transformer is cable
               connected (terminals/bushings not exposed) the multi-trip relay shall be a manually reset
               relay.
 RailCorp                                                                                         Page 21 of 71
Issued June 2012                          UNCONTROLLED WHEN PRINTED                                  Version 4.1
RailCorp Engineering Standard  Electrical
Protection System Requirements for the High Voltage Network                                    EP 19 00 00 02 SP
               The tripping of the circuit breakers shall be via a multi-trip relay. If the transformer is cable
               connected (terminals/bushings not exposed) the multi-trip relay shall be a manually reset
               relay for earth faults and an automatically reset relay for overcurrent faults.
               Three phase over current protection shall be provided on the low voltage side of the
               transformer as backup protection to the outgoing feeder overcurrent protection.
               The three phase overcurrent protection relay on the same side of the transformer as the
               scheme being backed up shall provide this function.
               Operation of either the oil or gas element of the buchholz relay shall trip both the primary
               and secondary circuit breakers via a manually reset multi-trip relay.
               Each element of the buchholz relay shall have voltage free alarm contacts, which are
               connected to the SCADA system.
               Where this is not practicable, it is acceptable that the current transformers for transformer
               protection be located on the transformer side of the transformer circuit breaker.
               The current transformer for the neutral leakage protection shall be located on the neutral
               to earth connection of the transformer.
 RailCorp                                                                                         Page 22 of 71
Issued June 2012                          UNCONTROLLED WHEN PRINTED                                  Version 4.1
RailCorp Engineering Standard  Electrical
Protection System Requirements for the High Voltage Network                                    EP 19 00 00 02 SP
               For transformers < 1MVA primary protection shall be overcurrent and earth leakage.
               Transformer differential schemes may be used on smaller transformers where required to
               ensure that the transformer protection grades over the LV protection.
               The tripping of the circuit breakers shall be via a multi-trip relay. If the transformer is cable
               connected (terminals/bushings not exposed) the multi-trip relay shall be a MTM relay.
               The backup protection scheme is not required to detect faults on the LV winding of a
               distribution transformer or the LV cables.
               The tripping of the circuit breakers shall be via a multi-trip relay. If the transformer is cable
               connected (terminals/bushings not exposed) the multi-trip relay shall be a MTM relay for
               earth faults and an MTA relay for overcurrent faults.
 RailCorp                                                                                         Page 23 of 71
Issued June 2012                          UNCONTROLLED WHEN PRINTED                                  Version 4.1
RailCorp Engineering Standard  Electrical
Protection System Requirements for the High Voltage Network                                 EP 19 00 00 02 SP
               		 Schematic diagrams
               		 Equipment arrangement / layout drawings
               		 Equipment label schedule
 RailCorp                                                                                      Page 24 of 71
Issued June 2012                          UNCONTROLLED WHEN PRINTED                               Version 4.1
RailCorp Engineering Standard  Electrical
Protection System Requirements for the High Voltage Network                                EP 19 00 00 02 SP
               The following table details the approved protection relays for use in the RailCorp
               electrical network when:
Notes:
               The VIP300LL relay can not be used for transformers less then 200kVA as there may be
               insufficient magnetising current to meet the self powering requirements of the relay.
 RailCorp                                                                                     Page 25 of 71
Issued June 2012                          UNCONTROLLED WHEN PRINTED                              Version 4.1
RailCorp Engineering Standard  Electrical
Protection System Requirements for the High Voltage Network                                EP 19 00 00 02 SP
The physical location of protection relays will depend on the type of switchgear installed.
               The location is usually on the low voltage compartment of the switchgear panels (indoor
               switchgear) or on dedicated protection panels (for outdoor ACCBs, indoor 66kV GIS or
               indoor switchgear that does not have the physical space for installing the relays).
                The test block shall be located adjacent to the protection relay to which it is connected
               (right side of protection relay).
The particular location requirements for specific relays and equipment are detailed below:
               		 Transformer protection  rectifier transformer frame leakage, MTA and MTM relays
                   located on the primary protection panel.
               		 33/11kV transformer  neutral leakage relay shall be located on the 11kV switchgear
                   panel.
               		 Bus-zone protection relay and associated MTM relay located on the appropriate end
                   panel.
               		 Bus cable tie protection relay and associated MTM relay located on either of the
                   associated bus tie ACCB panels.
               		 Pilot wire isolation transformers shall be located as close as possible to the
                   termination enclosure of the pilot cable.
