ABF Project Tracking

This document outlines the engineering, procurement, construction and commissioning (EPCC) requirements for an HVAC system project. It includes a checklist of required documents to be submitted for the basic engineering design, detail engineering design, materials, construction works, inspections, and commissioning. Key submission dates are provided.

Uploaded by

Takrimi Ismail
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
322 views34 pages

ABF Project Tracking

This document outlines the engineering, procurement, construction and commissioning (EPCC) requirements for an HVAC system project. It includes a checklist of required documents to be submitted for the basic engineering design, detail engineering design, materials, construction works, inspections, and commissioning. Key submission dates are provided.

Uploaded by

Takrimi Ismail
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 34

ENGINEERING, PROCUREMENT, CONSTRUCTION AND COMMISSIONING (EPCC) OF HVAC SYSTEM FOR TOXIC RELEASE SHELTER F

DOCUMENT & MATERIAL CHECKLIST

ITEM DESCRIPTION 1st Submission


Documents Date Submitted App / Reject

1 Project Schedule

-Work Programme
-Manpower Loading
-Equipment Loading

2 Health & Safety

-Org. Chart

-HSE Plans, HSE KPIs for the project, Emergency action plans for
construction phase

3 Engineering
-BED for HVAC system (Mechanical) 18-Sep-15
> Design Philosopy 18-Sep-15
> Unit selection 18-Sep-15
> Cooling capacity calculation 18-Sep-15
> HVAC system Scope of Work 18-Sep-15
> Air conditioner location 18-Sep-15
> Ducting single line 18-Sep-15
> Refrigerant piping single line 18-Sep-15

-BED for HVAC system (Electrical) 18-Sep-15


> Load analysis study 18-Sep-15
Basic > Substation main LV switchboard 18-Sep-15
Engineering > Block Diagram for LV distribution 18-Sep-15
Design > Motor & Electrical load schedules 18-Sep-15
> Equipment layouts 18-Sep-15
> Aircond cable single line 18-Sep-15
> Fresh air fan cable single line 18-Sep-15
> Dampers cable single line 18-Sep-15
> Exhaust fan cable single line 18-Sep-15
> Split unit aircond cable single line 18-Sep-15

-BED for HVAC system (Civil) 18-Sep-15


> Existing structural integrity assessment 18-Sep-15
> Site survey report 18-Sep-15
> AHU Room proposed layout 18-Sep-15

-DED for HVAC system (Mechanical)


> Cover 18-Sep-15
> Drawing index, System Legend, Abbreviations 18-Sep-15
> Equipment basic arrangement / single line 18-Sep-15
> Equipment schedule 18-Sep-15
> Detail drawing design of equipment layout 18-Sep-15
> Ducting sizing calculation 18-Sep-15
> Detail of Air Conditioner 18-Sep-15
> Detail of Fresh air fan 18-Sep-15
> Detail of dampers 18-Sep-15
> Detail of Exhaust fan 18-Sep-15
> Detail of Air cond split unit 18-Sep-15
> Detail of duct heater 18-Sep-15
> Miscellanoeus details 18-Sep-15
> Plan layout 18-Sep-15
> Isometric 18-Sep-15

-DED for HVAC system (Electrical)


> Cover 18-Sep-15
> Drawing index, System Legend, Abbreviations 18-Sep-15
> Load analysis study 18-Sep-15
> Cable sizing calculation 18-Sep-15
> Substation main LV switchboard 18-Sep-15
> Block Diagram for LV distribution 18-Sep-15
Detail > Aircond cable single line 18-Sep-15
Engineering > Fresh air fan cable single line 18-Sep-15
Design > Dampers cable single line 18-Sep-15
> Exhaust fan cable single line 18-Sep-15
> Split unit aircond cable single line 18-Sep-15
> Cable schedule 18-Sep-15
> Control Panel Layout 18-Sep-15
> Control diagram 18-Sep-15

-DED for HVAC system (Civil)


> Cover 18-Sep-15
> Drawing index, System Legend, Abbreviations 18-Sep-15
> Overall plot plan 18-Sep-15
> Foundation design basis & calculation 18-Sep-15
> Building structure calculation 18-Sep-15
> RC structure calculation 18-Sep-15
> Construction specification for buildings 18-Sep-15
> Building structure integrity calculation for placement of
18-Sep-15
load on roofs
> Underground services layout 18-Sep-15
> Building structural and architectural detail and drawings 18-Sep-15
> Foundation location plan and misc details 18-Sep-15
> Typical concrete plinth details 18-Sep-15

