Ref.
No:           CEH/QC/
                                                           Rev. No:           -
   CE                   VISUAL INSPECTION                  Date:
                                                           Page No:
 HYDRO                       REPORT
 Project Code: CEH/GHP/2017
 Customer: Ghalemdi Hydro Ltd.
 Job Details: Penstock Pipe & Hydro Mechanical Works
 Type of Inspection: Visual Inspection                 Date of inspection:
 Scope of work:
 Piece of Inspection:       Factory premises          Project site            Others
 Welders No. :
 Name of welder:
 Base Material:
 Type of weld:                            Fill Material:
 Parameter Checked:
 Weld Contour:                                  Acceptable           Not Acceptable
 Weld Filling:     UC        Incomplete        Acceptable            Not Acceptable
 Smoothness of Joint:                          Acceptable            Not Acceptable
 Surface Defects:                              Acceptable            Not Acceptable
 Remarks:
   NDE Inspector                       Approved By                           Witnessed By:
Name                       Name                                      Name
Level   Deg.   Deg.
Sign    Sign   Sign
Date    Date   Date