 RailCorp                                                                                      Page 26 of 71
Issued June 2012                          UNCONTROLLED WHEN PRINTED                               Version 4.1
RailCorp Engineering Standard  Electrical
Protection System Requirements for the High Voltage Network                                    EP 19 00 00 02 SP
                                                                             TRIP COIL
        EQUIPMENT                     PROTECTION SCHEME                                         NOTES
                                                                             NUMBER
                                Pilot wire                                       1
  Feeder Protection             Overcurrent & Earth Fault                        2
                                Inter-trip                                       1
                                Busbar protection  trips via MTM                2                  a
  Bus-zone & Bus-Tie            Cable Bus-tie protection  trips via
                                                                                 1                  d
                                MTM
                                Differential  trips via MTM or MTA              1                  f
                                33kVOvercurrent  trips via MTA                  1,2                b
  System Transformers
                                Neutral Leakage  trips via MTA                  2
                                11kV Overcurrent                                 2
  11kV/415V                     Differential  trips via MTM or MTA              1
  Transformers                  Overcurrent  trips via MTA                      1,2               b,e
                                Instantaneous Overcurrent                        2
  Rectifier Transformers                                                                            c
  (backup protn)
                                Earth Fault                                 2 & 1 via MTM
Notes:
                   a)     The operation of the bus-zone protection energises an MTM relay, which trips
                          all ACCBs on the section of the busbar. The trip coil number applies to all
                          ACCBs that are tripped.
                   b)     If the differential protection operates via an MTM then the overcurrent protection
                          shall trip via trip coil 2.
                   c)     Refer to 6.4 for requirements of when earth faults are required to energise
                          MTM.
                   d)     When there is duplicate protection on the bus-tie cable the duplicate scheme
                          shall trip the ACCBs via trip coil 2 (via an MTM).
                   e)     If there is no differential protection, then the overcurrent protection shall trip via
                          trip coil 1.
f) Trip coil number applies to both ACCBs (eg. 33kV & 11kV)
 RailCorp                                                                                         Page 27 of 71
Issued June 2012                             UNCONTROLLED WHEN PRINTED                               Version 4.1
RailCorp Engineering Standard  Electrical
Protection System Requirements for the High Voltage Network                                   EP 19 00 00 02 SP
               When there are two battery systems the equipment should be connected across the two
               battery systems to obtain balanced loads as close as possible.
               Protection designs for specific locations must be verified by RailCorp. Refer to 5.5.2 for
               details of the requirement for two battery systems.
Notes:
                   a) 	   When there is only one battery system, the two trip coils must be supplied from
                          separate submains originating from the 125V DC distribution board.
 RailCorp                                                                                        Page 28 of 71
Issued June 2012                          UNCONTROLLED WHEN PRINTED                                 Version 4.1
RailCorp Engineering Standard  Electrical
Protection System Requirements for the High Voltage Network                                EP 19 00 00 02 SP
                                         EXISTING             SCHEME TO BE
             SCHEME                                                                 NOTES
                                        EQUIPMENT               REPLACED
        Pilot wire               HO2                          YES
                                 HO4                          NO                       b
                                 HMB4                         YES
                                 MHOB04                       NO                       a
                                 MBCI02                       NO                       a
                                 MiCOM P521/P541              NO
                              Table 6 - Interfacing With Existing Pilot Wire Schemes
Notes:
 RailCorp                                                                                     Page 29 of 71
Issued June 2012                          UNCONTROLLED WHEN PRINTED                              Version 4.1
RailCorp Engineering Standard  Electrical
Protection System Requirements for the High Voltage Network                                EP 19 00 00 02 SP
               The following tables detail the ratio and designation of the majority of current
               transformers, which are used in the existing RailCorp electrical network for typical
               schemes on the 66kV & 33kV high voltage system.
               These tables do not detail current transformers used with 1A secondaries or for new
               equipment or installations.
               The current transformer designation details are calculated based on the following
               parameters:
               		 Maximum CT secondary lead (loop) length of 20m with 2.5mm2 size cable for indoor
                   equipment and a lead (loop) length of 150m with 16mm2 size cable for outdoor
                   equipment.
               		 CT core knee point flux density of 1.45T
               		 System X/R = 5
               		 MICOM P521 relay, refer to general equations for X/R<40 and tIdiff = 0.1s.
               		 MBCI relay, refer to general equations, X=1, large X/R, Kt = 20.
               		 Overcurrent and earth fault relays, Vk = In*If*(Rrelay+Rct+Rleads), with relay burdens
                   as specified by the manufacturer.
               Where the equipment to be protected is not in the following tables or the standard
               parameters above are not applicable then the protection CT requirements must be
               determined on an individual basis.
                                                                  RELAY
     EQUIPMENT              VOLTAGE/SIZE           CT RATIO                       CT DESIGNATION
                                                                   TYPE
                                                                              10 P100F20 (specified on
                                                                 MCAG33
                               5.3, 4.28 &          300/200/5                 200 tap)
 Rectifier Tx  33kV
                                2.5MVA                                        10 P50F20 (specified on
                                                                MiCOM P127
                                                                              200 tap)
                                                                              10 P100F20 (specified on
                                                                 MCAG33
                                5.3, 4.28,          150/100/5                 100 tap)
 Rectifier Tx  66kV
                                 2.5MVA                                       10 P50F20 (specified on
                                                                MiCOM P127
                                                                              100 tap)
 RailCorp                                                                                     Page 30 of 71
Issued June 2012                             UNCONTROLLED WHEN PRINTED                           Version 4.1
RailCorp Engineering Standard  Electrical
Protection System Requirements for the High Voltage Network                                        EP 19 00 00 02 SP
               CTs for use on overcurrent and earth leakage on feeders have been sized on a fault
               level of 31.5kA at 33kV and 15.75kA at 66kV.
