G+5 Building... Report Date 18-Oct-17 12:48 Project Start 02-Oct-17 Project Finish 10-Jul-18
G+5 Building... Report Date 18-Oct-17 12:48 Project Start 02-Oct-17 Project Finish 10-Jul-18
WBS
  Activity ID                                                      Activity Name                          Original     Remaining   Activity % Start          Finish      Primary Resource
                                                                                                         Duration       Duration   Complete
                    BES11.GG5.GG5 SubStructure
                          A1980                                    Levelling                                    1              1         0% 25-Oct-17        25-Oct-17   SS.Site Supervisor
                          A1990                                    Shuttering foundation                        1              1         0% 26-Oct-17        26-Oct-17   MZ.Mazdoor
                          A2000                                    Reinforcement for foundation and             1              1         0% 26-Oct-17        26-Oct-17   SS.Site Supervisor
                                                                   column
                          A2010                                    Concreting                                   1              1         0% 27-Oct-17        27-Oct-17   MS.Mason
                          A2030                                    De-shuttering                                1              1         0% 03-Nov-17        03-Nov-17   MZ.Mazdoor
                          A2040                                    Fill around foundation                       1              1         0% 03-Nov-17        03-Nov-17   SS.Site Supervisor
                          A2020                                    Curing                                       4              4         0% 30-Oct-17        02-Nov-17   MZ.Mazdoor
                    BES11.GG5.GG5 SuperStructure
                          BES11.GG5.GGround Floor
                            BES11.GGSkeletal Works
                                  A2060                            Plinth beam concreting                       1              1         0% 08-Nov-17        08-Nov-17   MS.Mason
                                  A2070                            Plinth beam deshuttering                     1              1         0% 09-Nov-17        09-Nov-17   MS.Mason
                                  A2100                            Column concreting                            1              1         0% 20-Nov-17        20-Nov-17   MS.Mason
                                  A2130                            Beam concreting and deshuttering             1              1         0% 29-Nov-17        29-Nov-17   MS.Mason
                          BES11.GG5.GFirst Floor
                            BES11.GGSkeletal Works
                                  A2210                            Concreting of column                         1              1         0% 22-Dec-17        22-Dec-17   MS.Mason
                                  A2240                            Concreting of beam                           1              1         0% 03-Jan-18        03-Jan-18   MS.Mason
                                  A2270                            Concreting of slab                           1              1         0% 15-Jan-18        15-Jan-18   MS.Mason
                                                                                                                                                      Page 1 of 4
  G+5 Building...                                                                                                                                                                     Project Start 02-Oct-17
  Report Date 18-Oct-17 12:48                                                                                                                                                         Project Finish 10-Jul-18
WBS
  Activity ID                                            Activity Name                            Original     Remaining   Activity % Start          Finish      Primary Resource
                                                                                                 Duration       Duration   Complete
                BES11.GG5.GSecond Floor
                  BES11.GGSkeletal Works
                       A2320                             Concreting of column                           1              1         0% 25-Jan-18        25-Jan-18   MS.Mason
                       A2350                             Concreting of beam                             1              1         0% 06-Feb-18        06-Feb-18   MS.Mason
                       A2380                             Concreting of slab                             1              1         0% 16-Feb-18        16-Feb-18   MS.Mason
                       A2310                             Reinforcement and shutering of                 2              2         0% 23-Jan-18        24-Jan-18   SS.Site Supervisor
                                                         column
                       A2340                             Reinforcement and shuttering of                2              2         0% 02-Feb-18        05-Feb-18   SS.Site Supervisor
                                                         beam
                       A2370                             Reinforcement and shuttering of                2              2         0% 14-Feb-18        15-Feb-18   SS.Site Supervisor
                                                         slab
                       A2330                             Deshuttering and curing of column              5              5         0% 26-Jan-18        01-Feb-18   MZ.Mazdoor
                BES11.GG5.GThird Floor
                  BES11.GGSkeletal Works
                       A2430                             Concreting of column                           1              1         0% 01-Mar-18        01-Mar-18   MS.Mason
                       A2460                             Concreting of beam                             1              1         0% 13-Mar-18        13-Mar-18   MS.Mason
                       A2490                             Concreting of slab                             1              1         0% 23-Mar-18        23-Mar-18   MS.Mason
                       A2420                             Reinforcement and shutering of                 2              2         0% 27-Feb-18        28-Feb-18   SS.Site Supervisor
                                                         column