-STQ
1. STQ-Civil ( AHU room extension) -001 18-Sep-15
2. STQ-Electrical (HVAC panel new cables)-002 18-Sep-15

4 Materials

UNIT DATASHEET - Mechanical


1. Catalogue - Air Conditioner 18-Sep-15
2. Catalogue - Fresh Air Fan 18-Sep-15
3. Catalogue - Internal Dampers 18-Sep-15
4. Catalogue - External Dampers 18-Sep-15
5. Catalogue - Split Unit Air Conditioner 18-Sep-15
6. Catalogue - Duct Heater 18-Sep-15
7. Catalogue - Exhaust Fan 18-Sep-15
8. Catalogue - Carbon Filter 18-Sep-15
9. Catalogue - Ammonia Gas Detector 18-Sep-15
10. Catalogue - Ducting and Flexible
UNIT DATASHEET - Electrical
1. Catalogue - Control Panel 18-Sep-15

UNIT DATASHEET - Civil


1. Catalogue - Fire Doors 18-Sep-15
2. Mill certificates - structural steel and high tensile steel

DELIVERY
1. Air Conditioner 20-Nov-15 4-Jan-16
2. Fresh Air Fan 10-Nov-15 8-Mar-16
3. Internal Dampers 20-Nov-15 8-Mar-16
4. External Dampers 15-Sep-15
5. Split Unit Air Conditioner 30-Sep-15 10-Dec-15
6. Duct Heater 30-Sep-15 8-Mar-16
7. Exhaust Fan 30-Sep-15 8-Mar-16
8. Carbon Filter c/w housing 7-Dec-15
9. Ammonia Gas Detector 10-Nov-15
10. Control Panel TBA
11. Fire Doors TBA 8-Mar-16
12. Ducting and Flexible TBA 8-Mar-16

FAT Documents TBA


SAT Documents TBA

5 Construction Works
- Safety Briefing TBA
- Work Leader TBA
- Fire Watcher TBA
- Equipment mobilization plan TBA
- Installation plan TBA
- Scaffolding TBA
- Mobile / Lorry Crane TBA
- JKJ 103 Form TBA
- Porta Cabin TBA
- Tools & Oxy-Acetylene TBA
- Distribution Board TBA

- Inspection Test Plan


1. Mechanical TBA
2. Electrical & Instrument TBA
3. Civil & Structure TBA

- Job Method Statements


1. JMS - Mechanical TBA
2. JMS - Electrical TBA
3. JMS - Civil TBA

- Job Hazard Analysis


1. JHA - Mechanical TBA
2. JHA - Electrical TBA
3. JHA - Civil TBA

- Installation Works
- Punch List
1.Mechanical TBA
2.Electrical TBA
3.Civil TBA

- Testing & Commissioning


1. HVAC Inspection, Testing & Commissioning Procedure TBA
AC SYSTEM FOR TOXIC RELEASE SHELTER FOR CCR

1st Submission 2nd Submission


Remark Date Submitted App / Reject Remark
ENGINEERING, PROCUREMENT, CONSTRUCTION AND COMMISSIONING (EPCC) OF HVAC SYSTEM FOR TOXIC RELEASE SHELTER F

PROJECT TRACKING

ITEM DESCRIPTION 1st Submission


Documents Date Submitted App / Reject

1 Project Schedule

-Work Programme Approved


-Manpower Loading Approved
-Equipment Loading Approved

2 Health & Safety

-Org. Chart Approved

-HSE Plans, HSE KPIs for the project, Emergency action plans for
construction phase Approved

3 Engineering
-BED for HVAC system (Mechanical) 18-Sep-15 Approved
> Design Philosopy 18-Sep-15 Approved
> Unit selection 18-Sep-15 Approved
> Cooling capacity calculation 18-Sep-15 Approved
> HVAC system Scope of Work 18-Sep-15 Approved
> Air conditioner location 18-Sep-15 Approved
> Ducting single line 18-Sep-15 Approved
> Refrigerant piping single line 18-Sep-15 Approved