                              VOLTAGE                          CT
      EQUIPMENT                                SCHEME                     RELAY TYPE         CT DESIGNATION
                               / SIZE                         RATIO
                                                                           KCEG142                10P150
       66kV Feeder                             OC & EF         250/5
                                                                          MiCOM P127              10P150
                                                                                             10P300 (specified
                                                                           KCEG142
                                                              500/400                           on 300 tap)
       33kV Feeder                             OC & EF
                                                               /300/5                        10P300 (specified
                                                                          MiCOM P127
                                                                                                on 300 tap)
  33/11KV Tx (5MVA )              33KV         OC & EF         150/5      MiCOM P127             10P50F20
               CTs for use on pilot wire schemes have been sized on a fault level of 31.5kA at 33kV
               and 15.75kA at 66kV
               The overall design of a bus-zone scheme is critical to ensure stability for through faults.
               The requirement for stabilising resistors to ensure stability and for metrosils to limit CT
               output voltage shall be determined for each individual scheme.
               Please refer to the AREVA MCAG34 application brochure for methods of calculation and
               requirements.
CTs for use on bus-zone schemes have been sized on a fault level of 31.5kA.
Notes:
                   a) 	   The P632 relay should be ordered with an extra I/O module. This is required to
                          allow for the transformer and tapchanger alarms.
 RailCorp                                                                                             Page 31 of 71
Issued June 2012                          UNCONTROLLED WHEN PRINTED                                      Version 4.1
RailCorp Engineering Standard  Electrical
Protection System Requirements for the High Voltage Network                                EP 19 00 00 02 SP
                                                              RELAY           CT
    EQUIPMENT                SCHEME            CT RATIO                                        Notes
                                                               TYPE      DESIGNATION
                                                              MiCOM
    11kV Feeder              Pilot Wire           300/1                   0.05PL50R1.0
                                                               P521
                                                              MiCOM
    11kV Feeder              OC & EF            300/150/1                   10P50F20
                                                               P127
                                                              MiCOM
                            Differential        450/0.577                0.02PL100R3.0               a
                                                               P632
                               Neutral                        MiCOM
                                                  150/1                     10P50F20
                              leakage                          P127
   11KV/415V Tx                                               MiCOM
                            Differential          100/1                   0.15L50R0.3                a
     (1MVA )                                                   P632
Notes:
a) The rated primary current value will depend on the size of the transformer.
b) The rated primary current value will depend on the rating of the busbar.
 RailCorp                                                                                     Page 32 of 71
Issued June 2012                           UNCONTROLLED WHEN PRINTED                             Version 4.1
RailCorp Engineering Standard  Electrical
Protection System Requirements for the High Voltage Network                                  EP 19 00 00 02 SP
63 Buchholz Relay
 RailCorp                                                                                       Page 33 of 71
Issued June 2012                          UNCONTROLLED WHEN PRINTED                                Version 4.1
RailCorp Engineering Standard  Electrical
Protection System Requirements for the High Voltage Network                                  EP 19 00 00 02 SP
               It is not general practice to connect alarms via the test block or connect spare output
               relays to the test block. The test block shall be located adjacent to the protection relay it
               is associated with.
               It is important that new installations comply with these diagrams as they affect the
               programming of numerical relays, the testing procedures for periodic maintenance and
               the production of standard designs.
               Any deviations from the standard configuration must be approved by the Protection
               Engineer.
 RailCorp                                                                                       Page 34 of 71
Issued June 2012                          UNCONTROLLED WHEN PRINTED                                Version 4.1
RailCorp Engineering Standard  Electrical
Protection System Requirements for the High Voltage Network                               EP 19 00 00 02 SP
MBOH04 RELAY
 RailCorp                                                                                    Page 35 of 71
Issued June 2012                          UNCONTROLLED WHEN PRINTED                             Version 4.1
RailCorp Engineering Standard  Electrical
Protection System Requirements for the High Voltage Network                                   EP 19 00 00 02 SP
P543 RELAY
               OUTPUT RELAYS:
               RELAY 1  PILOT WIRE TRIP
               RELAY 2  TCS ALARM
               RELAY 3  PILOT WIRE TRIP ALARM
               RELAY 4  PILOT WIRE COMMS FAIL ALARM
               RELAY 5  SPARE
               RELAY 6  BREAKER FAIL ALARM
               RELAY 7  SPARE
               RELAY 8  BREAKER FAIL TRIP
               RELAY 9  SPARE
               RELAY 10 SPARE
               RELAY 11 SPARE
               RELAY 12 SPARE
               RELAY 13 SPARE
               RELAY 14 SPARE
               INPUT RELAYS:
               L1      INTERTRIP INITIATE
               L2      TCS INPUT
               L 3  L16 SPARE
 RailCorp                                                                                        Page 36 of 71
Issued June 2012                          UNCONTROLLED WHEN PRINTED                                 Version 4.1
RailCorp Engineering Standard  Electrical
Protection System Requirements for the High Voltage Network                                     EP 19 00 00 02 SP
P521 RELAY
OUTPUT RELAYS:
               L1                    INTERIPT INITIATE
               L2                    TCS INPUT
               L3                    SPARE
               L4                    SPARE
               L5                    SPARE
 RailCorp                                                                                          Page 37 of 71
Issued June 2012                          UNCONTROLLED WHEN PRINTED                                   Version 4.1
RailCorp Engineering Standard  Electrical
Protection System Requirements for the High Voltage Network                                 EP 19 00 00 02 SP
OUTPUT RELAYS:
               Note: Output replays BO1, BO2 and BO3 are not voltage free contacts. Depending on
               the protection requirements additional relays will need to be installed to achieve voltage
               free contacts.