                       A2450                             Reinforcement and shuttering of                2              2         0% 09-Mar-18        12-Mar-18   SS.Site Supervisor
                                                         beam
                       A2480                             Reinforcement and shuttering of                2              2         0% 21-Mar-18        22-Mar-18   SS.Site Supervisor
                                                         slab
                       A2440                             Deshuttering and curing of column              5              5         0% 02-Mar-18        08-Mar-18   MZ.Mazdoor
                                                                                                                                              Page 2 of 4
  G+5 Building...                                                                                                                                                                   Project Start 02-Oct-17
  Report Date 18-Oct-17 12:48                                                                                                                                                       Project Finish 10-Jul-18
WBS
  Activity ID                                            Activity Name                          Original     Remaining   Activity % Start          Finish      Primary Resource
                                                                                               Duration       Duration   Complete
                BES11.GG5.GFourth Floor
                  BES11.GGSkeletal Works
                       A2560                             Concreting of column                         1              1         0% 04-Apr-18        04-Apr-18   MS.Mason
                       A2590                             Concreting of beam                           1              1         0% 16-Apr-18        16-Apr-18   MS.Mason
                       A2620                             Concreting of slab                           1              1         0% 26-Apr-18        26-Apr-18   MS.Mason
                       A2550                             Reinforcement and shutering of               2              2         0% 02-Apr-18        03-Apr-18   SS.Site Supervisor
                                                         column
                       A2580                             Reinforcement and shuttering of              2              2         0% 12-Apr-18        13-Apr-18   SS.Site Supervisor
                                                         beam
                       A2610                             Reinforcement and shuttering of              2              2         0% 24-Apr-18        25-Apr-18   SS.Site Supervisor
                                                         slab
                       A2570                             Deshuttering and curing of column            5              5         0% 05-Apr-18        11-Apr-18   MZ.Mazdoor
                BES11.GG5.GFifth Floor
                  BES11.GGSkeletal Works
                       A2670                             Concreting of column                         1              1         0% 08-May-18        08-May-18   MS.Mason
                       A2700                             Concreting of beam                           1              1         0% 18-May-18        18-May-18   MS.Mason
                       A2660                             Reinforcement and shutering of               2              2         0% 04-May-18        07-May-18   SS.Site Supervisor
                                                         column
                       A2690                             Reinforcement and shuttering of              2              2         0% 16-May-18        17-May-18   SS.Site Supervisor
                                                         beam
                       A2680                             Deshuttering and curing of column            5              5         0% 09-May-18        15-May-18   MZ.Mazdoor
                BES11.GG5.GRoof
                   A2730                                 Insulation and testing                       4              4         0% 05-Jun-18        08-Jun-18   MS.Mason
                   A2740                                 Tile roof                                    4              4         0% 11-Jun-18        14-Jun-18   MS.Mason
                   A2770                                 Install gutters                              4              4         0% 15-Jun-18        20-Jun-18   MS.Mason
                   A2760                                 Install wood member                          5              5         0% 15-Jun-18        21-Jun-18   MS.Mason
                   A2720                                 Cast concrete                                6              6         0% 28-May-18        04-Jun-18   SS.Site Supervisor
                                                                                                                                            Page 3 of 4
  G+5 Building...                                                                                                                                                       Project Start 02-Oct-17
  Report Date 18-Oct-17 12:48                                                                                                                                           Project Finish 10-Jul-18
WBS
  Activity ID                                 Activity Name                         Original     Remaining   Activity % Start          Finish      Primary Resource
                                                                                   Duration       Duration   Complete
                    BES11.GG5.GG5 Finishing
                        A2790                 Carpentry works                             5              5         0% 08-Jun-18        14-Jun-18   C.Carpenter
                        A2800                 Insulation and plastering                   5              5         0% 15-Jun-18        21-Jun-18   MS.Mason
                        A2780                 Electrical wirings                          6              6         0% 31-May-18        07-Jun-18   E.Electrician
                        A2810                 Inner wall painting                         6              6         0% 22-Jun-18        29-Jun-18   MZ.Mazdoor
                        A2820                 External painting and coating               7              7         0% 02-Jul-18        10-Jul-18   MZ.Mazdoor
Page 4 of 4