-BED for HVAC system (Electrical) 18-Sep-15 Approved


> Load analysis study 18-Sep-15 Approved
Basic > Substation main LV switchboard 18-Sep-15 Approved
Engineering > Block Diagram for LV distribution 18-Sep-15 Approved
Design > Motor & Electrical load schedules 18-Sep-15 Approved
> Equipment layouts 18-Sep-15 Approved
> Aircond cable single line 18-Sep-15 Approved
> Fresh air fan cable single line 18-Sep-15 Approved
> Dampers cable single line 18-Sep-15 Approved
> Exhaust fan cable single line 18-Sep-15 Approved
> Split unit aircond cable single line 18-Sep-15 Approved

-BED for HVAC system (Civil) 18-Sep-15 Approved


> Existing structural integrity assessment 18-Sep-15 Approved
> Site survey report 18-Sep-15 Approved
> AHU Room proposed layout 18-Sep-15 Approved

-DED for HVAC system (Mechanical)


> Cover 18-Sep-15 Approved
> Drawing index, System Legend, Abbreviations 18-Sep-15 Approved
> Equipment basic arrangement / single line 18-Sep-15 Approved
> Equipment schedule 18-Sep-15 Approved
> Detail drawing design of equipment layout 18-Sep-15 Approved
> Ducting sizing calculation 18-Sep-15 Approved
> Detail of Air Conditioner 18-Sep-15 Approved
> Detail of Fresh air fan 18-Sep-15 Approved
> Detail of dampers 18-Sep-15 Approved
> Detail of Exhaust fan 18-Sep-15 Approved
> Detail of Air cond split unit 18-Sep-15 Approved
> Detail of duct heater 18-Sep-15 Approved
> Miscellanoeus details 18-Sep-15 Approved
> Plan layout 18-Sep-15 Approved
> Isometric 18-Sep-15 Approved

-DED for HVAC system (Electrical)


> Cover 18-Sep-15 Approved
> Drawing index, System Legend, Abbreviations 18-Sep-15 Approved
> Load analysis study 18-Sep-15 Approved
> Cable sizing calculation 18-Sep-15 Approved
> Substation main LV switchboard 18-Sep-15 Approved
> Block Diagram for LV distribution 18-Sep-15 Approved
Detail > Aircond cable single line 18-Sep-15 Approved
Engineering > Fresh air fan cable single line 18-Sep-15 Approved
Design > Dampers cable single line 18-Sep-15 Approved
> Exhaust fan cable single line 18-Sep-15 Approved
> Split unit aircond cable single line 18-Sep-15 Approved
> Cable schedule 18-Sep-15 Approved
> Control Panel Layout 18-Sep-15 Approved
> Control diagram 18-Sep-15 Approved

-DED for HVAC system (Civil)


> Cover 18-Sep-15 Approved
> Drawing index, System Legend, Abbreviations 18-Sep-15 Approved
> Overall plot plan 18-Sep-15 Approved
> Foundation design basis & calculation 18-Sep-15 Approved
> Building structure calculation 18-Sep-15 Approved
> RC structure calculation 18-Sep-15 Approved
> Construction specification for buildings 18-Sep-15 Approved
> Building structure integrity calculation for placement of load
18-Sep-15
on roofs Approved
> Underground services layout 18-Sep-15 Approved
> Building structural and architectural detail and drawings 18-Sep-15 Approved
> Foundation location plan and misc details 18-Sep-15 Approved
> Typical concrete plinth details 18-Sep-15 Approved

-STQ
1. STQ-Civil ( AHU room extension) -001 18-Sep-15 Approved
2. STQ-Electrical (HVAC panel new cables)-002 18-Sep-15 Approved

4 Materials

UNIT DATASHEET - Mechanical


1. Catalogue - Air Conditioner 18-Sep-15 Approved
2. Catalogue - Fresh Air Fan 18-Sep-15 Approved
3. Catalogue - Internal Dampers 18-Sep-15 Approved
4. Catalogue - External Dampers 18-Sep-15 Approved
5. Catalogue - Split Unit Air Conditioner 18-Sep-15 Approved
6. Catalogue - Duct Heater 18-Sep-15 Approved
7. Catalogue - Exhaust Fan 18-Sep-15 Approved
8. Catalogue - Carbon Filter 18-Sep-15 Approved
9. Catalogue - Ammonia Gas Detector 18-Sep-15 Approved
10. Catalogue - Ducting and Flexible
UNIT DATASHEET - Electrical
1. Catalogue - Control Panel 18-Sep-15 Approved