               The +125V DC for the breaker fail trip is also connected to B01& B02 contacts by internal
               relay wiring.
 RailCorp                                                                                      Page 38 of 71
Issued June 2012                          UNCONTROLLED WHEN PRINTED                               Version 4.1
RailCorp Engineering Standard  Electrical
Protection System Requirements for the High Voltage Network                                   EP 19 00 00 02 SP
P127 RELAY
               OUTPUT RELAYS:
               RELAY 1      OVERCURRENT & EARTH FAULT TRIP
               RELAY 2      TCS ALARM
               RELAY 3      EARTH FAULT TRIP
               RELAY 4      OVERCURRENT ALARM
               RELAY 5      EARTH FAULT ALARM
               RELAY 6      BREAKER FAIL ALARM
               RELAY 7      SPARE
               RELAY 8      BREAKER FAIL TRIP
               INPUT RELAYS:
               INPUT L1              SPARE
               INPUT L2              SPARE
               INPUT L3              SPARE
               INPUT L4              TCS
               INPUT L5              TIMER INITIATE
               INPUT L6              SPARE
               INPUT L7              SPARE
 RailCorp                                                                                        Page 39 of 71
Issued June 2012                          UNCONTROLLED WHEN PRINTED                                 Version 4.1
RailCorp Engineering Standard  Electrical
Protection System Requirements for the High Voltage Network                                EP 19 00 00 02 SP
               OUTPUT RELAYS:
               RELAY 1      OVERCURRENT & EARTH FAULT TRIP
               RELAY 2      TCS ALARM
               RELAY 3      EARTH FAULT TRIP
               RELAY 4      OVERCURRENT & EARTH FAULT ALARM
               RELAY 5      EARTH FAULT ALARM
               RELAY 6      BREAKER FAIL ALARM
               INPUT RELAYS:
               INPUT L1              SPARE
               INPUT L2              SPARE
               INPUT L3              SPARE
               INPUT L4              TCS
               INPUT L5              SPARE
               INPUT L6              SPARE
               INPUT L7              SPARE
 RailCorp                                                                                     Page 40 of 71
Issued June 2012                          UNCONTROLLED WHEN PRINTED                              Version 4.1
RailCorp Engineering Standard  Electrical
Protection System Requirements for the High Voltage Network                                 EP 19 00 00 02 SP
MCAG33 RELAY
RELAY CONTACTS:
Notes:
1. A & C phase trip contacts are connected in parallel at the relay terminals.
 RailCorp                                                                                      Page 41 of 71
Issued June 2012                          UNCONTROLLED WHEN PRINTED                               Version 4.1
RailCorp Engineering Standard  Electrical
Protection System Requirements for the High Voltage Network                             EP 19 00 00 02 SP
MCAG14 RELAY
RELAY CONTACTS:
 RailCorp                                                                                   Page 42 of 71
Issued June 2012                          UNCONTROLLED WHEN PRINTED                            Version 4.1
RailCorp Engineering Standard  Electrical
Protection System Requirements for the High Voltage Network                                   EP 19 00 00 02 SP
P127 RELAY
OUTPUT RELAYS:
INPUT RELAYS:
               INPUT L1              SPARE
               INPUT L2              SPARE
               INPUT L3              SPARE
               INPUT L4              TCS
               INPUT L5              SPARE
               INPUT L6              SPARE
               INPUT L7              SPARE
 RailCorp                                                                                        Page 43 of 71
Issued June 2012                          UNCONTROLLED WHEN PRINTED                                 Version 4.1
RailCorp Engineering Standard  Electrical
Protection System Requirements for the High Voltage Network                                 EP 19 00 00 02 SP
P127 RELAY
OUTPUT RELAYS:
INPUT RELAYS:
               INPUT L1              SPARE
               INPUT L2              SPARE
               INPUT L3              SPARE
               INPUT L4              TCS
               INPUT L5              SPARE
               INPUT L6              SPARE
               INPUT L7              SPARE
 RailCorp                                                                                      Page 44 of 71
Issued June 2012                          UNCONTROLLED WHEN PRINTED                               Version 4.1
RailCorp Engineering Standard  Electrical
Protection System Requirements for the High Voltage Network                                 EP 19 00 00 02 SP
P127 RELAY
OUTPUT RELAYS:
               RELAY 1               SPARE
               RELAY 2               TCS ALARM
               RELAY 3               NEUTRAL LEAKAGE TRIP (TO MTA RELAY)
               RELAY 4               OVERCURRENT ALARM
               RELAY 5               NEUTRAL LEAKAGE ALARM
               RELAY 6               BREAKER FAIL ALARM
               RELAY 7               OVERCURRENT TRIP (TO 11KV ACCB)
               RELAY 8               BREAKER FAIL TRIP
INPUT RELAYS:
               INPUT L1              SPARE
               INPUT L2              SPARE
               INPUT L3              SPARE
               INPUT L4              TCS
               INPUT L5              SPARE
               INPUT L6              SPARE
               INPUT L7              SPARE
 RailCorp                                                                                      Page 45 of 71
Issued June 2012                          UNCONTROLLED WHEN PRINTED                               Version 4.1
RailCorp Engineering Standard  Electrical
Protection System Requirements for the High Voltage Network                                EP 19 00 00 02 SP
VIP300LL RELAY
VIP300LL RELAY
 RailCorp                                                                                     Page 46 of 71
Issued June 2012                          UNCONTROLLED WHEN PRINTED                              Version 4.1
RailCorp Engineering Standard  Electrical
Protection System Requirements for the High Voltage Network                                 EP 19 00 00 02 SP
P127 RELAY
OUTPUT RELAYS:
INPUT RELAYS:
               INPUT L1                      SPARE
               INPUT L2                      SPARE
               INPUT L3                      SPARE
               INPUT L4                      TCS
               INPUT L5                      SPARE
               INPUT L6                      SPARE
               INPUT L7                      SPARE
 RailCorp                                                                                      Page 47 of 71
Issued June 2012                          UNCONTROLLED WHEN PRINTED                               Version 4.1
RailCorp Engineering Standard  Electrical
Protection System Requirements for the High Voltage Network                               EP 19 00 00 02 SP
KCEG142 RELAY
OUTPUT RELAYS:
               RELAY 0                       SPARE
               RELAY 1                       BREAKER FAIL ALARM
               RELAY 2                       SPARE
               RELAY 3                       OVERCURRENT & EARTH FAULT TRIP
               RELAY 4                       OVERCURRENT ALARM
               RELAY 5                       EARTH FAULT ALARM
               RELAY 6                       SPARE
               RELAY 7                       BREAKER FAIL TRIP
 RailCorp                                                                                     Page 48 of 71
Issued June 2012                          UNCONTROLLED WHEN PRINTED                              Version 4.1
RailCorp Engineering Standard  Electrical
Protection System Requirements for the High Voltage Network                                   EP 19 00 00 02 SP
P632/MBCH RELAY
 RailCorp                                                                                        Page 49 of 71
Issued June 2012                          UNCONTROLLED WHEN PRINTED                                 Version 4.1
RailCorp Engineering Standard  Electrical
Protection System Requirements for the High Voltage Network                                 EP 19 00 00 02 SP
 RailCorp                                                                                      Page 50 of 71
Issued June 2012                          UNCONTROLLED WHEN PRINTED                               Version 4.1
RailCorp Engineering Standard  Electrical
Protection System Requirements for the High Voltage Network                                EP 19 00 00 02 SP
RELAY: MCGG52/82
 RailCorp                                                                                     Page 51 of 71
Issued June 2012                          UNCONTROLLED WHEN PRINTED                              Version 4.1
RailCorp Engineering Standard  Electrical
Protection System Requirements for the High Voltage Network                                 EP 19 00 00 02 SP
MCAG34 RELAY
RELAY CONTACTS:
Notes:
1. A, B &, C phase trip contacts are connected in parallel at the relay terminals.
 RailCorp                                                                                      Page 52 of 71
Issued June 2012                          UNCONTROLLED WHEN PRINTED                               Version 4.1
RailCorp Engineering Standard  Electrical
Protection System Requirements for the High Voltage Network                                 EP 19 00 00 02 SP
 RailCorp                                                                                      Page 53 of 71
Issued June 2012                          UNCONTROLLED WHEN PRINTED                               Version 4.1
RailCorp Engineering Standard  Electrical
Protection System Requirements for the High Voltage Network                               EP 19 00 00 02 SP
               		 Output of 020mA
               		 Mean sensing
               		 Self powered
               The following transducer is approved for connection in the protection current transformer
               circuit.
The following transducer is approved for connection in the voltage transformer circuit.