UNIT DATASHEET - Civil


1. Catalogue - Fire Doors 18-Sep-15 Approved
2. Mill certificates - structural steel and high tensile steel

DELIVERY
1. Air Conditioner 30-Dec-15 Delivered
2. Fresh Air Fan 24-Feb-16 Delivered
3. Internal Dampers 2-Feb-15 Delivered
4. External Dampers 29-Feb-16 Delivered
5. Split Unit Air Conditioner 30-Sep-15 Delivered
6. Duct Heater 22-Dec-15 Delivered
7. Exhaust Fan 30-Sep-15 Delivered
8. Carbon Filter c/w housing 23 Feb 2016 Delivered
9. Ammonia Gas Detector 10-Nov-15 Delivered
10. Control Panel 25-Apr-16 Delivered
11. Fire Doors 12-Jan-16 Delivered
12. Ducting and Flexible 22-Dec-16 Delivered

FAT Documents TBA


SAT Documents TBA

5 Construction Works
- Safety Briefing TBA
- Work Leader TBA
- Fire Watcher TBA
- Equipment mobilization plan TBA
- Installation plan TBA
- Scaffolding TBA
- Mobile / Lorry Crane TBA
- JKJ 103 Form TBA Submitted to DOSH. In Progress
- Porta Cabin TBA Completed
- Tools & Oxy-Acetylene TBA
- Distribution Board TBA

- Inspection Test Plan


1. Mechanical TBA
2. Electrical & Instrument TBA
3. Civil & Structure TBA

- Job Method Statements


1. JMS - Mechanical TBA Approved
2. JMS - Electrical TBA Approved
3. JMS - Civil TBA Approved

- Job Hazard Analysis


1. JHA - Mechanical TBA Approved
2. JHA - Electrical TBA Approved
3. JHA - Civil TBA Approved
Plan
Start End
- Installation Works 4/4/2016 26/10/2016
A) Civil
'i) Replacement of fire doors 4/4/2016 7/5/2016
1) Fire door (SFD-1) 4/4/2016 9/4/2016
2) Fire door (SFD-2) 11/4/2016 16/4/2016
3) Fire door (SFD-3) 18/4/2016 23/4/2016
4) Fire door (SFD-4) 25/4/2016 30/4/2016
5) Fire door (SFD-5) 2/5/2016 7/5/2016

ii) Installation of concrete plinth for ACCU 1A & 1B 9/5/2016 13/5/2016


iii) Installation of single leaf door for rest room 14/5/2016 16/5/2016
iv) Installation of shelter for filtration system 17/5/2016 20/5/2016

B) Mechanical 21/5/2016 19/9/2016


'i) Replacement of internal HVAC System 21/5/2016 22/8/2016
1) Central Air Conditioner 21/5/2016 13/6/2016
> Removal of existing air conditioner (FCU) at Corridor 1 21/5/2016 24/5/2016
> Removal of existing air conditioner (FCU) at Corridor 2 25/5/2016 27/5/2016
> Removal of existing air conditioner (ACCU 1A & 1B) 28/5/2016 31/5/2016
> Installation of AHU 1 1/6/2016 2/6/2016
> Installation of AHU 2 3/6/2016 4/6/2016
> Installation of ACCU 1A & 1B 6/6/2016 8/6/2016
> Installation of ACCU 2A & 2B 9/6/2016 11/6/2016

2) Ducting 13/6/2016 16/7/2016


> Removal of existing ducting at Corridor 1 13/6/2016 15/6/2016
> Removal of existing ducting at Corridor 2 16/6/2016 18/6/2016
> Removal of existing ducting at AHU Room 20/6/2016 21/6/2016
> Installation of internal ducting c/w fittings at Corridor 1 22/6/2016 29/6/2016
> Installation of internal ducting c/w fittings at Corridor 2 30/6/2016 7/7/2016
> Installation of internal ducting c/w fittings at AHU Room 8/7/2016 16/7/2016