               		 Areva Istat 400; Type I4VAEA0-125, (nominal input range of 0-125V ac to measure a
                   110V ac voltage transformer output, usually measuring the voltage between A &
                   C).
 RailCorp                                                                                     Page 54 of 71
Issued June 2012                          UNCONTROLLED WHEN PRINTED                              Version 4.1
RailCorp Engineering Standard  Electrical
Protection System Requirements for the High Voltage Network           EP 19 00 00 02 SP
 RailCorp                                                                Page 55 of 71
Issued June 2012                          UNCONTROLLED WHEN PRINTED         Version 4.1
RailCorp Engineering Standard  Electrical
Protection System Requirements for the High Voltage Network                                 EP 19 00 00 02 SP
               In general, one auto re-close in 5 seconds by SCADA (ie the master station initiates the
               auto re-close if all the requirements are met).
               During periods of total fire ban the auto re-close is inhibited on 33kV and 66kV feeders
               that traverse areas considered to be a bush fire risk . This is a master station function
               initiated by the ESO's.
Auto re-close is also automatically inhibited for 10 minutes after a close control.
 RailCorp                                                                                       Page 56 of 71
Issued June 2012                          UNCONTROLLED WHEN PRINTED                                Version 4.1
RailCorp Engineering Standard  Electrical
Protection System Requirements for the High Voltage Network                               EP 19 00 00 02 SP
               The following is a list of typical protection alarms required. The exact alarm requirement
               depends on the following factors:
               		   Type of relay
               		   Capacity of RTU
               		   Function of relay
               		   Value adding of the alarm information to the EOC operator and RailCorp Protection
                     Engineer.
               In many existing locations some of the protection alarms (eg. TCS) are connected in
               parallel for each piece of equipment to give one general alarm. This was due to the
               limitations on the quantity of alarms that could be connected to the RTU at the time of
               installation.
 RailCorp                                                                                    Page 57 of 71
Issued June 2012                          UNCONTROLLED WHEN PRINTED                             Version 4.1
RailCorp Engineering Standard  Electrical
Protection System Requirements for the High Voltage Network                                    EP 19 00 00 02 SP
 RailCorp                                                                                         Page 58 of 71
Issued June 2012                          UNCONTROLLED WHEN PRINTED                                  Version 4.1
RailCorp Engineering Standard  Electrical
Protection System Requirements for the High Voltage Network                                  EP 19 00 00 02 SP
               Numerical protection relays can be used to convey the information by using discrete
               output relays or via serial links. However certain information is critical for system
               operation and must be independent on the protection relay or communication link to the
               RTU.
               The following list details the SCADA alarms and control that are required to be hard wired
               to the RTU.
              * If all circuit breakers on a switchboard are not fitted with numerical relays having
              adequate RS485 communications to the RTU
 RailCorp                                                                                       Page 59 of 71
Issued June 2012                          UNCONTROLLED WHEN PRINTED                                Version 4.1
RailCorp Engineering Standard  Electrical
Protection System Requirements for the High Voltage Network           EP 19 00 00 02 SP
 RailCorp                                                                Page 60 of 71
Issued June 2012                          UNCONTROLLED WHEN PRINTED         Version 4.1
Issued June 2012
 RailCorp
                                                                                     --- ~                                                                                                                                      r --              - -B-;
                                                                                                                                                                                                                                i
                                                                                                                     EEE                                                                                                        i
                                                                                                                                                                                                                                I
                                                                                                                                                                                                                                          ~I- ~
UNCONTROLLED WHEN PRINTED
                                                       - - - - -,  : :   I                                                                !                                                                                     !i       i
                                                                   :     :                                               MOTOR            I         MOl OR                                 MOTOR                                I        I
                                                       - --:       :     :                                                                I                                                                                              j
                                                              I    I     I                                                                I                                                                                          I   .
                                                              :    :     :                                               COTROL                   CON1Rot.                               COtlfROC..                                 i   l
                                                              I    I     I                                                                I                                                                                          I   I
                                                             i / :                                                                        I                                                                                              I
                                                             i i i
                                                              I    I
                                                                                                                         OULV
                                                                                                                                               I
                                                                                                                                                ~B
                                                                                                                                                 URLY                                G'"~'
                                                                                                                                                                                      I
                                                                                                                                                                                                                               ::    -
                                                              :    :                                                                           : FUPCOl.2                             I   RIPCOU                                ! !
                                                              I
                                                              I
                                                                   I
                                                                   I
                                                                                                                                               I
                                                                                                                                               I                              I      I.                                        I. I.
                                                             : :                                                                               :                              :                                                 I I I
                                                              :    :                                          I                           I I                                        I                                          I I i
                                                             : :                                              :      I                    I :                                 I           - - - - - - - - -t-J-
                                                             : :                                              i      I                    '-- -t -       -- - :-- - - - - - - -                                        --f-J
                                                             r     :                       t_ ---- -l - __ ___ 1- - -- - _ __ ______ J
                                                                         1__ _______________                  J
                                                             I     I                                    I           I
                                                             II    !-----------------------------------'           II
                                                             I                                                                                                                I
                                                             ~---- --- - - ----- ----- - - -- ----- -- - - - -- -- - - ----- --~
                            = 
                            1. FOR SIMPllCITY OF DIAGRAM , Ot"i.Y ~ ve FUSES SHOWN
                            2. SUBMAlNS FOR f t-iE SAME HV PANEL ARE REQUIRED TO
                                                                                                ~
                                                                                                PRIM Rl.Y: PRIMARY PROTECTION RELAY
                                                                                                au  RlY:   BACKUP PROTECTION RELAY
                                                                                                                                                                                                                            .,......,.~                   ARRANGEMENT OF DC
                                                                                                                                                                                                                                                           AUXILIARY SYSTEMS
                               BE RUN VIA l NOEPENOAtn ROUTES.                                  IL!S;      INTELLIGENT LIGHT INFORMATION SYS TEM                                             &         !:E   R.'lilCo rp                                2 BATTERY SYSTEM
                            3. ORIGlN Of 125V SUPPlY FOR SCAOAALARMS DEPENDS Qt'                IGIS:      111/TElllGENT GA.5 INFORMATION SYSTEM
                               ORIGIN Of RTU SUPPLY.                                            OZ:        TRADITIONAL BUSZONE PROTECTION                                                                                                    tC.IS
                                                                                                                                                                                                                                                                                      EP 19 00 00 02 SP
                                                                                                                                                                  E n g i nuurlng Sk111d{lrd~ tmd SorvlCOG,
                                                                                                                                                                  E l t,>ctric.al.                                                                    17110/2005   I V(ll:SION   10
Page 61 of 71 
  Version 4.1
RailCorp Engineering Standard  Electrical
Protection System Requirements for the High Voltage Network                                   EP 19 00 00 02 SP
Location of Labels:
                      		 Labels should be located above the relay. If this is not possible, then they
                          should be located directly below the relay.
Colour of Labels:
                      		 All protection relays labels shall have black writing on a yellow background.
                      		 All auxiliary relays (such as multi-trip relays) shall have black writing on a white
                          background.
Format
                      		 To keep the length of labels to a minimum, abbreviations shall be used for the
                          protection functions. The valid abbreviations are detailed in Table 12.
                      		 All labels are to be in CAPITALS (except for abbreviations such as Tx & kV).
                      		 The description of equipment shall be consistent with terminology as used in the
                          AC operating diagrams. This is summarised below:
                      		 FEEDERS:          Feeder ID ;
                      		 Where Feeder ID is the unique 3 digit identification assigned to each high
                          voltage feeder.
                      		 TRANSFORMERS:            Unit ID + voltage ratio + Tx ;
                      		 Where Unit ID is the identification given where there are multiple transformers
                          (eg. No.1, No.2 etc). voltage ratio is the voltage ratio of the transformer
                          usually expressed in kV (eg. 33/11kV, 66/33kV).
                      		 RECTIFERS: Unit ID + RECTIFIER
                      		 Where Unit ID is the identification given where there are multiple rectifiers (eg.
                          No.1, No.2 etc).
Content:
                                  eg.        N
                                             	 o.1 RECTIFIER
                                             BUS ZONE
                                             792
                                             No.2 33/11kV Tx
 RailCorp                                                                                        Page 62 of 71
Issued June 2012                          UNCONTROLLED WHEN PRINTED                                 Version 4.1
RailCorp Engineering Standard  Electrical
Protection System Requirements for the High Voltage Network                       EP 19 00 00 02 SP
eg.
EXAMPLES OF LABELS:
 RailCorp                                                                            Page 63 of 71
Issued June 2012                          UNCONTROLLED WHEN PRINTED                     Version 4.1
RailCorp Engineering Standard  Electrical
Protection System Requirements for the High Voltage Network                          EP 19 00 00 02 SP
 RailCorp                                                                               Page 64 of 71
Issued June 2012                          UNCONTROLLED WHEN PRINTED                        Version 4.1
RailCorp Engineering Standard  Electrical
Protection System Requirements for the High Voltage Network           EP 19 00 00 02 SP
 RailCorp                                                                Page 65 of 71
Issued June 2012                          UNCONTROLLED WHEN PRINTED         Version 4.1
Issued June 2012
 RailCorp
                                                                                                                -
                                                                                                        ~
                            SUBSTATION
                             B USBARS
                                         ~Plll\.U
                                                                                                           --
                                                                                                      _, ' "
                                         C~I:                                                           ~~
UNCONTROLLED WHEN PRINTED
~ ~
                                                                                                       -
                                                                                                                -:-
                                                              fill   @
                                                              fill   ~ ,__
                                                     MICOM    ig     fill
                                                      P1 27   (B     ~ ,__
                                                     RELAY
                                                              fill
                                                              ~
                                                              fill
                                                                     ~
                                                                     ~
                                                                     ~
                                                                            --
                                                              ~      ~
                                                               ,,~    6
                                                               ~      t
                                                                                                                                                                                     EP 19 00 00 02 SP
                                                                                                                         J~ t't.!IJ.W'     TmE         C U RREHT~ 'ISFORMER
                                                                                                                                                           ARRANGEMENT
                                                                                                                                           ReLAVI
                                                                                                                                           SCMEME            PROTECTION
  Version 4.1
                                                                                                                              ~       ij ~
                                                         CTJ
                                                         ~'   ~   ;:)
                                                              U.S18l~ 2! "I                                                   I ~ ~sr:or:
                                           !ill
                                           ig
                                                              I                                                                                               fill
                                                                                                                                                              19
                                  Mi COM
                                           19                                                                                                                 19       MICOM
                                   P521
                                           fiS                                                                                                                ~         P521
                                  RELAY                                                                                                                              RELAY
                                           ~                                                                                                                  ~
                                           ID!                                                                                                                ID!