3) Piping 18/7/2016 5/8/2016


> Removal of existing refrigerant piping, trunking, etc. 18/7/2016 21/7/2016
> Installation of new refrigerant piping, trunking, etc. 22/7/2016 5/8/2016

4) Exhaust Fan System 6/8/2016 10/8/2016


> Relocation of existing exhaust fan c/w ducting at Rest Room 6/8/2016 10/8/2016

5) Split Unit System 11/8/2016 26/8/2016


> Installation of 2 nos ceiling cassette c/w accessories for 11/8/2016 18/8/2016
System Engineering Room and Control Room
> Installation of 2 nos ceiling exposed c/w accessories for 19/8/2016 26/8/2016
Marshalling Room

6) Installation of External System 27/8/2016 21/9/2016


> Installation of fresh air fan, filtration system, emergency shut 27/8/2016 29/8/2016
off dampers, etc.
> Installation of ducting system c/w gas detector 30/8/2016 21/9/2016

C) Electrical 22/9/2016 26/10/2016


1) Existing Control Panels 22/9/2016 27/9/2016
> Removal of existing hvac panels, cables, etc. 22/9/2016 27/9/2016

2) Installation of new Control Panels 28/9/2016 5/10/2016


> Installation of Main DB 1 28/9/2016 28/9/2016
> Installation of Main DB 2 29/9/2016 29/9/2016
> Installation of MISC 30/9/2016 30/9/2016
> Installation of Fan & Damper 1/10/2016 1/10/2016
> Installation of Duct Heater 3/10/2016 3/10/2016
> Installation of AHU 1 Panel 4/10/2016 4/10/2016
> Installation of AHU 2 Panel 5/10/2016 5/10/2016

3) Installation of cabling c/w trunking 6/10/2016 26/10/2016


> Installation of AHU & ACCU cables 6/10/2016 10/10/2016
> Installation of Duct Heater cables 11/10/2016 13/10/2016
> Installation of MSD, ESD and PRD cables 14/10/2016 18/10/2016
> Installation of Fresh Air Fan cables 19/10/2016 21/10/2016
> Installation of Ligthning Protection System at Roof Top 22/10/2016 25/10/2016
> Installation of Power Cables for MCC 6/10/2016 26/10/2016
> General Housekeeping 26/10/2016 26/10/2016
- Punch List
1.Mechanical TBA
2.Electrical TBA
3.Civil TBA

- Testing & Commissioning


1. HVAC Inspection, Testing & Commissioning Procedure TBA
C SYSTEM FOR TOXIC RELEASE SHELTER FOR CCR

1st Submission 2nd Submission


Remark Date Submitted App / Reject Remark
mitted to DOSH. In Progress
Target Date
Status
Start End

Completed
Completed
Completed
Completed
Awaiting for AHU Room Extension

Completed
Completed
In Progress 1/9/2016 5/9/2016 Team 2
Completed
Completed
Completed
In Progress 16/8/2016 17/8/2016 Team 1
Awaiting for AHU Room Extension
Completed
Completed

Completed
Completed
Completed
Completed
In Progress 8/8/2016 13/8/2016 Team 2
In Progress 20/9/2016 26/9/2016 Team 2

Completed
In Progress 1/9/2016 19/9/2016 Team 1

Completed

Completed

Awaiting Marshall Room


In Progress 15/8/2016 16/8/2016 Team 2

In Progress 17/8/2016 30/8/2016 Team 1 & 2

Completed

Completed 8/8/2016 8/8/2016 Team 1


Completed 9/8/2016 9/8/2016 Team 1
In Progress 10/8/2016 10/8/2016 Team 1
Completed 11/8/2016 11/8/2016 Team 1
In Progress 12/8/2016 12/8/2016 Team 1
In Progress 13/8/2016 13/8/2016 Team 1
In Progress 15/8/2016 15/8/2016 Team 1

In Progress 20/9/2016 22/9/2016 Team 1


In Progress 23/9/2016 26/9/2016 Team 1
In Progress 27/9/2016 29/9/2016 Team 1
In Progress 30/9/2016 3/10/2016 Team 1
In Progress 5/10/2010 7/10/2010 Team 1
Awaiting Delivery
In Progress