                                           !!                                                                                                                ~
                                           E.
                                           0
                                           ~
                                                    r:
                                                    "i                                                                                               .
                                                                                                                                                     ,
                                                                                                                                                     :;
                                                                                                                                                     ~
                                                                                                                                                              ,
                                                                                                                                                              ;:;
                                                                                                                                                               !
                                                                                                                                                                                                EP 19 00 00 02 SP
                                                                                                                                  CJ,IU_Y
                                                                                                                                             Tm.E             CUMENT TllAASFORMeR
                                                                                                                                                                 ARRANGEMENT
                                                                                                   s    ~   RailCof"p                        1------                                  -
Page 67 of 71 
               Endeavour Energy: Metering Design Instruction, Document No: MET 0002 (amendment
               0)
VOLTAGE TRANSFORMERS:
               		 Dedicated winding required (1 per phase), class 0.5 and 50VA for Ausgrid, class 0.2
                   and 100VA for Endeavour Energy, form factor of 1.9/30s. Associated LV circuit
                   breaker installed on the output with auxiliary contact of circuit breaker connected to
                   SCADA.
               		 Warning label required adjacent to VT isolating handle (eg. "WARNING - VT
                   SUPPLIES 7XX REVENUE METERING ").
CURRENT TRANSFORMERS:
               		 The CT's are required to be positioned adjacent to the metering CT's used for
                   RailCorp check metering.
               		 Additional secondary wiring and associated CT links are required for connection to the
                   new CTs
               The manufacturers test reports for the voltage transformers and current transformers are
               required to be submitted to RailCorp.
 RailCorp                                                                                      Page 68 of 71
Issued June 2012                          UNCONTROLLED WHEN PRINTED                               Version 4.1
RailCorp Engineering Standard  Electrical
Protection System Requirements for the High Voltage Network                             EP 19 00 00 02 SP
               		 The CT & VT secondary wiring is required to be run in separate conduits to the new
                   meter panel.
               		 The CT secondary wiring is to be a multi-core cable PVC/PVC minimum size of
                   2.5mm2
               		 The VT secondary wiring is to be a multi-core cable PVC/PVC minimum size
                   of 2.5mm2 for Ausgrid and 4mm2 for Endeavour Energy.
               		 Dedicated 240Vac supply from the 415V DB required to be run in separate conduit to
                   the metering panel.
               		 The 415V DB to have appropriate identification label and additional label "DO NOT
                   TURN OFF" or similar adjacent to circuit breaker.
METERING PANEL
               		 The proposed location of the metering panel has to be approved by RailCorp prior to
                   installation. The metering panel should be located on the external wall of the
                   substation.
               		 The metering panel (including equipment) should be purchased directly from the
                   Supply Authority where available.
 RailCorp                                                                                   Page 69 of 71
Issued June 2012                          UNCONTROLLED WHEN PRINTED                            Version 4.1
RailCorp Engineering Standard  Electrical
Protection System Requirements for the High Voltage Network                                  EP 19 00 00 02 SP
Notes:
If more numbers are required, add multiples of one hundred, e.g. 10-29 may be extended to 110-129, 210-229.
 RailCorp                                                                                        Page 70 of 71
Issued June 2012                          UNCONTROLLED WHEN PRINTED                                 Version 4.1
RailCorp Engineering Standard  Electrical
Protection System Requirements for the High Voltage Network                                EP 19 00 00 02 SP
These arrangements have been accepted for the ECRL project only.
11kV Protection
33kV Protection
               		 Multi-trip relays not used on the 33/11kV transformer protection (pushbutton installed
                   to reset latched P632 output relays).
               		 Dual trip coils not installed.
               		 Test blocks not wired in accordance with standard configuration.
               		 Protection relays not programmed with standard configuration.
 RailCorp                                                                                     Page 71 of 71
Issued June 2012                          UNCONTROLLED WHEN PRINTED                              Version 4.1